This is Amendment 0005 to solicitation 140P4325R0001 for the Replace Great Meadow Culvert project at Acadia National Park (ACAD). The amendment addresses RFIs 18-19 and establishes a period of performance from March 3, 2025 to March 6, 2026.

The amendment is issued by the National Park Service Northeast Region - Northeast MABO at Boston National Historical Park in the Charlestown Navy Yard. Offerors must acknowledge receipt of this amendment prior to the solicitation deadline of December 20, 2024. The amendment uses Standard Form 30 and is signed by Contracting Officer Mari Tolleson.

View the file

Other files for this federal contract opportunity

Other files attached to ACAD - REPLACE GREAT MEADOW CULVERT, newest first.
File Type Posted
Sol_140P4325R0001_Amd_0006.pdf PDF
B09-Amendment_-_006_-RFIs_20-21_0006.xlsx XLSX spreadsheet
B09-Amendment_-_005_-RFIs_18-19_0005.xlsx XLSX spreadsheet
Sol_140P4325R0001_Amd_0004.pdf PDF
Sol_140P4325R0001_Amd_0003.pdf PDF
B09-Amendment_-_003_-RFIs_15-17_0003.xlsx XLSX spreadsheet
Sol_140P4325R0001_Amd_0002.pdf PDF
B09-ACAD_251732_Great_Meadow_Culvert_-_Geotech_Design_Memo_0002.pdf PDF
B09-Amendment_-_002_-RFIs_1-14-_0002.xlsx XLSX spreadsheet
Sol_140P4325R0001_Amd_0001.pdf PDF
B03-Attachment_3_-_WD-ME20240036-4_05_24-mod2.pdf PDF
B08-Attachment_6-Past_Performance_Questionnaire.doc DOC document
B03-Attachment_1_-_Specifications.doc DOC document
Sol_140P4325R0001.pdf PDF
B03-_Attachment_2_-_Drawings.pdf PDF
B08-Attachment_4_-Construction_Contract_Administration.pdf PDF
B08-Attachment_5_-_Subcontracting_Percentage_Worksheet.xlsx XLSX spreadsheet
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P4325R0001 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Boston MA 02129-4543

PNN

Building I-1 Charlestown Navy Yard Boston National Historical Park

NPS, NER - NE MABO

12/20/20240005

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

12/20/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Header Text: Replace Great Meadow Culvert Acadia National Park (ACAD).

Amendment 0005.

RFIs 18-19

Period of Performance: 03/03/2025 to 03/06/2026

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Mari Tolleson

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .