This document provides a project schedule for the construction of a new Department of Veterans Affairs mental health clinic and domiciliary in Tampa, Florida. The schedule outlines key milestones and tasks from notice to proceed through final activation, spanning from February 2022 through January 2024. It details construction phases including site work, structure erection, building enclosure, buildout of clinic and domiciliary spaces, and offsite roadway improvements. The schedule identifies task dependencies and durations for concrete work, structural steel installation, mechanical system rough-ins and finishes, interior partitions and casework, and other building components. The solicitation number for the related IOTA contract to complete this work is 36C77622Q0199.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task
Mode
Task Name Start Finish Duration
1 MILESTONES Tue 3/9/21 Tue 1/30/24 726 days
23 Construction Duration Mon 11/29/21 Mon 7/31/23 436 days
26 Notice to Proceed Fri 2/18/22 Fri 2/18/22 0 days
27 Groundbreaking Ceremony Tue 4/19/22 Tue 4/19/22 0 days
28 GSA/VA Inspection Notice (4.10A) Fri 7/14/23 Fri 7/14/23 0 days
29 Substantial Completion = VA Acceptance Thu 7/27/23 Thu 7/27/23 0 days
30 Activation 4.01G Fri 7/28/23 Tue 1/30/24 128 days
32 CONSTRUCTION MILESTONES Mon 5/3/21 Thu 7/27/23 559 days
50 SWFMD Phase 2 Permit Thu 11/4/21 Mon 2/28/22 77 days
62 Foundation Permit Mon 11/22/21 Mon 2/14/22 57 days
63 Building Permit Tue 2/15/22 Mon 2/28/22 9 days
72 Temporary Power On For Trailer Thu 2/24/22 Thu 2/24/22 0 days
73 Comissioning - Prefunctional Checklist Issued Mon 4/4/22 Mon 4/4/22 0 days
74 Complete Mockup Wall Thu 4/14/22 Thu 4/14/22 0 days
75 Comissioning - Functional Test Protcol Templates Issued Mon 10/3/22 Mon 10/3/22 0 days
76 Permanent Power On Tue 10/18/22 Tue 10/18/22 0 days
77 Main Electrical Room Complete/Ready to Energize Tue 10/18/22 Tue 10/18/22 0 days
78 Set Clinic RTU's Fri 9/16/22 Tue 9/20/22 3 days
79 Set Chillers & Energize Wed 9/21/22 Fri 9/30/22 8 days
80 Set Transformers Wed 9/21/22 Wed 9/21/22 1 day
81 Startup RTU's Tue 10/25/22 Mon 10/31/22 5 days
82 Set Generators Thu 12/1/22 Fri 12/2/22 2 days
83 Gas Turned On Tue 5/9/23 Tue 5/9/23 0 days
84 Test & Balance Wed 12/14/22 Mon 3/6/23 55 days
85 Comissioning - Functional Testing Tue 3/7/23 Mon 3/20/23 10 days
86 Domiciliary Buildout Duratioin Fri 9/9/22 Tue 5/2/23 161 days
87 Clinic Buildout Duration Tue 6/21/22 Tue 5/9/23 222 days
88 Final Inspections Fri 5/19/23 Fri 6/9/23 15 days
89 Certificate of Occupancy Fri 6/9/23 Fri 6/9/23 0 days
90 Final Punchlist Wed 6/28/23 Thu 6/29/23 2 days
91 Work Off Punchlist Fri 6/30/23 Thu 7/27/23 20 days
93 SITEWORK Wed 12/1/21 Tue 5/23/23 370 days
99 Cut / Fill Site Fri 1/7/22 Mon 2/28/22 35 days
100 Storm Water Piping Tue 3/1/22 Mon 4/18/22 35 days
101 CLINIC BUILDING PAD COMPLETE Wed 2/9/22 Wed 2/9/22 0 days
102 Domicilaries Building Pads Complete Wed 2/9/22 Wed 2/9/22 0 days
103 Fine Grade Site (Stone for Crane) Thu 2/10/22 Thu 3/10/22 20 days
104 Clear Site Phase 2 Tue 3/1/22 Thu 3/10/22 8 days
CONSTRUCTION DURATION
2/18
4/19
7/14
7/27
Activation 4.01G
SWFMD Phase 2 Permit
Foundation Permit
Building Permit
2/24
4/4
4/14
10/3
10/18
10/18
Set Clinic RTU's
Set Chillers
Set Transformers
Startup RTU's
Set Generators
5/9
Test & Balance
Comissioning - Functional Testing
Domiciliary Buildout Duratioin
Clinic Buildout Duration
Final Inspections
6/9
Final Punchlist
Work Off Punchlist
Cut / Fill Site
Storm Water Piping
2/9
2/9
Fine Grade Site (Stone for Crane)
Clear Site Phase 2
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
VA Tampa Mental Health Clinic and Domicilary
Cullinan Properties, LTD
Leo A Daly
Prosser Inc.
Hoar Construction
Wed 2/16/22 Page 1 VA/GSA
Task Name Start Finish Duration
105 Install Sanitary Sewer Piping Tue 3/1/22 Mon 3/21/22 15 days
106 Grading Retention/Detention Ponds Fri 3/11/22 Thu 3/24/22 10 days
107 Bulkhead @ Ponds Fri 3/25/22 Thu 5/5/22 30 days
108 Domestic Water / Fire Main Piping Tue 3/22/22 Mon 4/18/22 20 days
109 Install Lift Station Tue 4/19/22 Wed 4/20/22 2 days
110 Install Phone Lines/Conduits Tue 4/19/22 Mon 4/25/22 5 days
111 Install Gas Line Tue 4/19/22 Mon 5/2/22 10 days
112 Install New Primary & Secondary Electrical Lines Tue 4/19/22 Mon 5/2/22 10 days
113 Install Site Lighting Tue 5/3/22 Tue 6/14/22 30 days
114 Curb and Gutter @ Perimeter Wed 6/15/22 Thu 7/28/22 30 days
115 Install Grease Interceptor Mon 8/1/22 Fri 8/5/22 5 days
116 Stone Base / Fine Grade Fri 7/15/22 Thu 8/18/22 25 days
117 Install Base for Paving Fri 8/19/22 Fri 9/9/22 15 days
118 Install Curb and Gutter / Sidewalks/ Bike Rack Pads Tue 12/20/22 Thu 1/26/23 25 days
119 Irrigation Thu 1/12/23 Fri 2/24/23 30 days
120 Hardscapes Fri 1/27/23 Fri 3/24/23 40 days
121 Landscaping Fri 2/10/23 Fri 4/7/23 40 days
122 Install Basketball Court & Goal Fri 1/27/23 Fri 2/24/23 20 days
123 Light Poles & Bases Fri 1/27/23 Fri 2/24/23 20 days
124 Paint Basketball Court Mon 2/27/23 Tue 2/28/23 2 days
125 Install Pavilions & Sheds Mon 3/27/23 Fri 4/14/23 15 days
126 Site Furnishings & Bike Racks & Flag Poles Mon 3/27/23 Fri 4/14/23 15 days
127 Install Site Fencing Mon 4/10/23 Fri 5/5/23 20 days
128 Install Lift Gates & Arms Mon 3/27/23 Wed 3/29/23 3 days
129 Install Monument Sign Thu 3/30/23 Wed 4/5/23 5 days
130 Patch / Clean Base Mon 3/13/23 Fri 4/14/23 25 days
131 Final Asphalt Paving Wed 3/29/23 Tue 4/18/23 15 days
132 Cure Asphalt Wed 4/19/23 Tue 5/2/23 10 days
133 Striping / Signage Wed 5/3/23 Tue 5/9/23 5 days
134 Punchlist / Inspections Wed 5/10/23 Tue 5/23/23 10 days
136 TEMPLE TERRACE OFFSITE ROADWAY WORK Thu 6/23/22 Fri 1/6/23 135 days
137 TECO Power Pole Relocation Thu 6/23/22 Thu 7/7/22 10 days
138 Permitting Mon 10/10/22 Fri 10/14/22 5 days
139 Lane Closures/Signage Mon 10/17/22 Tue 10/18/22 2 days
140 Erosion Control Mon 10/17/22 Tue 10/18/22 2 days
141 Demo/Regrade Wed 10/19/22 Tue 11/1/22 10 days
142 Storm Drain Modifications Wed 11/2/22 Tue 11/8/22 5 days
143 Curbs/Gutters/Sidewalks Wed 11/9/22 Mon 11/14/22 3 days
Install Sanitary Sewer Piping
Grading Retention/Detention Ponds
Bulkhead @ Ponds
Domestic Water / Fire Main Piping
Install Lift Station
Install Phone Lines/Conduits
Install Gas Line
Install New Primary & Secondary Electrical Lines
Install Site Lighting
Curb and Gutter @ Perimeter
Install Grease Interceptor
Stone Base / Fine Grade
Install Base for Paving
Install Curb and Gutter / Sidewalks/ Bike Rack Pads
Irrigation
Hardscapes
Landscaping
Install Basketball Court & Goal
Light Poles & Bases
Paint Basketball Court
Install Pavilions & Sheds
Site Furnishings & Bike Racks & Flag Poles
Install Site Fencing
Install Lift Gates & Arms
Install Monument Sign
Patch / Clean Base
Final Asphalt Paving
Cure Asphalt
Striping / Signage
Punchlist / Inspections
TECO Power Pole Relocation
Permitting
Lane Closures/signage
Erosion Control
Demo/Regrade
Storm Drain Modifications
Curbs/Gutters/Sidewalks
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
VA Tampa Mental Health Clinic and Domicilary
Cullinan Properties, LTD
Leo A Daly
Prosser Inc.
Wed 2/16/22 Page 2 VA/GSA
Task Name Start Finish Duration
144 Asphalt Base Wed 11/2/22 Fri 11/4/22 3 days
145 Install Asphalt Wed 11/9/22 Thu 11/10/22 2 days
146 Cure Asphalt Mon 11/14/22 Thu 11/17/22 4 days
147 Striping/Signage Fri 11/18/22 Mon 11/21/22 2 days
148 Inspections Tue 11/22/22 Tue 11/22/22 1 day
150 DAVIS ROAD OFFSITE WORK Wed 11/23/22 Fri 1/6/23 30 days
151 Permitting Wed 11/23/22 Tue 11/29/22 5 days
152 Lane Closures/Signage Wed 11/30/22 Thu 12/1/22 2 days
153 Erosion Control Wed 11/30/22 Thu 12/1/22 2 days
154 Demo/Regrade Fri 12/2/22 Thu 12/15/22 10 days
155 Storm Drain Modifications Fri 12/16/22 Thu 12/22/22 5 days
156 Curbs/Gutters/Sidewalks Fri 12/23/22 Wed 12/28/22 3 days
157 Asphalt Base Fri 12/16/22 Tue 12/20/22 3 days
158 Install Asphalt Fri 12/23/22 Tue 12/27/22 2 days
159 Cure Asphalt Wed 12/28/22 Tue 1/3/23 4 days
160 Striping/Signage Wed 1/4/23 Thu 1/5/23 2 days
161 Inspections Fri 1/6/23 Fri 1/6/23 1 day
163 STRUCTURE Thu 2/10/22 Fri 9/23/22 157 days
164 Layout Thu 2/10/22 Wed 2/16/22 5 days
165 Install Spread Footing (Start Col Line 1 Moving East) Mon 2/14/22 Mon 3/28/22 30 days
166 Continuous Footings Tue 2/22/22 Mon 4/4/22 30 days
167 Set Stem Wall with Brick Ledge Tue 3/22/22 Mon 4/11/22 15 days
168 Dig/Form/Pour Elev Pit 1 Tue 2/22/22 Mon 2/28/22 5 days
169 Dig/Form/Pour Elev Pit 2-4 Tue 3/1/22 Mon 3/21/22 15 days
170 Waterproofing @ Elevator Pits Tue 3/22/22 Thu 3/24/22 3 days
171 Underground Plbg R-ins Area 1 Fri 3/18/22 Mon 4/4/22 12 days
172 Underground Elec Area 1 Tue 3/29/22 Thu 4/7/22 8 days
173 Prep/Pour Clinic SOG Area 1 Fri 4/8/22 Thu 4/14/22 5 days
174 Underground Plbg R-ins Area 2 Mon 4/4/22 Tue 4/19/22 12 days
175 Underground Elec Area 2 Mon 4/11/22 Fri 4/22/22 10 days
176 Prep/Pour Clinic SOG Area 2 Mon 4/25/22 Fri 4/29/22 5 days
177 Underground Plbg R-ins Area 3 Wed 4/20/22 Tue 5/3/22 10 days
178 Underground Elec Area 3 Wed 4/27/22 Fri 5/6/22 8 days
179 Prep/Pour Clinic SOG Area 3 Mon 5/9/22 Fri 5/13/22 5 days
180 Undeground Plbg R-ins Domiciliary Area 1 Wed 5/4/22 Tue 5/17/22 10 days
181 Underground Elec Domiciliary Area 1 Wed 5/11/22 Fri 5/20/22 8 days
182 Erect Structural Steel/Deck/Detail/Stairs Mon 5/2/22 Wed 8/24/22 80 days
183 Clinic Steel Phase 1 Complete Mon 6/13/22 Mon 6/13/22 0 days
Asphalt Base
Install Asphalt
Cure Asphalt
Striping/Signage
Inspections
Permitting
Lane Closures/signage
Erosion Control
Demo/Regrade
Storm Drain Modifications
Curbs/Gutters/Sidewalks
Asphalt Base
Install Asphalt
Cure Asphalt
Striping/Signage
Inspections
Layout
Install Spread Footing (Start Col Line 1 Moving East)
Continuous Footings
Set Stem Wall with Brick Ledge
Dig/Form/Pour Elev Pit 1
Dig/Form/Pour Elev Pit 2-4
Waterproofing @ Elevator Pits
Underground Plbg R-ins Area 1
Underground Elec Area 1
Prep/Pour Clinic SOG Area 1
Underground Plbg R-ins Area 2
Underground Elec Area 2
Prep/Pour Clinic SOG Area 2
Underground Plbg R-ins Area 3
Underground Elec Area 3
Prep/Pour Clinic SOG Area 3
Undeground Plbg R-ins Domiciliary Area 1
Underground Elec Domiciliary Area 1
Erect Structural Steel/Deck/Detail/Stairs
6/13
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
VA Tampa Mental Health Clinic and Domicilary
Cullinan Properties, LTD
Leo A Daly
Prosser Inc.
Wed 2/16/22 Page 3 VA/GSA
Task Name Start Finish Duration
184 Clinic Phase 2 Complete Wed 7/27/22 Wed 7/27/22 0 days
185 Stair Systems Complete Wed 8/10/22 Wed 8/10/22 0 days
186 Domiciliary Area 1 Steel Complete Wed 8/10/22 Wed 8/10/22 0 days
187 Domiciliary Area 2 Steel Complete Wed 8/24/22 Wed 8/24/22 0 days
188 Set Clinic RTU Curbs Wed 8/17/22 Wed 8/17/22 0 days
189 Set Domiciliary RTU Curbs Thu 9/8/22 Thu 9/8/22 0 days
190 Prep/Pour Domiciliary SOG Area 1 Mon 5/23/22 Thu 6/2/22 8 days
191 Underground Plbg Domiciliary Area 2 Wed 5/18/22 Wed 6/1/22 10 days
192 Underground Elec Domiciliary Area 2 Wed 5/25/22 Mon 6/6/22 8 days
193 Prep/Pour Domiciliary SOG Area 2 Tue 6/7/22 Mon 6/13/22 5 days
194 Prep/Pour 2nd Flr. Clinic SOM Area 1 Fri 6/10/22 Thu 6/16/22 5 days
195 Prep/Pour 2nd Flr. Clinic SOM Area 2 Thu 7/28/22 Wed 8/3/22 5 days
196 Prep/Pour 2nd Flr. Clinic SOM Area 3 Tue 8/2/22 Mon 8/8/22 5 days
197 Install Equipment Pads @ Loading Dock Area Tue 8/9/22 Tue 9/20/22 30 days
198 Install Dock Leveler & Scissor Lift Wed 9/21/22 Fri 9/23/22 3 days
200 ENCLOSURE CLINIC Thu 4/14/22 Fri 3/10/23 226 days
201 Exterior Mockup Wall Complete Thu 4/14/22 Thu 4/14/22 0 days
202 Exterior Studs/Sheathing 1st Floor Clinic Tue 6/21/22 Tue 7/26/22 25 days
203 Exterior Studs/Sheathing 2nd Flr. Clinic Thu 6/23/22 Thu 7/28/22 25 days
204 Deliver Exterior Hollow Metal Door Frames Tue 6/21/22 Tue 6/21/22 0 days
205 Install Early Test Windows & Waterproofing Wed 7/13/22 Thu 7/14/22 2 days
206 Water Test Early Window Install Fri 7/29/22 Fri 7/29/22 1 day
207 Exterior Sheathing Punchlist Fri 7/29/22 Mon 8/1/22 2 days
208 Waterproofing Wed 7/6/22 Tue 8/9/22 25 days
209 Install Canopy/Awning/Building Signage Structural Ties/All threads Wed 7/20/22 Tue 7/26/22 5 days
210 Waterproofing Punchlist Wed 8/10/22 Thu 8/11/22 2 days
211 Install Window Systems & Curtainwalls Wed 7/20/22 Wed 9/7/22 35 days
212 Window Punchlist Thu 9/22/22 Fri 9/23/22 2 days
213 Install Brick Wed 7/20/22 Wed 9/14/22 40 days
214 Install Dumpster Enclosure Walls - CMU/Brick Thu 9/15/22 Thu 10/13/22 20 days
215 Water Test Remaining Windows Thu 10/6/22 Thu 10/6/22 0 days
216 Install Roof Wood Blocking Clinic Thu 7/28/22 Wed 8/10/22 10 days
217 Install 2nd Floor Roof System Clinic Thu 8/4/22 Thu 9/15/22 30 days
218 Measure/Fab Panels Area 1 Wed 8/17/22 Wed 10/5/22 35 days
219 Install Fiber Cement Siding Plank Thu 9/15/22 Tue 10/25/22 28 days
220 Measure/Fab Panels Area 2 Thu 9/15/22 Thu 11/3/22 35 days
221 Install Metal Panels Area 1 Thu 10/6/22 Thu 10/27/22 15 days
222 Measure/Fab Panels Area 3 Thu 10/6/22 Mon 11/28/22 35 days
7/27
8/10
8/10
8/24
8/17
9/8
Prep/Pour Domiciliary SOG Area 1
Underground Plbg Domiciliary Area 2
Underground Elec Domiciliary Area 2
Prep/Pour Domiciliary SOG Area 2
Prep/Pour 2nd Flr. Clinic SOM Area 1
Prep/Pour 2nd Flr. Clinic SOM Area 2
Prep/Pour 2nd Flr. Clinic SOM Area 3
Install Equipment Pads @ Loading Dock Area
Install Dock Leveler & Scissor Lift
4/14
Exterior Studs/Sheathing 1st Floor Clinic
Exterior Studs/Sheathing 2nd Flr. Clinic
6/21
Install Early Test Windows & Waterproofing
Water Test Early Window Install
Exterior Sheathing Punchlist
Waterproofing
Install Canopy/Awning/Building Signage Structural Ties/All threads
Waterproofing Punchlist
Install Window Systems
Window Punchlist
Install Brick
Install Dumpster Enclosure Walls - CMU/Brick
10/6
Install Roof Wood Blocking Clinic
Install 2nd Floor Roof System Clinic
Measure/Fab Panels Area 1
Install Hardie Plank
Measure/Fab Panels Area 2
Install Metal Panels Area 1
Measure/Fab Panels Area 3
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
VA Tampa Mental Health Clinic and Domicilary
Cullinan Properties, LTD
Leo A Daly
Prosser Inc.
Wed 2/16/22 Page 4 VA/GSA
Task Name Start Finish Duration
223 Install Metal Panels Area 2 Fri 11/4/22 Mon 11/28/22 15 days
224 Install Metal Panels Area 3 Tue 11/29/22 Mon 12/19/22 15 days
225 Install Storefront Doors & Aluminum Entry Slides Tue 12/20/22 Wed 1/11/23 15 days
226 Install Screenwall Metal Panels Tue 12/20/22 Wed 1/4/23 10 days
227 Install Building Signage Tue 12/20/22 Wed 1/11/23 15 days
228 Install Canopies/Awnings Tue 12/20/22 Thu 1/19/23 20 days
229 Install Coping Cap Fri 2/3/23 Thu 2/16/23 10 days
230 Install Overhead Doors Tue 12/20/22 Wed 1/11/23 15 days
231 Exterior Skin (Metal Panel & Brick )Punchlist Fri 2/17/23 Fri 3/10/23 15 days
233 ENCLOSURE DOMICILARY AREA 1 & 2 Fri 7/29/22 Fri 3/24/23 163 days
234 Exterior Studs / Sheathing Domicilary Area 1 Fri 7/29/22 Thu 8/11/22 10 days
235 Install Roof Wood Blocking Domicilary Area 1 Fri 8/12/22 Fri 8/19/22 6 days
236 Exterior Studs / Sheathing Domicilary Area 2 Fri 8/12/22 Thu 8/25/22 10 days
237 Install Domiciliary Waterproofing Area 1 & 2 Fri 8/19/22 Thu 9/1/22 10 days
238 Install Brick Thu 9/15/22 Thu 10/13/22 20 days
239 Install Domiciliary Windows Area 1 & 2 Fri 9/2/22 Fri 9/16/22 10 days
240 Install Roof System Domicilary Area 1 Fri 9/9/22 Thu 9/22/22 10 days
241 Install Roof Wood Blocking Domicilary Area 2 Fri 9/23/22 Fri 9/30/22 6 days
242 Install Roof System Domicilary Area 2 Mon 10/3/22 Mon 10/17/22 10 days
243 Water Test Window Fri 9/23/22 Fri 9/23/22 0 days
244 Measure/Fab Panels Area 1 Fri 10/14/22 Mon 12/5/22 35 days
245 Install Hardie Plank Wed 10/26/22 Mon 11/21/22 18 days
246 Measure/Fab Panels Area 2 Wed 10/26/22 Thu 12/15/22 35 days
247 Install Metal Panels Area 1 Tue 12/20/22 Wed 1/4/23 10 days
248 Install Metal Panels Area 2 Thu 1/5/23 Thu 1/19/23 10 days
249 Install Screenwall Metal Panels Fri 1/20/23 Thu 2/2/23 10 days
250 Install Coping Cap Fri 2/17/23 Fri 3/3/23 10 days
251 Exterior Skin Punchlist Mon 3/6/23 Fri 3/24/23 15 days
253 BUILDOUT Tue 6/21/22 Tue 6/27/23 255 days
254 BUILDOUT CLINIC FIRST FLOOR AREA 1 Tue 6/21/22 Wed 3/1/23 173 days
255 Layout Walls Tue 6/21/22 Thu 6/30/22 8 days
256 Deliver Interior Clinic Door Frames Tue 6/21/22 Tue 6/21/22 0 days
257 Install Hangers / Z Plates Fri 7/1/22 Fri 7/8/22 5 days
258 Frame / Top Out Priority Walls ( Densarmor ) Mon 7/11/22 Thu 7/21/22 9 days
259 Electrical Rooms (Main and Subs) Ready for Gear Wed 7/20/22 Wed 7/20/22 0 days
260 MEP / FP Above Ceiling Rough-Ins Mon 7/18/22 Fri 8/26/22 30 days
261 Interior Metal Studs Mon 7/25/22 Fri 8/12/22 15 days
262 MEP In Wall Rough-Ins Mon 8/1/22 Wed 8/24/22 18 days
Install Metal Panels Area 2
Install Metal Panels Area 3
Install Storefront Doors & Aluminum Entry Slides
Install Screenwall Metal Panels
Install Building Signage
Install Canopies/Awnings
Install Coping Cap
Install Overhead Doors
Exterior Skin Punchlist
Exterior Studs / Sheathing Domicilary Area 1
Install Roof Wood Blocking Domicilary Area 1
Exterior Studs / Sheathing Domicilary Area 2
Install Domiciliary Waterproofing
Install Brick
Install Domiciliary Windows
Install Roof System Domicilary Area 1
Install Roof Wood Blocking Domicilary Area 2
Install Roof System Domicilary Area 2
9/23
Measure/Fab Panels Area 1
Install Hardie Plank
Measure/Fab Panels Area 2
Install Metal Panels Area 1
Install Metal Panels Area 2
Install Screenwall Metal Panels
Install Coping Cap
Exterior Skin Punchlist
Layout Walls
6/21
Install Hangers / Z Plates
Frame / Top Out Priority Walls ( Densarmor )
7/20
MEP / FP Above Ceiling Rough-Ins
Interior Metal Studs
MEP In Wall Rough-Ins
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
VA Tampa Mental Health Clinic and Domicilary
Cullinan Properties, LTD
Leo A Daly
Prosser Inc.
Wed 2/16/22 Page 5 VA/GSA
Task Name Start Finish Duration
263 MEP In Wall Inspections Thu 8/25/22 Mon 8/29/22 3 days
264 Pull Wire Mon 8/29/22 Mon 9/12/22 10 days
265 Test / Insulate Duct Mon 8/29/22 Mon 9/12/22 10 days
266 Hang Drywall Thu 9/1/22 Thu 9/29/22 20 days
267 Frame Drywall Soffits / Ceilings Fri 9/9/22 Thu 9/15/22 5 days
268 Firetape / Finish Drywall Tue 9/13/22 Fri 10/14/22 23 days
269 Rough-In Soffits / Ceilings Wed 9/14/22 Tue 9/20/22 5 days
270 Soffit / Ceiling R-In Inspections Wed 9/21/22 Thu 9/22/22 2 days
271 Hang Soffits / Ceilings Fri 9/23/22 Tue 9/27/22 3 days
272 Install Low Voltage Cabling Fri 9/30/22 Fri 10/14/22 10 days
273 Install Elevators Fri 9/30/22 Tue 12/13/22 50 days
274 Prime/1st Coat Finish ( Spray, Backroll ) Thu 10/13/22 Fri 10/28/22 12 days
275 Firestopping / Accoustical Sealant Mon 10/17/22 Tue 10/25/22 7 days
276 Operable Partitions Wed 10/26/22 Tue 11/1/22 5 days
277 Ceiling Grid Thu 10/27/22 Wed 11/23/22 20 days
278 Lights / Grilles / Diffusers / Sprinkler Drops Thu 11/3/22 Fri 12/2/22 20 days
279 Float Floors/Level Fri 11/25/22 Tue 12/6/22 8 days
280 Flooring Wed 12/7/22 Wed 12/28/22 15 days
281 Terrazo @ Monument Stair Thu 12/29/22 Fri 1/20/23 15 days
282 Install Interior Glass @ Monument Stair Mon 1/23/23 Fri 1/27/23 5 days
283 Casework Thu 12/29/22 Fri 1/20/23 15 days
284 Install Wall Protection Recievers Mon 10/31/22 Mon 11/14/22 10 days
285 Ceramic Tile @ Toilets Mon 12/5/22 Thu 12/29/22 18 days
286 Above Ceiling Punchlist / Inspections Mon 12/5/22 Fri 12/9/22 5 days
287 Energize Lights Fri 12/2/22 Fri 12/2/22 0 days
288 Install Plumbing Fixtures Wed 1/11/23 Thu 1/26/23 12 days
289 Ceiling Tile Mon 12/12/22 Tue 12/20/22 7 days
290 Finish Paint Wed 12/21/22 Mon 1/9/23 12 days
291 Toilet Partitions / Toilet Accessories Thu 12/22/22 Fri 1/6/23 10 days
292 Doors and Hardware Thu 12/29/22 Thu 1/12/23 10 days
293 Install Wall Protection/Handrail/Crashrail Thu 12/29/22 Thu 1/12/23 10 days
294 Install Interior Glass & Firelites Fri 1/13/23 Thu 1/19/23 4 days
295 Install Blinds & Window Shades Thu 12/29/22 Thu 1/5/23 5 days
296 MEP Trim Out Tue 1/3/23 Tue 1/17/23 10 days
297 Install Interior Signage Tue 1/10/23 Tue 1/17/23 5 days
298 Install Owner Furnished Equipment Tue 1/10/23 Tue 1/24/23 10 days
299 Carpet and Base Tue 1/10/23 Tue 1/24/23 10 days
300 Hoar Punchlist Wed 1/25/23 Wed 1/25/23 1 day
MEP In Wall Inspections
Pull Wire
Test / Insulate Duct
Hang Drywall
Frame Drywall Soffits / Ceilings
Firetape / Finish Drywall
Rough-In Soffits / Ceilings
Soffit / Ceiling R-In Inspections
Hang Soffits / Ceilings
Install Low Voltage Cabling
Install Elevators
Prime/1st Coat Finish ( Spray,Backroll )
Firestopping / Accoustical Sealant
Operable Partitions
Ceiling Grid
Lights / Grilles / Diffusers / Sprinkler Drops
Float Floors/Level
Flooring
Terrazo @ Monument Stair
Install Interior Glass & Monument Stair
Casework
Install Wall Protection Recievers
Ceramic Tile @ Toilets
Above Ceiling Punchlist / Inspections
12/2
Install Plumbing Fixtures
Ceiling Tile
Finish Paint
Toilet Partitions / Toilet Accessories
Doors and Hardware
Install Wall Protection/Handrail/Crashrail
Install Interior Glass & Firelites
Install Blinds & Window Shades
MEP Trim Out
Install Interior Signage
Install Owner Furnished Equipment
Carpet and Base
Hoar Punchlist
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
VA Tampa Mental Health Clinic and Domicilary
Cullinan Properties, LTD
Leo A Daly
Prosser Inc.
Wed 2/16/22 Page 6 VA/GSA
Task Name Start Finish Duration
301 Work Off Punchlist Thu 1/26/23 Wed 2/15/23 15 days
302 Final Clean Thu 2/16/23 Wed 3/1/23 10 days
304 BUILDOUT CLINIC FIRST FLOOR AREA 2 Thu 8/11/22 Tue 4/25/23 176 days
305 Layout Walls Thu 8/11/22 Mon 8/22/22 8 days
306 Install Hangers / Z Plates Tue 8/23/22 Mon 8/29/22 5 days
307 Frame / Top Out Priority Walls ( Densarmor ) Tue 8/30/22 Mon 9/12/22 9 days
308 Electrical Rooms Ready for Gear Thu 9/22/22 Thu 9/22/22 0 days
309 MEP / FP Above Ceiling Rough-Ins Tue 9/13/22 Tue 10/25/22 30 days
310 Interior Metal Studs Tue 9/20/22 Tue 10/11/22 15 days
311 MEP In Wall Rough-Ins Tue 9/27/22 Fri 10/21/22 18 days
312 MEP In Wall Inspections Mon 10/24/22 Wed 10/26/22 3 days
313 Pull Wire Wed 10/26/22 Tue 11/8/22 10 days
314 Test / Insulate Duct Wed 10/26/22 Tue 11/8/22 10 days
315 Hang Drywall Thu 10/27/22 Fri 11/25/22 20 days
316 Frame Drywall Soffits / Ceilings Thu 11/3/22 Wed 11/9/22 5 days
317 Firetape / Finish Drywall Mon 11/7/22 Fri 12/9/22 23 days
318 Rough-In Soffits / Ceilings Tue 11/8/22 Tue 11/15/22 5 days
319 Soffit / Ceiling R-In Inspections Wed 11/16/22 Thu 11/17/22 2 days
320 Hang Soffits / Ceilings Fri 11/18/22 Tue 11/22/22 3 days
321 Install Low Voltage Cabling Mon 11/28/22 Fri 12/9/22 10 days
322 Prime/1st Coat Finish ( Spray, Backroll ) Thu 12/8/22 Fri 12/23/22 12 days
323 Firestopping / Accoustical Sealant Mon 12/12/22 Tue 12/20/22 7 days
324 Install Wall Protection Recievers Tue 12/27/22 Tue 1/10/23 10 days
325 Operable Partitions Tue 12/27/22 Tue 1/3/23 5 days
326 Ceiling Grid Thu 12/22/22 Wed 1/18/23 20 days
327 Set/Install Kitchen Equipment Thu 1/19/23 Wed 2/1/23 10 days
328 Lights / Grilles / Diffusers / Sprinkler Drops Fri 12/30/22 Mon 1/30/23 20 days
329 Float Floors/Level Thu 1/19/23 Mon 1/30/23 8 days
330 Flooring Tue 1/31/23 Tue 2/21/23 15 days
331 Casework Wed 2/22/23 Tue 3/14/23 15 days
332 Ceramic Tile @ Toilets Tue 1/31/23 Wed 2/15/23 12 days
333 Quarry Tile in Kitchen Thu 2/16/23 Thu 3/9/23 15 days
334 Above Ceiling Punchlist / Inspections Tue 1/31/23 Mon 2/6/23 5 days
335 Energize Lights Mon 1/30/23 Mon 1/30/23 0 days
336 Install Plumbing Fixtures Mon 3/6/23 Tue 3/21/23 12 days
337 Ceiling Tile Tue 2/7/23 Wed 2/15/23 7 days
338 Finish Paint Thu 2/16/23 Mon 3/6/23 12 days
339 Toilet Partitions / Toilet Accessories Thu 2/9/23 Thu 2/23/23 10 days
Work Off Punchlist
Final Clean
Layout Walls
Install Hangers / Z Plates
Frame / Top Out Priority Walls ( Densarmor )
9/22
MEP / FP Above Ceiling Rough-Ins
Interior Metal Studs
MEP In Wall Rough-Ins
MEP In Wall Inspections
Pull Wire
Test / Insulate Duct
Hang Drywall
Frame Drywall Soffits / Ceilings
Firetape / Finish Drywall
Rough-In Soffits / Ceilings
Soffit / Ceiling R-In Inspections
Hang Soffits / Ceilings
Install Low Voltage Cabling
Prime/1st Coat Finish ( Spray,Backroll )
Firestopping / Accoustical Sealant
Install Wall Protection Recievers
Operable Partitions
Ceiling Grid
Set/Install Kitchen Equipment
Lights / Grilles / Diffusers / Sprinkler Drops
Float Floors/Level
Flooring
Casework
Ceramic Tile @ Toilets
Quarry Tile in Kitchen
Above Ceiling Punchlist / Inspections
1/30
Install Plumbing Fixtures
Ceiling Tile
Finish Paint
Toilet Partitions / Toilet Accessories
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
VA Tampa Mental Health Clinic and Domicilary
Cullinan Properties, LTD
Leo A Daly
Prosser Inc.
Wed 2/16/22 Page 7 VA/GSA
Task Name Start Finish Duration
340 Doors and Hardware Wed 2/22/23 Tue 3/7/23 10 days
341 Install Wall Protection/Handrail/Crashrail Tue 1/31/23 Mon 2/13/23 10 days
342 Install Interior Glass & Firelites Wed 3/8/23 Mon 3/13/23 4 days
343 Install Blinds & Window Shades Wed 2/22/23 Tue 2/28/23 5 days
344 MEP Trim Out Tue 2/28/23 Mon 3/13/23 10 days
345 Install Interior Signage Tue 3/7/23 Mon 3/13/23 5 days
346 Install Owner Furnished Equipment Tue 3/7/23 Mon 3/20/23 10 days
347 Carpet and Base Tue 3/7/23 Mon 3/20/23 10 days
348 Hoar Punchlist Tue 3/21/23 Tue 3/21/23 1 day
349 Work Off Punchlist Wed 3/22/23 Tue 4/11/23 15 days
350 Final Clean Wed 4/12/23 Tue 4/25/23 10 days
352 BUILDOUT CLINIC SECOND FLOOR AREA 1 Thu 7/28/22 Mon 5/8/23 195 days
353 Layout Walls Thu 7/28/22 Mon 8/8/22 8 days
354 Install Hangers / Z Plates Mon 8/1/22 Tue 8/16/22 12 days
355 Frame / Top Out Priority Walls ( Densarmor ) Mon 8/8/22 Fri 8/26/22 15 days
356 Electrical Rooms Ready for Gear Thu 9/8/22 Thu 9/8/22 0 days
357 MEP / FP Above Ceiling Rough-Ins Mon 8/29/22 Thu 10/13/22 32 days
358 Interior Metal Studs Tue 9/6/22 Mon 9/26/22 15 days
359 MEP In Wall Rough-Ins Tue 9/13/22 Tue 10/18/22 25 days
360 MEP In Wall Inspections Wed 10/19/22 Fri 10/21/22 3 days
361 Pull Wire Fri 10/14/22 Thu 10/27/22 10 days
362 Test / Insulate Duct Fri 10/14/22 Thu 10/27/22 10 days
363 Hang Drywall Mon 10/24/22 Tue 11/29/22 25 days
364 Frame Drywall Soffits / Ceilings Mon 10/31/22 Fri 11/4/22 5 days
365 Firetape / Finish Drywall Mon 10/31/22 Tue 12/13/22 30 days
366 Rough-In Soffits / Ceilings Thu 11/3/22 Wed 11/9/22 5 days
367 Soffit / Ceiling R-In Inspections Thu 11/10/22 Mon 11/14/22 2 days
368 Hang Soffits / Ceilings Tue 11/15/22 Thu 11/17/22 3 days
369 Install Low Voltage Cabling Wed 11/30/22 Tue 12/13/22 10 days
370 Prime/1st Coat Finish ( Spray, Backroll ) Mon 12/12/22 Wed 12/28/22 12 days
371 Firestopping / Accoustical Sealant Wed 12/14/22 Thu 12/22/22 7 days
372 Operable Partitions Thu 12/29/22 Thu 1/5/23 5 days
373 Ceiling Grid Mon 12/26/22 Fri 1/20/23 20 days
374 Lights / Grilles / Diffusers / Sprinkler Drops Wed 1/4/23 Wed 2/1/23 20 days
375 Float Floors/Level Mon 1/23/23 Wed 2/1/23 8 days
376 Flooring Thu 2/2/23 Thu 2/23/23 15 days
377 Casework Fri 2/24/23 Thu 3/16/23 15 days
378 Install Wall Protection Recievers Thu 12/29/22 Thu 1/12/23 10 days
Doors and Hardware
Install Wall Protection/Handrail/Crashrail
Install Interior Glass & Firelites
Install Blinds & Window Shades
MEP Trim Out
Install Interior Signage
Install Owner Furnished Equipment
Carpet and Base
Hoar Punchlist
Work Off Punchlist
Final Clean
Layout Walls
Install Hangers / Z Plates
Frame / Top Out Priority Walls ( Densarmor )
9/8
MEP / FP Above Ceiling Rough-Ins
Interior Metal Studs
MEP In Wall Rough-Ins
MEP In Wall Inspections
Pull Wire
Test / Insulate Duct
Hang Drywall
Frame Drywall Soffits / Ceilings
Firetape / Finish Drywall
Rough-In Soffits / Ceilings
Soffit / Ceiling R-In Inspections
Hang Soffits / Ceilings
Install Low Voltage Cabling
Prime/1st Coat Finish ( Spray,Backroll )
Firestopping / Accoustical Sealant
Operable Partitions
Ceiling Grid
Lights / Grilles / Diffusers / Sprinkler Drops
Float Floors/Level
Flooring
Casework
Install Wall Protection Recievers
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
VA Tampa Mental Health Clinic and Domicilary
Cullinan Properties, LTD
Leo A Daly
Prosser Inc.
Wed 2/16/22 Page 8 VA/GSA
Task Name Start Finish Duration
379 Ceramic Tile @ Toilets Thu 2/2/23 Tue 2/28/23 18 days
380 Above Ceiling Punchlist / Inspections Thu 2/2/23 Wed 2/8/23 5 days
381 Energize Lights Wed 2/1/23 Wed 2/1/23 0 days
382 Install Plumbing Fixtures Wed 3/8/23 Thu 3/23/23 12 days
383 Ceiling Tile Thu 2/9/23 Wed 2/22/23 10 days
384 Finish Paint Thu 2/23/23 Wed 3/15/23 15 days
385 Toilet Partitions / Toilet Accessories Wed 2/22/23 Tue 3/7/23 10 days
386 Doors and Hardware Fri 2/24/23 Thu 3/9/23 10 days
387 Install Wall Protection/Handrail/Crashrail Fri 2/24/23 Thu 3/9/23 10 days
388 Install Interior Glass & Firelites Fri 3/10/23 Wed 3/15/23 4 days
389 Install Blinds & Window Shades Fri 2/24/23 Thu 3/2/23 5 days
390 MEP Trim Out Thu 3/9/23 Wed 3/22/23 10 days
391 Install Interior Signage Thu 3/16/23 Wed 3/22/23 5 days
392 Install Owner Furnished Equipment Thu 3/16/23 Wed 3/29/23 10 days
393 Carpet and Base Thu 3/16/23 Fri 3/31/23 12 days
394 Hoar Punchlist Mon 4/3/23 Mon 4/3/23 1 day
395 Work Off Punchlist Tue 4/4/23 Mon 4/24/23 15 days
396 Final Clean Tue 4/25/23 Mon 5/8/23 10 days
398 BUILDOUT CLINIC SECOND FLOOR AREA 2 Mon 8/29/22 Tue 6/27/23 207 days
399 Layout Walls Mon 8/29/22 Thu 9/8/22 8 days
400 Install Hangers / Z Plates Fri 9/9/22 Tue 9/20/22 8 days
401 Frame / Top Out Priority Walls ( Densarmor ) Wed 9/21/22 Wed 10/12/22 15 days
402 Electrical Rooms Ready for Gear Mon 10/24/22 Mon 10/24/22 0 days
403 MEP / FP Above Ceiling Rough-Ins Thu 10/13/22 Tue 11/29/22 32 days
404 Interior Metal Studs Thu 10/20/22 Wed 11/9/22 15 days
405 MEP In Wall Rough-Ins Thu 10/27/22 Fri 12/2/22 25 days
406 MEP In Wall Inspections Mon 12/5/22 Wed 12/7/22 3 days
407 Pull Wire Wed 11/30/22 Tue 12/13/22 10 days
408 Test / Insulate Duct Wed 11/30/22 Tue 12/13/22 10 days
409 Hang Drywall Thu 12/8/22 Fri 1/13/23 25 days
410 Frame Drywall Soffits / Ceilings Thu 12/15/22 Wed 12/21/22 5 days
411 Firetape / Finish Drywall Thu 12/15/22 Mon 1/30/23 30 days
412 Rough-In Soffits / Ceilings Tue 12/20/22 Tue 12/27/22 5 days
413 Soffit / Ceiling R-In Inspections Wed 12/28/22 Thu 12/29/22 2 days
414 Hang Soffits / Ceilings Fri 12/30/22 Wed 1/4/23 3 days
415 Install Low Voltage Cabling Tue 1/17/23 Mon 1/30/23 10 days
416 Prime/1st Coat Finish ( Spray, Backroll ) Fri 1/27/23 Mon 2/13/23 12 days
417 Firestopping / Accoustical Sealant Tue 1/31/23 Wed 2/8/23 7 days
Ceramic Tile @ Toilets
Above Ceiling Punchlist / Inspections
2/1
Install Plumbing Fixtures
Ceiling Tile
Finish Paint
Toilet Partitions / Toilet Accessories
Doors and Hardware
Install Wall Protection/Handrail/Crashrail
Install Interior Glass & Firelites
Install Blinds & Window Shades
MEP Trim Out
Install Interior Signage
Install Owner Furnished Equipment
Carpet and Base
Hoar Punchlist
Work Off Punchlist
Final Clean
Layout Walls
Install Hangers / Z Plates
Frame / Top Out Priority Walls ( Densarmor )
10/24
MEP / FP Above Ceiling Rough-Ins
Interior Metal Studs
MEP In Wall Rough-Ins
MEP In Wall Inspections
Pull Wire
Test / Insulate Duct
Hang Drywall
Frame Drywall Soffits / Ceilings
Firetape / Finish Drywall
Rough-In Soffits / Ceilings
Soffit / Ceiling R-In Inspections
Hang Soffits / Ceilings
Install Low Voltage Cabling
Prime/1st Coat Finish ( Spray,Backroll )
Firestopping / Accoustical Sealant
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
VA Tampa Mental Health Clinic and Domicilary
Cullinan Properties, LTD
Leo A Daly
Prosser Inc.
Wed 2/16/22 Page 9 VA/GSA
Task Name Start Finish Duration
418 Operable Partitions Tue 2/14/23 Tue 2/21/23 5 days
419 Ceiling Grid Fri 2/10/23 Mon 3/13/23 22 days
420 Lights / Grilles / Diffusers / Sprinkler Drops Fri 2/17/23 Tue 3/21/23 22 days
421 Float Floors/Level Tue 3/14/23 Thu 3/23/23 8 days
422 Flooring Fri 3/24/23 Thu 4/13/23 15 days
423 Casework Fri 4/14/23 Thu 5/4/23 15 days
424 Install Wall Protection Recievers Tue 2/14/23 Tue 2/28/23 10 days
425 Ceramic Tile @ Toilets Wed 3/22/23 Fri 4/14/23 18 days
426 Above Ceiling Punchlist / Inspections Wed 3/22/23 Tue 3/28/23 5 days
427 Energize Lights Tue 3/21/23 Tue 3/21/23 0 days
428 Install Plumbing Fixtures Wed 4/26/23 Thu 5/11/23 12 days
429 Ceiling Tile Wed 3/29/23 Tue 4/11/23 10 days
430 Finish Paint Wed 4/12/23 Tue 5/2/23 15 days
431 Toilet Partitions / Toilet Accessories Mon 4/10/23 Fri 4/21/23 10 days
432 Doors and Hardware Fri 4/14/23 Thu 4/27/23 10 days
433 Install Wall Protection/Handrail/Crashrail Fri 3/24/23 Thu 4/6/23 10 days
434 Install Interior Glass & Firelites Fri 4/28/23 Wed 5/3/23 4 days
435 Install Blinds & Window Shades Fri 4/14/23 Thu 4/20/23 5 days
436 MEP Trim Out Wed 4/26/23 Tue 5/9/23 10 days
437 Install Interior Signage Wed 5/3/23 Tue 5/9/23 5 days
438 Install Owner Furnished Equipment Wed 5/3/23 Tue 5/16/23 10 days
439 Carpet and Base Wed 5/3/23 Thu 5/18/23 12 days
440 Hoar Punchlist Fri 5/19/23 Tue 5/23/23 3 days
441 Work Off Punchlist Wed 5/24/23 Tue 6/13/23 15 days
442 Final Clean Wed 6/14/23 Tue 6/27/23 10 days
444 DOMICILIARY 1 Fri 9/9/22 Fri 4/14/23 149 days
445 Layout Walls Fri 9/9/22 Thu 9/15/22 5 days
446 Install Hangers / Z Plates Tue 9/13/22 Mon 9/19/22 5 days
447 Frame / Top Out Priority Walls ( Densarmor ) Tue 9/20/22 Mon 9/26/22 5 days
448 Electrical Rooms Ready for Gear Thu 10/6/22 Thu 10/6/22 0 days
449 MEP / FP Above Ceiling Rough-Ins Tue 9/27/22 Fri 10/21/22 18 days
450 Interior Metal Studs Tue 10/4/22 Tue 10/18/22 10 days
451 MEP In Wall Rough-Ins Wed 10/12/22 Tue 11/1/22 15 days
452 MEP In Wall Inspections Wed 11/2/22 Fri 11/4/22 3 days
453 Pull Wire Mon 10/24/22 Fri 11/4/22 10 days
454 Test / Insulate Duct Mon 10/24/22 Fri 11/4/22 10 days
455 Hang Drywall Mon 11/7/22 Tue 11/29/22 15 days
456 Frame Drywall Soffits / Ceilings Tue 11/15/22 Mon 11/21/22 5 days
Operable Partitions
Ceiling Grid
Lights / Grilles / Diffusers / Sprinkler Drops
Float Floors/Level
Flooring
Casework
Install Wall Protection Recievers
Ceramic Tile @ Toilets
Above Ceiling Punchlist / Inspections
3/21
Install Plumbing Fixtures
Ceiling Tile
Finish Paint
Toilet Partitions / Toilet Accessories
Doors and Hardware
Install Wall Protection/Handrail/Crashrail
Install Interior Glass & Firelites
Install Blinds & Window Shades
MEP Trim Out
Install Interior Signage
Install Owner Furnished Equipment
Carpet and Base
Hoar Punchlist
Work Off Punchlist
Final Clean
Layout Walls
Install Hangers / Z Plates
Frame / Top Out Priority Walls ( Densarmor )
10/6
MEP / FP Above Ceiling Rough-Ins
Interior Metal Studs
MEP In Wall Rough-Ins
MEP In Wall Inspections
Pull Wire
Test / Insulate Duct
Hang Drywall
Frame Drywall Soffits / Ceilings
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
VA Tampa Mental Health Clinic and Domicilary
Cullinan Properties, LTD
Leo A Daly
Prosser Inc.
Wed 2/16/22 Page 10 VA/GSA
Task Name Start Finish Duration
457 Firetape / Finish Drywall Wed 11/23/22 Thu 12/22/22 21 days
458 Rough-In Soffits / Ceilings Wed 11/16/22 Fri 11/25/22 7 days
459 Soffit / Ceiling R-In Inspections Mon 11/28/22 Fri 12/2/22 5 days
460 Hang Soffits / Ceilings Mon 12/5/22 Fri 12/16/22 10 days
461 Install Low Voltage Cabling Wed 11/30/22 Tue 12/13/22 10 days
462 Prime/1st Coat Finish ( Spray, Backroll ) Wed 12/21/22 Thu 1/5/23 10 days
463 Firestopping / Accoustical Sealant Wed 12/14/22 Thu 12/22/22 7 days
464 Install Cubicle Curtain Track Fri 1/6/23 Wed 1/18/23 8 days
465 Ceiling Grid Fri 1/6/23 Thu 1/12/23 5 days
466 Lights / Grilles / Diffusers / Sprinkler Drops Fri 1/13/23 Fri 1/27/23 10 days
467 Float Floors/Level Fri 1/13/23 Wed 1/25/23 8 days
468 Flooring Thu 1/26/23 Wed 2/8/23 10 days
469 Casework Thu 2/9/23 Thu 2/23/23 10 days
470 Install Wall Protection Recievers Fri 1/6/23 Tue 1/17/23 7 days
471 Ceramic Tile @ Toilets Mon 1/30/23 Thu 2/23/23 18 days
472 Above Ceiling Punchlist / Inspections Mon 1/30/23 Fri 2/3/23 5 days
473 Energize Lights Fri 1/27/23 Fri 1/27/23 0 days
474 Install Plumbing Fixtures Wed 2/22/23 Thu 3/9/23 12 days
475 Ceiling Tile Mon 2/6/23 Thu 2/9/23 4 days
476 Finish Paint Fri 2/3/23 Tue 2/21/23 12 days
477 Toilet Partitions / Toilet Accessories Thu 2/16/23 Thu 3/2/23 10 days
478 Doors and Hardware Thu 2/9/23 Thu 2/16/23 6 days
479 Install Wall Protection/Handrail/Crashrail Thu 2/9/23 Thu 2/23/23 10 days
480 Install Interior Glass & Firelites Fri 2/17/23 Wed 2/22/23 3 days
481 Install Blinds & Window Shades & Shower Curtains Thu 2/9/23 Wed 2/15/23 5 days
482 MEP Trim Out Tue 2/14/23 Thu 3/2/23 12 days
483 Install Interior Signage Wed 2/22/23 Tue 2/28/23 5 days
484 Install Owner Furnished Equipment Wed 2/22/23 Thu 3/9/23 12 days
485 Carpet and Base Wed 2/22/23 Thu 3/9/23 12 days
486 Hoar Punchlist Fri 3/10/23 Fri 3/10/23 1 day
487 Work Off Punchlist Mon 3/13/23 Fri 3/31/23 15 days
488 Final Clean Mon 4/3/23 Fri 4/14/23 10 days
490 DOMICILIARY 2 Fri 9/16/22 Wed 5/3/23 157 days
491 Layout Walls Fri 9/16/22 Thu 9/22/22 5 days
492 Install Hangers / Z Plates Tue 9/20/22 Mon 9/26/22 5 days
493 Frame / Top Out Priority Walls ( Densarmor ) Tue 9/27/22 Mon 10/3/22 5 days
494 Electrical Rooms Ready for Gear Fri 10/14/22 Fri 10/14/22 0 days
495 MEP / FP Above Ceiling Rough-Ins Mon 10/17/22 Wed 11/9/22 18 days
Firetape / Finish Drywall
Rough-In Soffits / Ceilings
Soffit / Ceiling R-In Inspections
Hang Soffits / Ceilings
Install Low Voltage Cabling
Prime/1st Coat Finish ( Spray,Backroll )
Firestopping / Accoustical Sealant
Install Cubicle Curtain Track
Ceiling Grid
Lights / Grilles / Diffusers / Sprinkler Drops
Float Floors/Level
Flooring
Casework
Install Wall Protection Recievers
Ceramic Tile @ Toilets
Above Ceiling Punchlist / Inspections
1/27
Install Plumbing Fixtures
Ceiling Tile
Finish Paint
Toilet Partitions / Toilet Accessories
Doors and Hardware
Install Wall Protection/Handrail/Crashrail
Install Interior Glass & Firelites
Install Blinds & Window Shades & Shower Curtains
MEP Trim Out
Install Interior Signage
Install Owner Furnished Equipment
Carpet and Base
Hoar Punchlist
Work Off Punchlist
Final Clean
Layout Walls
Install Hangers / Z Plates
Frame / Top Out Priority Walls ( Densarmor )
10/14
MEP / FP Above Ceiling Rough-Ins
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
VA Tampa Mental Health Clinic and Domicilary
Cullinan Properties, LTD
Leo A Daly
Prosser Inc.
Wed 2/16/22 Page 11 VA/GSA
Task Name Start Finish Duration
496 Interior Metal Studs Mon 10/24/22 Fri 11/4/22 10 days
497 MEP In Wall Rough-Ins Mon 10/31/22 Mon 11/21/22 15 days
498 MEP In Wall Inspections Tue 11/22/22 Fri 11/25/22 3 days
499 Pull Wire Thu 11/10/22 Fri 11/25/22 10 days
500 Test / Insulate Duct Thu 11/10/22 Fri 11/25/22 10 days
501 Hang Drywall Mon 11/28/22 Fri 12/16/22 15 days
502 Frame Drywall Soffits / Ceilings Mon 12/5/22 Fri 12/9/22 5 days
503 Firetape / Finish Drywall Tue 12/13/22 Thu 1/12/23 21 days
504 Rough-In Soffits / Ceilings Tue 12/6/22 Wed 12/14/22 7 days
505 Soffit / Ceiling R-In Inspections Thu 12/15/22 Wed 12/21/22 5 days
506 Hang Soffits / Ceilings Thu 12/22/22 Fri 1/6/23 10 days
507 Install Low Voltage Cabling Mon 12/19/22 Tue 1/3/23 10 days
508 Prime/1st Coat Finish ( Spray, Backroll ) Wed 1/11/23 Wed 1/25/23 10 days
509 Firestopping / Accoustical Sealant Wed 1/4/23 Thu 1/12/23 7 days
510 Install Cubicle Curtain Track Thu 1/26/23 Mon 2/6/23 8 days
511 Ceiling Grid Thu 1/26/23 Wed 2/1/23 5 days
512 Lights / Grilles / Diffusers / Sprinkler Drops Thu 2/2/23 Wed 2/15/23 10 days
513 Float Floors/Level Thu 2/2/23 Mon 2/13/23 8 days
514 Flooring Tue 2/14/23 Tue 2/28/23 10 days
515 Casework Wed 3/1/23 Tue 3/14/23 10 days
516 Install Wall Protection Recievers Thu 1/26/23 Fri 2/3/23 7 days
517 Ceramic Tile @ Toilets Thu 2/16/23 Tue 3/14/23 18 days
518 Above Ceiling Punchlist / Inspections Thu 2/16/23 Thu 2/23/23 5 days
519 Energize Lights Wed 2/15/23 Wed 2/15/23 0 days
520 Install Plumbing Fixtures Mon 3/13/23 Tue 3/28/23 12 days
521 Ceiling Tile Fri 2/24/23 Wed 3/1/23 4 days
522 Finish Paint Thu 2/23/23 Fri 3/10/23 12 days
523 Toilet Partitions / Toilet Accessories Wed 3/8/23 Tue 3/21/23 10 days
524 Doors and Hardware Wed 3/1/23 Wed 3/8/23 6 days
525 Install Wall Protection/Handrail/Crashrail Wed 3/1/23 Tue 3/14/23 10 days
526 Install Interior Glass & Firelites Thu 3/9/23 Mon 3/13/23 3 days
527 Install Blinds & Window Shades & Shower Curtains Wed 3/1/23 Tue 3/7/23 5 days
528 MEP Trim Out Mon 3/6/23 Tue 3/21/23 12 days
529 Install Interior Signage Mon 3/13/23 Fri 3/17/23 5 days
530 Install Owner Furnished Equipment Mon 3/13/23 Tue 3/28/23 12 days
531 Carpet and Base Mon 3/13/23 Tue 3/28/23 12 days
532 Hoar Punchlist Wed 3/29/23 Wed 3/29/23 1 day
533 Work Off Punchlist Thu 3/30/23 Wed 4/19/23 15 days
Interior Metal Studs
MEP In Wall Rough-Ins
MEP In Wall Inspections
Pull Wire
Test / Insulate Duct
Hang Drywall
Frame Drywall Soffits / Ceilings
Firetape / Finish Drywall
Rough-In Soffits / Ceilings
Soffit / Ceiling R-In Inspections
Hang Soffits / Ceilings
Install Low Voltage Cabling
Prime/1st Coat Finish ( Spray,Backroll )
Firestopping / Accoustical Sealant
Install Cubicle Curtain Track
Ceiling Grid
Lights / Grilles / Diffusers / Sprinkler Drops
Float Floors/Level
Flooring
Casework
Install Wall Protection Recievers
Ceramic Tile @ Toilets
Above Ceiling Punchlist / Inspections
2/15
Install Plumbing Fixtures
Ceiling Tile
Finish Paint
Toilet Partitions / Toilet Accessories
Doors and Hardware
Install Wall Protection/Handrail/Crashrail
Install Interior Glass & Firelites
Install Blinds & Window Shades & Shower Curtains
MEP Trim Out
Install Interior Signage
Install Owner Furnished Equipment
Carpet and Base
Hoar Punchlist
Work Off Punchlist
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
VA Tampa Mental Health Clinic and Domicilary
Cullinan Properties, LTD
Leo A Daly
Prosser Inc.
Wed 2/16/22 Page 12 VA/GSA
Task Name Start Finish Duration
534 Final Clean Thu 4/20/23 Wed 5/3/23 10 days Final Clean F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J
Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024
VA Tampa Mental Health Clinic and Domicilary
Cullinan Properties, LTD
Leo A Daly
Prosser Inc.
Wed 2/16/22 Page 13 VA/GSA
File details come from the government source that posted it. Updated .