This is a Statement of Work (SOW) for the AMMO Extended Storage Project at the James J. Rowley Training Center (JJRTC), a United States Secret Service facility in Laurel, Maryland. The project consists of two phases: Phase 1 involves relocating two existing 54,000-pound ARMAG Corporation outdoor explosive storage magazines from Wilkie Parking Area to a new location, including design and construction of reinforced concrete pad foundations with proper grounding and bonding systems, site improvements, and utility coordination. Phase 2 involves design and construction of a new 5,400 square-foot ATF Specification Type 2 multiplex explosives and ammunition storage magazine system on a reinforced concrete pad within the southwest portion of Wilkie Parking Area, including site preparation, HVAC systems, electrical infrastructure, ceiling lighting, doors, entry ramps, and associated site improvements. The project also requires disassembly and reassembly of an existing metal shed system and removal/restoration of affected parking areas.

The contractor shall provide comprehensive design-build services on a turn-key basis with a 180-calendar-day period of performance from award. Key deliverables include existing conditions surveys and reports due within 14 days of award, 65% and 100% design package submissions with Designer of Record (DOR) certifications, Issue for Construction (IFC) documents, as-built drawings within 30 days of construction completion, and comprehensive commissioning documentation. The contractor must obtain all required permits and regulatory approvals, coordinate with Baltimore Gas & Electric for permanent power service (with temporary power required 60 days before equipment delivery if permanent power is unavailable), maintain a Construction Quality Control Plan meeting USACE standards, ensure compliance with OSHA and EM 385-1-1 safety requirements, and provide all warranties and operations/maintenance manuals. Liquidated damages are assessed at $1,051 per calendar day for failure to achieve substantial completion by the contract deadline. The contractor must also comply with extensive security requirements including SSF 3237 facility access requests for all personnel, U.S. citizenship verification, and restrictions on photography and information disclosure at the USSS facility.

View the file

Other files

File Type Posted
Q and A Rev 1.xlsx XLSX spreadsheet
Attch 3 Provisions and Clauses Rev 1.pdf PDF
Attch 2 SOW Rev 1.pdf PDF
Attch 1 Instructions Rev 1.pdf PDF
Q and A.xlsx XLSX spreadsheet
70US0926R70094023 Rev 1.pdf PDF
Attch 3 Provisions and Clauses.pdf PDF
Attch 1 Instructions.pdf PDF
70US0926R70094023 DRAFT.pdf PDF
Attch 4 RTCFAC Access requests for Contractors.xlsx XLSX spreadsheet
Attch 5 Pre bid RFI.xlsx XLSX spreadsheet
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMMO EXTENDED STORAGE PROJECT

Non USSS / Personal

STATEMENT OF WORK (SOW)

for

AMMO Extended Storage -Multiplex ATF SPEC Type 2 Explosives Storage and Ammo Storage Magazines

Project Background and Requirements

1.1. Project Background

1.1.1. The James J. Rowley Training Center (JJRTC) is the primary training facility for the

United States Secret Service (USSS). The campus is located at 9200 Powder Mill Road in Laurel, Maryland on approximately 500 acres. The United States Secret Service, James J. Rowley Training

Center (JJRTC) is the main training facility for USSS personnel. The campus consists of commercial buildings, classrooms and conference rooms spread over a 500-acre campus. JJRTC must provide the best training environment for USSS law enforcement Agents, Officers and civilian support personnel.

The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the contractor who, in turn, is responsible to the Government.

1.2. Project Objectives – Phases 1 & 2

• The contractor shall provide all necessary design, engineering, labor, equipment, materials, testing, construction services, any coordination, requirements and services necessary to execute the design and construction of the following. Contractor is responsible for verifying and accounting for new installation, removal and/or relocation, and all required coordination of utilities as a part of this contract during design, construction and warranty period. Further, all relocation support including on-site installation assistance, civil/site improvements required for transportation, and installation of the storage magazines.

The objective of this project is to provide professional turn-key design and build services to furnish and construct new concrete reinforced pads and a 5,400 square foot outdoor Alcohol, Tobacco

Firearms and Explosives (ATF) SPEC Multiplex Magazine with heavy duty flooring, doors, entry ramps, awning, ceiling lighting, wall mounted HVAC & humidity control system, and other associated items. In the location where the new Multiplex will be constructed, there are two (2) existing ARMAG

Corporation branded Outdoor Explosive Storage Magazines that shall be to be relocated to within the campus footprint; there is also a large metal shed system that shall be disassembled, stored & protected, and reassembled after the Multiplex system is delivered, set and fully operational. Although the project requirements under this SOW are divided into two (2) phases of work, the project remains a standalone, turnkey design-build effort. However, we are open to considering a more efficient sequencing plan, provided it meets all project requirements, maintains continuity of work, and does not adversely impact schedule, cost, quality, or operational needs. The concrete pads associated with this project shall be slab-on-grade designed and constructed to the American Concrete Institute (ACI) core standards including 301.1R. No concrete admixtures and accelerants are authorized for this project. In the event of any conflict or discrepancy, the most stringent applicable code, regulation, law, standard, or industry best practice shall govern.

Phase 1: Professional Turn-Key design, construction, furnishing, testing, and installation of a new reinforced concrete pad, and relocation of two (2) Outdoor Explosives Storage & Ammunitions Storage

Magazines systems include, but not limited to, the following tasks:

• Relocate two (2) existing ARMAG Corporation Outdoor Explosive Storage & Ammunition Storage

Magazines and all associated items.

• Disassembly of any required components including electrical, grounding and bonding systems.

