This is a Statement of Work (SOW) prepared by the National Park Service for the replacement of a failed sewer lateral line serving Boulder Beach Housing Units 402 and 403 at Lake Mead National Recreation Area in Boulder City, Nevada. The project involves the complete removal and replacement of approximately 234 linear feet of deteriorated 3-inch ductile iron sanitary sewer lateral with 4-inch SDR 35 PVC pipe meeting current plumbing and wastewater conveyance standards. The existing sewer line has collapsed, causing system clogs that render both housing units unusable. The new pipe will connect to an existing 6-inch main sewer line and serve interior plumbing fixtures at each unit consisting of one toilet, two sinks, one bathtub, and one laundry outlet.

The contractor must furnish all labor, materials, equipment, and supervision to complete site preparation, demolition, trenching and excavation (approximately 27 linear feet per unit manually under crawlspaces and 180 linear feet via machine in open ground, plus asphalt sawcutting of approximately 25 square feet), pipe installation with proper slope maintenance (1/8 inch per foot minimum), backfilling and compaction, testing and inspection coordination with the NPS Contracting Officer's Representative (COR), and site restoration. The contractor is responsible for protecting adjacent infrastructure during all phases, maintaining site cleanliness and organization in designated staging areas, properly disposing of all construction waste, and repairing any NPS property damaged during construction at the contractor's expense. Final inspection and testing must be completed and approved by the NPS COR before final backfill operations commence.

View the file

Other files for this federal contract opportunity

Other files attached to LAKE - Replace Sewer Lateral Line at Boulder Beach, newest first.
File Type Posted
Atch_1_-_Revised_SOW_3_5_0001.docx DOCX document
Sol_140P8126Q0007_Amd_0001.pdf PDF
B08_-_Atch_2_-_Wage_Determination_NV20260024_1_30_26.pdf PDF
Sol_140P8126Q0007.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LAKE – Replace Sewer Lateral Line at Boulder Beach Housing Unit 402 and 403

Lake Mead National Recreation Area

Boulder City, Nevada

Replace Sewer Lateral Line at Boulder Beach Housing Unit 402 and 403

February 10, 2026

Prepared By: Trent Martinez, Supervisory Facility Operations Specialist

DEPARTMENT OF THE INTERIOR

NATIONAL PARK SERVICE

A04 STATEMENT OF WORK: REPLACE SEWER LINE LATERAL LINE AT

BOULDER BEACH HOUSING UNIT 403

1. BACKGROUND

Lake Mead National Recreation Area (LAKE) is a U.S. national recreation area in Southeastern Nevada and Northwestern Arizona. Operated by the National Park Service, Lake Mead NRA follows the Colorado River corridor from the westernmost boundary of Grand Canyon National Park to just north of the cities of Laughlin, Nevada and Bullhead City, Arizona.

LAKE employees roughly 180 staff, some of which live within the park in NPS owned employee housing. Employee housing is critical for staff who need to respond to emergencies and to be within proximity to their work. Recently, it was discovered that within the Boulder Beach housing area that housing unit 402 and 403’s sewer line has failed. The crawl space was investigated, and staff found the sewer lines had collapsed causing the systems to clog. It was determined the entire lateral line has been compromised and needs to be replaced.

This project involves the full removal and replacement of the existing 3-inch ductile iron sanitary sewer lateral serving both Boulder Beach Housing Unit 403 and 402 (see approximate map of sewer line locations in attachments). The system will be upgraded to a 4-inch SDR 35 PVC sewer pipe meeting current plumbing and wastewater conveyance standards. The new pipe will connect to an existing 6-inch sewer main and interior plumbing fixtures, including one toilet, two sinks, one bathtub, and one laundry outlet at each housing unit.

2. PROJECT LOCATION:

1. Boulder Beach Housing Unit 402 and 403

402 - 403 Lakeshore Rd, Boulder City, NV 89005 GPS Coordinates 36.044417, -114.814421

3. PROJECT TASKS

The contractor shall furnish all labor, materials, equipment, and supervision to perform the following:

1) Site Preparation and Mobilization

a) Mobilize tools, equipment, and personnel to the site.

b) Coordinate site access, schedule, and utility locates with NPS.

c) Protect adjacent infrastructure, buildings, and utilities during all phases of work.

2) Demolition and Removal

a) Carefully expose and remove approximately 234 linear feet of 3-inch ductile iron sewer lateral (117 LF per unit).

b) Manually excavate ~27 LF per unit under crawl spaces.

c) Properly dispose of pipe and related demolition materials per local/state regulations.

3) C. Trenching and Excavation

a) Excavate trenches to a depth of 2 feet per design specifications.

b) Trenching under crawlspaces shall be conducted manually (~54 LF total).

c) Machine trenching is permitted in accessible open ground (~180 LF).

d) Sawcut approximately 25 SF of asphalt for trenching through paved driveways.

4) D. Pipe Installation

a) Supply and install approximately 234 linear feet of 4-inch SDR 35 PVC sewer lateral.

b) Maintain minimum slope of 1/8 inch per foot for proper drainage.

c) Connect each lateral to the 6-inch main using proper reducer fittings.

d) Reconnect internal plumbing: 1 toilet, 2 sinks, 1 bathtub, and 1 laundry per unit.

5) E. Backfilling and Compaction

a) Backfill trenches in controlled lifts using native or approved fill.

b) Compact to prevent future settlement per local code.

c) Patch asphalt surfaces to match existing grade and finish.

6) Testing and Inspection

a) Conduct leak and flow tests for both laterals.

b) Coordinate final inspection with the NPS COR before final backfill.

7) Site Restoration and Cleanup

a) Restore all disturbed surfaces to pre-construction condition or better.

b) Remove equipment, tools, and debris from the site.

8) Contractor Use of Premises

a) Contractor shall keep the site clean, organized, and safe.

b) Designated staging areas will be assigned by the NPS COR.

c) All construction waste must be removed and disposed of properly.

d) Any NPS property damaged during construction shall be repaired at contractor’s expense.

e) COR may revoke site privileges due to non-compliance or unprofessional conduct.

9) 5. Attachments and Photos

a) Project Location Map

b) Sewer Layout Diagrams for Units 402 and 403

c) Photos of Existing Conditions

5. ATTACHMENTS AND PHOTOS

See attachments on next page.

A. Project Location Map

B. Project Photos

See photos on next page.

Photo 1: Broken section of sewer line under crawl space.

Photo 2: Approximate Map Layout of Sewer Lines at 402 and 403

Sewer Line 402

Sewer Line 403

Photo 3: Sewer Line Path Under Asphalt

Photo 4: Main Sewer Line Connection Point

End of Document