This document outlines requirements for a design-build contract to improve visitor safety and remediate rockfall hazards at the Paw Paw Tunnel within Chesapeake and Ohio Canal National Historical Park. Key details include:

The scope of work involves design, engineering, construction, testing, and quality assurance services to stabilize approximately 1,000 linear feet of rock slopes north of the Paw Paw Tunnel, remove fallen rock from the canal prism, and replace an existing deteriorated timber boardwalk. Design development documents are due by December 4, 2020, with construction to be completed by June 30, 2022. The contract also specifies requirements for project scheduling, meetings, submittals, construction coordination and staging, environmental and sustainability compliance, quality control, health and safety protocols, and closeout deliverables such as as-built drawings and operations/maintenance documentation.

View the file

Other files

File Type Posted
2020.08.07 Boundary SheetG1_SheetC1 - Notes Shown_0004.pdf PDF
Sol_140P2020R0109_Amd_0004.pdf PDF
B09_140P2020R0109 Amend 03.pdf PDF
Sol_140P2020R0109_Amd_0002.pdf PDF
B08_16 - CHOH 241450 HAZMAT_0001.doc DOC document
B08_13 - CHOH 241450 Past Perform Questionnaire_0001.doc DOC document
CHOH 241450 Paw Paw Tunnel Site Visit Attendees_0001.pdf PDF
B08_12 - CHOH 241450 Project Exp Questionnaire _0001.docx DOCX document
B08_14 - CHOH 241450 Proposed Equals_0001.doc DOC document
Sol_140P2020R0109_Amd_0001.pdf PDF
B08_15 - CHOH 241450 General References_0001.doc DOC document
B08_17 - CHOH Paw Paw Draft EA 508_0001.pdf PDF
B08_18 - CHOH 241450 DIVISION 1 SECTION_0001.pdf PDF
B08_5 - CHOH 241450 - Rockfall Geohazard Evaluation Report.pdf PDF
B08_6 - CHOH 241450 - Seepage Evaluation Report.pdf PDF
B08_10 - CHOH 241450 Site Access Constraints Opt.pdf PDF
B08_4 - CHOH 241450 - EX-TOPO.pdf PDF
B08_3 - CHOH 241450 - Basis of Design Report.pdf PDF
B08_2 - CHOH 241450 - FINAL SDs DRAWINGS.pdf PDF
B08_8 - Wage Determination MD20200011 6-5-20.pdf PDF
B08_9 - Price Schedule.xlsx XLSX spreadsheet
Sol_140P2020R0109.pdf PDF
B08_11 - CHOH 241450 - Pre-Application Meeting Notes - FINAL.pdf PDF
B08_140P2020R0109.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CHESAPEAKE & OHIO CANAL

NATIONAL HISTORICAL PARK

PAW PAW TUNNEL, MARYLAND

SOLICITATION 140P2020R0109

IMPROVE VISITOR SAFETY AND REMEDIATE ROCK FALL

HAZARDS AT AREA AROUND MILEPOST 155.5

(PAW PAW TUNNEL)

NEAR OLDTOWN, MARYLAND

CHOH 241450

DESIGN-BUILD (DB) PROJECT SCOPE

NATIONAL PARK SERVICE (NPS)

DENVER SERVICE CENTER (DSC)

JULY 13, 2020

Table of Contents

PROJECT INTRODUCTION

1.1 SCOPE

1.2 NPS/DSC SHAREPOINT PROJECT WEBSITE

1.3 LOCATION

1.4 BACKGROUND

1.5 DESCRIPTION

1.6 SCHEDULE

DB DESIGN DEVELOPMENT (DD) DOCUMENTS:

100% DRAFT DB CONSTRUCTION DOCUMENTS (CD):

100% COMPLETE DB CONSTRUCTION DOCUMENTS (CD):

COMPLETE STAMPED AND SIGNED DB CONSTRUCTION DOCUMENTS (CD):

CONSTRUCTION:

AS-CONSTRUCTED DRAWINGS:

1.7 NPS CONTACTS & ADDRESS:

1.8 DATA AND MATERIALS PROVIDED BY NPS

PROJECT REQUIREMENTS

2.1 GENERAL REQUIREMENTS

2.1.1 SCOPE OF WORK AND PROJECT SUMMARY/REQUIREMENTS

2.1.2 DEFINITION OF CONTRACT LINE ITEMS

2.1.3 PROGRESS PAYMENTS

2.1.4 PROJECT MEETINGS

2.1.5 PROJECT SCHEDULE

2.2 DESIGN REQUIREMENTS

2.2.1 DB DESIGN DEVELOPMENT (DD) DOCUMENTS AND DB CONSTRUCTION

DOCUMENTS (CD)

2.2.2 ENVIRONMENTAL AND SUSTAINABILITY REQUIREMENTS FOR DESIGN

(NOT USED)

2.3 CONSTRUCTION REQUIREMENTS

2.3.1 ENVIRONMENTAL AND SUSTAINABILITY REQUIREMENTS

2.3.2 SCHEDULE OF VALUES

2.3.3 CONSTRUCTION SUPPORT

2.3.4 SUBMITTALS DURING CONSTRUCTION

2.3.5 CONSTRUCTION COORDINATION

2.3.6 DIGITAL IMAGES

2.3.7 QUALITY CONTROL

2.3.8 WORKING HOUR RESTRICTIONS

2.3.9 TEMPORARY SERVICES

2.3.10 ACCESS

2.3.11 PRESERVATION OF ADJACENT FEATURES

2.3.12 EXISTING UTILITIES (NOT ANTICIPATED TO BE NEEDED)

2.3.13 HAULING RESTRICTIONS

2.3.14 ACCIDENT PREVENTION

2.3.15 TEMPORARY CONTROLS

2.3.16 FIELD ENGINEERING

2.3.17 PROJECT CLOSE-OUT

2.3.18 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

2.4 FORMS

PERFORMANCE REQUIREMENTS

3.1 DESIGN IMPERATIVES

3.2 SUSTAINABILITY

3.3 INTEGRATED DESIGN PRINCIPLES

3.4 FACILITY PERFORMANCE

3.5 ELEMENTS AND PRODUCTS

TECHNICAL REQUIREMENTS

ATTACHMENTS

PROJECT INTRODUCTION

Park Acronym and PMIS Number: CHOH 241450

Project Title: Improve Visitor Safety and Remediate Rock Fall Hazards at Milepost 155.5