• Each magazine is owned by the USSS and will be unoccupied prior to relocation. Contractor shall provide the Government with at least 1-month advanced written notification prior to the units being relocated to ensure that all material is removed.

• Relocate magazines from the existing location to a COR designated location on the JJRTC.

• Facilitate and manage the transportation of the magazines.

• Design and construct a reinforced concrete pad foundation, including anchoring systems, to support the maximum required load capacity of the two (2) ARMAGS and all associated components.

• Provide the necessary site preparations, grading, drainage, grounding & bonding systems, and site improvements to support the two (2) ARMAG storage magazines.

• Disassemble, store and protect the existing metal shed and associated items.

• Design and construct coordinate utilities.

• Complete all site preparations and improvements to ensure safe placement and operation.

• The new reinforced concrete pad and all associated items, including power, must be completed in no less than 60 calendar days before the scheduled delivery of the new 5,400 S.F Multiplex ATF Spec

Type 2 Explosives Storage and Ammo Storage magazine system.

• The existing magazines shall be relocated and fully operational at the new site location no later than 45 days prior to the scheduled delivery of the new Multiplex magazine.

• All relocation support including on-site installation assistance, civil/site improvements required for the transportation, installation, the storage magazines.

• Furnish, install and certify new components including anchoring, grounding and bonding systems.

• The ARMAGS shall remain operational throughout construction period except for one (1) day.

Phase 2: This phase includes the turnkey design, construction, furnishing, testing, and installation of a new reinforced concrete pad and a 5,400 usable-square-foot Multiplex ATF Specification Type 2 explosives and ammunition storage magazine system. The work includes, but is not limited to, the following tasks:

• Provide the necessary site preparation, grading, drainage, and site improvements to support the new storage magazines.

• To the extent possible, the electrical distribution and disconnect equipment shall be mounted and affixed to the magazines.

• Design and construct a reinforced concrete pad foundation to support the maximum required load capacity of the Multiplex system and all associated components.

• Design, construct, deliver, and install the 5,400 usable-square-foot Multiplex ATF Specification Type

2 explosives and ammunition storage magazine system as shown in attachment 1.4.6.8 or COR approved equivalent system.

• Furnish, install and certify new components including anchoring, grounding and bonding systems.

• Furnish and install the storage magazines as per the manufacturer’s specifications, requirements, recommendations and best practices.

• For future use, provide and install two (2) empty 2” PVC conduits with pull strings. The location shall be specified by the COR during the design phase. The Multiplex shall utilize a truss system that allows the interior space to be clear spanning, without the need for support columns.

• Removal, modification and restoration of affected portions of the Wilkie parking area, as needed.

• Reassemble the metal shed in proximity of the new Multiplex system; the exact location will be provided by COR during design phase.

1.2.1.1. Contractor is responsible for assessing the electrical power, HVAC systems requirements and coordinating with Baltimore Gas Electric (BGE) company to provide and install the necessary equipment, temporary and/or permanent power, and all associated items of the entire project. If permanent power service cannot in place prior to the scheduled relocation and delivery of the equipment identified in Phases 1 and 2 above, then provide temporary power service to the equipment and all associated items sixty (60) days prior to its scheduled relocation and/or delivery; generator use shall not be considered. The temporary power service shall be entirely removed once permanent power

& breakers are commissioned and all equipment (Phases 1 and/or 2) and all other associated items are completely powered.

1.2.1.2. Contractor shall be responsible for all utilities including Electrical power and HVAC systems requirements for the entire project – Phase 1 and Phase 2.

1.2.1.3. Contractor shall comply with all applicable federal, state, local codes & regulations.

1.2.1.4. Contractor shall obtain all required permits, approvals, tests, certifications, research, surveys, inspections and other required services to successfully complete the project.

1.3. Period of Performance - The period of performance for this task order is 180 calendar days from award.

1.4. Project Requirements

1.4.1. The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, and supervision necessary to meet the requirements established in the statement of work.

1.4.1.1. The project is Turn-key.

1.4.1.2. The contractor should coordinate all construction activities to the JJRTC or COR prior to start of work. Provide warranties, O&M manuals, spare keys, test reports, and as-built drawings at closeout.

Phase 1 – Features of work

1.4.1.3. The contractor shall design & construct a new reinforced concrete pad and concrete apron capable of safely supporting the maximum capacity loads of the two (2) Outdoor Explosives

Storage & Ammunitions Storage Magazines, including all associated operational and structural loading requirements.

1.4.1.4. Relocate the two (2) existing Outdoor Explosives Storage & Ammunitions Storage

Magazines, each having an empty weight of approximately 54,000 lbs., from the existing location to the new designated location on to the new reinforced concrete pad. The work shall include relocation of all associated components and accessories to include the existing HVAC units required for complete installation and operational use at the relocation site. The contractor shall verify and account for all existing storage dimensions, weights, clearances, and associated equipment prior to design, relocation and construction activities. The contractor shall verify that all systems are working in accordance with manufacturer's requirements and best practices.

1.4.1.5. Design and construct a new reinforced concrete pad to relocate, install, anchor, and ground the two (2) existing 54,000 lbs. each Outdoor Explosives Storage & Ammunitions Storage Magazines and all other associated items.

1.4.1.6. The concrete pad shall be designed & constructed with high strength rebar (regular steel rebar, Welded Wire Fabric (WWF), or Fiber Reinforced Polymer (FRP) no wire mesh shall be used.

Top of concrete pad shall be smooth, level finish suitable for placement. All contributing building loads shall be determined by the Designer of Record to establish the concrete pad requirements. The east edge of the proposed reinforced concrete pad shall align with and terminate at the outside face of the west exterior wall of the Knight building. The Contractor shall ensure that the top surface of the concrete pad is uniformly level and free of depressions or other low spots to prevent rainwater ponding. See attached 1.4.4.3 – Site Plan

1.4.1.7. Relocate two (2) existing 54,000 lbs. empty Outdoor Explosives Storage &

Ammunitions Storage Magazines, including associated items from the Wilkie Parking Area to a COR designated location at JJRTC.

1.4.1.8. The contractor shall confirm all final equipment locations with the COR prior to issuing the IFC documents and installation. See attached 1.4.4.2 - Location Map.

1.4.1.9. Protect the Outdoor Explosives Storage & Ammunitions Storage Magazines during transport and handling.

1.4.2. The contractor shall only relocate and install the two (2) existing Outdoor Explosives

Storage & Ammunitions Storage Magazines to the new location after the reinforced concrete pad has reached its design strength and full curing.

1.4.2.1. Install Outdoor Explosives Storage & Ammunitions Storage Magazines on the new concrete pad in proper alignment. Ensure that each Outdoor Explosives Storage & Ammunitions

Storage Magazines is stable, secured, and operational after installation.

1.4.2.2. Maintain 3’ clear gap between the two (2) Outdoor Explosives Storage &

Ammunitions Storage Magazines after installation.

1.4.2.3. Provide a minimum 12” clearance between the left, right, & rear faces of the Outdoor

Explosives Storage & Ammunitions Storage Magazines and the concrete pad edges. Also, provide a minimum of 60” front clearance for door swing, ramp access, and operational use.

See attached 1.4.4.3 – Site Plan (Conceptual)

1.4.2.4. Option: Custom Exterior Panels. Turn-key and install custom exterior panels of equivalent quality of those revealed during the bid walk. Further, the panels shall be completely installed on all exposed exterior sides of the Multiplex system; If this option is exercised, the COR will provide the actual images that will be displayed on the panels. See attached 1.4.4.8 – Metal Panel &

Graphics (reference only)

1.4.2.5. Provide and construct reinforced concrete driveway (16’ wide), reinforced concrete apron for truck, forklifts, and loading/unloading operations. The apron shall slope downward toward the proposed driveway with a smooth transition to accommodate vehicles and equipment.

Option: Provide forklift reinforced concrete driveway from concrete apron to existing electrical station.

See attached 1.4.4.3 – Site Plan

1.4.2.6. The concrete driveway, concrete apron, and concrete pad could carry a maximum load.

DOR shall determine the concrete compressive strength (PSI).

1.4.2.7. The Outdoor Explosives Storage & Ammunitions Storage Magazines concrete pad edge shall be 6’ closer to the existing HVAC unit concrete pad.

1.4.2.8. The space (6’) between the Outdoor Explosives Storage & Ammunitions Storage

Magazines concrete pad and the existing HVAC unit concrete pad shall be filled with reinforced concrete slab in plain cement finish. Remove the existing handhole/manhole covers located between the proposed pad and the existing HVAC pad. Replace the existing covers with new removable reinforced concrete handhole/manhole covers equipped with recessed metal lifting handles. The new covers shall be designed to provide safe access for future maintenance and shall match the surrounding finished grade.

1.4.2.9. Provide a positive drainage along the south side of the proposed reinforced concrete slab and apron, and along the east side of the proposed 16-foot-wide driveway, to convey stormwater by sheet flow. In addition, provide an underground storm drainage pipe crossing beneath the driveway to collect and convey runoff, discharging by daylight into the existing drainage ditch/swale. Ensure that the storm drainage has 2% slope towards the ditch.

1.4.2.10. Provide selected boulders, as required, along the edge of the proposed concrete pad, apron & part of the driveway to reduce elevation difference between the adjacent grade and the top of the concrete surface and to serve as a barrier to help prevent accidental vehicle runoff.

1.4.2.11. The Contractor shall maintain a minimum horizontal clearance of 3 feet between the west edge of the proposed 16-foot-wide driveway and the edge of the existing electrical manhole. The

Contractor shall filed verify the manhole location prior to construction. The driveway entrance (start) shall be constructed to match the existing roadway asphalt grade level, providing a smooth, continuous transition without abrupt changes in elevation.

1.4.2.12. Contractor responsible for verifying and accounting for utilities as a part of this contract during design and construction.

Phase 1 - Attachments

Attachment: 1.4.4.2 – Location Map

Attachment: 1.4.4.3 – Site Plan (Conceptual)

Attachment: 1.4.4.4 – GIS Data (Knight Building Area) - Phase 1

Attachment: 1.4.4.4 – GIS Data (Wilkie Parking) - Phase 1

Attachment 1.4.6.4 (GIS Data) - Phase 1

Attachment 1.4.4.5 – Electrical Transformer (Existing)

Attachment 1.4.4.6 – Electrical Transformer (Existing)

Attachment 1.4.4.6 – HVAC (Existing)

Attachment 1.4.4.7 – 2 Outdoor Explosives Storage & Ammunitions Storage Magazines (Existing)

Attachment 1.4.4.8 – Metal Panel & Graphics (Reference)

Phase 2 – Features of work

1.1.1.1. The contractor shall design & construct a new reinforced concrete pad and a

5,400 SF Multiplex ATF Spec Outdoor Explosives Storage & Ammunitions Storage Magazines, including all associated operational and structural loading requirements.

facility within the southwest portion of the Wilkie Parking Area. Work shall include all required site preparation, grading, excavation, subgrade preparation, reinforced concrete foundation construction, utility coordination, and associated civil/site improvements necessary to support the proposed facility and its operational requirements. See attached 1.4.6.4 (Enlarged Site Plan)

1.1.1.2. Design and construct a new reinforced concrete pad to hold a 5,400 S.F.

Multiplex ATF Spec Outdoor Explosives Storage & Ammunitions Storage Magazines at full capacity.

