Nampula Surgical Suite Renovation, Mozambique
Solicitation number
W912GB25RA007
Issued by

About this file

The document is a Period of Performance Clause for the Nampula Military Hospital Renovations project in Mozambique. The clause specifies that the contractor must commence work within 7 calendar days of receiving the Notice to Proceed, prosecute the work diligently, and complete the entire renovation project within 450 calendar days. The government intends to issue a single Notice to Proceed for all work associated with the project.

This renovation project is part of a design-build solicitation (W912GB25RA007) issued by the Department of the Army European Command. The project involves renovating a surgical suite in Nampula, Mozambique, with a project location at latitude 15°07'52.8"S and longitude 39°15'06.3"E. The estimated construction magnitude ranges between $500,000 and $1,000,000, and the contract will be awarded as a firm-fixed price using a best value trade-off acquisition method under full and open competition.

View the file

Other files

File Type Posted
B.08 RFP_Att 2 Conceptual Site Plan AMD1.pdf PDF
B.08 W912GB25RA0070001 - SF 30.pdf PDF
A.02 SOW_Nampula Hospital, Mozambique (dated 22 April 2025).pdf PDF
B.08 W912GB25RA007 Nampula Surgical Suite Renovation, MOZ(s)30MAY25.pdf PDF
B.08 RFP_Att 10_Bank Letter of Assurance (BLA).docx DOCX document
B.08 RFP_Att 11_Bank Letter of Guarantee (BLG).docx DOCX document
B.08 RFP_Att 1 Location Map.pdf PDF
B.08 RFP_Att 13_Past Performance Overview Sheet_Rev 19 Jan 2023.xlsx XLSX spreadsheet
B.08 RFP_Att 14_Past Performance Questionnaire PPQ.docx DOCX document
B.08 RFP_Att 6_Scope For Independent Structural Proofing.pdf PDF
B.08 RFP_Att 12_Past Performance Information Sheet_Rev 13 Feb 2023.docx DOCX document
B.08 RFP_Att 16_Instructions and Evaluation Criteria_IAF-25-0032 Nampula, MOZ v2.pdf PDF
B.08 RFP_Att 2 Conceptual Site Plan.pdf PDF
B.08 RFP_Att 4_Structural Calculations Guideline.pdf PDF
B.08 RFP_Att 3_Floor Plans.pdf PDF
B.08 RFP_Att 8_Price Schedule.docx DOCX document
B.08 RFP_Att 7_Specs Binder_Nampula Hospital, Mozambique (dated May 2024).pdf PDF
B.08 RFP_Att 5_Dedication Plaque.pdf PDF
B.08 RFP_01 22 00 Price and Payment Procedures.docx DOCX document
B.08 RFP_Att 15_Commitment Letters.docx DOCX document
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MOZ NAMPULA MILITARY HOSPITAL RENOVATIONS

NAMPULA, MOZAMBIQUE

21-April-2025

COMMENCEMENT PROSECUTION AND EXECUTION OF WORK (52.211-10)

The Contractor shall be required to (a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use no later than 450 calendar days after the contractor receives the Notice to Proceed. Any options, if awarded, shall be completed concurrently with the associated work.

The time stated for completion shall include final cleanup of the premises. The Government intends to issue a single Notice to Proceed for all work.

File details come from the government source that posted it. Updated .