(Paw Paw Tunnel)

Project Drawing Number: 412/152883

1.1 Scope

In accordance with terms and conditions of the Contract, the Design-Build (DB) Contractor shall perform the work of this Request for Proposal (RFP) for the National Park Service

(NPS) as described herein. Contractor shall provide all labor, personnel, supervision, tools, equipment, installed and consumable materials, testing devices, and each and every item of expense necessary for design-build construction services, including but not limited to: site investigation and studies, design, engineering, construction, testing, quality assurance, management, and the specific requirements set forth in the Contract.

Architect-Engineer (A/E) Services required to be performed by the DB Contractor shall be performed by licensed Engineers/Geologists registered in State of Maryland. The work of this Contract shall be performed in accordance with the Denver Service Center (DSC)

Design-Build (DB) Workflows website.

The DB homepage of the Design-Build (DB) Workflows website. includes links to design phases describing required workflow process from Predesign (PD) through Construction

Documents (CD). Each design phase webpage contains links to definitions, forms, templates, samples, and guidelines.

The DB homepage also includes links to the Design Standards and Design Deliverables sections which provide design requirements and criteria that shall be used for completing the work of this contract:

• Design Standards are arranged by discipline and/or specialty.

• DB Design Deliverables - Content and Format Requirements:

o Design phase submission requirements for:

o Technical content o Submission format (hard-copy and electronic)

In addition, the Information section has links directly to:

• Definitions: A list of terms relevant to design and construction in National Parks.

• Forms/Templates/Samples/Guidelines: A list of forms, templates, samples, and guidelines used for a typical project.

• Law/Regulations/Polices/Guidance: A list of sources for retrieving laws, regulations, policies, and guidance applicable to NPS projects.

• Quality Assurance (QA) Guideline & Review Checklists: Overview of the DSC QA

Process for reviewing Design Documents.

In case of conflict between the Contract and the DSC DB Workflows website, the Contract shall take precedence.

https://www.nps.gov/dscw/designbuild.htm https://www.nps.gov/dscw/designbuild.htm https://www.nps.gov/dscw/dstandards.htm https://www.nps.gov/dscw/del_designbuild.htm https://www.nps.gov/dscw/information.htm https://www.nps.gov/dscw/definitions.htm https://www.nps.gov/dscw/publicforms.htm https://www.nps.gov/dscw/laws-policies.htm https://www.nps.gov/dscw/qaguideline.htm

The DB Contractor remains fully responsible for determining if the standards or provisions cited on the DSC DB Workflows website have been revised or updated. Any such conflicts between the website and the identified standard or provisions shall be brought to the attention of the

Contracting Officer (CO).

1.2 NPS/DSC SharePoint Project Website

At this time the Department of Interior is changing how electronic files are shared. Due to this process, The DB Contractor shall use the a NPS supplied website or such other site as determined by the Government (such as MSTeams) for managing project communication and documentation throughout the Contract performance period, for these including the following - . Project directory.

Project correspondence.

Meeting agendas and minutes.

Contract modifications and logs (if any).

RFI form and processing (if any).

Task and issue management.

Photo documentation.

Baseline schedule, schedule updates and calendar management.

Submittal form and processing.

Progress payment coordination documentation.

Drawing and specification document hosting, viewing, and updating.

Online document collaboration.

Reminder and tracking functions.

Archiving functions.

Notification of submittal and RFI statuses and current responsible party.

Some documents however are not suitable to be shared websites. Documents containing Personal

Identifying Information (PII) (i.e. certified payrolls) shall not be shared and shall be coordinated with the project team as appropriate.

1.3 Location

The project is located in in Oldtown, Allegany County, Maryland within the Chesapeake and

Ohio (C&O) Canal National Historical Park (NHP) in and around milepost 155.5, which is accessed from the Paw Paw Tunnel Campground located off of Oldtown Road SE. See Sheet G1

– Construction Access of the site plans for information regarding alternatives for access to the project site.

1.4 Background

The canal tunnel was constructed by the Chesapeake & Ohio Company to allow boats to bypass a 6- mile long sinuous stretch of the Potomac River near mile post 155, known as the ‘Paw Paw

Bends’, and the adjacent steep cliffs on their way to Cumberland, Maryland. The tunnel was constructed between 1836 and 1850 and remained in operation until 1924 when it fell into disuse. The canal was purchased by the Federal Government in 1938 and by the early 1950’s, plans were being developed to repurpose the canal into a non-motorized recreational trail. In the mid-1950’s, the National Park Service started making improvements to stabilize and repair the condition of the tunnel and the towpath, and these efforts continue today.

This section of the canal and the tunnel follows the valley of Mill Run, a former tributary of the

Potomac River. Mill Run generally followed the alignment of a geologic fold axis (i.e. anticlinal fold) in the bedrock. North of the tunnel, the canal was created by deepening and widening the valley through predominantly shale bedrock. The excavation for the canal cuts across the anticlinal axis of the fold at an oblique angle exposing potentially unstable rock slope conditions on both the east and west sides of the canal prism. Historic landslides and rockfall events have occurred within the canal prism since its construction.

In 2017-2019, the National Park Service took measures to stabilize the east slope of the canal prism. This stabilization effort included rock scaling, and installation of rock bolts, shear blocks, barrier fences (installed in 2013), and weep drains. This project builds upon that project by stabilizing the landslide area on the west slope of the canal prism and providing additional stabilization support for the east slope.

1.5 Description

The 184.5-mile C&O Canal Towpath is currently the backbone of the Potomac Heritage National

Scenic Trail network. Along with the Great Allegany Passage (GAP) trail, the towpath is part an off-road recreational trail stretching 335 miles from Pittsburgh to Washington, DC.

Approximately 250,000 people cycle the entire route annually and these numbers continue to grow each year. Cyclists have had a positive economic impact on “Canal Towns” throughout

Maryland and nearby West Virginia. Should the boardwalk at the Paw Paw Tunnel fail, there is no alternative route for the towpath. Mitigating rockslide potential and hazards helps ensure that the towpath is safe for users in years to come.

This section of the park is used heavily by hikers and cyclists on a daily basis. The condition of the rock slopes presents a significant life safety hazard for park visitors and staff. The number and size of falling rocks have increased, and visual inspections by park staff and geotechnical engineers have revealed multiple vertical fissures and cracks, as well as precariously perched stones. Mitigation of the rock fall hazard will provide for a safer visitor experience and will reduce the potential for having to close the Paw Paw Tunnel section of the trail, which is a favorite biking and camping destination for groups. In 2016, C&O Canal NHP formalized a two-mile-long hiking trail as a by-pass to the Paw Paw Tunnel; however, the trail is strenuous, extends through an area with limited emergency communications/response capability, and includes large grade changes which make traversing of it arduous. The Paw Paw Tunnel remains the only bicycle passage through the mountains of western Maryland.

This project requires the contractor to mitigate rock fall hazards along approximately 1,000 linear feet of rock face adjacent to the C&O canal towpath and historic canal prism at milepost

155 and will remove rock and debris deposited in the canal prism from a large rockslide that occurred in April 2016.

The scope of the project includes geotechnical slope stability analysis and design work for remediation of the rock slope based on the site geology and potential stabilization methods. The structural geology changes along the length of the prism due to the canal excavation through the anticlinal axis of the geologic fold, so the rock stabilization methods must be tailored to fit the conditions. Preliminary investigation suggests there are two primary modes of slope failure occurring at the site depending on the local structural geology of the shale and siltstone rock mass, as well as the slope orientation within each segment of the canal prism. Preliminary documents have observed and calculated planar failure for both the west and east canal prism slopes. Toppling and wedge failures occur in the upper portion of the east slope and rock cuts above the north tunnel portal. The Contractor is fully responsible to evaluate the sufficiency of the preliminary work and adopt its own design to meet the performance requirement of fully stabilizing the area. While the contractor is responsible to determine its own means and methods, the preliminary information suggests that rock stabilization methods may include rock scaling, pattern and spot rock bolts, pinned mesh, weep drains, and shear blocks. This project requires the Contractor to deliver a slope stabilization program integrating all interrelated activities, including but not limited to, geotechnical engineering, environmental considerations, safety issues, construction methods and costs, and contracting procedures to ensure safe operation and maintenance of the project area in accordance with park objectives for this site.

In addition, the timber boardwalk towpath within the project area is in poor condition and is to be removed and replaced as part of the project.

1.6 Schedule

The Contractor shall complete all work within the Contract period of performance according to following milestone schedule which may only be amended by written modification by the

Contracting Officer. The period of performance is stated in the Solicitation, Box 11 and is approximately 18-months from notice-to-proceed.

DB Design Development (DD) Documents:

Submit Design Development Documents no later than December 4, 2020

100% Draft DB Construction Documents (CD):

Continue work on 100% Draft Construction Documents during DB Design Development

Documents review. After receiving DB Design Development review comments, address and incorporate comments in 100% Draft DB Construction Documents.

Submit 100% Draft Construction Documents and responses to NPS Review form with responses to DB Design Development Documents no later than 45 calendar days after submitting DB

Design Development Documents.

100% Complete DB Construction Documents (CD):

Submit 100% Complete DB Construction Documents and NPS Review form with responses to

100% Draft DB Construction Documents review comments no later than February 12, 2021.

Complete Stamped and Signed DB Construction Documents (CD):

Submit Complete Stamped and Signed DB Construction Documents and NPS Review form with responses to 100% Complete DB Construction Documents review comments no later than March

12, 2021. Reference in the Solicitation to “Final Design” means the 100% Complete DB

Construction Documents.

Construction:

Construction begins when Contracting Officer issues construction Notice-to-Proceed.

Complete construction no later than June 30, 2022.

As-Constructed Drawings:

Complete As-Constructed Drawings no later than 15 calendar days after Substantial Completion.

Submit DB Design Development (DD) Documents, DB Construction Documents (CD), and As-

Constructed Drawings to NPS Project Manager (PM).

1.7 NPS Contacts & Address:

Contractual:

Contracting Officer (CO): Anne LaPorta, 303.969.2473, anne_laporta@nps.gov

Contract Specialist (CS): James Waller, 303.969.2488, james_waller@nps.gov

Technical:

Project Manager (PM): Dan Tower, 303.969.2553, dan_tower@nps.gov

Project Specialist (PS) (Contractor to NPS): Chris McKenna,303.969.2910, christopher_mckenna@contractor.nps.gov

Contracting Officer’s Representative (COR): Dan Tower (PM), 303.969.2553, dan_tower@nps.gov mailto:dan_tower@nps.gov mailto:dan_tower@nps.gov

Alternate Contracting Officer’s Representative (COR): TBD

C&O Canal NHP Point of Contact/Park Civil Engineer: Joe Reed, P.E., CFM, 240.291.6612, joseph_reed@nps.gov

Address of Denver Service Center (currently closed due to COVID-19):

National Park Service - Denver Service Center

12795 West Alameda Parkway

Post Office Box 25287

Denver, Colorado 80225

Points of Contact: anne_laporta@nps.gov and james_waller@nps.gov

1.8 Data and Materials Provided by NPS

NPS will provide to DB Contractor the following data and materials. (Add as attachments in

Section 5.)