1.1.1.3. The concrete pad shall be designed & constructed with high strength Rebar (regular steel rebar, WWF, or FRP) no wire mesh shall be used. Compact sub-grade and base course. Top of concrete pad shall be smooth, level finish suitable for placement. All contributing building loads shall be determined by the Designer of Record to establish the concrete pad thickness. The Contractor shall ensure that the top surface of the concrete pad is uniformly level and free of depressions or other low spots to prevent rainwater ponding.

1.1.1.4. The contractor shall always identify and secure the construction area. Maintain safe pedestrian and vehicle circulation around the project site. The contractor shall protect all existing such as building facility, utilities (Drainage Systems & Electrical Transformer/Source), electrical manholes, and other site features during construction. These utilities can be in the existing or to its new project locations.

1.1.2. The new concrete pad shall reach 100 percent of its design strength and full curing before installing the 5,400 SF Multiplex ATF Spec Outdoor Explosives Storage & Ammunitions Storage

Magazines.

1.1.1.1. The concrete pad could carry a heavy-duty maximum load. DOR shall determine the concrete compressive strength (PSI).

1.1.2.1. Demolish designated portion of the existing parking area as required for the new facility footprint and associated site improvements.

1.1.2.2. Remove and legally dispose of demolished asphalt/concrete, pavement, debris, unsuitable materials, and obstruction from the JJRTC.

1.1.2.3. The contractor should disassemble, protect and store the existing shed and reassemble it to return to the assigned placed as directed.

1.1.2.4. Period of Performance

1.1.2.5. Completion within 180 days of receipt of Notice to Proceed

Phase 2 - Attachments

Attachment 1.4.6.2 (Location Plan)

Attachment 1.4.6.3 (Site Plan)

Attachment: 1.4.4.2 – Location Map

Attachment 1.4.6.4 (Enlarged Site Plan)

Attachment 1.4.6.5 (GIS Data) - Phase 2

Attachment 1.4.6.6 (Existing Shed)

Attachment 1.4.6.7 (Project Site)

Attachment 1.4.6.8 (Reference)

1.1.1. Pre-Bid Site Investigations

1.1.1.1. Offerors who submit a proposal must attend a pre-bid site visit for Phase 1 & phase 2 that will be scheduled during the solicitation period to verify field conditions. If additional clarification is necessary, the Contractor must submit in writing a formal request for information (RFI) to the

Contracting Officer.

1.1.1.2. The Contractor shall conduct an in-person site visit prior to submitting proposal.

Administrative Project Requirements

2. Safety Requirements

2.1. Health and Safety Standards: The facilities, systems, and equipment design standards of the

Occupational Safety and Health Act, Code of Federal Regulations, Title 29, Chapter XVII, Parts 1910 and 1926 as applicable will be incorporated by the Architect-Engineer into all engineering design and analyses furnished pursuant to this contract. Any problems in incorporating these standards due to conflicts with other technical criteria will be promptly submitted to the Safety, Health and

Environmental Programs Division and Contracting Officer for decision.

2.2. Accident Prevention Plan (APP) and Activity Hazard Analysis (AHA): Before initiation of any work, the Contractor shall develop and submit to the Safety, Health and Environmental Programs

Division and COR for acceptance, prior to a comprehensive site specific Accident Prevention Plan

(APP) and Activity Hazard Analysis (AHA), in accordance with the EM-385-1-1, U.S. Army Corps of

Engineer Safety and Health Requirements Manual (latest edition at time of solicitation on website):

http://www.usace.army.mil/SafetyandOccupationalHealth.aspx).

2.3. Site Safety and Health: The Contractor shall comply with FAR 52.236-13 and all site/safety/health/ environmental/personal protection and pedestrian/vehicular traffic control plans. The

APP and AHA shall comply with Occupational Safety & Health Administration (OSHA) rules/regulations/laws, Corps of Engineers Safety and Health Requirements EM 385-1-1, Federal

Highway Administration (FHWA) standards/recommendations (if applicable), Uniform Federal

Accessibility Standards (UFAS), Architectural Barriers Act (ABA) and all other laws, codes, rules, regulations, executive orders, Authority Having Jurisdiction (AHJ) and guidelines applicable or associated with the type of work required under this contract prior to the start of on-site work. In the event of conflict between any requirements the more stringent requirement shall apply.

2.4. Other Government Contractor’s Construction Zone: In the event the Contractor’s activities require them to traverse into an Other Government Contractor’s (OGC) construction zone, the

Contractor and their subcontractors shall be responsible for participating in the OGC’s safety training program.

2.5. First Response Coordinator for Emergency Services: The Contractor’s Site Safety and

Health Officer (SSHO) shall ensure that all their employees, including subcontractors, are aware that for emergencies inside the campus are to call 911. All injuries or incidents shall be reported to the

COR and Government Safety Representative within one hour of the occurrence. The Contractor is required to use the USACE ENG 3394 Accident Reporting Form and submit within 5 business days of an accident/incident.

http://www.usace.army.mil/SafetyandOccupationalHealth.aspx

2.6. The Contractor must limit production of particulates during construction and ensure that no airborne particles leave the space in question.

2.7. The Contractor shall take all reasonable measures to protect USSS personnel and property from exposure, injury or damage resulting from their operations. The Contractor shall be responsible for the cost of restoration work to the Government’s property.

3. Existing Conditions Survey, Testing, and Reports

3.1. Existing Conditions Survey: The Contractor shall conduct an existing conditions survey of the adjacent spaces to the project area which have direct impact on the project. The survey shall include all systems affected by the scope of work including those not functional at the time the survey was conducted. The Contractor shall evaluate the availability, capacity, location, and connections of existing utilities.

3.2. Existing Conditions Tests: The Contractor shall be responsible for performing any testing necessary to confirm the existing conditions are adequate for the full execution of all planned work

(e.g. structural capability, geotechnical investigation, mechanical equipment). If the Contractor proceeds with the work before testing and confirmation have been completed, any rework due to issues with unsuitable existing conditions shall be at the cost of the Contractor. This includes implementation of manufacturer’s recommendations, recommended tests, and validation of product’s installation requirements.

3.3. Existing Conditions Reports: The Contractor shall provide existing conditions reports for

Government acceptance. The existing conditions reports shall summarize the findings from the existing conditions survey. All deficiencies and any modifications to the existing conditions shall be identified in the existing conditions report and the report will be presented within 60 calendar days from Task Order Award. Failure to identify deficiencies in the existing conditions reports shall indicate the Contractor’s concurrence that such systems are in good working condition or will be brought to acceptable working condition by the Contractor according to the technical requirements of this RFP.

3.3.1. Existing Conditions Report – General Report: The Contractor shall include utilities located within the project areas having points of origin outside of the project area. All necessary modifications to the existing systems shall be identified in the existing conditions report and included in the Contractor’s design.

4. Design and Construction Submissions

4.1. Design Work: The Contractor shall provide a design for the work under this contract in accordance with the requirements of this RFP, any referenced attachments, and all applicable local, state, and federal codes. The design shall be functional, compatible with existing systems, and shall meet the overall project scope, cost, and schedule. The design for this project shall be coordinated with existing conditions in adjacent spaces as to not cause any safety hazards or adverse impacts to existing systems. All systems, devices, doors and other work, equipment and materials designed, modified and/or installed by the Contractor shall be compatible with and operate in conjunction with existing systems.

4.2. Obligating the Government: The Contractor shall not design and/or use proprietary components that will obligate the Government (i.e. subscriptions, license, maintenance contracts).

4.3. Designer of Record (DOR): The Contractor shall obtain the services of a designated

Registered Architect/Professional Engineer defined in Unified Facilities Criteria UFC 1-300-09N to serve as the Designer of Record (DOR). The DOR must have proven experience in design, installation, and commissioning in projects of similar scope and is the design-certifying authority throughout the project. The DOR shall be involved at every step of the project and is responsible for design work of his or her respective discipline.

4.4. Design Packages: The Contractor shall produce a design package in accordance with the

RTC Electronic Drawing Standards and UFC 1-300-09N.

4.5. For the Issue for Construction (IFC) submission and all submissions during construction, the DOR shall seal, date, and sign all components of the submission in hard copy form as released for construction and provide copies for distribution from the original set. The DOR shall electronically sign and date Issue for Construction (IFC) submissions in accordance with UFC 1-300-09N.

4.6. Design documentation and specifications shall not be proprietary.

4.7. All documentation and products produced in this contract shall be in accordance with the

Site Security Classification.

4.8. The Contractor shall provide Erosion and Sedimentation controls as required by Federal, State and local laws and regulations. General Permit for Stormwater Associated with Construction

Activity (if >1 acre of land disturbed) and the MS4 Phase II General Permit for State and Federal

Agencies (if > 5000 sqft or > 0.1 acres of land area or 100 cubic yards or earth movement are involved.

4.9. Government review or acceptance of any design submission under this contract shall not relieve Contractor of its sole responsibility to perform all contract requirements and deliver a product that in all respects conforms to the contract requirements. Acceptance/review by the Government shall not constitute a waiver or change to the contract requirements unless that change or waiver is expressly approved in writing by the Contracting Officer.

4.10. Submittals: All construction submittals such as Pre-Construction, design, shop-drawings and close-out documents shall be reviewed by the DOR and contain the DOR approval stamp with signature and date along with corresponding specification number and paragraph, variation / deviation notification, and whether the submittal is For Information Only (FIO) or Government Acceptance

(GA). All submittals shall also be reviewed by the Contractor’s Quality Control Manager (QCM) and contain the QCM’s stamp with signature. The stamp(s) shall also identify the specific project, transmittal number, submittal description and corresponding date of submittal. If the information is not complete, the submittal shall be rejected and returned to the Contractor. Submittals that contain deviations from the SOW must be specifically identified as containing a deviation from the SOW and contain a detailed explanation for the deviation. Government review or approval of any design document submittal, shop drawing or plan shall not be deemed to approve any deviation from the SOW unless the deviation is specifically identified in the submittal and expressly approved in writing by the

Government.

4.11. Design Coordination with Other Government Contractors (OGCs) and Other Government

Agencies: The Contractor shall coordinate work with OGCs, and shall carefully adapt its design (as applicable), schedule and performance of the work to accommodate the work of the OGCs. The

Contractor shall take coordination direction from the COR. The Contractor shall make every reasonable effort to avoid interference with the performance of work by the OGCs, as scheduled by the

OGCs or by the Government. The Contractor shall be responsible for coordinating the work of OGCs and other Government agencies into their design package (as applicable).

4.12. Telecommunications: N/A

4.13. Paint Requirements: N/A

4.14. Stormwater Management: The Contractor must follow requirements stated in detailed in the RTC MS4 permit and applicable Maryland regulations.

