Attch 7 - DRAFT FPIF CLIN Structure Spreadsheet 20220721.xlsx
XLSX spreadsheet 25 KB Posted
- Attached to
- Joint Navigation Warfare Center (JNWC) IV - DRAFT Request for Proposal Federal contract opportunity
- Solicitation number
- FA2518-22-R-0027
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| DRAFT JNWC IV TO One PWS.pdf | ||
| DRAFT JNWC IV Basic IDIQ Work Statement.pdf | ||
| 0 - DRAFT Request for Proposal FA251822R0027.pdf | ||
| Attch 6 - DRAFT Factor 2 Staffing Matrix 20220721.xlsx | XLSX spreadsheet | |
| Attch 5 - DRAFT J9 Engineering Support Scenario 20220721.pdf | ||
| Attch 9 - FPIF Monthly Invoicing Worksheet 20220721.xlsx | XLSX spreadsheet | |
| Attch 8 - Professional Compensation Evaluation Plan Form 20220721.xlsx | XLSX spreadsheet | |
| 0 - DRAFT Request for Proposal FA251822R0027.pdf | ||
| Attch 1 - DRAFT Section L Instructions Conditions Notices to Offerors 20220721.pdf | ||
| Attch 2 - DRAFT Section M Evaluation Factors for Award 20220721.pdf | ||
| Attch 3 - DRAFT J3 Warfighter Support Scenario 20220721.pdf | ||
| Attch 4 - DRAFT J3 Warfighter Support Grading Key 20220721.xlsx | XLSX spreadsheet |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
DRAFT
Joint Navigation Warfare Center (JNWC) IV - RFP: FA2518-22-R-0027 Section J Attachment 7: FPIF CLIN Structure Spreadsheet
For the purposes of this RFP, please note the following:
In accordance with (IAW) Attachment 1 - Section L Instructions, Conditions & Notices to Offerors, para e.1.a., offerors are to insert proposed unit and extended prices, including all option periods.
Offerors must propose on every contract line item, even if it is $0.00, in order to be considered for award.
Phase-in CLINs will not be included in the total evaluated price.
Offeror is to complete the yellow-shaded cells only
NOTE: IAW IDIQ CLIN X003, Fixed Price Incentive Fee (FPIF) orders will be issued against this CLIN. Cost share ration is 50%/50%, Ceiling Price is 120%.
&"-,Bold"&KFF0000Contractor Proprietary Information
| To be protected IAW FAR 2.101 and 3.104 | &"-,Bold"JNWC IV |
| FA2518-22-R-0027 | &"-,Bold"&KFF0000Contractor Proprietary Information |
To be protected IAW FAR 2.101 and 3.104
&"Arial,Regular"&10
TO 1 CLIN Schedule
| DRAFT Joint Navigation Warfare Center (JNWC) IV - RFP: FA2518-22-R-0027 - Attachment 7: FPIF CLIN Structure Spreadsheet | ||
| OFFEROR TO COMPLETE YELLOW-SHADED CELLS ONLY | ||
| Total Evaluated Price (TEP) for award of JNWC IV IDIQ: | $ 4,249,956 |
| Task Order One FPIF Geometry: | Target Cost | $ - 0 | ||||
| Target Profit | 10% | $ - 0 | ||||
| Target Price | $ - 0 | |||||
| Ceiling Price | 120% | $ - 0 | ||||
| CLIN | DESCRIPTION | TYPE | QTY | UNIT | UNIT PRICE | EXTENDED AMOUNT |
| PHASE-IN | ||||||
| 0001 | Phase-in (FFP) | FFP | 1 | Each | $ - 0 | |
| BASE PERIOD | ||||||
| 0003 | Task Order 1 - Labor (FPIF) (include costs of the labor only; no profit) | FPIF | 7 | Months | $ - 0 | |
| 0004 | Task Order 1 - Travel (Cost) | COST | 7 | Months | $ 64,285 | $ 449,995 |
| 0006 | Task Order 1 - Materials / Equipment (Cost) | COST | 7 | Months | $ 28,571 | $ 199,997 |
| OPTION YEAR 1 | ||||||
| 1003 | Task Order 1 - Labor (FPIF) (include costs of the labor only; no profit) | FPIF | 12 | Months | $ - 0 | |
| 1004 | Task Order 1 - Travel (Cost) | COST | 12 | Months | $ 50,000 | 600,000 |
| 1006 | Task Order 1 - Materials / Equipment (Cost) | COST | 12 | Months | $ 16,666 | 199,992 |
| OPTION YEAR 2 | ||||||
| 2003 | Task Order 1 - Labor (FPIF) (include costs of the labor only; no profit) | FPIF | 12 | Months | $ - 0 | |
| 2004 | Task Order 1 - Travel (Cost) | COST | 12 | Months | $ 50,000 | 600,000 |
| 2006 | Task Order 1 - Materials / Equipment (Cost) | COST | 12 | Months | $ 16,666 | 199,992 |
| OPTION YEAR 3 | ||||||
| 3003 | Task Order 1 - Labor (FPIF) (include costs of the labor only; no profit) | FPIF | 12 | Months | $ - 0 | |
| 3004 | Task Order 1 - Travel (Cost) | COST | 12 | Months | $ 50,000 | 600,000 |
| 3006 | Task Order 1 - Materials / Equipment (Cost) | COST | 12 | Months | $ 16,666 | 199,992 |
| OPTION YEAR 4 | ||||||
| 4003 | Task Order 1 - Labor (FPIF) (include costs of the labor only; no profit) | FPIF | 12 | Months | $ - 0 | |
| 4004 | Task Order 1 - Travel (Cost) | COST | 12 | Months | $ 50,000 | 600,000 |
| 4006 | Task Order 1 - Materials / Equipment (Cost) | COST | 7 | Months | $ 16,666 | 199,992 |
| EXTENSION OF SERVICES (Rates within Option Year 4) | ||||||
| 5003 | Task Order 1 - Labor (FPIF) (include costs of the labor only; no profit) | FPIF | 6 | Months | $ - 0 | $ - 0 |
| 5004 | Task Order 1 - Travel (Cost) | COST | 6 | Months | $ 50,000 | $ 300,000 |
| 5006 | Task Order 1 - Materials / Equipment (Cost) | COST | 6 | Months | $ 16,666 | $ 99,996 |
&"-,Bold"&KFF0000Contractor Proprietary Information
| To be protected IAW FAR 2.101 and 3.104 | &"-,Bold"JNWC IV |
| FA2518-22-R-0027 | &"-,Bold"&KFF0000Contractor Proprietary Information |
To be protected IAW FAR 2.101 and 3.104
&"Arial,Regular"&10
File details come from the government source that posted it. Updated .