B03-Attachment_1_-_Specifications.doc

DOC document 11 MB Posted

Attached to
ACAD - REPLACE GREAT MEADOW CULVERT Federal contract opportunity
Solicitation number
140P4325R0001
Issued by
Department of the Interior National Park Service Northeast Region

About this file

I apologize, but I don't see the actual content of the specifications document in what was provided. While I can see this is meant to be an Attachment 1 - Specifications document related to replacing a Great Meadow Culvert at Acadia National Park, without access to the actual content of the specifications file, I cannot provide a detailed summary of its requirements, scope, or technical details.

View the file

Other files for this federal contract opportunity

Other files attached to ACAD - REPLACE GREAT MEADOW CULVERT, newest first.
File Type Posted
Sol_140P4325R0001_Amd_0006.pdf PDF
B09-Amendment_-_006_-RFIs_20-21_0006.xlsx XLSX spreadsheet
B09-Amendment_-_005_-RFIs_18-19_0005.xlsx XLSX spreadsheet
Sol_140P4325R0001_Amd_0005.pdf PDF
Sol_140P4325R0001_Amd_0004.pdf PDF
Sol_140P4325R0001_Amd_0003.pdf PDF
B09-Amendment_-_003_-RFIs_15-17_0003.xlsx XLSX spreadsheet
Sol_140P4325R0001_Amd_0002.pdf PDF
B09-ACAD_251732_Great_Meadow_Culvert_-_Geotech_Design_Memo_0002.pdf PDF
B09-Amendment_-_002_-RFIs_1-14-_0002.xlsx XLSX spreadsheet
Sol_140P4325R0001_Amd_0001.pdf PDF
B03-Attachment_3_-_WD-ME20240036-4_05_24-mod2.pdf PDF
B08-Attachment_6-Past_Performance_Questionnaire.doc DOC document
Sol_140P4325R0001.pdf PDF
B03-_Attachment_2_-_Drawings.pdf PDF
B08-Attachment_4_-Construction_Contract_Administration.pdf PDF
B08-Attachment_5_-_Subcontracting_Percentage_Worksheet.xlsx XLSX spreadsheet
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACADIA NATIONAL PARK

Hancock County, Maine

CULVERT REPLACEMENT AT GREAT MEADOW ACAD PMIS NO. 251732

PROJECT SPECIFICATIONS

file_0.png file_1.wmf

NATIONAL PARK SERVICE ACADIA NATIONAL PARK

ACAD-251732

TOC-1

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00Summary of Work.......................................................................................................................
01 26 01Contract Modification Procedures..............................................................................................
01 27 00Definition of Contract Line Items...............................................................................................
01 31 00Project Management and Coordination ......................................................................................
01 32 16Construction Schedule ................................................................................................................
01 33 23Submittal Procedures ..................................................................................................................
01 35 13.22Archeological Protection.............................................................................................................
01 35 23Safety Requirements ...................................................................................................................
01 40 00Quality Requirements .................................................................................................................
01 42 00References ...................................................................................................................................
01 50 00Temporary Facilities and Controls .............................................................................................
01 57 23Temporary Storm Water Pollution Prevention...........................................................................
01 67 00Product Requirements .................................................................................................................
01 73 40Execution.....................................................................................................................................
01 74 19Construction Waste Management and Disposal.........................................................................
01 77 00Closeout Procedures....................................................................................................................
01 81 13Sustainable Design Requirements for Non-LEED Projects.......................................................

DIVISION 03 – CONCRETE

03 30 98 Precast Structural Concrete

DIVISION 04 – MASONRY

04 40 30 Guardwall Stones

DIVISION 31 – EARTHWORK

31 00 00Earthwork ....................................................................................................................................
31 11 00Clearing and Grubbing................................................................................................................
31 25 00Erosion and Sedimentation Control ...........................................................................................
31 32 00Geocell Soil Stabilization System ..............................................................................................
31 37 00Riprap .........................................................................................................................................