ATTACHMENTS TO SOLICITATION 140P2020R0109 (see Section J):

A. 7/2/2020 Topographic Survey

B. 7/7/2020 Schematic Design Documents

C. 4/15/2020 Rockfall Geohazard Evaluation Report

D. 6/26/2020 Basis of Design Report (BDR)

E. 4/15/2020 Tunnel Seepage Evaluation Report

F. 4/15/2020 Tunnel Condition Assessment Report

G. 4/2/2020 NPS Site Access Constraints

H. 4/15/2020 Discussions with Environmental Permitting Agencies

I. TBD Draft Environmental Assessment (EA) (To be provided)

J. 7/13/2020 NPS Division 1 Specifications

TO BE PROVIDED AS TIMES NOTED:

• Historic Photographs – within 30 days of Award

• Historic Plans – within 30 days of Award

• Existing Permit Authorizations – within 30 days of Award

PROJECT REQUIREMENTS

2.1 General Requirements

2.1.1 Scope of Work and Project Summary/Requirements

The project will consist of the design and construction for remediation of rockfall hazards along

1,000 linear feet of east and west slopes north of the Paw Paw Tunnel. Removal of all fallen rock will also be included in this project. The project also includes reconstruction of an existing timber boardwalk.

The project includes, but not be limited to:

• Upon award, provide design schedule of work within the timeframe of Deliverable Dates stated in this Scope of Work.

• Perform all design-build construction services required to complete the work requirements under the Contract, including but not limited to:

o Any additional geotechnical analyses as required to complete the project.

o Provide supplemental topographic survey as required to complete project.

• Review Schematic Design documents and site data provided in the RFP package.

• Submit DB Design Development and DB Construction Documents to the NPS for review and approval.

• Submit list of required permits and obtain required permits as the authorized agent on behalf of NPS in a timely manner. The contractor is responsible to ascertain and obtain all necessary permits prior to commencing construction.

o Anticipated permits may include, but not be limited to:

▪ Maryland Department of the Environment (MDE) Waterway & Wetland

Authorization

▪ U.S. Army Corps of Engineers (USACE) Authorization under Section 404 of the

Clean Water Act and Section 10 of the Rivers and Harbor Act

▪ General Permit for Stormwater Associated with Construction Activity (NOI) from

MDE

▪ Erosion and Sediment Control (if exceeds MDE thresholds)

• Provide schedule to deliver the project within the Contract period of performance.

• Secure work area and provide for continued access to the facilities as described herein.

See the Section entitled, “Visitor Experience” below.

• Construct project

• Provide as-constructed drawings

2.1.2 Definition of Contract Line Items

Refer to Schematic Design drawings and reports for detailed descriptions of these bid items. Note that the term “Priority” in the SDs refers to “Tasks” below.

BASE BID:

CONTRACT LINE ITEM 1 - DESIGN: This item consists of A/E services, for improving visitor safety and remediating rockfall hazards along approximately 1,000 linear feet of north and south slopes north of a section of the Paw Paw Tunnel.Design work shall include but not be limited to, all work Priorities at all Rock Fall Section (RF) sections, reconstruction of existing timber boardwalk, proposed method to access the site, and remove rock offsite.

CONTRACT LINE ITEM 2 - CONSTRUCTION:

This item consists of work for improving visitor safety and remediating rockfall hazards along approximately 1,000 linear feet of north and south slopes north of a section of the Paw Paw

Tunnel, C&O Canal Mile Post 155 for work described below and at the following Rock Fall

Section (RF) sections:

This item consists of:

Task 1 – Boardwalk Demo and Reinstall

Task 2 – Remove fallen rock from canal prism RF12

Task 3 – Remove Drape, Scaling & Rock Remove, RF1 - RF10

Task 4 – Scaling, Shear Blocks, Rock Drains & Rock Removal – RF12

OPTIONAL LINE ITEMS:

CONTRACT LINE ITEM BID OPTION A - Task5 Pin Mesh RF4 - RF8, RF10:

This item consists of work improving visitor safety and remediating rockfall hazards along approximately 1,000 linear feet of north and south slopes north of a section of the Paw Paw

Tunnel, C&O Canal Mile Post 155, for work described below and at the following Rock Fall

Section (RF) sections: Task 5 - Pin Mesh RF4 - RF8, RF10.

CONTRACT LINE ITEM BID OPTION B - Task 6 – Spot Rock Bolt RF2 - RF8, RF10

This item consists of work improving visitor safety and remediating rockfall hazards along approximately 1,000 linear feet of north and south slopes north of a section of the Paw Paw

Section (RF) sections: Task 6 - Spot Rock Bolt RF2 - RF8, RF10.

CONTRACT LINE ITEM BID OPTION C - Task 7A – Maintenance Scaling RF11 approximately 1,000 linear feet of north and south slopes north of a section of the Paw Paw

Section (RF) sections: Task 7A – Maintenance Scaling RF11.

CONTRACT LINE ITEM BID OPTION D - Task 7B – Maintenance Scaling RF13 approximately 1,000 linear feet of north and south slopes north of a section of the Paw Paw

Section (RF) sections: Task 7B – Maintenance Scaling RF13.

CONTRACT LINE ITEM BID OPTION E - Task 8A – Rock bolting, drains, shear blocks RF11 approximately 1,000 linear feet of north and south slopes north of a section of the Paw Paw

Section (RF) sections: Task 8A – Rock bolting, drains, shear blocks RF11.

CONTRACT LINE ITEM BID OPTION F - Task 8B – Rock bolting, drains, shear blocks RF13 approximately 1,000 linear feet of north and south slopes north of a section of the Paw Paw

Section (RF) sections: Task 8B – Rock bolting, drains, shear blocks RF13.

2.1.3 Progress Payments

Payments shall be made in accordance with the Contract. See Solicitation, in particular but not limited to, Section titled, “ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS –

INTERNET PAYMENT PLATFORM (APR 2013).”

