Attch 5 Submittal Register.xlsx
XLSX spreadsheet 18 KB Posted
- Attached to
- Repair Engine Shop Floors, Bldg. 822
- Solicitation number
- FA663326Q003
About this file
This is a Submittal Register that outlines the contractor's required submittals and documentation schedule for the "Sustain Engine Shop Floors, B822" project (Job Number 25-0016) under Contract FA6633-26-Q-0003. The register functions as a tracking document for preconstruction, construction, and closeout submittals, establishing deadlines and approval workflows for 34 line items across multiple specification sections.
The preconstruction submittals include standard contractor documentation such as Entry Authorization Request, List of Contact Personnel, Existing Conditions Pictures, Baseline Construction Schedule, Submittal Register, Accident Prevention Plan, and Contractor Quality Control Plan. Product and material-related submittals required include epoxy coatings, concrete materials (mix design, curing materials, reinforcement), joint sealants and fillers, vapor retarders, polymers, and slip-resistance recommendations. Test reports and certifications required include Compressive Strength Tests, Slump Tests, Moisture/Alkalinity/Bond Tests, Accident Reports, Hot Work Permits, Quality Control Personnel Certifications, and Laboratory Accreditation. Closeout submittals include As-Built Drawings, Final Construction Waste Diversion Report, and Warranted Materials documentation. The register designates certain submittals for Government (G) or A/E (Architecture/Engineering) review, and specifies approval dates, material needed dates, and reviewer routing procedures. This submittal schedule ensures compliance with construction specifications and enables systematic project oversight from preconstruction through final closeout.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation - FA663326Q0003 -Rev1.pdf | ||
| Attch 3 Drawings Rev 1.pdf | ||
| Attch 4 Wage Determination.pdf | ||
| Attch 2 Specifications.pdf | ||
| Attch 3 Drawings.pdf | ||
| Solicitation - FA663326Q0003.pdf | ||
| Attch 1 Statement of Work.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal_Register
| JOB TITLE: | Sustain Engine Shop Floors, B822 | SUBMITTAL REGISTER | ||||||||||||||||
| JOB NUMBER: | 25-0016 | |||||||||||||||||
| LOCATION: | B822 | |||||||||||||||||
| CONTRACT NO: | ||||||||||||||||||
| CONTRACTOR: | ||||||||||||||||||
| CONTRACTOR SCHEDULE DATES | CONTRACTOR ACTION | APPROVING AUTHORITY | ||||||||||||||||
| (a) | (b) | (c) | (d) | (e) | (f) | (g) | (h) | (i) | (j) | (k) | (l) | (m) | (n) | (o) | (p) | (q) | (r) |
| Line | Activity # | Transmittal # | Specification Section | SD # | Submittal Description | Item Submitted | Paragraph # | Classification: GOVT or A/E Reviewer | Submit | Approval Needed By | Material Needed By | Action Code | Date Of Action | Date FWD to APPR / Auth Date RCD From CONTR | Date FWD To Other Revwr | Date RCD From Other Reviewer | Action Code | Date Of Action | Mailed To CONTR/ Date RCD From APPR Authority | Remarks |
| 1 | 01 11 00 | 01 | Preconstruction Submittals | Entry Authorization Request | 1.4 | |||||||||||||||
| 2 | 01 14 00 | 01 | Preconstruction Submittals | List of Contact Personnel | 1.2.1.1 | |||||||||||||||
| 3 | 01 30 00 | 01 | Preconstruction Submittals | Existing Conditions Pictures | 1.3 | G | ||||||||||||||
| 4 | 01 32 16.00 20 | 01 | Preconstruction Submittals | Baseline Construction Schedule | 1.2 | G | ||||||||||||||
| 5 | 01 32 16.00 20 | 07 | Certificates | Schedule Updates | 1.4 | |||||||||||||||
| 6 | 01 33 00 | 01 | Preconstruction Submittals | Submittal Register | 1.7 | G | ||||||||||||||
| 7 | 01 35 26 | 01 | Preconstruction Submittals | Accident Prevention Plan (APP) | 1.7.1 | G | ||||||||||||||
| 8 | 01 35 26 | 06 | Test Reports | Accident Reports | 1.10.2 | G | ||||||||||||||
| 9 | 01 35 26 | 07 | Certificates | Hot Work Permit | 1.11 | |||||||||||||||
| 10 | 01 45 00 | 01 | Preconstruction Submittals | Contractor Quality Control (CQC) Plan | 1.5.2 | G | ||||||||||||||
| 11 | 01 74 19 | 11 | Closeout Submittals | Final Construction Waste Diversion Report | 1.8 | S | ||||||||||||||
| 12 | 01 78 00 | 11 | Closeout Submittals | As-Built Drawings | 3.1 | G | ||||||||||||||
| 13 | 01 78 00 | 11 | Closeout Submittals | Warranted Materials | 1.4.1 | |||||||||||||||
| 14 | 03 01 00 | 01 | Preconstruction Submittals | Qualifications | 1.5.2 | G | ||||||||||||||
| 15 | 03 01 00 | 03 | Product Data | Polymers | 2.2 | |||||||||||||||
| 16 | 03 01 00 | 05 | Design Data | Repair Procedures | 1.5.1 | G | ||||||||||||||
| 17 | 03 01 00 | 06 | Test Reports | Polymers | 2.2 | |||||||||||||||
| 18 | 03 01 00 | 08 | Manufacturer's Instructions | Polymers | 2.2 | |||||||||||||||
| 19 | 03 30 00 | 01 | Preconstruction Submittals | Quality Control Personnel Certifications | 1.6.3 | G | ||||||||||||||
| 20 | 03 30 00 | 01 | Preconstruction Submittals | Laboratory Accreditation | 1.6.5 | G | ||||||||||||||
| 21 | 03 30 00 | 03 | Product Data | Joint Sealants | 2.4.4 | S | ||||||||||||||
| 22 | 03 30 00 | 03 | Product Data | Joint Filler | 2.4.3 | S | ||||||||||||||
| 23 | 03 30 00 | 03 | Product Data | Vapor Retarder | 2.4.5 | |||||||||||||||
| 24 | 03 30 00 | 03 | Product Data | Concrete Curing Materials | 2.4.1 | |||||||||||||||
| 25 | 03 30 00 | 03 | Product Data | Reinforcement | 2.6 | S | ||||||||||||||
| 26 | 03 30 00 | 05 | Design Data | Concrete Mix Design | 1.6.1.1 | G | ||||||||||||||
| 27 | 03 30 00 | 06 | Test Reports | Compressive Strength Tests | 3.10.2.3 | G | ||||||||||||||
| 28 | 03 30 00 | 06 | Test Reports | Slump Tests | 3.10.2.1 | |||||||||||||||
| 29 | 03 30 00 | 06 | Test Reports | Field Testing Technician and Testing Agency | 1.6.3.1 | |||||||||||||||
| 30 | 09 96 00 | 03 | Product Data | Epoxy Coatings | 2.1 | G | ||||||||||||||
| 31 | 09 96 00 | 03 | Product Data | Slip-Resistance Recommendations | 2.2.1 | G | ||||||||||||||
| 32 | 09 96 00 | 04 | Samples | Color Chips | 1.3 | G | ||||||||||||||
| 33 | 09 96 00 | 06 | Test Reports | Moisture, Alkalinity, and Bond Tests | 3.1.1 | G | ||||||||||||||
| 34 | 09 96 00 | 07 | Certificates | Manufacturer's Printed Instructions | 3.1.5 | G |
File details come from the government source that posted it. Updated .