This document is a Pre-Proposal Meeting Summary for the Wapato Irrigation Project Drop 1 Pumping Plant Water Screens Project, solicitation number 140A1625R0017, issued by the Bureau of Indian Affairs Office of Trust Services. The project aims to improve safety and operability at the Drop 1 Pumping Plant by installing new traveling water screens, including six bays that combine into three hydraulic pump chambers, plus a spare screen. Key project scope elements include fabricating steel structures to support the screens, adding a debris conveyance system, installing new gate actuators and automation systems, implementing a fall arrest system, upgrading site lighting, and adding a telecommunications line for auto dialer connectivity.
The project has a defined timeline with major milestones, including approved specifications for a diesel generator set and traveling water screen by August 1, 2025, limited in-canal access starting November 1, 2025, and in-canal work from November 18, 2025, to February 28, 2026. The project will involve work at the Drop 1 Pumping Plant located at 46° 29.055' North, 120° 31.420' West, with final completion and acceptance targeted for April 30, 2026. The pre-proposal meeting was held on May 15, 2025, with two parts: an initial meeting at Legends Casino Hotel and a site visit at the pumping plant, featuring presentations on project background, purpose, scope, and a facility walkthrough.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Proposal Meeting Summary
Wapato Irrigation Project Drop 1 Pumping Plant Water Screens Project
(Solicitation No. 140A1625R0017) Bureau of Indian Affairs - Office of Trust Services
Division of Water and Power
Date and Time: May 15, 2025, 08:30 AM Pacific Daylight Time
Location: Part 1: Legends Casino Hotel Yakama Room (1st Floor Conference Room) 580 Fort Rd Toppenish, WA 98948
Agenda
Part 2: Drop 1 Pumping Plant Adjacent to 520 Adams Lane Wapato, WA 98951
Time Topic Lead by Notes
Part 1 – Legends Casino Hotel
8:30 am to 9:00 am Sign-In and Introductions BIA/WIP/Jacobs Refer to sign-in sheet
9:00 am to 10:00 am Administrative Procedures BIA Contracting Officer • BIA presented Tribal Employment Rights Office (TERO) contact information
• BIA presented on administrative procedure and bidding process
10:00 am to 11:00 am Project Overview Jacobs • Jacobs presented on the Wapato Irrigation Project (WIP) background
• Jacobs presented on the Drop 1 Pumping Plant facility overview
• Jacobs presented on the project purpose
• Jacobs presented on the project scope
• Jacobs presented on excerpts taken from the project drawings
• Jacobs presented on project major milestones
11:00 am to 11:30 am General Q&A Prospective Bidders N/A
11:30 am to 1:00 pm Lunch (on your own) and Travel to Site N/A
Part 2 – Project Site (Drop 1 Pumping Plant)
1:00 pm to 1:30 pm General Facility Walk Through WIP • Walked the project site and described existing infrastructure
1:30 pm to 2:00 pm Description of Project Features Jacobs • Described project elements
2:00 pm to 2:30 pm General Q&A Prospective Bidders N/A
2:30 pm Adjournment N/A
ADDITIONAL INFORMATION REGARDING THE MEETING:
• The project site has the following location:
Latitude and Longitude Coordinates
46° 29.055’ North, 120° 31.420’ West
• Driving Directions from Legends Casino Hotel to the Drop 1 Pumping Plant Project Site o Turn left onto Fort Road and continue on Fort Road for 6.8-miles o Turn right onto Lateral A Road and continue for 7.1-miles o Turn left onto Lateral 1 Road and continue for 2.1-miles o Turn right onto Adams Lane and continue for 0.5- miles o Site will be on the right
• Personal Protective (Safety) Equipment is suggested but not required for this event at the project site. Recommended PPE includes, but is not limited to: safety vest, ear protection, eye protection, and hard hat. Attendees will be responsible for providing their own PPE.
