B.08 RFP Att 6 - Scope For Independent Structural Proofing.pdf

PDF 123 KB Posted

Attached to
IAF-25-0004 Ndava Primary School Construction
Solicitation number
W912GB25R0041
Issued by

About this file

This document is an Attachment to a Design Build Statement of Work (SOW) for Independent Structural Proofing, dated October 2023. The attachment outlines comprehensive requirements for an independent structural engineering review process for a construction project. The scope mandates that an independent, licensed proofing engineer must review and verify all structural design calculations, drawings, and fire protection verifications, ensuring compliance with host nation building codes and regulations.

Key deliverables include a detailed proofing report documenting the review process, which must include specifics such as project description, structural system details, applicable codes, technical findings, and a final statement confirming no structural concerns. The proofing engineer must provide red-lined and stamped calculation sets and drawings, with all proofing remarks to be addressed in the final design documents. The contractor is responsible for coordinating with the proofing engineer, ensuring all conflicts of interest are disclosed, and demonstrating that all structural proofing remarks have been incorporated into the final design submittal.

View the file

Other files

File Type Posted
B.08 RFP Att 15- Price Schedule AMD1.docx DOCX document
B.08 Solicitation W912GB25R00410001 Ndava Primary School Construction.pdf PDF
B.08 SF30 W912GB25R00410001 Ndava Primary School Construction.pdf PDF
B.08 RFP Att 18 - Specs Binder (dated 05-24).pdf PDF
B.08 RFP Att 11 - Bank Letter of Guarantee Sample.docx DOCX document
B.08 RFP Att 17 - Commitment Letters.docx DOCX document
B.08 RFP Att 2 - Conceptual Site Plan.pdf PDF
B.08 RFP Att 5 - Dedication Plaque.pdf PDF
B.08 RFP Att 14 - Past Performance Questionnaire PPQ.pdf PDF
B.08 RFP Att 16 -Site Visit Attendee Worksheet.xlsx XLSX spreadsheet
B.08 RFP Att 15 - Price Schedule.docx DOCX document
B.08 RFP Att 9 - TAG13 The Design of Ventilated Improved Pit (VIP) Latrines.pdf PDF
B.08 Solicitation - W912GB25R0041(s)_27MAY25.pdf PDF
B.08 RFP Att 10 - Bank Letter of Assurance Sample.docx DOCX document
B.08 RFP Att 1 - Location Map.pdf PDF
B.08 RFP Att 3 - Conceptual Floor Plan, Section and Elevations.pdf PDF
B.08 RFP Att 12 - Past Performance Information Sheet_Rev 13 Feb 2023.docx DOCX document
B.08 RFP Att 13 - Past Performance Overview Sheet_Rev 19 Jan 2023.xlsx XLSX spreadsheet
B.08 RFP Att 7 - Gabon Standard Classroom Plan.pdf PDF
B.08 RFP Att 8 - Ventilated Improved Pit (VIP) Latrine.pdf PDF
B.08 RFP Att 4 - Structural Calculations Guideline.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT TO DESIGN BUILD SOW – SCOPE FOR INDEPENDENT STRUCTURAL PROOFING

CENAU-EC-E OCT 2023

Page | 1

I. General scope The structural calculations and drawings must be proofed by an independent proofing engineer, licensed as required for structural design in the host nation (HN) of the appropriate discipline(s)

(ie. Concrete, steel timber) at the Contractor’s expense. A complete set of proofed and stamped structural design documents as well as the final structural proofing report must be submitted with the Corrected Final design submittal. For this purpose the Contractor must coordinate early enough with the selected proofing engineer. Contractor is responsible for ensuring proofing meets all requirements of the applicable building code, and as applicable meets all requirements necessary to achieve HN permitting. The proofing engineer must be objective and independent from DOR. All conflicts of interest between the proofing engineer and the DOR must be disclosed to the COR prior to the start of the proofing process.

II. Specific scope: The proofing effort includes:

1. Proofing of the Structural Design Calculations and the verifications of structural fire protection.

2. Proofing of structural execution drawings, including but not limited to: Reinforcement drawings, structural steel drawings, structural shop drawings, etc.

3. For high seismic zones proofing of structural execution drawings shown in non-structural sheets, including but not limited to: Anchorage and bracing of non-structural components (electrical, mechanical, architectural, fire protection, etc)

III. Deliverables: This task shall include the following deliverables at the final design stage:

1. Proofing Report(s):

The proofing report(s) need(s) to clearly document the proofing effort.

The report shall list as a minimum:

A. Name, title, and address of proofing engineer Name, title, and address of designer of record

B. Project name and location C. Complete list of proofed documents

If the proofing effort consists of different review phases the report shall be updated with each phase listing all proofed documents with dates of proofing effort.

D. Project description E. Description of the structural system, including but not limited to: Foundation system, vertical forces resisting system, lateral forces resisting system, structural materials, etc.

F. Structural assumptions including but not limited to:

- Gravity Loads (dead load, live load, etc.).

- Environmental loads (wind, snow, rain, ice, etc.).

- Seismic loads and seismic design information (seismic zone, seismic design category, base shear, design spectrum, etc.).

- Soil data (allowable bearing capacity, subgrade reaction modulus, lateral earth pressures, etc.).

G. Applicable codes and regulations H. Findings:

- Interim proofing reports shall list in detail the technical findings and the required

ATTACHMENT TO DESIGN BUILD SOW – SCOPE FOR INDEPENDENT STRUCTURAL PROOFING

CENAU-EC-E OCT 2023

Page | 2 actions

- Final proofing reports shall document that all findings are addressed within the final design package.

If items still need to be addressed during execution, the report shall state so.

I. Final statement: The final statement shall summarize the proofing effort. If the proofing effort is completed the statement shall state that the proofing effort is completed and that there are no structural concerns against the execution in accordance with the proofed documents

J. Stamp and signature

2. Calculations:

Complete set of red lined proofed structural calculations with proofing remarks provided to the Contractor Designer of Record during the proofing process.

The set shall be stamped and signed on the title page by the Independent Proofing Engineer.

3. Drawings

Complete set of structural red lined drawings with proofing remarks.

The set be stamped and signed on the title page by the Independent Proofing Engineer remarks provided to the Contractor Designer of Record during the proofing process.

IV. Final design documents:

The Contractor DOR shall demonstrate at the final design submittal that all structural proofing remarks are addressed within the final design documents. The final drawings shall receive a remark indicating that the independent proofing remarks are addressed.