4.15. Plumbing Requirements – N/A

4.16. Electrical Requirements:

4.16.1. Electrical panels serving the project area shall have a minimum 50% spare capacity.

4.16.2. All low voltage wiring, including security, IT, and controls, shall be in continuous pathways. These pathways shall be furnished and installed by the Contractor after fully coordinating and documenting the locations with Other Government Contractors (OGC) as applicable. Pathways shall be of flex conduit, rigid conduit, or cable tray and installed in accordance with the applicable code.

4.16.3. All lighting shall be LED.

4.16.4. The contractor is responsible for the removal and/or relocation of site lighting poles and fixtures with the appropriate utility authority.

4.17. Grounding

4.17.1. Ground electrical circuits, equipment and enclosures in accordance with National Fire

Protection Association (NFPA70) and International Electrical and Electronics Engineers (IEEE C2) to provide a permanent, continuous and effective path to ground unless otherwise noted by EM 385-1-1.

4.17.2. Check grounding circuits to ensure that the circuit between the ground and a grounded power conductor has a resistance low enough to permit sufficient current flow to allow the fuse or circuit breaker to interrupt the current.

4.18. Utilities and Underground Pipes

4.18.1. Provide detectable aluminum plastic backed tape for detectable magnetic plastic taped manufactured specifically for warning and identification of direct buried piping. Tape must be detectable by an electronic detection instrument. Warning tape to be color coded with warning and identification of utility type imprinted in bold black letters continuously over the entire tape length.

Warning and identification to read, “CAUTION, BURIED (utility type) LINE BELOW” or similar wording.

4.18.2. All utilities shall be sized to accommodate future expansion.

4.18.3. The contractor is responsible for the connection of all utilities and the proper coordination with the applicable utility authority; utility connections include but not limited to power, communications.

4.18.4. No utility marking resources are available on-site, therefore, at the Contractor’s expense, he/she shall arrange separately the services of a private utility locating company. At a minimum, utility marking scanning should be accomplished with GPR and/or other appropriate equipment, and the surfaces where existing underground utilities are found should be marked. Also, elevations and existing piping/utilities discovered during scanning should be verified.

4.19. Optimize Energy Performance

5. Ventilation and Thermal Comfort

5.1.1.1. Design to meet American Society of Heating Refrigerating and Air Conditioning

Engineers (ASHRAE) 189.1, Section 8.3.1 "Indoor Air Quality" 62.1 and Section 6.3.2 "Thermal

Environmental Conditions for Human Occupancy". Design submittal documentation required Provide documentation showing project HVAC system meets minimum requirements of Sections 4 through 7 of ASHRAE 62.1. (Documentation as described in Section 6.2 is not required), and other provisions of

ASHRAE 189.1.

5.1.1.2. Provide documentation showing that HVAC systems and the building envelope have been designed to meet the requirements of ASHRAE 55 (Documentation as described in Section 6.2 is not required).

5.1.1.3. The HVAC system shall be supplied by electric power.

6. Moisture Control

6.1.1.1. Follow the requirements for UFC 3-101-01.

6.2. Fire Protection and Life Safety

6.2.1. Applicable code requirements.

6.2.2. Fire Alarm and Mass Notification Systems (If applicable)

6.2.2.1. The RTC fire alarm and mass notification system is manufactured by Notifier®.

Any new equipment shall be manufactured by or fully compatible with Notifier® to operate accurately and reliably with the existing system. Modifications to the existing system and new systems shall incorporate mass notification requirements and be compatible with the existing system network.

6.2.2.2. Fire Alarm and Mass Notification System Shop Drawings: The Contractor shall provide complete information on system additions and modifications per NFPA 72, including specifications, type of system, shop drawings, input/output matrix, battery calculations, point-to-point wiring diagrams for initiating devices and notification appliance circuits, and notification appliance circuit voltage drop calculations submitted for approval.

6.2.2.3. Fire Alarm As-Built shop drawings shall be provided including source files. There shall be no exclusion of documenting small diameter wires as applied specifically to fire alarm initiating circuits and fire alarm notification appliance circuits. Although these fire alarm wires have a smaller diameter, they are essential for maintaining the fire alarm system.

6.2.3. Fire Suppression Systems

6.2.3.1. The Contractor shall provide complete information on system additions and modifications in accordance with the appropriate NFPA Standard (e.g., NFPA 13, 15, 20, 2001) submitted for approval.

6.2.3.2. Fire Suppression as-built shop drawings shall be provided including source files.

6.3. Design Deliverables

6.3.1. All AutoCAD files and Requests For Information (RFI’s).

6.3.2. The Contractor’s design and specifications shall document correct size, capacity, location, and connections to meet project requirements.

6.3.3. Unless specified otherwise, the Contractor shall provide materials and equipment that are products of manufacturers regularly engaged in the production of such products which are of equal material, design and workmanship. Products shall be in satisfactory commercial or industrial use for 2 years prior to bid opening. The 2-year period shall include applications for equipment and materials under similar circumstances and of similar size. Materials and equipment shall not be end-of-life products or in the final stages of a product’s existence.

6.3.4. The Contractor’s design deliverables shall comply with UFC 1-300-09N and requirements listed within the RFP.

6.3.5. Basis of Design (BOD): The Contractor shall develop a BOD for all design submissions and include all disciplines. The BOD narrative, broken out by discipline, shall include design and engineering calculations and assumptions in support of the design and shall describe the systems, components, conditions, and methods chosen to meet the project requirements and design intent.

6.3.6. Specifications: The Contractor shall provide project specifications that, in conjunction with the drawings, demonstrate compliance with materials, equipment, execution, field quality control requirements. The Contractor shall provide location and project-specific Division 01 specifications.

