This document is a Schedule of Values for the MRF Stormwater Treatment System, Request for Proposal (RFP) No. PW-0238, detailing pricing for a comprehensive stormwater treatment system with both permanent and temporary deployment options. The proposal covers system mobilization, equipment purchase/rental, installation, operation, maintenance, and potential reinstallation, including transportation of equipment, labor for turn-key treatment system installation, initial polymer and sand filter media loads, startup and training, and generator/fuel cell/berm mobilization. The system includes multiple 20,000-gallon open top frac tanks, a sand filter, pumps, an industrial controller, and a polymer injection system, with provisions for monthly site visits, system inspections, and polymer dosing rate adjustments.

The pricing structure is broken down into several categories with lump sum and per 30-day billing cycle rates, including pre-construction expenses, permanent and temporary system mobilization and equipment costs, operation and maintenance manual, generator and fuel cell provisions, submersible pump rental, system reinstallation, and additional extras. Each section includes a subtotal with a 10% contingency, leading to a grand total for both permanent and temporary systems. The document allows for flexibility in system deployment, with options for equipment purchase or rental, potential relocation, and additional services like tank cleaning and on-call personnel, providing a comprehensive pricing framework for the stormwater treatment system.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MRF STORMWATER TREATMENT SYSTEM

RFP No. PW-0238

SCHEDULE OF VALUES (1 of 2)

FOR PROPOSED CONTRACT TOTAL PRICE

PRE-CONSTRUCTION

1. Contract Expenses (i.e. bonds, insurance, etc.)

2. Project Planning and Coordination Price as Lump Sum: $

PERMANENT SYSTEM - SYSTEM MOBILIZATION

1. Transportation of equipment, including permits

2. Labor for installing turn-key treatment system

3. Initial 1 tote of polymer

4. Initial load of sand filter media

5. Initial startup and training

6. Mobilization of generator, fuel cell, and berm

7. Reach lift for system mobilization Included Price as Lump Sum: $

PERMANENT SYSTEM - EQUIPMENT PURCHASE (or EQUIVALENT SYSTEM)

1. Two (2) 20,000 gallon open top frac tanks

2. One (1) 20,000 gallon open top frac tank with weir

3. One (1) Sand filter

4. One (1) filter pump

5. One (1) transfer pump

6. One (1) industrial controller

7. Polymer injection system Price as Lump Sum: $

OPERATION & MAINTENANCE MANUAL

1. O&M MANUAL

Price per Lump Sum: $

OPERATION & MAINTENANCE (Wet Season billing cycle)

1. Monthly site visits

• Overall inspection of system

• Adjust polymer dosing rate as needed

2. Standard maintenance of system Price per Lump Sum: $

GENERATOR AND FUEL CELL (30-day billing cycle, 5-month period)

1. Generator to power entire treatment system

2. 250-gallon fuel cell

3. Safeguard Berm Price per 30-day billing cycle: $

SUBMERSIBLE PUMP (30-day billing cycle)

1. One (1) submersible influent pump

Price per 30-day billing cycle: $

PERMANENT SYSTEM - SYSTEM REINSTALLATION

1. Labor to breakdown system

2. Transportation of all equipment to new site

3. Labor for reinstalling turn-key treatment system at new site

4. Demobilization and transportation of generator, fuel cell, and berm to new site (at the end of wet season)

5. Tank cleaning excluded

6. Reach lift for system demobilization Included Price as Lump Sum: $

EXTRAS AND O&M AS NEEDED (DO NOT INCLUDE IN SUBTOTAL PRICE)

1. Tank cleaning $

2. Replacement tote for polymer, include freight $

3. Hourly rate of on-call personnel $

SUBTOTAL $

10% CONTINGENCY $

GRAND TOTAL $

PERMANENT SYSTEM Grand Total (Cost in Words)

MRF STORMWATER TREATMENT SYSTEM

RFP No. PW-0238

SCHEDULE OF VALUES (2 of 2)

FOR PROPOSED CONTRACT TOTAL PRICE

TEMPORARY SYSTEM - SYSTEM MOBILIZATION

1. Transportation of equipment, including permits

2. Labor for installing turn-key treatment system

3. Initial 1 tote of polymer

4. Initial load of sand filter media

5. Initial startup and training

6. Mobilization of generator, fuel cell, and berm

7. Reach lift for system mobilization Included Price as Lump Sum: $

TEMPORARY SYSTEM – EQUIPMENT (or EQUIVALENT SYSTEM) RENTAL (5-Month Period)

1. Two (2) 20,000 gallon open top frac tanks

2. One (1) 20,000 gallon open top frac tank with weir

3. One (1) Sand filter

4. One (1) filter pump

5. One (1) transfer pump

6. One (1) industrial controller

7. Polymer injection system Price per 30-day billing cycle: $

TEMPORARY SYSTEM – DEMOBILIZATION IF VENDOR WILL NOT REINSTALL

TEMPORARY SYSTEM TO PERMANENT LOCATION

1. Labor to breakdown system

2. Demobilization and transportation of generator, fuel cell, and berm off site (at the end of the wet season)

3. Transportation of all temporary system equipment off site, including permits

4. Tank cleaning included

5. Reach lift for system demobilization Included Price as Lump Sum: $

SUBTOTAL $

10% CONTINGENCY $

GRAND TOTAL $

TEMPORARY SYSTEM Grand Total (Cost in Words)

[D] Schedule of Values 1 - MRF Stormwater Treatment System - Permanent