Other files for this federal contract opportunity
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The file's text, extracted by GovTribe without its formatting.
Year 1 Cost
| Only Yellow Cells Are To Be Populated By The Offeror | | | |
| Total Hours | 1000 | | |
| Normal Operation Labor Cost | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 10.0% | $ 35.00 | $ 3,500.00 |
| TS Escort | 70.0% | $ 30.00 | $ 21,000.00 |
| TS ECM | 10.0% | $ 25.00 | $ 2,500.00 |
| Outside Normal Operations Labor Cost - Night/Weekend | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 1.5% | $ 50.00 | $ 750.00 |
| TS Escort | 7.0% | $ 45.00 | $ 3,150.00 |
| TS ECM | 1.5% | $ 40.00 | $ 600.00 |
| | Base Year Total Cost | $ 31,500.00 |
Year 2 Cost
| Only Yellow Cells Are To Be Populated By The Offeror | | | |
| Total Hours | 1000 | | |
| Escalation Rate | 5% | | |
| Normal Operation Labor Cost | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 10.0% | $ 36.75 | $ 3,675.00 |
| TS Escort | 70.0% | $ 31.50 | $ 22,050.00 |
| TS ECM | 10.0% | $ 26.25 | $ 2,625.00 |
| Outside Normal Operations Labor Cost - Night/Weekend | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 1.5% | $ 52.50 | $ 787.50 |
| TS Escort | 7.0% | $ 47.25 | $ 3,307.50 |
| TS ECM | 1.5% | $ 42.00 | $ 630.00 |
| | Base Year Total Cost | $ 33,075.00 |
Year 3 Cost
| Only Yellow Cells Are To Be Populated By The Offeror | | | |
| Total Hours | 1000 | | |
| Escalation Rate | 5% | | |
| Normal Operation Labor Cost | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 10.0% | $ 38.59 | $ 3,858.75 |
| TS Escort | 70.0% | $ 33.08 | $ 23,152.50 |
| TS ECM | 10.0% | $ 27.56 | $ 2,756.25 |
| Outside Normal Operations Labor Cost - Night/Weekend | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 1.5% | $ 55.13 | $ 826.88 |
| TS Escort | 7.0% | $ 49.61 | $ 3,472.88 |
| TS ECM | 1.5% | $ 44.10 | $ 661.50 |
| | Base Year Total Cost | $ 34,728.75 |
Year 4 Cost
| Only Yellow Cells Are To Be Populated By The Offeror | | | |
| Total Hours | 1000 | | |
| Escalation Rate | 5% | | |
| Normal Operation Labor Cost | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 10.0% | $ 40.52 | $ 4,051.69 |
| TS Escort | 70.0% | $ 34.73 | $ 24,310.13 |
| TS ECM | 10.0% | $ 28.94 | $ 2,894.06 |
| Outside Normal Operations Labor Cost - Night/Weekend | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 1.5% | $ 57.88 | $ 868.22 |
| TS Escort | 7.0% | $ 52.09 | $ 3,646.52 |
| TS ECM | 1.5% | $ 46.31 | $ 694.58 |
| | Base Year Total Cost | $ 36,465.19 |
Year 5 Cost
| Only Yellow Cells Are To Be Populated By The Offeror | | | |
| Total Hours | 1000 | | |
| Escalation Rate | 5% | | |
| Normal Operation Labor Cost | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 10.0% | $ 42.54 | $ 4,254.27 |
| TS Escort | 70.0% | $ 36.47 | $ 25,525.63 |
| TS ECM | 10.0% | $ 30.39 | $ 3,038.77 |
| Outside Normal Operations Labor Cost - Night/Weekend | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 1.5% | $ 60.78 | $ 911.63 |
| TS Escort | 7.0% | $ 54.70 | $ 3,828.84 |
| TS ECM | 1.5% | $ 48.62 | $ 729.30 |
| | Base Year Total Cost | $ 38,288.45 |
Year 6 Cost
| Only Yellow Cells Are To Be Populated By The Offeror | | | |
| Total Hours | 1000 | | |
| Escalation Rate | 5% | | |
| Normal Operation Labor Cost | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 10.0% | $ 44.67 | $ 4,466.99 |