The products specified shall include equipment, fixtures, devices, and systems to be utilized in the construction of this project. Per ER-1110-1-8155, specifications shall follow CSI MasterFormat®

(latest edition).

6.3.7. Design Package Submissions: Please submit as follows:

6.3.8. 65% Design Package Submission: These documents shall include all applicable disciplines, any key information from the Contractor’s existing conditions survey, site walks, and any other design data requested to illustrate design intent per UFC 1-300-09N. Additionally, it shall address all design aspects that must be incorporated into this project in sufficient detail to show that all systems are defined and developed. These systems should be compatible with and work effectively with the existing Site systems. All deliverables shall incorporate all project-related findings, such as testing, investigations and verifications necessary to complete the final design. The submission shall include:

6.3.8.1. Drawings, including title sheet and index, following the AIA Electronic Drawing

Standards.

6.3.8.2. Basis of Design including all applicable design calculations.

6.3.8.3. Specifications: At a minimum, an outline of proposed specification sections applicable to this project and location shall follow the CSI Master Format.

6.3.8.4. Design and Construction Submittal Registers.

6.3.8.5. Conceptual Sketch.

6.3.8.6. Drawings, including title sheet and index,

6.3.8.7. Updated Basis of Design including all design calculations.

6.3.8.8. The specifications shall include each applicable specification

(including Division 1) updated to be project and location specific.

6.3.8.9. Updated Design and Construction Submittal Registers.

6.3.8.10. Finish (color) boards for all finishes and Furniture Fixtures and Equipment (FFE).

Finish boards shall contain actual material samples at least 12”x12” in size.

6.3.8.11. A DVD-RW containing the SKM analysis for all Short Circuit Analysis, Arc Flash

Analysis and the Coordination Studies.

6.3.8.12. Commissioning Design Requirements shall be in accordance with the

Commissioning section of this RFP.

6.3.9. Demolition and Decommissioning: The Contractor may request to start demolition as early as the acceptance of the 65% design package submission, provided the Contractor has submitted a 100% demolition plan and a decommissioning plan. T h e s u b m i t t a l m u s t i n c l u d e a list of equipment or utilities being removed or relocated during demolition must be specified in the demolition plan narrative.

6.3.10. 100% Design Package Submission: The intent is to provide a complete set of design documents. These documents shall address all design aspects that must be incorporated into this project in sufficient detail to show that all systems are defined and developed. These systems shall be compatible with and work effectively with the existing Site systems. All deliverables shall incorporate any and all 65% design comments, project-related findings, such as testing, investigations and verifications necessary to complete the final design. The submission shall include:

6.3.10.1. All items listed in the 65% design submission.

6.3.10.2. Copies of the discipline-specific Designer of Record (DOR) quality control checklists (provided in Contractor’s DQC Plan).

6.3.10.3. 65% comment incorporation back check, using comment spreadsheet from 65%

OBR.

6.3.10.4. Drawings, including title sheet and index, following the RTC Electronic Drawing

Standards (attached).

6.3.10.5. Basis of Design including all applicable calculations.

6.3.10.6. Specifications shall be project and location specific

6.3.10.7. Updated Design and Construction Submittal Registers, reflecting each specification’s submittal requirements.

6.3.10.8. Updated finish (color) boards for all finishes and FFE, if necessary.

6.3.11. Issue for Construction (IFC) Requirements: All comments from 100% Design Package must be resolved in the IFC Submission. Any Contractor initiated changes to the drawings or specifications after the Government acknowledges receipt of the IFC Documents will require

Government review and acceptance. Changes to these drawings and/or specifications shall include the condition or change, any revised calculations, and any impacts to the cost, schedule, or performance.

6.3.12. Drawing Revisions for Field Changes: On a monthly basis, the Contractor shall submit updated drawings, Basis of Design (BOD), and specifications revised due to field changes and contract modifications. These revisions shall also reflect engineering changes by Other Government

Contractors (OGC) components. Whole packages are not required, only drawing sheets and/or sections impacted. Field copies of drawings shall include all slip sheets with all updates.

6.4. Design Submissions Reviews

6.4.1. The Government shall have a total of 14 calendar days to review all design package submissions. The Contractor shall schedule an over the shoulder review to deliver the design package.

The Contractor shall review the design with the Government, capture comments, and address all comments. Additional comments may be submitted by the end of the review period. During the review meeting the Contractor shall address outstanding comments, from previous design reviews.

6.4.2. The Government will review and comment on each design submission using a government-provided design comment tracking spreadsheet. The Contractor shall respond to these comments by providing their responses on the same spreadsheet within seven business days after the

Government submits comments.

6.4.3. For Government acceptance of a design package, all review comments from prior submission(s) must be resolved, or an explanation of deferment must be included for any unresolved

Government comments.

6.5. Over the Shoulder Review Meetings

6.5.1. An over the shoulder review meeting shall occur with all design submissions, except for the Issue for Construction submission. The over the shoulder meeting agenda shall include review of Government-provided comments and the Contractor’s responses to those comments. The

Contractor shall lead each meeting. Participants at the over the shoulder meeting shall include but are not limited to the Contractor project manager, superintendent, Quality Control Manager, the Designer of Record, Design lead for each discipline, Government representatives and other key design personnel. The Contractor shall bring two (2) original ANSI “E” and two (2) ANSI “B” hard copy drawings, and one soft copy of each deliverable for review purposes. These meetings may be virtual at the discretion of the USSS.

6.5.2. On Board Review (OBR) Meeting Minutes: The Contractor shall incorporate and address any additional comments into the design comment spreadsheet. The Contractor shall submit meeting minutes, to include responses to all Government comments as well as documentation of all other items discussed during the meeting, the sign-in sheet, and scanned redlines of any marked-up drawings within 3 calendar days of the OBR meeting. The Government will review and provide feedback on these minutes to the Contractor within 3 calendar days.