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 01 11.53Removal of Existing Pavement Markings..................................................................................
32 01 16.71Cold Milling Asphalt Paving ......................................................................................................
32 01 17.61Sealing Cracks in Asphalt Paving...............................................................................................
32 11 23Aggregate Subbase Course Gravel .............................................................................................
32 12 16.03Asphalt Pavement........................................................................................................................
32 16 23Trails............................................................................................................................................
32 17 23Pavement Markings.....................................................................................................................
32 17 23.13Temporary Pavement Markings and Markers............................................................................
32 36 00Coir Fiber Matting for Streambed and Floodplain..................................................................... 32 36 01Coir Fiber Rolls...........................................................................................................................
32 36 02Rootwads .....................................................................................................................................
32 36 03Special Fill (Streambed Material)...............................................................................................
32 36 04Streambed Rock Features ...........................................................................................................
32 36 05Void-Filled Riprap ......................................................................................................................
32 90 00Planting........................................................................................................................................
32 91 19.14Aggregate Topsoil Course ..........................................................................................................
32 92 20Seeding ........................................................................................................................................

DIVISION 34 – TRANSPORTATION

34 01 00 Maintenance of Traffic

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 - 1

SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK PART 1 - GENERAL

SUMMARY

This Section includes the following:
Work covered by the Contract Documents.
Contractor use of premises.
Public use of site.
Work Restrictions.

WORK COVERED BY CONTRACT DOCUMENTS

Project Location: Great Meadow Culvert carrying the Park Loop Road over Cromwell Brook at the north side of Great Meadow in Acadia National Park on Mount Desert Island in Hancock County, Maine.
The Work of this contract consists of replacing the existing reinforced concrete pipe culvert with a new precast concrete box culvert incorporating stream simulation channel bottom for wildlife habitat connectivity and construction of a new nature-like weir at the outlet of Great Meadow. The major elements of work generally include:
Mobilization and demobilization.
Locating and protecting all existing utilities during construction.
Installation, maintenance, and removal of maintenance of traffic and erosion control measures.
Removal of existing guardwall stones along the south side of the Park Loop Road within the project limits and storing on site for resetting later in the project.
Maintenance of Cromwell Brook flow from Great Meadow through the existing reinforced concrete pipe culvert during construction of the new replacement precast concrete box culvert to the east of the existing culvert.
Installation of a new precast concrete box culvert and wingwalls to the east of the existing culvert, including excavation and subgrade preparation, backfilling, placement of geotextile, waterproofing, construction of new mortared stone masonry headwall and wingwall capstones, and incorporating stream-simulation channel bottom for wildlife habitat connectivity.
Construction of a new nature-like weir at the outlet of Great Meadow, including removal and stockpiling of topsoil and organic material for reuse in the project, regrading and placement of fill for berm, construction of weir, and installation of geocell reinforcement for maintenance equipment access path at top of west side of berm.

Relocation of Cromwell Brook flow from the existing culvert through the new precast concrete culvert, and rehabilitation and restoration of damaged stream channel and floodplain upstream and downstream of the culvert.

Removing the existing inlet and outlet headwall stones from the existing culvert and transporting to a storage area within the Park as directed by the Contracting Officer.
Complete removal of the existing reinforced concrete pipe culvert, including excavation and backfilling, and salvaging of any undamaged existing pipe sections to a storage area within the Park as directed by the Contracting Officer.
Full depth reconstruction of the Park Loop Road wearing surface and subgrade over the culvert within the limits shown in the Construction Drawings.
Milling and repaving of the roadway approaches within the limits shown in the Construction Drawings to match into the adjacent Park Loop Road pavement.
Construction of a pedestrian trail on the south side of the Park Loop Road to connect to the existing Great Meadow Loop Trail at the west end of the project and to the existing trail at the Great Meadow Drive intersection at the east end of the project.
Construction of a gravel parallel parking area on the south side of the Park Loop Road at the east end of the project near the Great Meadow Drive intersection.
Resetting existing guardwall stones and placing new guardwall stones on the south side of the Park Loop Road.
Placement of topsoil or loam on, and planting and revegetation of, the nature-like weir and all slopes, floodplain areas, and other disturbed areas as shown in the Construction Drawings.
This project will be constructed under a single prime contract.

CONTRACTOR USE OF SITE

General: Contractor’s use of the site for construction operations during the construction period will be limited by parking restrictions noted herein. Contractor's use of the site is also limited by the Government's right to perform work or to retain other contractors on portions of Project. The Contractor shall coordinate his/her work with other contractors working within the project area. The Contractor shall allow other contractors hired by the Government access and use of the project area insofar as this access does not directly impede the Contractor’s immediate plan of operations.
Storage of Materials: Confine storage of materials to staging area locations mutually acceptable to the Contractor and the Contracting Officer. Contractor shall not store any equipment or materials within 15ft of the edge of any active travel lane, unless it is behind temporary concrete barrier that was installed as part of the approved maintenance of traffic plan.
Preservation of Natural Features:
Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
Provide temporary barriers to protect existing trees, plants, and root zones.
Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.
Do not fasten ropes, cables, or guys to existing trees.
Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
Do not operate machinery off of existing road surfaces without approval of the contracting officer and without first placing timbers to protect ground cover from compaction and disturbance.
Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
Schedule deliveries to minimize use of driveways and entrances.
Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
Construction Camp: Establishment of a camp within the park will not be permitted.
Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

PUBLIC USE OF SITE

A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public. The Contractor’s Traffic Control Plans shall discuss/address ways to minimize impacts to the traveling public and Park visitors.

CONDUCT OF OPERATIONS

At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 72 hours in advance of the work to the Contracting Officer for approval.
No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

WORK RESTRICTIONS

On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 6 p.m., Monday through Friday, except when otherwise indicated.
Weekend and NPS Holiday Hours: No work shall be performed on the weekends and NPS holidays without prior approval.
Early Morning Hours: No work shall be performed before 7 a.m. unless approved by the Contracting Officer.
Existing Utilities
Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
Notify Contracting Officer not less than 48 hours in advance of any proposed utility interruptions.
Do not proceed with any utility interruptions without Contracting Officer’s written permission.
Disruptions to facilities outside the project limits shall be prevented by investigation of existing utilities and protection during construction. Contractor shall be responsible for all costs associated with remedy of accidental disruptions to facilities outside the project limits. Maximum utility interruption shall be four hours.

SPECIAL CONSTRUCTION REQUIREMENTS

All construction signing, fencing, erosion control measures, and traffic control measures shall be in place before starting construction.
Contractor shall coordinate Detour Route with Municipality and all local and state emergency responders. Contractor shall provide Detour Plans to the Region 4 Maine DOT office for review and approval. No work will begin until Detour Plans are approved by Maine DOT.
In coordination with the Maine DOT and the Park, the Contractor shall close the Park Loop Road between Kebo Street and Sieur de Monts and detour vehicular traffic as shown in the Detour Plan in the Construction Drawings. Unless otherwise approved by the Park, the closure may only occur between the Tuesday after Indigenous Peoples Day and May 15. Outside of any approved complete road closure period, a minimum of one lane of traffic shall be maintained on the Park Loop Road at all times during construction. Temporary lane widths shall not be less than 11.0 feet.
A 48-hour notice is required for any changes in the approved work schedule.
Do no pave or stripe when and if conditions are not suitable for paving and striping work.
A 48-hour notice is required for all paving and milling operations.
Equipment when not in use shall be shut off to minimize noise and air-pollution.
Areas of the Park damaged by the movement of the Contractor’s vehicles and equipment, or other construction operations, shall be restored as approved by the Contracting Officer, at no additional expense to the Government.
Some roads and parking areas have intersecting trails and walks that require passage of pedestrians. The Contractor’s maintenance of traffic plans shall address controls to detour and reroute pedestrian traffic through the work site safely, and to include a protected walking surface from hot asphalt if necessary.