The following general guidelines shall apply to the work requirements but see the Contract requirements for payment:

Design Deliverables - Progress payments will be based on acceptance of design deliverables.

Construction Work - Progress payments will be based on percentage of work completed on items listed in approved schedule of values. Actual construction completed and in place will form basis for payment. DB Contractor shall verify percent complete under direction of the

Contracting Officer Representative unless Contracting Officer waives this requirement in a specific instance. DB Contractor shall make computations for payment based on Government’s verification of work completed and in place for periods which progress payments are requested.

DB Contractor shall furnish to Contracting Officer originals of field notes and other records relating to basis for payment. Contracting Officer shall determine the final amount of each progress payment. DB Contractor shall retain copies of material furnished to Contracting Officer.

2.1.4 Project Meetings

Post-Award Initial Meeting

After award of contract and acceptance of Performance and Payment bonds, Contracting Officer will arrange a design meeting with DB Contractor. Meeting agenda shall include the following as a minimum:

• Areas available for use by DB Contractor

• Access requirements of the Park

• Design schedule (minimum two, color hard copies).

• Environmental and sustainability requirements

• Natural and Cultural Resource Protection

• Payments to DB Contractor

• Review and emphasize Park needs and design objectives

• Modifications during design

• Schedule of Values

• Submittals during design

• Submittals required for construction notice-to-proceed

During the design phase, the DB Contractor shall hold weekly design progress meetings. The

DB Contractor shall prepare meeting agendas and complete meeting minutes for distribution to designated stakeholders.

Preconstruction Meeting

Submit following Part 2 Project Requirement deliverables a minimum of one week prior to

Preconstruction Meeting.

• Accident Prevention Program (APP)

• Evidence of liability insurance coverage and workman’s compensation for DB Contractor and Subcontractors

• Historic Preservation Treatment Program

• Letter designating your Project Superintendent

• List of required permits

• List of Subcontractors for project (same as proposal)

• Project Schedule with construction portion fully developed

• Quality Control Plan

• Schedule of Values

• Storm Water Pollution Prevention Plan (SWPPP) Submittal process

• Waste Management Plan

• Written statements from Subcontractors certifying compliance with applicable labor standard clauses

After 100% Complete DB Construction Documents are approved, or such other time as the

Contracting Officer may determine, and before start of construction, Contracting Officer will arrange on-site Preconstruction meeting with DB Contractor. Meeting agenda will include the following as a minimum:

• Accident reporting

• Construction schedule (Provide minimum two, color hard copies and electronic copy in software it was created in.)

• Correspondence procedures

• Jobsite safety

• Labor standards

• Lines of Authority

• Modifications

• NPS/DSC SharePoint “like” Project website

• Park Rules and Regulations

• Payroll reports

• Progress Payments

• Resolution to comments provided by NPS on the Part 2 Project Requirements

• Roles and responsibilities

• Schedule of Values

• Submittal process

Other project specific concerns:

• Integrate NPS document on access constraints.

• Preconstruction Emergency Exercise - Due to remote location and difficult access, Contractor is required to meet with local fire and rescue company (and other local emergency responders) prior to the beginning of construction and escort them to job site so they are aware of the access constraints and work that will be ongoing as part of this project.

• Conduct of Operations o On-site Work hours will generally consist of normal business working hours of 7AM to 7 PM, Monday thru Friday, except when otherwise indicated.

o Work on Saturdays, Sundays, Federal Holidays or at night may not be performed without prior consent from the contracting officer. Submit requests a minimum of 3 business days in advance of the proposed work to the Contracting Officer for approval.

o No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

o Traffic Control Plan shall be submitted by the contractor providing means to establish detours and shuttle services (see additional requirements elsewhere in the RFP).

o Weather considerations during winter months (see Section titled, “Project Schedule” below) o See (See Solicitation Clause 52.236-4 PHYSICAL DATA (APR 1984))

Progress Meetings

DB Contractor shall participate in weekly telephone conference calls with Contracting Officer and other project team members with updates to following meeting agenda items and such other items as the Government may require to coordinate and inform the Government of all work and future tasks:

• Approval of minutes of previous meetings

• Review of off-site fabrication and delivery

• Work in progress and projected

• Other business relating to work

2.1.5 Project Schedule

General: DB Contractor shall upload project schedule to NPS/DSC SharePoint “like” Project website or other designated system and provide two (2) color copies after award and before design meeting. Schedule shall include detailed design phase with design deliverable submission dates, and summary construction schedule with important milestones included for both phases.

The designer should assume that construction operations at this site, for this type of work, may only be undertaken between approximately March 1 and October 30 due to weather (See See

Solicitation Clause 52.236-4 PHYSICAL DATA (APR 1984)). For this reason, the NPS has established the period of performance as stated in the Contract, of approximately 620 days from notice to proceed for the project, which period includes A/E design and construction efforts, and ending approximately June 30, 2022. The project completion date will not change except by written modification to the Contract.

Update project schedule monthly throughout contract period until project substantial completion.

Purpose: Project schedule ensures adequate planning, coordinating, scheduling, and reporting of

DB Contractor’s progress. Project schedule will assist DB Contractor and Contracting Officer to monitor work progress, and process DB Contractor's monthly progress payment requests.

Software: Latest version of Microsoft Project, Primavera Project Planner, SureTrak, or approved equal.

Schedule Development: Project schedule shall cover entire contract period. Late finish date is same as contract’s established completion date.

DB Contractor shall use Critical Path Method (CPM) with limited use of lead or lag durations between schedule activities. DB Contractor's project schedule shall consist of procurement activities (including mobilization, submittal, and fabrication and delivery of key and long-lead procurement items) and construction activities.

DB Contractor's project schedule shall consist of, but not be limited to, the following for each activity:

• Identify activities and numbers numerically (maximum 5-digit). Number activities in increments of 10

• Concisely describe work represented by activity (maximum 48 characters). Avoid using non-standard abbreviations. Limit work related to each activity to one work trade

• Activity duration shall be in whole working days with maximum duration 15 work days each, unless otherwise approved by Contracting Officer, except for non-construction activities including mobilization, shop drawing and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing

DB Contractor shall ensure project schedule includes own work and Subcontractor work.

Project schedule shall show sequence and interdependence of activities required for complete performance of work and shall be cost and resource loaded. DB Contractor shall ensure work sequences are logical and project schedule shows a coordinated work plan. Proposed durations assigned to each activity shall be DB Contractor's best estimate of time required to complete activity, considering scope and resources planned. Resource loading of each activity shall list personnel by labor category and equipment type, and capacity proposed to complete activity in duration shown. Include permit requirements and constraints. Consider and include seasonal weather conditions in planning and scheduling of work influenced by high or low ambient temperatures and wind and/or precipitation, to ensure completion of work within contract time.

The project schedule shall clearly show where construction can occur simultaneously with design and areas where design must be completed in advance of start of construction of all or a portion of the project.

Project Schedule Updates

Monthly updates: Monthly updates of project schedule shall be an integral part and basic element of estimate upon which progress payments shall be made under this contract. If, in judgment of

Contracting Officer, DB Contractor fails or refuses to provide schedule of values and complete schedule update or revision as specified hereinafter, DB Contractor shall be deemed to have not provided required information upon which progress payment may be made and shall be subject to retainage of a portion of the payment.

Narrative: Include in report:

• Brief description of actual progress made during update period

• Actual and potential delaying activities

• Impediments to progress

• Issues related to inclement weather

• Progress toward established milestones

• Project float

• Brief description of work anticipated to be performed in next month

• Identify minor revisions to schedule for evaluation and accepted or rejected

As work progresses, indicate Actual Completion percentage for each activity. If schedule update shows late finish date after contract completion date, at a minimum, include the following in narrative with submission:

• Known delays

• Actions taken to get back on schedule

• Impediments or constraints affecting progress

Progress Payments: Update currently accepted construction schedule monthly. If DB

Contractor fails to provide monthly updates or revisions to currently accepted construction schedule, a portion of monthly payment may be retained until updates/revisions made.

Time Impact Analysis for Contract Modifications, Changes, Delays, and Contractor

Requests Requirements: When contract modifications or changes are initiated, delays are experienced, or DB Contractor revises project schedule, DB Contractor shall submit to

Contracting Officer a written time impact analysis illustrating influence of each modification, change, delay, or DB Contractor’s request on the contract time.

• Time Extensions: Activity delays shall not automatically mean an extension of contract time is warranted or due to DB Contractor. It is possible that modification, change, or delay will not affect existing critical activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of available total float that may exist within an activity chain of the project schedule, thereby not effecting the contract time. Time extensions will be granted according with terms of contract.

• Float: Float is not for exclusive use or benefit for NPS or DB Contractor. Extension of contract time is granted only to extent the equitable time adjustments to activity or activities affected by modification, change, or delay exceeds total (positive or zero) float available on a particular activity.

2.2 Design Requirements

2.2.1 DB Design Services Coordination

• Concurrently, engineers and geologists are required to begin engineering/geological assessments, compile critical information, review existing conditions, including but not limited to field surveys and review of Contract Documents (Section J of Solicitation).

• Identify areas of need and define key parameters such as codes, compliance requirements, topography, the area’s weather characteristics, usable on-site natural resources and more.

• Design should capture value to the greatest extent possible for the project while reducing risk of cost increases in the construction phase.

• Contractor and its engineering and construction resources shall work together to define elements of the project that can be designed and constructed early, thus enabling the construction to proceed while the balance of the design is being completed.

2.2.2 DB Design Development (DD) Documents and DB Construction Documents (CD)

Prepare DB Design Development Documents and DB Construction Documents using English

System of Weights and Measurements and according to DSC Design Standards and DSC Design

Deliverables - Content and Format Requirements for DB Design Development Documents and

DB Construction Documents.

List salient characteristics for products and materials specified. Refer to Guide for Specifiers.

Deliverables

The following deliverables are required (refer to Section 1.6 for schedule) for NPS Review:

All deliverables shall be submitted electronically to DSC and the Park/Region offices, pursuant to a Distribution List to be provided by the Government within 30 days of Award. Provide electronic versions in the formats stated for each design phase. In addition, hard copies for each design phase shall be submitted in the quantities required below with addresses for submitting hard copies to be provided on the Distribution List.

• DB Design Development (DD) Documents o Submit to the park/region, four (4) hard copies (4 to park and/or region) and electronic files, in native formats (no PDF (Portable Document Format) files), of the following DB Design Development Documents for review:

▪ Draft DB Design Development Drawings

▪ NPS Division 1 Specifications (in substantially the format provided in the attachments to this RFP (See Section 1.8 herein))

▪ (https://www.nps.gov/dscw/upload/Division01Specs-INSTRUCTIONS_5-6-

11_AF_120117.pdf)

▪ Divisions 2 through 49 Outline Specifications

▪ Product File

▪ Statement of Structural Tests and Special Inspections

▪ Design Calculations

• 100% Draft DB Construction Documents (CD) o Submit to the park/region, four (4) hard copies and electronic files, in native formats

(no PDF files), of the following 100% Draft DB Construction Documents for review:

▪ 100% Draft DB Construction Drawings

▪ NPS Division 1 Specifications

▪ Divisions 2 through 49 Construction Specifications (Construction

Specifications Institute (CSI) MasterFormat 04 Edition). DB Contractor shall utilize and modify their own Divisions 2 through 49 Construction

Specifications templates.

▪ Product File

▪ Statement of Structural Tests and Special Inspections

▪ Design Calculations

▪ Checklists for internal review of drawings, specifications, calculations, and cost estimates

• Required documents for each submission are included and complete per contract requirements.

https://www.nps.gov/dscw/dstandards.htm https://www.nps.gov/dscw/del_designdevelopdb.htm https://www.nps.gov/dscw/del_constructiondb.htm https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=242817 https://www.nps.gov/dscw/upload/Division01Specs-INSTRUCTIONS_5-6-11_AF_120117.pdf https://www.nps.gov/dscw/upload/Division01Specs-INSTRUCTIONS_5-6-11_AF_120117.pdf

• Required documents have been through a Quality Control (QC) review. NPS requires documentation and submittal of QC work performed.

▪ NPS Review form with responses to DB Design Development Documents review comments

• 100% Complete DB Construction Documents (CD) o Submit to the park/region four (4) hard copies (and electronic files, in native formats

(no PDF files), of the following 100% Complete DB Construction Documents for review and final approval:

▪ 100% Complete DB Construction Drawings

▪ Divisions 2 through 49 Construction Specifications

▪ Product File

▪ Statement of Structural Tests and Special Inspections

▪ NPS Project Sustainability Checklist (CD portion completed and updated)

▪ Design Calculations

▪ Checklists for internal review of drawings, specifications, calculations, and cost estimates

• Required documents for each submission are included and complete per contract requirements.

• Required documents have been through a Quality Control (QC) review. NPS requires documentation and submittal of QC work performed.

▪ NPS Review form with responses to 100% Draft DB Construction

Documents review comments

• Complete Stamped and Signed DB Construction Documents (CD) o Upon final approval of 100% Complete DB Construction Documents, Complete

Stamped and Signed DB Construction Documents shall be submitted: i) to DSC, one

(1) hard copy; and ii) to the Park/Region, four (4) hard copies (and electronic files, in native formats (no PDF files), of the following 100% Complete Stamped and

Signed DB Construction Documents (CD) o Upon final approval of 100% Complete DB Construction Documents, submit

Complete Stamped and Signed DB Construction Documents per following table for construction, NPS archiving, and general use. For format and media submission requirements, see Design Deliverables - Content and Format Requirements DB Hard

Copy and Electronic Submittal Requirements.

COMPLETE STAMPED AND SIGNED

DB CONSTRUCTION DOCUMENTS (CD)

ELECTRONIC

FORMATS *

HARD COPY

FORMATS

DB Construction Drawings ** PDF & AutoCAD Full-Size Paper

(ANSI D)

Division 1 Specifications

PDF &

MS (Microsoft)-Word

N/A

(Not Applicable) https://www.nps.gov/dscw/del_submitformatdb.htm https://www.nps.gov/dscw/del_submitformatdb.htm

Divisions 2 through 49 Construction Specifications

PDF &

MS (Microsoft)-Word

N/A

(Not Applicable)

Product File PDF N/A

Statement of Structural Tests and Special Inspections PDF & MS-Word N/A

Supplemental Design Reports if needed PDF N/A

Design Calculations PDF N/A

Checklists for internal review of drawings, specifications, calculations, and cost estimates PDF & MS-Excel N/A

NPS Review form with responses to 100% Complete DB CD review comments PDF & MS-Excel N/A

* The recipient of the electronic files is TIC (Technical Information Center).

** DB Construction Drawings shall be printed from the native software (e.g. AutoCAD .dwg or Revit .rvt).

Currently, due to the COVID pandemic, NPS is accepting electronic, stamped copies of the Construction Drawings. This could change

2.2.2 Environmental and Sustainability Requirements for Design (NOT USED)

NPS established environmental and sustainability requirements for project. Notify Contracting

Officer if conflicts arise between performance of work and environmental and sustainability requirements. NPS does not intend to limit alternative means of achieving these requirements.

For sustainability requirements for design, see Part 3 Performance Requirements and NPS

Project Sustainability Checklist. Complete checklist by concisely explaining how each credit/requirement will be met.

2.3 Construction Requirements

2.3.1 Environmental and Sustainability Requirements

Specific sustainability requirements generated in design will dictate more stringent environmental requirements for this project. Refer to Part 3 Performance Requirements and NPS

Project Sustainability Checklist. General requirements:

• Site Disturbance: Minimize construction limits of project to reduce impact on site.

• Toxic Chemicals: Avoid materials that can leach toxic chemicals into ground water. Do not allow toxic chemicals to enter sewers or storm drains or contaminate land or any body of water. Refer to NPS Project Sustainability Checklist for additional requirements.

• Soil Erosion: Protect against erosion and topsoil depletion according to Stormwater

Pollution Prevention Plan (SWPPP).

• Habitats: Protect natural habitats and ecological systems on facility site as identified in

Environmental Assessment (EA).

• Noise: Minimize noise during construction. Operate power equipment according to local/Park noise restrictions.

• Waste Management: Employ processes ensuring minimal waste output and in landfills.

Recycling is a requirement of this project. Specific recycling goals were established in

NPS Project Sustainability Checklist. Legally dispose materials unsuitable for recycling at public or private dumping areas outside the Park.

https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=387018 https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=387018

DB Contractor shall designate an on-site party (or parties) responsible for instructing workers and overseeing environmental and sustainability requirements of this project. Distribute copies of environmental and sustainability requirements to Job Site Foreman and each Subcontractor.

Waste Management Plan: Prior to scheduled Preconstruction meeting, DB Contractor shall submit draft Waste Management Plan to Contracting Officer for approval. Develop and implement according to ASTM E1609 and as required in contract documents. Plan shall include, but not be limited to:

• List of recycling facilities, reuse facilities, municipal solid waste landfills, and other disposal area(s) to be used. Include name, location, and phone number.

• List of proposed materials to be reused or recycled.

• List of materials that cannot be recycled or reused with explanation or justification.

• Storage and collection methods of waste and recyclables, handling procedures, and means of keeping recyclables free of contamination.

• Describe means of transporting recyclable materials and estimate frequency of emptying bins.

• Identity person or persons responsible for ensuring project recycling goals are achieved.

• Revise and resubmit Plan per Contracting Officer. Approval of DB Contractor’s Plan does not relieve DB Contractor of complying with applicable environmental regulations.

