This document is an Asbestos Pre-Demolition Survey Report prepared by ASAP Environmental Inc. for the Army Corps of Engineers at a restroom facility located at 60 Doug Hill Road, Holland, Massachusetts.
The survey was conducted on August 18, 2025, in accordance with EPA NESHAP, OSHA 1926.1101, and Massachusetts Department of Environmental Protection regulations. The inspection identified one asbestos-containing material (ACM): chrysotile caulking present where the CMU block foundation meets on all four exterior sides of the building, with a quantity of 72 linear feet and a concentration of 2 percent asbestos. The caulking material is in intact condition. Additional samples tested negative for asbestos (NAD): CMU block mortar, foundation material, roof shingles, and window glazing/caulking. The report recommends that all identified ACM materials be removed by licensed and trained asbestos personnel prior to any renovation or demolition activities. The abatement, monitoring, and clearance activities must comply with EPA 40 CFR Part 61 Subpart M (NESHAP), OSHA 29 CFR 1910 and 1926, Massachusetts Department of Labor Standards, and Massachusetts Department of Environmental Protection regulations. The survey was conducted by Michael Sullivan, a licensed asbestos inspector, with laboratory analysis performed by Environmental Hazards Services, LLC using Polarized Light Microscopy per EPA methods 600/M4-82/020 and 600/R-93/116.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachments_Amendment.pdf | ||
| Amendment W912WJ26QA109-0003.pdf | ||
| Amendment W912WJ26QA109-0002.pdf | ||
| Amendment W912WJ26QA109-0001.pdf | ||
| Solicitation Survey 26QA109.pdf | ||
| Solicitation W912WJ26QA109.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
25.5’ - 26.5’
9.5’ - 10.5’
9’ - 10’
8’ - 9’
9’ - 10’
7’ - 8’
Preliminary Sketch, for reference only
RESTROOM DEMOLILTION & NEW RESTROOM INSTALLATION
LAKE SIOG RECREATION AREA
HOLLAND, MA
PHOTOS
Photo 1 – View of restroom exterior facing south
Photo 2 - View of restroom exterior facing north
Photo 3 - View of restroom facing east
Photo 4 - View of men’s restroom
Photo 5 - View of women’s restroom
Photo 6 - View of women’s restroom vestibule
Photo 7 - View of utility room