SOILS INVESTIGATION REPORT

A. A soils investigation report is available for this project upon request.

SALVAGE OF NATIVE STONE AND EXCAVATED MATERIAL

A. All blasted ledge, native stones and all other excavated material suitable for reuse shall remain property of the Park. Separate stones from other excavated material. Transport all salvage materials that will not be reused in the project to the Park storage area at Liscomb Pit, Liscomb Pit Road off Route 233 near Eagle Lake. Place in storage piles as directed by Contracting Officer.

SALVAGE OF NATIVE VEGETATION

A. All vegetation and plantings suitable for reuse shall remain property of the Park. Prior to the commencement of work, a designee of the Park will coordinate with the Contractor to designate which existing vegetation the Contractor shall stockpile for reuse. During the project other vegetation may be selected to be salvaged. Contractor shall coordinate with the Contracting Officer to ensure proper salvage techniques are followed and salvaged vegetation is properly stored.

PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 01 11 00

ACAD - 251732

01 26 01 - 1

CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES PART 1 - GENERAL

SUMMARY
The work of this section consists of administrative and procedural requirements for contract modifications.
DEFINITIONS AND ALLOWANCES
Home Office Overhead: Allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR).
General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
Project Manager, Assistant Project Manager
Superintendent, Assistant Superintendent
Quality Control, Safety Officer, Environmental Manager, etc.
Engineers
Travel, lodging, and per diem (as established by Federal Travel Regulations)
Scheduling
Field Office Trailers and associated temporary utilities
Field office supplies
Mailing and couriers
Reproduction costs
Storage
Phones
Computers
Copiers
Personal vehicles i.e. Superintendent Pickup trucks
General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
Hoisting
Material handling
Temporary fencing

Port-a-lets Trash removal, dumpsters Barricades

Small tools
Safety supplies

Scaffolding

Daily cleaning
Traffic control
Temporary signage
Temporary heating and power
Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
Base Rate: This is the hourly rate paid directly to the worker.
Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums, such as:
Social Security
Medicare
Workers Compensation– Policy and company calculation to be made available.
FUTA– Cap Rate and percentage to be proportionally allocated over one year.
SUTA– Cap Rate and percentage to be proportionally allocated over one year.
Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
Fringe Benefits: Various non-wage compensations provided to employees such as:
Health Care Insurance Premiums
Cell Phone

Clothing

401K and Pensions
Vehicle allowances
Gas allowance
Life insurance premiums
Disability insurance
Other Fringe Benefits required under an enforceable collective bargaining agreement
Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

MODIFICATION PROPOSAL PRICING REQUIREMENTS

General:

Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
Labor:
Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work. Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
Itemize labor costs for equipment operators separate from equipment costs.
The labor cost for foremen shall only be costs for related work required for the modification.
Materials:
The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
No markup shall be applied to any material provided by the NPS.
Equipment:
Equipment used for the project must be appropriately sized for the work being performed.
Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
U.S. Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
Construction Blue Book
Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs, and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized, then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
Requests for compensation for equipment stand by time must be justified, documented, and itemized separately.
The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
Establishment and Application of Overhead and Profit Percentages:
Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit. Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead…10%
Profit……10%

Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3, E,1 above). It is the responsibility of the partners to decide on the division of revenue.

Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

PART 2 - PRODUCTS PART 3 - EXECUTION END OF SECTION 01 26 01

ACAD - 251732

01 27 00 - 1

DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS PART 1 - GENERAL

SUMMARY
The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends, and another begins.
If no contract line item exists for a portion of the work, include the costs in a related item.
Any estimated quantities of major elements of the work shown in the Contract Plans are approximate. It is the Contractor’s responsibility to visit the project site prior to bid to identify existing conditions that will affect the work and determine the quantities of all materials required to complete the work at each location.

PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION

LIST OF CONTRACT LINE ITEMS
Contract Line Item No. 1 – Base Proposal: Fixed price, lump sum, that includes all the work of this project. The Base Proposal includes all work shown in the Contract Drawings and called for in the Specifications.

