B08_Att_02_Quote_Sheet.xlsx
XLSX spreadsheet 19 KB Posted
- Attached to
- DEEP CLEAN BARRY BAKER TUNNEL Federal contract opportunity
- Solicitation number
- 140P8624Q0064
About this file
This document contains pricing templates and sample contract price schedules for Design-Bid-Build (DBB) and Design-Build (DB) federal contract opportunities.
The DBB template is for a National Park Service solicitation (N2011080811) for a Johnstonian Visitors Center project at Yellowstone National Park, with line items for the visitors center, water line, sewer line, rock excavation, and optional geothermal wells and photovoltaic system. The DB template is for a NPS solicitation (N2011080811) for a new structure in Yosemite Valley, with line items for design and construction, plus an optional photovoltaic system.
The pricing template for the federal contract opportunity 140P8624Q0064 is for deep cleaning of the Barry Baker Tunnel at the Golden Gate National Recreation Area. The contract line item is for the tunnel deep cleaning on a lump-sum basis.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8624Q0064_Amd_0001.pdf | ||
| B08_Att_07_Site_Visit_Sign-In_Sheet_0001.pdf | ||
| B08_Att_01_Barry_Baker_Tunnel_Statement_of_Work.pdf | ||
| B08_Att_04_Wage_Determinations_2015-5725__7-22-24.pdf | ||
| B08_Att_06_Past_Performance_Questionnaire.docx | DOCX document | |
| B08_Att_03_Drawings_Maps_Figures.pdf | ||
| Sol_140P8624Q0064.pdf | ||
| B08_Att_05_Relevant_Experience_.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule Template
| Quote Sheet | |
| National Park Service | |
| Solicitation Number: | 140P8624Q0064 |
| Developed Area: | Golden Gate National Recreation Area | |||
| Project Title: | Deep Clean Barry Baker Tunnel | |||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | ||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | ||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | ||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | ||||
| govern. Round totals and extended prices to whole dollars. | ||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Unit of Measure | QTY | Total |
| 1 | Deep Clean Barry Baker Tunnel | LS | 1 | |
| TOTAL |
TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 9) ----------------------------------------------------------- ERROR:#REF!
Design-Bid-Build (DBB) Sample
| Contract Price Schedule - Design-Bid-Build (DBB) SAMPLE | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | N2011080811 | ||||
| PARK - PMIS: | YELL 012345 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Old Faithful | ||||
| Project Title: | Johnstonian Visitors Center | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Visitors Center | 1 | Lump Sum | $0.00 | |
| 2 | Water Line | 400 | Lineal Feet | - 0 | |
| 3 | Sanitary Sewer Line | 200 | Lineal Feet | - 0 | |
| 4 | Rock Excavation | 150 | Cubic Yards | - 0 | |
| TOTAL BASE PRICE (Contract Line Item Number 1 through 4) --------------------------------------------------------------------------------- | $0.00 | ||||
| 5 | OPTION A, Geothermal Wells | 1 | Lump Sum | - 0 | |
| 6 | OPTION B, Photovoltaic System | 1 | Lump Sum | - 0 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 5 and 6) ------------------------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 6) ---------------------------- | $0.00 | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |
Design-Build (DB) Sample
| Contract Price Schedule - Design-Build (DB) SAMPLE | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | N2011080811 | ||||
| PARK - PMIS: | YELL 012345 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Yosemite Valley | ||||
| Project Title: | Design and Build a New Structure | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Design | 1 | Lump Sum | $0.00 | |
| 2 | Construction | 1 | Lump Sum | - 0 | |
| TOTAL BASE PRICE (Contract Line Item Number 1 and 2) --------------------------------------------------------------------------------------- | $0.00 | ||||
| 3 | OPTION A, Photovoltaic System | 1 | Lump Sum | - 0 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 3) ---------------------------------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 3) ---------------------------- | $0.00 | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |
File details come from the government source that posted it. Updated .