B08__A1_Pricing_Schedule.pdf

PDF 115 KB Posted

Attached to
Wapato Drop One Water Screens Federal contract opportunity
Solicitation number
140A1625R0017
Issued by
Department of the Interior Bureau of Indian Affairs Central Office

About this file

This document is a Bid Schedule for the Wapato Irrigation Project Drop 1 Pumping Plant Water Screens Project, Solicitation No. 140A1625R0017. The bid schedule details 14 line items for project work, all priced on a lump sum (LS) basis with an estimated quantity of 1 for each item. Major work components include mobilization, dewatering, canal access, demolition, structural support for screens, traveling water screens, fall arrest system, safety boom, mobile generator, gate actuators, electrical work, telecommunications, sitework, and demobilization.

The pricing schedule includes a 3% Tribal Employment Rights Ordinance addition to the subtotal, which will be applied to the total project cost. The document specifies that all costs for work not specifically mentioned in the schedule are to be included in the prices for the most applicable schedule items, and that payment for any work item will be made only once. The solicitation is issued by the Department of the Interior Bureau of Indian Affairs Central Office, with bidders expected to provide unit pricing for each project component.

View the file

Other files for this federal contract opportunity

Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Wapato Irrigation Project Drop 1 Pumping Plant Water Screens Project

Solicitation No. 140A1625R0017

Bid Schedule

B-1

SECTION B – SUPPLIES OR SERVICES AND PRICES /COSTS

Wapato Irrigation Project Drop 1 Pumping Plant Water Screens Project

B.1 SCHEDULE

Payment for the various priced items set forth in the Schedule shall constitute full compensation to the Contractor for providing all plant, equipment, machinery, materials, tools, supplies, transportation, labor and all other property, services, and expenditures for performing all operations required to complete the work in conformity with the Specifications and all other requirements of this Contract.

(1) All costs for work required by this Contract not specifically mentioned in the following Schedule; or not specifically mentioned in measurement, payment, and cost statements shall be deemed to be included in the prices for the most applicable Schedule items.

(2) When a separate item which includes furnishing of a material is provided in the Schedule, include the cost of furnishing, hauling, storing, and handling in the price offered in the Schedule for the item.

(3) When a separate item is not provided in the Schedule for furnishing a material, include the cost of furnishing, hauling, storing, and handling in the price offered in the Schedule for work for which the material is required.

(4) Payment for an item of work will be made only once. Work measured and paid for under a CLIN will not be measured and paid for under any other item of work.

Definitions:

(1) LS – Lump sum.

Item No.

Description Unit Estimated Quantity

Unit Price Bid Amount

1 Mobilization and Preparatory Work

LS 1 $

2 See below

3 Dewatering and Canal Access

LS 1 $

4 Demolition LS 1 $

Wapato Irrigation Project Drop 1 Pumping Plant Water Screens Project

Solicitation No. 140A1625R0017

Bid Schedule

B-2

Item No.

Description Unit Estimated Quantity

Unit Price Bid Amount

5 Structural Support for Screens

LS 1 $

6 Traveling Water Screens LS 1 $

7 Fall Arrest System LS 1 $

8 Safety Boom LS 1 $

9 Mobile Generator LS 1 $

10 Gate Actuators LS 1 $

11 Electrical LS 1 $

12 Telecommunications LS 1 $ 13 Sitework LS 1 $ 14 Demobilization LS 1 $

Subtotal $

2 Tribal Employment Rights Ordinance 3% $

GRAND TOTAL FOR SCHEDULE $

File details come from the government source that posted it. Updated .