END OF SECTION 01 27 00

01 31 00 - 1

PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL

SUMMARY
This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
Definitions
Construction Coordination.

Submittals

Requests for Information (RFIs).
NPS/DSC SharePoint Project Website.
Project meetings.
Environmental Coordination.

Permits

Related Requirements:
Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
Section 01 73 40 “Execution” for procedures for coordinating general installation and field- engineering services, including establishment of benchmarks and control points.
Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
DEFINITIONS
Agency with Jurisdiction
Construction Permits – Contractor Provided
Government Furnished Permits
CONSTRUCTION COORDINATION
Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
Make adequate provisions to accommodate items scheduled for later installation.
Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
Preparation of Contractor's Construction Schedule.
Preparation of the Schedule of Values.
Installation and removal of temporary facilities and controls.
Delivery and processing of submittals.
Progress meetings.
Permit requirements.
Pre-installation conferences.
Commissioning activities.
SUBMITTALS
Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
Letter designating Project Superintendent.
Construction Schedule.
A comprehensive breakdown of the Schedule of Values.
Accident Prevention Plan.
A list of Subcontractors for this project.
Written statements from subcontractors certifying compliance with applicable labor standard clauses.
Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
Waste Management Plan.
Quality Control Plan.
Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).
List of Required Construction Permits. Include the following information for each permit:
Name of Permit.
The Agency(ies) with Jurisdiction issuing the permit.
Information required from the Government to complete the permit application.
REQUESTS FOR INFORMATION (RFIs)
General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.
CO will not respond to RFIs submitted by other entities controlled by Contractor.
Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
RFI number, numbered sequentially.
Date.
RFI subject.
Specification Section number and title and related paragraphs, as appropriate.
Drawing number and detail references, as appropriate.
Field dimensions and conditions, as appropriate.
Contractor's suggested resolution.If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
Contractor's signature.
Requested date for response.
Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
RFI Form: Utilize the RFI form that can be downloaded from the Workflows website at http://www.nps.gov/dscw/con_rfi217.htm or Software-generated form with substantially the same content as indicated above, approved by the CO.
Attachments shall be electronic files in Adobe Acrobat PDF format.
Enter the general information at the top of the form.
Under the “Action” section at the bottom of the form, select “Question” then select “CMR” in the drop-down of the “Send to” box.
Enter the details of the question and attach related documents.
Select “Submit Form” at the bottom of the page.
Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.
The following are not considered to be RFIs and will receive no action:
Requests for approval of submittals.
Requests for approval of substitutions.
Requests for approval of Contractor's means and methods.
Requests for coordination information already indicated in the Contract Documents.
Requests for adjustments in the Contract Time or the Contract Sum.
Incomplete RFIs or inaccurately prepared RFIs.
CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
PROJECT MEETINGS
Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
Roles & Responsibilities/ Lines of Authority.
Park rules and regulations.
Jobsite Safety.
Resolution of comments on required Division 01 documents.
Coordination of Subcontractors.
Labor law application.

Modifications.

Payments to Contractor.
Payroll reports.
Contract time.
Liquidated damages.
Contractor Performance Evaluation.
Display of Hotline posters.
Notice to proceed.
Correspondence procedures.
NPS/DSC SharePoint Project website.
Acceptance/rejection of work.
Progress meetings.
Submittal procedures.
NPS Final Accessibility Inspection.
Environmental requirements.
Permit requirements.
As-constructed drawings
Saturday, Sunday, holiday, and night work.
Reference materials.
Value engineering.
Schedule of Values.
Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.
Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
Approval of minutes of previous meetings.
Submittal status.
Requests for information (RFI) and other issues.

Modifications.

