Attachment_Zd__Schedule_Template_for_CAVE.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- CAHA SIGN PLAN
- Solicitation number
- 140P2124Q0026
About this file
This document is a schedule template for a federal sign plan contract between the National Park Service and a contractor. The template outlines four tasks for the contractor to complete, including project overview and existing conditions documentation, sign planning and locating sketches, sign drawings and fabrication details, and final deliverables. The contractor must fill in planned completion dates for each task and subtask which will be reviewed by the government on the dates indicated. The contractor will work with the National Park Service and the Historic Facilities Center on reviews at various stages of the project. All work must be completed by the contract end date listed.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Attachment Zd - Schedule Template for CAHA Contractor to fill in all yellow boxes
| Title of project/park name | CAHA Comprehensive Sign Plan |
| Contract Number | |
| Contractor Name |
| Contract award date |
| Contract end date |
| Item | # days to complete task | Due Date |
| Task 1: Project Overview and Existing Conditions Documentation | ||
| Post award Tele-conference call date | ||
| Written Summary Kick-off Notes | TBD by Contractor | |
| Project Schedule | within 10 fed. Business days of Kick-off Call | |
| Government Review of Notes | 5 fed. Business days | |
| Site visit with Contractor, COR, and Park staff | 4 Days | |
| Existing Conditions Report | TBD by Contractor | |
| Review by government | 10 fed. business days | |
| Existing Conditions Report Revisions | TBD by Contractor | leave blank unless needed |
| Additional Reviews if required | 6 fed. business days |
| After approval of Task 1 contractor may continue on to Task 2 | |
| Task 2: Sign Planning and Locating | |
| Sketches Meeting Notes | TBD by Contractor |
| Government Review of Notes | 5 fed. Business days |
| Sign Type Menu | TBD by Contractor | |
| Initial HFC review | 10 fed. business days | |
| Revision of SM | TBD by Contractor | |
| HFC and Park Review | 15 fed. business days | |
| Revision of SM | TBD by Contractor | |
| Additional Review or approval | 10 fed. business days | |
| Revision of SM | TBD by Contractor | leave blank unless needed |
| Additional Reviews if required | 10 fed. business days |
| Message Programming, Location, and Demolition Plan | TBD by Contractor | |
| Initial HFC review | 10 fed. business days | |
| Revisions of MP, LP, and DP | TBD by Contractor | |
| HFC and Park Review | 20 fed. business days | |
| Revision of MP, LP, and DP | TBD by Contractor | |
| Additional Review or approval | 10 fed. business days | |
| Revision of MP, LP, and DP | TBD by Contractor | leave blank unless needed |
| Additional Reviews if required | 10 fed. business days |
| After approval of Task 2 contractor may continue on to Task 3 | ||
| Task 3: Sign Drawings and Fabrication Details | ||
| Sign Panel Layouts, Structures, and Sign Location Plans | TBD by Contractor | |
| Initial HFC review | 10 fed. business days | |
| Revisions of SPL, S, and LP | TBD by Contractor | |
| 1st Review with Park | 20 fed. business days | |
| 1st Revision of SPL, S, and LP | TBD by Contractor | |
| 2nd Review with Park | 10 fed. business days | |
| 2nd Revision of SPL, S, and LP | TBD by Contractor | leave blank unless needed |
| Additional Reviews if required | 10 fed. business days |
| Fabrication Details | TBD by Contractor | |
| Initial HFC review | 7 fed. business days | |
| Revisions of FD | TBD by Contractor | |
| 1st Review with Park | 10 fed. business days | |
| 1st Revision of FD | TBD by Contractor | |
| 2nd Review with Park | 7 fed. business days | |
| 2nd Revision of FD | TBD by Contractor | leave blank unless needed |
| Additional Reviews if required | 7 fed. business days |
| After approval of Task 3 contractor may continue on to Task 4 | |
| Task 4 | |
| All final files in PDF and native design program | TBD by Contractor |
| Government Review | 7 fed. business days |
Contract end date