Attch 4 ICS Contractor Work Surveilance Checklist .pdf

PDF 119 KB Posted

Attached to
DLA Disposition Services Hazardous Waste Removal New England Region
Solicitation number
SP450024R0020
Issued by

About this file

This document is a Combined Synopsis/Solicitation for a federal contract opportunity from the Defense Logistics Agency (DLA) for the removal, transportation, and disposal of hazardous and other regulated wastes in the New England region. The contract will have a 30-month base period with a 30-month option period, with an anticipated start date of February 3, 2025. The solicitation is being issued as a competitive 8(a) set-aside, with the associated NAICS code of 562211 and a small business size standard of $47M. Key requirements include the use of specific equipment like vacuum trucks and power washing units, as well as proper documentation and inspection procedures. Pricing is to be submitted using the provided price schedule, with the government reserving the right to negotiate if prices exceed the fair market price. Past performance and technical capability are the two non-price evaluation factors, with past performance being equal in importance to price when combined.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contractor Work Surveillance Checklist

Industrial Cleaning Services (ICS) – CLINs 1002SV-1004SV & 1007SV-1009SV

Date(s) of Work Surveillance: _________________ Start Time: ___________ Stop Time: ___________

Name of Designated Government Representative: ___________________________________________

Title of Designated Government Representative: ____________________________________________

Phone Number of Designated Government Representative: (______) ________-___________

Yes No N/A Description of Contractor Work Surveillance

Did the work crew arrive on site at the scheduled time and date?

Did the crew arrive on site with all of the requisite equipment, including

- One standard vacuum truck (3,500-gal capacity) w/ 300 feet of hoses,

- One self-contained heated power washing unit,

- One liquid transfer pump w/ 300 feet of hoses, and

- All appropriate PPE and tools?

Did the vacuum truck driver provide a weight ticket showing the empty (tare) weight of the vacuum truck?

Was the vacuum truck inspected by a designated Government representative prior to use?

Did the vacuum truck arrive with a clean tank and hose fittings that were constructed of material that that was chemically compatible with the waste to be removed?

Did the vacuum truck arrive free of visible waste residue unless the truck was being used for multiple removals from the same project involving the same waste stream

(in which case it arrived as meeting definition of RCRA empty per 40 CFR 261.7)?

Did all of the equipment operate properly without causing delay in work?

Was the work performed to the satisfaction of the designated Government representative?

Comments:

Signature of Designated Government Representative Date