• All Q&A at both locations to be proctored (no “side-bar” Q&A will be permitted)
Bureau of Indian Affairs Wapato Irrigation Project - Drop 1 Water Screens
Solicitation Notice ID 140A1625R0017 Pre-Proposal Meeting
May 15, 2025
Agenda
• Introductions
• TERO Office Contact
• Administrative procedures by BIA
• WIP background
• Facility overview
• Facility photos
• Project purpose
• Project scope
• Drawing excerpts
• Major milestones
• Questions
• Site visit preview
Introductions
Tribal Employment Rights Office (TERO)
• Contact Information:
Patricia Estrada, Interim TERO Director 410 S. G Street Toppenish, WA 98948
(509) 314-6701 Patricia_estrada@yakama.com TERO@yakama.com
Administrative Procedure & Bidding Process
Bid/Proposal Submittal Overview (refer to Sections L and M)
• Volume 1 – Price Proposal
• Acknowledgement of any and all amendments
• Price schedule submitted with unit prices extended
• Electronic Bid Guarantee in the amount 20% of the bid price or $3M, whichever is less
• Volume 2 – Technical Approach
• Technical approach
• Key project management / technical support
• Proposed summary schedule including critical path elements and milestones
• Relevant experience and past performance
• Example projects
Administrative Procedure & Bidding Process (Continued)
Bid Addenda Process
Procedures for Questions
• Verbal Q&A is non-binding
• Use the Q&A form in the solicitation
• Questions due: tbd*
• BIA responses shortly thereafter
Solicitation Deadline – tbd* (unless modified through addenda)
* Refer to solicitation on SAM.gov for the most current dates
Wapato Irrigation Project (WIP) Background
• Largest irrigation project in the Yakima River Basin
• BIA performs operations and maintenance
• Provides irrigation water to approximately 140,000 acres of farmland
• Estimated crop value of $458M-560M (2013)
• Construction from 1905-1948
Drop 1 Pumping Plant:
Facility Overview
• Integral part of Wapato Irrigation Project (WIP)
• Lifts water from Main Canal 90 feet into the East and West Highline Canals
• Has three 725 hp hydraulic turbine pumps with original combined pumping capacity of 163 cfs
• Has four supplemental electric 200 hp pumps each designed to convey 13 cfs
Facility Overview
Imagery Source: Jacobs Geospatial Imagery Location
Project Purpose
• Improve safety by:
• Removing manual screen cleaning
• Adding fall protection
• Adding safety boom
• Increasing site lighting
• Improve operability by automating controls and processes
Project Scope
• New traveling water screens on six bays that combine into 3 hydraulic pump chambers, plus one spare traveling water screen
• Fabricated steel structure appended onto existing concrete piers to support traveling water screens, including concrete build up
• Debris conveyance system from new traveling water screens
• New gate actuators, pedestals, stems, and automation system
• Fall arrest system
• Lighting
• Telecommunications line for auto dialer connectivity
Project Scope (Continued)
• Supply of mobile diesel generator for backup power
• Safety boom spanning canal upstream of pumping plant
• Ancillary site upgrades to support scope described
Note:
• Work affecting canal operations restricted to November 18, 2025, to
February 28, 2026
• BIA has right of way to accomplish operational work for in canal access
Excerpt from
CD-101:
Contractor staging areas
Pumping plant, Spillway/Drop Structure, Main Extension Canal Headworks
N
Excerpt from
CS-101:
Safety boom
Gravel path, grading, and concrete pad
Grading
Direct burial conduit
Traveling screens
Excerpt from SS-301:
Concrete build up
Existing trash rack
New traveling screen
Debris conveyor Fall arrest post
Excerpt from MS-102:
Existing Trash rack
New traveling screen Debris conveyor Concrete equipment pad
Excerpt from MS-301:
Actuator/operator
Threaded rodConnection to existing bracket
Excerpts from E-101:
Major Milestones
1. Approved specifications for diesel generator set: August 1, 2025
2. Approved shop drawings for traveling water screen and debris conveyance system: August 1, 2025
3. Limited in-canal access for minor work and final measurements:
November 1, 2025
4. In-canal work start: November 18, 2025
5. Functional testing complete: February 14, 2026
6. In-canal work end: February 28, 2026
7. Start of facility performance demonstration: upon canal filling by owner (after February 28, 2026)
8. Final completion and acceptance: April 30, 2026
Questions?
Site Visit Preview
1. Agenda:
• General facility walk through (30 minutes)
• Description of project features (30 minutes)
• General Q&A (30 Minutes)
• Adjournment
2. Meeting at Drop 1 Pumping plant
• Located at 46° 29.055’ North, 120° 31.420’ West
• Turn left onto Fort Road and continue to Fort Road for 6.8-miles
• Turn right onto Lateral A Road and continue for 7.1-miles
• Turn left onto Lateral 1 Road and continue for 2.1-miles
• Turn right onto Adams Lane and continue for 0.5- miles
• Site will be on the right
3. PPE: see meeting agenda
| 140A1625R0017_Pre-bid Mtg Presentation_Final.pdf |
| Bureau of Indian Affairs�Wapato Irrigation Project - Drop 1 Water Screens |
| Agenda |
| Introductions |
| Tribal Employment Rights Office (TERO) |
| Administrative Procedure & Bidding Process |
| Administrative Procedure & Bidding Process�(Continued) |
| Wapato Irrigation Project (WIP) Background |
| Drop 1 Pumping Plant: Facility Overview |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
| Slide Number 12 |
| Slide Number 13 |
| Slide Number 14 |
| Slide Number 15 |
| Slide Number 16 |
| Project Purpose |
| Project Scope |
| Project Scope (Continued) |
| Excerpt from CD-101: |
| Excerpt from CS-101: |
| Excerpt from SS-301: |
| Excerpt from MS-102: |
| Excerpt from MS-301: |
| Excerpts from E-101: |
| Major Milestones |
| Questions? |
| Site Visit Preview |
| Slide Number 29 |