Work in progress and projected.
Status of required inspections (Special Inspections, Accessibility, etc.)
Inspections of work in progress and projected (Special inspections,
Construction Schedule update (provide updated CPM).
Status of Project Record Drawings
Other business relating to work.
Permit requirements.
Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
ENVIRONMENTAL COORDINATION
Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.
Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:
Overview of environmental issues related to the Project.
Review of site-specific procedures and management plans:
Construction Waste Management.
Temporary Storm Water Pollution Prevention.
Pollution Prevention (P2) practices.
Compliance with environmental regulations: As specified in Regulatory Requirements. Submit Contractor 40 CFR employee training records upon request of Contracting Officer.
Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, and Storm Water Pollution Prevention Plan.

PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used) END OF SECTION 01 31 00

ACAD-251732

01 32 16 - 1

CONSTRUCTION SCHEDULE

SECTION 01 32 16 – CONSTRUCTION SCHEDULE PART 1 - GENERAL

SUMMARY
This Section consists of Construction Schedule requirements including but not limited to the following:
Schedule of Values
Construction Schedule Requirements.
Construction Schedule Updates.
Time Impact Analysis.
Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.
DEFINITIONS
Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
Predecessor Activity: An activity that precedes another activity in the network.
Successor Activity: An activity that follows another activity in the network.
Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
Float: The measure of leeway in starting and completing an activity.
Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.
Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

F.

Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.

G.

Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.3

SUBMITTALS

A.

Electronic Copies: All schedules and reports submitted shall be posted on the NPS DSC SharePoint project website, provided in the native electronic file format. It is the intent of the Government to limit the number of printed reports to only those reports determined by the project team to be essential.

B.

Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.

C.

Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show entire schedule for entire construction period.

D.

Construction Schedule Updates: On or before the 7th day preceding the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data. Provide two paper copies.

1.4

QUALITY ASSURANCE

A.

The Contractor shall meet with the Contracting Officer on the day of the preconstruction conference to go over the following:

Review software limitations, content, and format for reports.
Verify availability of qualified personnel needed to develop and update schedule.
Discuss constraints, including phasing, work stages, area separations, interim milestones, and partial Government occupancy.
Review delivery dates for Government-furnished products.
Review schedule for work of separate Government contracts.
Review time required for review of submittals and re-submittals.
Review requirements for tests and inspections by independent testing and inspecting agencies.
Review time required for completion and startup procedures.
Review time required for obtaining and activating permits.
Review and finalize list of construction activities to be included in schedule.
Review baseline schedule comments, resolve issues and progress on incorporating them.
Review procedures for updating schedule.
Discuss reporting requirements and establish a protocol for naming and transmitting electronic schedules.

Contractor's Schedule Representative: Before or at the preconstruction conference, designate an authorized representative to be responsible for the preparation and maintenance of the Construction Schedule. A resume outlining the qualifications of the Scheduler shall be submitted to the Contracting Officer for acceptance. The Scheduler shall have prepared and maintained at least 5 previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency in the use of scheduling software. The authorized representative will be responsible for preparing the Baseline Schedule, all required updates, revisions, Time Impact Analyses, and preparation of reports.

COORDINATION
Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.

Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

In developing the Construction Baseline Schedule, ensure that the Subcontractor’s work at all tiers, as well as the prime Contractor’s work, is included and coordinated.
Secure time commitments for performing critical elements of the Work from parties involved.
Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PART 2 - PRODUCTS

SCHEDULE OF VALUES
Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
Do not break down unit price items. Use only the contract price for unit price items.
The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.

An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer before the first progress payment is processed.

CONSTRUCTION SCHEDULE REQUIREMENTS
Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, cost and resource-loaded, time-scaled CPM network analysis diagram for the Work.
Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than 30 days after date established for the Notice of Award.
Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of Governments acceptance of the schedule.
Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the preliminary CPM network diagram, prepare a skeleton network to identify probable critical paths.
Activities: Indicate the estimated duration, sequence requirements, and relationship of each activity in relation to other activities.
Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.

Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.

The Construction Baseline Schedule as developed shall show the sequence and interdependence of activities required for complete performance of the work. Ensure all work sequences are logical and the Construction Baseline Schedule shows a coordinated plan of the work.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .