Attch 5 ROB Contractor Work Surveilance Checklist.pdf
PDF 45 KB Posted
- Solicitation number
- SP450024R0020
- Issued by
-
Defense Logistics Agency
About this file
This document is a combined synopsis/solicitation for a federal contract opportunity issued by the Defense Logistics Agency (DLA) for the removal, transportation, and disposal of various hazardous and non-hazardous wastes in the New England region.
The solicitation, numbered SP450024R0020, is a competitive 8(a) set-aside with a 30-month base period and a 30-month option period. It requires the contractor to provide services such as the removal, transport, and disposal of RCRA hazardous wastes, non-RCRA wastes, state-regulated wastes, universal wastes, compressed gases, PCBs, and PFAS from military installations and within a 50-mile radius in Connecticut, Massachusetts, Rhode Island, and Fishers Island, New York. The solicitation provides details on the performance work statement, pickup and service locations, pricing schedule, past performance requirements, and evaluation factors, which include price, technical capability, and past performance. Proposals are due 30 calendar days from the date of distribution of the solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attch 12 DLA Form 2507 Facility Application Nov 2023.pdf | ||
| Attch 13 DLA Form 2503 Transporter Application MAR 2022.pdf | ||
| Attch 11 SOL Questions and Answers.docx | DOCX document | |
| Attch 4 ICS Contractor Work Surveilance Checklist .pdf | ||
| Attch 3 Pickup_Service Locations.pdf | ||
| Attch 2 Performance Work Statement_Description of Requirement.docx | DOCX document | |
| Attch 7 CAC Application Process.docx | DOCX document | |
| Attch 9 CLAUSES PROVISIONS.docx | DOCX document | |
| Attch 1 Price Schedule VER2.xlsx | XLSX spreadsheet | |
| Attch10 PPI Questionnaire.pdf | ||
| Attch 6 Invoice DLA Form 2505 v02JAN24.xlsx | XLSX spreadsheet | |
| Attch 8 Offeror Representations and Certifications and 6-4 PWS info.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contractor Work Surveillance Checklist
Placement or Removal of Empty Rented Rolloff Box (ROB) or Vacuum Box
Date(s) of Work Surveillance: _________________ Start Time: ___________ Stop Time: ___________
Contract Number: SP4500-______-D-___________ TO #: ________________ CLIN: ______________
Name of Designated Government Representative: ___________________________________________
Title of Designated Government Representative: ____________________________________________
Phone Number of Designated Government Representative: (______) _______-___________ Ext.______
Yes No N/A Description of Contractor Work Surveillance: [ROB] or [Vac Box] (Circle one)
Did the Contractor arrive on site at the scheduled time and date?
Did the Contractor arrive on site with all of the requisite equipment, including
- One ROB or Vacuum Box container of the appropriately ordered size, with
- One plastic liner of sufficient size and thickness to adequately contain the waste for which it was intended (ROB only), and
- One watertight tarp cover that was generally free of rips and tears (ROB only)?
Does the Contractor have an approved weight ticket showing the empty (tare) weight of the container?
Was the container inspected by a Designated Government Representative upon arrival at the designated location?
Was the container of acceptable appearance and integrity, with minimal evidence of corrosion, visibly void of waste residue and legible/offensive graffiti upon delivery?
Was the ROB, bows and cover free of any defects or damage, other than those attributable to normal wear and tear, and determined acceptable for Government use? Please document below any noteworthy defects or damage and have driver initial for acknowledgment.
Note: Failure of the driver to acknowledge any existing noteworthy defects or damage will be cause for rejection of the ROB and liner.
Did the equipment operate properly without causing a delay in work?
Was the work performed safely and did the equipment meet the satisfaction of the Designated Government Representative?
Comments:
Signature of Designated Government Representative Date