Questions & Answers for RFP 36C259-19-R-0071, Replace ER Flooring:

(Q 1).) Drawing A-101, note 9 mentions to provide a Class 2 Infection control barrier. Are the specific specs for the barrier, similar to note 8 on drawing AD101?

(A 1). Specifications have been attached

(Q 2). Drawing A-101, shows a section/detail callout 2/A-101 in the floor plan, however we don't see detail 2. Is there a detail drawing for this callout?

(A 2). The callout is referring to diagram 2 which is the millwork elevation along with key note 4.

(Q 3). Note 7 on sheet A101: Seal Existing Door per requirements of Spec Section 01 35 26

“Safety Requirements. Question: Where is this Spec Section available?

(A 3). The Specifications have been attached.

(Q 4). Will there be any requirements for Lead Shielding for Radiation at the temporary infectious control walls. Reference notes 3 and 9/A101.

(A 4). If needed. The temporary wall should be removed before the new scanner is installed.

(last question – total of 4)