| TS Escort | 70.0% | $ 38.29 | $ 26,801.91 |
| TS ECM | 10.0% | $ 31.91 | $ 3,190.70 |
| Outside Normal Operations Labor Cost - Night/Weekend | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 1.5% | $ 63.81 | $ 957.21 |
| TS Escort | 7.0% | $ 57.43 | $ 4,020.29 |
| TS ECM | 1.5% | $ 51.05 | $ 765.77 |
| | Base Year Total Cost | $ 40,202.87 |
Year 7 Cost
| Only Yellow Cells Are To Be Populated By The Offeror | | | |
| Total Hours | 1000 | | |
| Escalation Rate | 5% | | |
| Normal Operation Labor Cost | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 10.0% | $ 46.90 | $ 4,690.33 |
| TS Escort | 70.0% | $ 40.20 | $ 28,142.01 |
| TS ECM | 10.0% | $ 33.50 | $ 3,350.24 |
| Outside Normal Operations Labor Cost - Night/Weekend | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 1.5% | $ 67.00 | $ 1,005.07 |
| TS Escort | 7.0% | $ 60.30 | $ 4,221.30 |
| TS ECM | 1.5% | $ 53.60 | $ 804.06 |
| | Base Year Total Cost | $ 42,213.01 |
Year 8 Cost
| Only Yellow Cells Are To Be Populated By The Offeror | | | |
| Total Hours | 1000 | | |
| Escalation Rate | 5% | | |
| Normal Operation Labor Cost | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 10.0% | $ 49.25 | $ 4,924.85 |
| TS Escort | 70.0% | $ 42.21 | $ 29,549.11 |
| TS ECM | 10.0% | $ 35.18 | $ 3,517.75 |
| Outside Normal Operations Labor Cost - Night/Weekend | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 1.5% | $ 70.36 | $ 1,055.33 |
| TS Escort | 7.0% | $ 63.32 | $ 4,432.37 |
| TS ECM | 1.5% | $ 56.28 | $ 844.26 |
| | Base Year Total Cost | $ 44,323.66 |
Year 9 Cost
| Only Yellow Cells Are To Be Populated By The Offeror | | | |
| Total Hours | 1000 | | |
| Escalation Rate | 5% | | |
| Normal Operation Labor Cost | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 10.0% | $ 51.71 | $ 5,171.09 |
| TS Escort | 70.0% | $ 44.32 | $ 31,026.56 |
| TS ECM | 10.0% | $ 36.94 | $ 3,693.64 |
| Outside Normal Operations Labor Cost - Night/Weekend | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 1.5% | $ 73.87 | $ 1,108.09 |
| TS Escort | 7.0% | $ 66.49 | $ 4,653.98 |
| TS ECM | 1.5% | $ 59.10 | $ 886.47 |
| | Base Year Total Cost | $ 46,539.85 |
Year 10 Cost
| Only Yellow Cells Are To Be Populated By The Offeror | | | |
| Total Hours | 1000 | | |
| Escalation Rate | 5% | | |
| Normal Operation Labor Cost | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 10.0% | $ 54.30 | $ 5,429.65 |
| TS Escort | 70.0% | $ 46.54 | $ 32,577.89 |
| TS ECM | 10.0% | $ 38.78 | $ 3,878.32 |
| Outside Normal Operations Labor Cost - Night/Weekend | | | |
| Labor Category | % of Total Hours | Fully Burdened Labor Rate | Total Weighted Cost |
| TS CST | 1.5% | $ 77.57 | $ 1,163.50 |
| TS Escort | 7.0% | $ 69.81 | $ 4,886.68 |
| TS ECM | 1.5% | $ 62.05 | $ 930.80 |
| | Base Year Total Cost | $ 48,866.84 |
Total Price
| Year 1 Total Cost | $ 31,500.00 |
| Year 2 Total Cost | $ 33,075.00 |
| Year 3 Total Cost | $ 34,728.75 |
| Year 4 Total Cost | $ 36,465.19 |
| Year 5 Total Cost | $ 38,288.45 |
| Year 6 Total Cost | $ 40,202.87 |
| Year 7 Total Cost | $ 42,213.01 |
| Year 8 Total Cost | $ 44,323.66 |
| Year 9 Total Cost | $ 46,539.85 |
| Year 10 Total Cost | $ 48,866.84 |
| Total Evaluated Price | $ 396,203.61 |
File details come from the government source that posted it.