Progress Documentation: Supplemental to Waste Management Plan, document solid waste disposal, diversion, and cost/revenue analysis, and submit completed worksheet monthly. Use

Appendix A - Project Waste Management Plan Worksheet and report totals to date for column headings. Use Appendix B for solid waste volume to weight conversions.

Prior to commencement of work, schedule and conduct meeting with Contracting Officer.

Discuss proposed Waste Management Plan and develop mutual understanding of details of environmental protection.

Minimize Construction Impacts

Implement following mitigation measures to minimize impacts of construction activities:

Soil Erosion: Protect staging areas against erosion and topsoil depletion. SWPPP is required.

Exotic Vegetation and Noxious Weeds: Prevent introduction and minimize spread of exotic vegetation and noxious weeds. Incorporate following procedures:

• Obtain fill or additional topsoil needed from a Government approved source.

• Use NPS approved native seed and/or plants and revegetate areas disturbed by construction.

• Where seeding is required, a weed-free native grass/forb seed mix would be obtained and used in accordance with NPS policies and guidance. Management techniques would be implemented to foster rapid development of native plant growth.

• To avoid transport of nonnative species to terrestrial portions of the study area, all construction vehicles would be washed prior to use on the project and only clean and weed-free fill material would be used.

• Any equipment used for construction would be decontaminated prior to use in the canal so they are free of any vegetation, animals, mud, and any other organic material that is not native to the canal.

Vegetation Salvage and Revegetation Plan: Required for this project. For revegetation efforts, use approved native species and/or native seed and incorporate Park policies regarding vegetation and site restoration. Consider use of native species, plant salvage potential, exotic vegetation and noxious weeds, and pedestrian barriers. Policy related to revegetation will be referenced in NPS Management Policies 2006 (Section 9.1.3.2). If disturbance of vegetation occurs outside the approved limit of disturbance, for any required restoration, the contractor shall work with NPS to install appropriate replacement species or seeding.

Special Status Species: To protect unknown or undiscovered threatened, endangered, or special status species, construction contract will include provisions for these discoveries. DB Contractor should contact Park for direction to evaluate special species at the site.

State plants of concern would be located and fenced or flagged prior to construction. NPS will provide a briefing to the contractor identifying plants of concern. Contractor shall work with

NPS to avoid, reduce, and minimize impacts to plants of concern when possible.

To minimize potential impacts on northern long-eared bat habitat, removal of trees greater than

4-inches DBH is prohibited from June 1 to July 31. Contractor shall coordinate with NPS and

MD-DNR to minimize impacts to bats when possible. Of note is that the Paw Paw Tunnel is used to varying degrees for hibernating bats over the winter.

Visitor Experience: Incorporate following mitigation measures into action alternatives to minimize impacts of construction activities on visitor experience:

Contractor shall provide & maintain signage for detours, maintenance of traffic, and safety throughout the length of the project. Closure measures at either end of any closed portions of towpath within the immediate work area will be established and maintained by the contractor. A traffic control plan detailing signage for detour will be submitted by the contractor for government approval. At this time, it is assumed by the government that for the purposes of towpath closure, the immediate work area extends between the North portal of Paw Paw Tunnel and intersection of towpath with Tunnel Hill Trail. An existing pedestrian detour path used by

NPS during previous stabilization efforts in 2017 – 2019 exists over tunnel hill road to tunnel hill trail that may be used to bypass pedestrians around the immediate work area. A Minimum of 3 weeks will be provided to the park in advance of any towpath closures.

During transport of equipment and materials outside of the immediate work area along open portions of towpath construction vehicles will have shared usage with pedestrians. Any vehicles larger than a pickup truck are required to have flaggers/escorts provided by the contractor to ensure pedestrian safety.

During hauling operations, a shuttle service will be provided by the contractor to avoid any conflicts between pedestrians and construction vehicles. During the hours of hauling or high/heavy trucking activity the contractor shall provide a shuttle service to transport visitors from either end of the towpath closure. Shuttle shall be capable of transporting a minimum of 8 visitors. Shuttle shall be ADA accessible. Shuttle shall be able to transport a minimum of 8 https://www.nps.gov/policy/mp/policies.html bicycles. Shuttle shall operate during hours when hauling or high/heavy trucking activity outside of the immediate work area is anticipated. The shuttle shall run at 30 minute intervals. A schedule of shuttle routes shall be prepared and submitted to the CO for review/approval. The shuttle loading and unloading zone shall be clearly marked and approved schedule and route posted at each location. A Minimum of 3 weeks will be provided to the park in advance of the start of shuttling activities.

Any driving on the towpath must comply with the most recent version of the NPS C&O Canal

NHP Safety Officer Memo for Towpath Driving. Notable items are highlighted below:

• The maximum speed for any vehicle on the towpath is 15mph. This is under ideal conditions when the towpath is dry, there are no visitors in the area, and you have clear visibility on both side of the towpath for at least 200’ in front of you. If any of these conditions don’t exist, SLOW DOWN.

• When possible, avoid driving on the towpath when snow covered, icy, or muddy. Any damage to the towpath will be repaired by the contractor at no additional expense to the government.

• Seatbelts shall be worn at all times.

• Yield to all visitors on the towpath.

• If a visitor is coming toward you, you must pull over and come to a full stop until the visitor is completely clear of your vehicle.

• If you are approaching a visitor traveling in the same direction, us a slight tap of the horn to notify them that you are coming up. Wait for the visitor to step off the towpath to allow you to proceed and do so at a very slow speed.

• If you must park on the towpath, pull over as far as you can. Fold in your mirrors and keep doors shut except to exit and enter vehicle.

• This project area has limited communication capabilities – define alternate means to communicate between vehicles if no cell phone coverage exists.

Public access to Paw Paw Campground shall be maintained at all times through construction. No closure of the campground is currently anticipated by NPS. Measures by the contractor shall be taken to provide for visitor parking by expansion of the existing parking area (contractor shall have use of the West…