Attch1_SPEC CT Site Prep_Specs.pdf
PDF 305 KB Posted
- Attached to
- Y1DA-660-CSI-109 SPEC CT Site Prep Federal contract opportunity
- Solicitation number
- 36C25920Q0432
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attch2_SIGN IN SHEET CT-Sit Prep.pdf | ||
| Attch3_RFIs_SPEC CT Site Prep.pdf | ||
| Attch1_CT Site Prep _Site Visit Doc.pdf | ||
| Attch4_PN 660-CSI-109 100PCT Stamped - Specifications.docx | DOCX document | |
| Amendment0001_36C25920Q0432 0001.docx | DOCX document | |
| Attch2_SPEC CT Site Prep_Drawings.pdf | ||
| 36C25920Q0432_1_SOLICITATION.docx | DOCX document | |
| Attch4_Calculation Worksheet for Self-Performed and Subcontracted Work.docx | DOCX document | |
| Attch3_Past Performance Questionnaire.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date: February 26, 2020 Re: QA for Spec CT, Project #660-CSI-109
Questions from the set QA review:
Sheet GI002- General Information
1. Note 13 – Why do we have the bidding purposes clause on that note – it doesn’t seem applicable.
2. Note 20 – Please clarify what is meant when it says, “must be centered in the wall” centered which way?
Sheet AD101-Demolition Floor Plan
1. VA to coordinate the removal of the existing scanner and existing control equipment.
Sheet AD201-Demolition Reflected Ceiling Plan
No Comments
Sheet A-101-Floor Plan
1. VA to coordinate the instillation of the CT Scan.
2. The finishes are not called out on the Floor Plan and on the millwork.
3. Privacy Curtain provided by the VA.
4. VA to provide patient lift and track.
Sheet A-201-Reflected Ceiling Plan
1. VA to coordinate the addition of the patient lift system after the work on the ceiling is completed.
Sheet A-301-Floor and Wall Finish Plan
1. Stainless steel mounted plates provided by the VA
Sheet P-101-Plumbing Plan
1. There isn’t a plumbing schedule because there are no changes to the existing plumbing.
Sheet M-001-Mechanical Abbreviations and General Notes
No Comments
Sheet M-002-Mechanical Symbols and Legends
No Comments
Sheet MP101-Mechanical Piping Plans
No Comments
Sheet E-001-Symboles & Abbreviations
No Comments
Sheet ED101-Demolition Plan
1. The call outs are too light to see what they are referencing.
Sheet ED102-Electrical Demo Lighting Plan
No Comments
Sheet EL101-Electrical Lighting Plan
No Comments
Sheet EP101-Power Plans
1. The call outs are too light to see what they are referencing.
Sheet E-501-Electrical Details
No Comments
Sheet E-502-Electrical Details
No Comments
Sheet E-503-Electrical Seismic Details
No Comments
Sheet E-504-Electrical Seismic Details
No Comments
Sheet E-601-One-Line Diagrams & Phase Diagrams
No Comments
Sheet E-602-Electrical Schedules
No Comments
Sheet E-603-Electrical Schedules
1. Fix the text overlap in Schedule MP
Overall Comments: There are no finishes called out on this set of plans. There needs to be finishes that are required with the bid set to insure a proper bid.