This is a Statement of Work (SOW) from the National Park Service at Crater Lake National Park for the supply, delivery, and installation of a remote power pack trash compactor system.
The contractor must furnish one remote power pack unit and two 20-yard compactor/container units that are fully integrated, interchangeable, and operational upon installation. Each 20-cubic-yard container must measure 20 feet long by 8 feet wide by 8 feet high with heavy-duty steel construction, reinforced floors and sidewalls, leak-resistant design, and corrosion-resistant industrial coating. The remote power pack system shall consist of a centralized hydraulic/electrical power unit capable of operating both containers independently with quick-connect hydraulic and electrical connections that require no specialized tools for disconnection and reconnection. The system must include high-performance hydraulic pumps and motors, integrated hydraulic cylinders, fluid reservoirs, factory-installed and tested components, and 240V 3-phase 60Hz electrical service with push-button controls, emergency stop, safety interlocks, overload protection, and UL-listed components. The containers must be fully interchangeable with standardized connections and compatible with trucks rated up to 58,000 lbs GVW with 32-inch center-to-center rail spacing and typical loaded weight of approximately 34,120 lbs.
Delivery must occur fully assembled to Crater Lake National Park's Maintenance Building 14 in Klamath County, Oregon, with coordination required through the Government point of contact. The contractor shall offload, position, level, connect to electrical service, integrate the system, perform operational testing, and ensure full functionality. The system is subject to Government inspection and must meet all specifications before final acceptance. A minimum 12-month warranty covering the power pack, hydraulic system, electrical components, and containers is required. The contractor must provide operator manuals, maintenance manuals, hydraulic and electrical schematics, and parts lists. All work must comply with OSHA, NEC, EPA, and industry standards. Payment requests must be submitted electronically through the U.S. Department of Treasury's Invoice Processing Platform System (IPP) within 30 days of work completion. The Government point of contact is Nick Ryan.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8426Q0040_Amd_0001.pdf | ||
| B08_140P8426Q0040_Att04_Q-n-A_0001.pdf | ||
| Sol_140P8426Q0040.pdf | ||
| B08_140P8426Q0040_Attachment_03_Exp_PP_Form.pdf | ||
| B08_140P8426Q0040_Attachment_01_Quote_Sheet.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
NATIONAL PARK SERVICE
Crater Lake National Park
Post Office Box 7 Crater Lake, Oregon 97604
STATEMENT OF WORK (SOW)
Supply, Delivery, and Installation of Remote Power Pack Trash Compactor System (20-Yard Capacity)
1. Scope of Work The Contractor shall provide all labor, materials, equipment, transportation, supervision, and incidentals necessary to furnish, deliver, and install a Remote Power Pack Trash Compactor System consisting of:
• One (1) remote power pack unit
• Two (2) 20-yard compactor/container units
The system shall be fully integrated, interchangeable, and operational upon installation.
2. Equipment Requirements
2.1 General Description
The system shall consist of a remote power pack configuration, where a single stationary power unit operates multiple compactor containers. The system shall allow either container to be connected and operated using the same power pack.
2.2 Quantity
• One (1) Remote Power Pack Unit
• Two (2) 20-Yard Compactor Containers
2.3 Compactor Container Specifications
Each container shall meet or exceed the following minimum requirements:
• Capacity: 20 cubic yards
• Nominal Dimensions: 20 feet long x 8 feet wide x 8 feet high
• Type: Self-contained compactor container compatible with remote power pack
• Construction:
o Heavy-duty steel construction o Reinforced floor and sidewalls o Leak-resistant design suitable for wet waste
• Finish:
o Corrosion-resistant industrial coating
2.4 Remote Power Pack System Requirements
The Contractor shall provide a Remote Power Pack System with the following:
• One (1) centralized hydraulic/electrical power unit capable of operating both containers
• Designed for interchangeable use between both compactors
• Quick-connect hydraulic and electrical connections
• Ability to safely disconnect and reconnect containers without specialized tools
• Weather-resistant control panel enclosure
• System designed for outdoor, high-use conditions
2.5 Hydraulic System
• High-performance hydraulic pump and motor
• Hydraulic cylinders integrated into containers
• Fluid reservoir
• All hoses, fittings, and quick-connect couplings
• Factory installed and tested
2.6 Electrical/Power Requirements
• 240V, 3-phase, 60 Hz
• Push-button control operation
• Emergency stop
• Safety interlocks
• Overload protection
• UL-listed or equivalent components
2.7 Interchangeability Requirement
• Both containers shall be fully interchangeable with the remote power pack
• Power unit shall operate either container independently
• All connections shall be standardized across both units
• Contractor shall ensure full system compatibility
2.8 Haul Truck Compatibility Requirements
• Compatible with trucks rated up to 58,000 lbs GVW
• Typical loaded container weight: ~34,120 lbs (17.06 tons) (based on existing container configuration; used for compatibility reference)
• Rail spacing: 32 inches center-to-center
Contractor shall verify compatibility or identify deviations in proposal.
3. Delivery Requirements
• Deliver all components fully assembled (as applicable)
• Contractor shall coordinate delivery with the Government POC
• Delivery Location:
Crater Lake National Park, Klamath County, Oregon Maintenance building 14
The address below is for park headquarters. Sometimes GPS systems and digital map services do not recognize it. Try entering or selecting "Rim Village" as a town or waypoint, or entering the coordinates for park headquarters, which is 3 miles south of Rim Village:
42° 53' 48.91" North 122° 08' 03.08" West Note that the park's North Entrance is closed November 1(or earlier, if there is significant snowfall) to late May (and sometimes into June). GPS and map services may direct visitors to the North Entrance Road when it is closed. Check current conditions for road closures.
Crater Lake National Park Headquarters 1 Sager Building Crater Lake, OR 97604
Maintenance building 14 does not have a mailing address, however, 1 Sager Building is the closest.
Picture of Headquarters with a red arrow pointing to Sager, and the blue arrow pointing to the maintenance building where the trash compactor system will be installed.
4. Installation and System Integration The Contractor shall:
• Offload and place power unit and containers
• Position and level all equipment
• Connect remote power pack to electrical service
• Integrate system with both containers
• Verify operation of each container using the shared power unit
• Perform full operational testing
• Ensure system is fully functional upon completion
5. Inspection and Acceptance
• Subject to Government inspection
• Must meet all specifications
• Government may reject non-conforming equipment
• Final acceptance after successful testing of full system
6. Warranty Requirements
• Minimum 12-month warranty
• Covers:
o Power pack o Hydraulic system o Electrical components o Containers
7. Documentation Provide:
• Operator manuals
• Maintenance manuals
• Hydraulic schematics
• Electrical schematics
• Parts list
• Warranty documentation
8. Compliance Requirements Must comply with:
• OSHA
• NEC
• EPA (as applicable)
• Industry standards
9. Contractor Responsibilities
• Provide new equipment
• Ensure full compatibility of remote power pack system
• Coordinate delivery and installation
• Ensure safe setup and operation
• Provide all documentation
10. Government Responsibilities
• Provide site access
• Provide 240V electrical service
• Designate a point of contact
11. Government Point of Contact (POC)
• Name: Nick Ryan
• Contact information to be provided at time of award
12. Payment
• Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP) at https://www.ipp.gov/. The Contractor shall submit all invoices through www.ipp.gov within 30 days of work completion. Failure of the contractor to upload an attached copy of the invoice and any requested documentation through IPP.gov will result in invoice being rejected.