IDIQ OP

DRAFT

Joint Navigation Warfare Center (JNWC) IV

RFP: FA2518-22-R-0027

Section J Attachment 9: FPIF Monthly Invoicing Worksheet NOTE: This attachment is for informational purposose ONLY. It is used to identfy how the FPIF will be administered on a monthly basis and is NOT required for proposal submission.

EXAMPLE: Illistration not meant to be a representation of all Task Oders
12345678910
IDIQBASIC ORDERING PERIODOPTIONAL ORDER PERIOD
TO #1
base periodOY1OY2OY3OY4
TO #2
base periodOY1OY2OY3OY4
0Base +4
0Monthly

Instructions

Will be completed prior to final RFP release

Cumulative Annual Summary

RWW FPIF with: Target Cost $700,000; Target Profit $70,000; Target Price $770,000; Ceiling Price $840,000. Share 50/50 Under & 50/50 Over.

Target Cost$ 700,000
Target Profit %/$10.00%$ 70,000
Target Price$ 770,000
Ceiling %/$120.00%$ 840,000
Assigned Shares
Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target50.0%/50.0%
Over Target50.0%/50.0%
Calculated Shares
Desktop Williams: For calculated shares to be used, any assigned shares above must be cleared.CostProfit
Optimistic

DAU User: Optimistic cost must be less than target cost and optimistic profit must be greater than target profit.

Pessimistic DAU User: Pessimistic cost must be greater than target cost and pessimistic profit must be less than target profit.

Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target/
Over Target/

Point of Total Assumption (PTA) $ 840,000

Final Actual Audited Allowable Cost: $ 696,500

Final Contract Price: $ 768,250

Final Contractor Profit (Loss): $ 71,750

Final Contractor Profit (Loss) %: 10.30%

Example purposes only to show how annual/monthly FPIF math will work. Offerors are highly encouraged to experiment with this spreadsheet to familiarize themselves with how it is anticipated to work.

Govt/Ktr
50%50%Under505050/50 Under
50%50%Over505050/50 Over
Under TargetTarget-PTACeiling
CostProfit/(Loss)CostProfit/(Loss)CostProfit
left Scaler$ 700,000$ 70,000$ 700,000$ 70,000$ 840,000$ - 0
2$ 420,000$ 210,000$ 840,000$ - 0right scaler$ 840,0000
1$ 980,000$ (140,000)
$ 980,000$ (140,000)
Final Cost - Profit (Loss)Final Price horizontalDollar Text
CostProfit/(Loss)CostProfit/(Loss)Target Cost$700,000
$ 696,500$ 71,7500$ 71,750Target Profit$70,000
$ 696,5000$ 696,500$ 71,750Target Price$770,000
Ceiling Price$840,000

Target-PTA

700000840000700000Ceiling
84000084000098000098000000-140000-140000Under Target70000042000070000210000Final Cost - Profit (Loss)
696500696500717500Final Price horizontal
06965007175071750Analyst Notes

Annual Math

RWW FPIF with: Target Cost $700,000; Target Profit $70,000; Target Price $770,000; Ceiling Price $840,000. Share 50/50 Under & 50/50 Over.

Target Cost$ 700,000
Target Profit %/$10.00%$ 70,000
Target Price$ 770,000
Ceiling %/$120.00%$ 840,000
Assigned Shares
Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target50.0%/50.0%
Over Target50.0%/50.0%
Calculated Shares
Desktop Williams: For calculated shares to be used, any assigned shares above must be cleared.CostProfit
Optimistic

DAU User: Optimistic cost must be less than target cost and optimistic profit must be greater than target profit.

Pessimistic DAU User: Pessimistic cost must be greater than target cost and pessimistic profit must be less than target profit.

Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target/
Over Target/

Point of Total Assumption (PTA) $ 840,000

Final Actual Audited Allowable Cost: $ 696,500

Final Contract Price: $ 768,250

Final Contractor Profit (Loss): $ 71,750

Final Contractor Profit (Loss) %: 10.30%

Example purposes only to show how annual/monthly FPIF math will work. Offerors are highly encouraged to experiment with this spreadsheet to familiarize themselves with how it is anticipated to work.

Govt/Ktr
50%50%Under505050/50 Under
50%50%Over505050/50 Over
Under TargetTarget-PTACeiling
CostProfit/(Loss)CostProfit/(Loss)CostProfit
left Scaler$ 700,000$ 70,000$ 700,000$ 70,000$ 840,000$ - 0
2$ 420,000$ 210,000$ 840,000$ - 0right scaler$ 840,0000
1$ 980,000$ (140,000)
$ 980,000$ (140,000)
Final Cost - Profit (Loss)Final Price horizontalDollar Text
CostProfit/(Loss)CostProfit/(Loss)Target Cost$700,000
$ 696,500$ 71,7500$ 71,750Target Profit$70,000
$ 696,5000$ 696,500$ 71,750Target Price$770,000
Ceiling Price$840,000

Target-PTA

700000840000700000Ceiling
84000084000098000098000000-140000-140000Under Target70000042000070000210000Final Cost - Profit (Loss)
696500696500717500Final Price horizontal
06965007175071750Analyst Notes

Base Aug 2023

RWW FPIF with: Target Cost $100,000; Target Profit $10,000; Target Price $110,000; Ceiling Price $120,000. Share 50/50 Under & 50/50 Over.

Target Cost100,000
Target Profit %/$10.00%$ 10,000
Target Price$ 110,000
Ceiling %/$120.00%$ 120,000
Assigned Shares
Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target50.0%/50.0%
Over Target50.0%/50.0%
Calculated Shares
Desktop Williams: For calculated shares to be used, any assigned shares above must be cleared.CostProfit
Optimistic

DAU User: Optimistic cost must be less than target cost and optimistic profit must be greater than target profit.

Pessimistic DAU User: Pessimistic cost must be greater than target cost and pessimistic profit must be less than target profit.

Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target/
Over Target/

Point of Total Assumption (PTA) $ 120,000

Final Actual Audited Allowable Cost: $ 90,000

Final Contract Price: $ 105,000

Final Contractor Profit (Loss): $ 15,000

Final Contractor Profit (Loss) %: 16.67%

Example purposes only to show how annual/monthly FPIF math will work. Offerors are highly encourage to experiment with this spreadsheet to familiarize themselves with how it is anticipated to work.

Govt/Ktr
50%50%Under505050/50 Under
50%50%Over505050/50 Over
Under TargetTarget-PTACeiling
CostProfit/(Loss)CostProfit/(Loss)CostProfit
left Scaler$ 100,000$ 10,000$ 100,000$ 10,000$ 120,000$ - 0
2$ 60,000$ 30,000$ 120,000$ - 0right scaler$ 120,0000
1$ 140,000$ (20,000)
$ 140,000$ (20,000)
Final Cost - Profit (Loss)Final Price horizontalDollar Text
CostProfit/(Loss)CostProfit/(Loss)Target Cost$100,000
$ 90,000$ 15,0000$ 15,000Target Profit$10,000
$ 90,0000$ 90,000$ 15,000Target Price$110,000
Ceiling Price$120,000

Target-PTA

100000120000100000Ceiling
12000012000014000014000000-20000-20000Under Target100000600001000030000Final Cost - Profit (Loss)
9000090000150000Final Price horizontal
0900001500015000Analyst Notes

Sep 2023

RWW FPIF with: Target Cost $100,000; Target Profit $10,000; Target Price $110,000; Ceiling Price $120,000. Share 50/50 Under & 50/50 Over.

Target Cost100,000
Target Profit %/$10.00%$ 10,000
Target Price$ 110,000
Ceiling %/$120.00%$ 120,000
Assigned Shares
Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target50.0%/50.0%
Over Target50.0%/50.0%
Calculated Shares
Desktop Williams: For calculated shares to be used, any assigned shares above must be cleared.CostProfit
Optimistic

DAU User: Optimistic cost must be less than target cost and optimistic profit must be greater than target profit.

Pessimistic DAU User: Pessimistic cost must be greater than target cost and pessimistic profit must be less than target profit.

Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target/
Over Target/

Point of Total Assumption (PTA) $ 120,000

Final Actual Audited Allowable Cost: $ 100,000

Final Contract Price: $ 110,000

Final Contractor Profit (Loss): $ 10,000

Final Contractor Profit (Loss) %: 10.00%

Example purposes only to show how annual/monthly FPIF math will work. Offerors are highly encouraged to experiment with this spreadsheet to familiarize themselves with how it is anticipated to work.

Govt/Ktr
50%50%Under505050/50 Under
50%50%Over505050/50 Over
Under TargetTarget-PTACeiling
CostProfit/(Loss)CostProfit/(Loss)CostProfit
left Scaler$ 100,000$ 10,000$ 100,000$ 10,000$ 120,000$ - 0
2$ 60,000$ 30,000$ 120,000$ - 0right scaler$ 120,0000
1$ 140,000$ (20,000)
$ 140,000$ (20,000)
Final Cost - Profit (Loss)Final Price horizontalDollar Text
CostProfit/(Loss)CostProfit/(Loss)Target Cost$100,000
$ 100,000$ 10,0000$ 10,000Target Profit$10,000
$ 100,0000$ 100,000$ 10,000Target Price$110,000
Ceiling Price$120,000

Target-PTA

100000120000100000Ceiling
12000012000014000014000000-20000-20000Under Target100000600001000030000Final Cost - Profit (Loss)
100000100000100000Final Price horizontal
01000001000010000Analyst Notes

Oct 2023

RWW FPIF with: Target Cost $100,000; Target Profit $10,000; Target Price $110,000; Ceiling Price $120,000. Share 50/50 Under & 50/50 Over.

Target Cost100,000
Target Profit %/$10.00%$ 10,000
Target Price$ 110,000
Ceiling %/$120.00%$ 120,000
Assigned Shares
Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target50.0%/50.0%
Over Target50.0%/50.0%
Calculated Shares
Desktop Williams: For calculated shares to be used, any assigned shares above must be cleared.CostProfit
Optimistic

DAU User: Optimistic cost must be less than target cost and optimistic profit must be greater than target profit.

Pessimistic DAU User: Pessimistic cost must be greater than target cost and pessimistic profit must be less than target profit.

Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target/
Over Target/

Point of Total Assumption (PTA) $ 120,000

Final Actual Audited Allowable Cost: $ 104,000

Final Contract Price: $ 112,000

Final Contractor Profit (Loss): $ 8,000

Final Contractor Profit (Loss) %: 7.69%

Example purposes only to show how annual/monthly FPIF math will work. Offerors are highly encouraged to experiment with this spreadsheet to familiarize themselves with how it is anticipated to work.

Govt/Ktr
50%50%Under505050/50 Under
50%50%Over505050/50 Over
Under TargetTarget-PTACeiling
CostProfit/(Loss)CostProfit/(Loss)CostProfit
left Scaler$ 100,000$ 10,000$ 100,000$ 10,000$ 120,000$ - 0
2$ 60,000$ 30,000$ 120,000$ - 0right scaler$ 120,0000
1$ 140,000$ (20,000)
$ 140,000$ (20,000)
Final Cost - Profit (Loss)Final Price horizontalDollar Text
CostProfit/(Loss)CostProfit/(Loss)Target Cost$100,000
$ 104,000$ 8,0000$ 8,000Target Profit$10,000
$ 104,0000$ 104,000$ 8,000Target Price$110,000
Ceiling Price$120,000

Target-PTA

100000120000100000Ceiling
12000012000014000014000000-20000-20000Under Target100000600001000030000Final Cost - Profit (Loss)
10400010400080000Final Price horizontal
010400080008000Analyst Notes

Nov 2023

RWW FPIF with: Target Cost $100,000; Target Profit $10,000; Target Price $110,000; Ceiling Price $120,000. Share 50/50 Under & 50/50 Over.

Target Cost100,000
Target Profit %/$10.00%$ 10,000
Target Price$ 110,000
Ceiling %/$120.00%$ 120,000
Assigned Shares
Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target50.0%/50.0%
Over Target50.0%/50.0%
Calculated Shares
Desktop Williams: For calculated shares to be used, any assigned shares above must be cleared.CostProfit
Optimistic

DAU User: Optimistic cost must be less than target cost and optimistic profit must be greater than target profit.

Pessimistic DAU User: Pessimistic cost must be greater than target cost and pessimistic profit must be less than target profit.

Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target/
Over Target/

Point of Total Assumption (PTA) $ 120,000

Final Actual Audited Allowable Cost: $ 98,000

Final Contract Price: $ 109,000

Final Contractor Profit (Loss): $ 11,000

Final Contractor Profit (Loss) %: 11.22%

Example purposes only to show how annual/monthly FPIF math will work. Offerors are highly encouraged to experiment with this spreadsheet to familiarize themselves with how it is anticipated to work.

Govt/Ktr
50%50%Under505050/50 Under
50%50%Over505050/50 Over
Under TargetTarget-PTACeiling
CostProfit/(Loss)CostProfit/(Loss)CostProfit
left Scaler$ 100,000$ 10,000$ 100,000$ 10,000$ 120,000$ - 0
2$ 60,000$ 30,000$ 120,000$ - 0right scaler$ 120,0000
1$ 140,000$ (20,000)
$ 140,000$ (20,000)
Final Cost - Profit (Loss)Final Price horizontalDollar Text
CostProfit/(Loss)CostProfit/(Loss)Target Cost$100,000
$ 98,000$ 11,0000$ 11,000Target Profit$10,000
$ 98,0000$ 98,000$ 11,000Target Price$110,000
Ceiling Price$120,000

Target-PTA

100000120000100000Ceiling
12000012000014000014000000-20000-20000Under Target100000600001000030000Final Cost - Profit (Loss)
9800098000110000Final Price horizontal
0980001100011000Analyst Notes

Dec 2023

RWW FPIF with: Target Cost $100,000; Target Profit $10,000; Target Price $110,000; Ceiling Price $120,000. Share 50/50 Under & 50/50 Over.

Target Cost100,000
Target Profit %/$10.00%$ 10,000
Target Price$ 110,000
Ceiling %/$120.00%$ 120,000
Assigned Shares
Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target50.0%/50.0%
Over Target50.0%/50.0%
Calculated Shares
Desktop Williams: For calculated shares to be used, any assigned shares above must be cleared.CostProfit
Optimistic

DAU User: Optimistic cost must be less than target cost and optimistic profit must be greater than target profit.

Pessimistic DAU User: Pessimistic cost must be greater than target cost and pessimistic profit must be less than target profit.

Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target/
Over Target/

Point of Total Assumption (PTA) $ 120,000

Final Actual Audited Allowable Cost: $ 99,000

Final Contract Price: $ 109,500

Final Contractor Profit (Loss): $ 10,500

Final Contractor Profit (Loss) %: 10.61%

Example purposes only to show how annual/monthly FPIF math will work. Offerors are highly encouraged to experiment with this spreadsheet to familiarize themselves with how it is anticipated to work.

Govt/Ktr
50%50%Under505050/50 Under
50%50%Over505050/50 Over
Under TargetTarget-PTACeiling
CostProfit/(Loss)CostProfit/(Loss)CostProfit
left Scaler$ 100,000$ 10,000$ 100,000$ 10,000$ 120,000$ - 0
2$ 60,000$ 30,000$ 120,000$ - 0right scaler$ 120,0000
1$ 140,000$ (20,000)
$ 140,000$ (20,000)
Final Cost - Profit (Loss)Final Price horizontalDollar Text
CostProfit/(Loss)CostProfit/(Loss)Target Cost$100,000
$ 99,000$ 10,5000$ 10,500Target Profit$10,000
$ 99,0000$ 99,000$ 10,500Target Price$110,000
Ceiling Price$120,000

Target-PTA

100000120000100000Ceiling
12000012000014000014000000-20000-20000Under Target100000600001000030000Final Cost - Profit (Loss)
9900099000105000Final Price horizontal
0990001050010500Analyst Notes

Jan 2024

RWW FPIF with: Target Cost $100,000; Target Profit $10,000; Target Price $110,000; Ceiling Price $120,000. Share 50/50 Under & 50/50 Over.

Target Cost100,000
Target Profit %/$10.00%$ 10,000
Target Price$ 110,000
Ceiling %/$120.00%$ 120,000
Assigned Shares
Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target50.0%/50.0%
Over Target50.0%/50.0%
Calculated Shares
Desktop Williams: For calculated shares to be used, any assigned shares above must be cleared.CostProfit
Optimistic

DAU User: Optimistic cost must be less than target cost and optimistic profit must be greater than target profit.

Pessimistic DAU User: Pessimistic cost must be greater than target cost and pessimistic profit must be less than target profit.

Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target/
Over Target/

Point of Total Assumption (PTA) $ 120,000

Final Actual Audited Allowable Cost: $ 102,500

Final Contract Price: $ 111,250

Final Contractor Profit (Loss): $ 8,750

Final Contractor Profit (Loss) %: 8.54%

Example purposes only to show how annual/monthly FPIF math will work. Offerors are highly encouraged to experiment with this spreadsheet to familiarize themselves with how it is anticipated to work.

Govt/Ktr
50%50%Under505050/50 Under
50%50%Over505050/50 Over
Under TargetTarget-PTACeiling
CostProfit/(Loss)CostProfit/(Loss)CostProfit
left Scaler$ 100,000$ 10,000$ 100,000$ 10,000$ 120,000$ - 0
2$ 60,000$ 30,000$ 120,000$ - 0right scaler$ 120,0000
1$ 140,000$ (20,000)
$ 140,000$ (20,000)
Final Cost - Profit (Loss)Final Price horizontalDollar Text
CostProfit/(Loss)CostProfit/(Loss)Target Cost$100,000
$ 102,500$ 8,7500$ 8,750Target Profit$10,000
$ 102,5000$ 102,500$ 8,750Target Price$110,000
Ceiling Price$120,000

Target-PTA

100000120000100000Ceiling
12000012000014000014000000-20000-20000Under Target100000600001000030000Final Cost - Profit (Loss)
10250010250087500Final Price horizontal
010250087508750Analyst Notes

Feb 2024

RWW FPIF with: Target Cost $100,000; Target Profit $10,000; Target Price $110,000; Ceiling Price $120,000. Share 50/50 Under & 50/50 Over.

Target Cost100,000
Target Profit %/$10.00%$ 10,000
Target Price$ 110,000
Ceiling %/$120.00%$ 120,000
Assigned Shares
Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target50.0%/50.0%
Over Target50.0%/50.0%
Calculated Shares
Desktop Williams: For calculated shares to be used, any assigned shares above must be cleared.CostProfit
Optimistic

DAU User: Optimistic cost must be less than target cost and optimistic profit must be greater than target profit.

Pessimistic DAU User: Pessimistic cost must be greater than target cost and pessimistic profit must be less than target profit.

Desktop Williams: Shares assigned here take precedence over calculated shares below using optimistic and pessimistic values.Govt/Ktr
Under Target/
Over Target/

Point of Total Assumption (PTA) $ 120,000

Final Actual Audited Allowable Cost: $ 103,000

Final Contract Price: $ 111,500

Final Contractor Profit (Loss): $ 8,500

Final Contractor Profit (Loss) %: 8.25%

Example purposes only to show how annual/monthly FPIF math will work. Offerors are highly encouraged to experiment with this spreadsheet to familiarize themselves with how it is anticipated to work.

Govt/Ktr
50%50%Under505050/50 Under
50%50%Over505050/50 Over
Under TargetTarget-PTACeiling
CostProfit/(Loss)CostProfit/(Loss)CostProfit
left Scaler$ 100,000$ 10,000$ 100,000$ 10,000$ 120,000$ - 0
2$ 60,000$ 30,000$ 120,000$ - 0right scaler$ 120,0000
1$ 140,000$ (20,000)
$ 140,000$ (20,000)
Final Cost - Profit (Loss)Final Price horizontalDollar Text
CostProfit/(Loss)CostProfit/(Loss)Target Cost$100,000
$ 103,000$ 8,5000$ 8,500Target Profit$10,000
$ 103,0000$ 103,000$ 8,500Target Price$110,000
Ceiling Price$120,000

Target-PTA

100000120000100000Ceiling
12000012000014000014000000-20000-20000Under Target100000600001000030000Final Cost - Profit (Loss)
10300010300085000Final Price horizontal
010300085008500Analyst Notes