6.5.3. Regardless of who calls the meeting, the Contractor shall provide meeting minutes to the COR within 48 hours after all Teams, telephonic, and/or in-person meetings/discussions held with

Government representative.

6.6. Design Deliverables Table: The Table summarizes the initial design deliverables. This does not relieve the Contractor of submitting all other identified deliverables required in this SOW.

Electronic copies will be accepted via email or DVD. Electronic copies must include both source file and PDF versions. Email files are limited to 5MB. The Contractor shall follow submittal procedures outlined in their approved Quality Control Plan. in this case, the 65% design is referenced below to provide the minimum requirements for the applicable project design submissions (35%, 65% and IFC).

Table 1 – Design Deliverables

Deliverable Due Date Quantity

Government Review

Period

Existing Conditions Survey

Reports

14 calendar days from award and prior to first design submission

2 electronic copies

1 hard copy

14 calendar days

Design Quality Control (DQC)

Plan

Acceptance prior to the first design submission

1 electronic copy

1 hard copy

Design Package Submissions Per contractor schedule

Hard copy Drawings:

(1) ANSI “D”, (2)

ANSI “B”; 2 electronic copies

Drawing Revisions for Field

Changes monthly

2 electronic copies

2 hard copies

FIO

As-Built Package

Within 30 calendar days after construction completion

(2) ANSI “D”, (1) ANSI

“B”; 2 electronic copies

6.7. Design Changes During Construction: If changes to the design are required, the

Contractor shall immediately submit a Request for Information (RFI) to the COR describing the issue and providing possible solutions. The solution shall be verified and coordinated with the designer of record and shall include a sketch and design narrative. If a new product is required, a specification for this product shall be included as part of the RFI. The Government review period for RFI’s is fourteen

(14) calendar days.

6.8. Design Support During Construction: On a monthly basis, or more often, as necessary, to review construction prior to close-ins or to resolve field issues, the Contractor’s core A/E Team shall verify field construction and perform design administration to ensure that the design is correctly implemented. The Contractor team shall submit a report detailing what was inspected and conformance with the design. If differences occur from the original design, the Contractor shall immediately submit a Request for Information (RFI) to the COR, describing the issue and providing possible solutions. The solution shall be verified and coordinated with the designer(s) and engineer(s), shall include a sketch, a design narrative, and will require approval from the COR. If a new product is required, a specification for this product shall be included as part of the RFI.

6.9. The Contractor may submit a phased design which shall be reflected in the initial schedule and in the Basis of Design (BOD) to support a phased construction. Should subsequent design submissions require changes to the design and/or construction in progress, it will be at the risk of the

Contractor.

7. Code Requirements: The Contractor shall ensure that all systems within the construction space meet current (as of the proposal submission date) industry standards, regulations, and codes.

7.1. Discrepancies: If there are discrepancies in any of the code requirements, the most stringent code shall prevail. In each of the publications referred to herein, consider the advisory provisions to be mandatory, as though the word “shall” had been substituted for “should” wherever it appears. Interpret references in these publications to the “authority having jurisdiction” or works of similar meaning to mean the Contracting Officer.

7.2. Codes: The Contractor shall comply with all requirements of the latest addition of the

International Code Council (ICC) codes, American Society of Heating, Refrigerating and Air-

Conditioning Engineers (ASHRAE) guidelines, National Electric Code (NEC), NFPA, and any other applicable codes. Completed facilities and systems must meet Occupational Safety & Health

Administration (OSHA) General Industry Standards. Construction in progress must meet OSHA construction standards. The Contractor shall follow the scoping provisions of the Uniform Federal

Accessibility Standards (UFAS) and the design guidance in the Accessibility Guidelines of the

Americans with Disabilities Act (ADAAG).

7.3. Code Interpretation: The Government has final authority concerning all code and JJRTC regulation interpretation issues and shall make the final determination concerning any compliance, deviation, waiver or risk acceptance with applicable codes. The Government is the Authority Having

Jurisdiction (AHJ).

7.4. Environmental Regulatory Codes: The following codes shall be incorporated: National

Environmental Policy Act (NEPA): [42 USC 4321 et seq.]; Federal regulations.

7.5. IT systems shall be designed in accordance with CIO requirements listed herein.

8. Sustainability Requirements

8.1. Energy Efficiency: The Contractor shall meet or exceed the goals and objectives stated in

Executive Orders EO 14057 Catalyzing Clean Energy Industries and Jobs Through Federal

Sustainability, EO 13327-Federal Real Property Asset Management, EO 13514-Federal Leadership in

Environmental, Energy, and Economic Performance, EO 13508- Strategy for Protecting and Restoring the Chesapeake Bay Watershed, EO 13221-Energy Efficient Standby Power Devices as applicable to the task order.

8.2. Environmental Initiatives: The Contractor shall meet or exceed the goals and objectives stated in Executive Order EO 13423, Strengthening Federal Environmental, Energy, and

Transportation Management.

9. Demolition and Construction Requirements

9.1. Start of Demolition or Construction: The Contractor shall coordinate with Government at least 2 weeks prior to the start of any demolition or construction activities. All applicable plans, permits, prerequisite submittals, and safety considerations shall be submitted and accepted prior to any demolition or construction.

9.2. Impacts to Other Areas: Existing utilities shall remain in service throughout construction.

The Contractor shall notify the COR in writing when work will affect areas outside the limits of work under this Contract at least two weeks in advance of such work.