ATTACHMENT U - VA Tampa Project Schedule.pdf

PDF 295 KB Posted

Attached to
Q702--Tampa Mental Health Clinic & Domiciliary IOTA Contract
Solicitation number
36C77622Q0199
Issued by

About this file

This document provides a project schedule for the construction of a new Department of Veterans Affairs mental health clinic and domiciliary in Tampa, Florida. The schedule outlines key milestones and tasks from notice to proceed through final activation, spanning from February 2022 through January 2024. It details construction phases including site work, structure erection, building enclosure, buildout of clinic and domiciliary spaces, and offsite roadway improvements. The schedule identifies task dependencies and durations for concrete work, structural steel installation, mechanical system rough-ins and finishes, interior partitions and casework, and other building components. The solicitation number for the related IOTA contract to complete this work is 36C77622Q0199.

View the file

Other files

File Type Posted
36C77622Q0199 0003.docx DOCX document
Addendum to 52.212-1 - Tampa Mental Health Clinic _ Domiciliary Instructions.pdf PDF
S05 - Questions Answers - Tampa Mental Health Clinic and Domiciliary Continued.pdf PDF
IOTA PWS Mental Health and Dom 29MAR2022.pdf PDF
36C77622Q0199 0002.docx DOCX document
ATTACHMENT X - FFE (IF series) Pages from VA Tampa IFC - Drawings.pdf PDF
36C77622Q0199 0001.docx DOCX document
ATTACHMENT W - MH SF plan.pdf PDF
S05 - Questions Answers - Tampa Mental Health Clinic and Domiciliary.pdf PDF
ATTACHMENT J1 - Meeting Minutes Template.pdf PDF
ATTACHMENT B - TRAVEL AUTHORIZATION REQUEST.pdf PDF
ATTACHMENT V - Pricing Worksheet Mental Health.xlsx XLSX spreadsheet
ATTACHMENT E - Contract Staff Roster.pdf PDF
ATTACHMENT A - IOTA PWS Mental Health Clinic and Domiciliary.pdf PDF
ATTACHMENT M - Furniture IDIQ Templates.pdf PDF
36C77622Q0199.docx DOCX document
ATTACHMENT J2 - Meeting Agenda Template.pdf PDF
ATTACHMENT S - MH VA Tampa PRCL 02MAR2022.xlsx XLSX spreadsheet
ATTACHMENT D - Hospital Police Memo - 00-02 - Mental Health.pdf PDF
ATTACHMENT O - 6500.6 Appendix A.pdf PDF
ATTACHMENT P - QASP.docx DOCX document
ATTACHMENT R - VSC Security Request Forms.pdf PDF
ATTACHMENT Q - PDAT SUMMARY.pdf PDF
ATTACHMENT I - WBS Template.pdf PDF
ATTACHMENT G - Integrated Move Plan Template.xlsx XLSX spreadsheet
ATTACHMENT K - Room Contents and Acq Plan Template.xlsx XLSX spreadsheet
ATTACHMENT F - Risk Management Plan and Register Template.xlsx XLSX spreadsheet
ATTACHMENT N - Procurement Package Template 2022.pdf PDF
ATTACHMENT C - Hospital Policy Memo - 00-05 - Mental Health.pdf PDF
ATTACHMENT T - Wage Determination.pdf PDF
ATTACHMENT L - Re-Use Disposal Plan Template.xlsx XLSX spreadsheet
ATTACHMENT H - Change Management Plan _ Log Template.xlsx XLSX spreadsheet
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task

Mode

Task Name Start Finish Duration

1 MILESTONES Tue 3/9/21 Tue 1/30/24 726 days

23 Construction Duration Mon 11/29/21 Mon 7/31/23 436 days

26 Notice to Proceed Fri 2/18/22 Fri 2/18/22 0 days

27 Groundbreaking Ceremony Tue 4/19/22 Tue 4/19/22 0 days

28 GSA/VA Inspection Notice (4.10A) Fri 7/14/23 Fri 7/14/23 0 days

29 Substantial Completion = VA Acceptance Thu 7/27/23 Thu 7/27/23 0 days

30 Activation 4.01G Fri 7/28/23 Tue 1/30/24 128 days

32 CONSTRUCTION MILESTONES Mon 5/3/21 Thu 7/27/23 559 days

50 SWFMD Phase 2 Permit Thu 11/4/21 Mon 2/28/22 77 days

62 Foundation Permit Mon 11/22/21 Mon 2/14/22 57 days

63 Building Permit Tue 2/15/22 Mon 2/28/22 9 days

72 Temporary Power On For Trailer Thu 2/24/22 Thu 2/24/22 0 days

73 Comissioning - Prefunctional Checklist Issued Mon 4/4/22 Mon 4/4/22 0 days

74 Complete Mockup Wall Thu 4/14/22 Thu 4/14/22 0 days

75 Comissioning - Functional Test Protcol Templates Issued Mon 10/3/22 Mon 10/3/22 0 days

76 Permanent Power On Tue 10/18/22 Tue 10/18/22 0 days

77 Main Electrical Room Complete/Ready to Energize Tue 10/18/22 Tue 10/18/22 0 days

78 Set Clinic RTU's Fri 9/16/22 Tue 9/20/22 3 days

79 Set Chillers & Energize Wed 9/21/22 Fri 9/30/22 8 days

80 Set Transformers Wed 9/21/22 Wed 9/21/22 1 day

81 Startup RTU's Tue 10/25/22 Mon 10/31/22 5 days

82 Set Generators Thu 12/1/22 Fri 12/2/22 2 days

83 Gas Turned On Tue 5/9/23 Tue 5/9/23 0 days

84 Test & Balance Wed 12/14/22 Mon 3/6/23 55 days

85 Comissioning - Functional Testing Tue 3/7/23 Mon 3/20/23 10 days

86 Domiciliary Buildout Duratioin Fri 9/9/22 Tue 5/2/23 161 days

87 Clinic Buildout Duration Tue 6/21/22 Tue 5/9/23 222 days

88 Final Inspections Fri 5/19/23 Fri 6/9/23 15 days

89 Certificate of Occupancy Fri 6/9/23 Fri 6/9/23 0 days

90 Final Punchlist Wed 6/28/23 Thu 6/29/23 2 days

91 Work Off Punchlist Fri 6/30/23 Thu 7/27/23 20 days

93 SITEWORK Wed 12/1/21 Tue 5/23/23 370 days

99 Cut / Fill Site Fri 1/7/22 Mon 2/28/22 35 days

100 Storm Water Piping Tue 3/1/22 Mon 4/18/22 35 days

101 CLINIC BUILDING PAD COMPLETE Wed 2/9/22 Wed 2/9/22 0 days

102 Domicilaries Building Pads Complete Wed 2/9/22 Wed 2/9/22 0 days

103 Fine Grade Site (Stone for Crane) Thu 2/10/22 Thu 3/10/22 20 days

104 Clear Site Phase 2 Tue 3/1/22 Thu 3/10/22 8 days

CONSTRUCTION DURATION

2/18

4/19

7/14

7/27

Activation 4.01G

SWFMD Phase 2 Permit

Foundation Permit

Building Permit

2/24

4/4

4/14

10/3

10/18

10/18

Set Clinic RTU's

Set Chillers

Set Transformers

Startup RTU's

Set Generators

5/9

Test & Balance

Comissioning - Functional Testing

Domiciliary Buildout Duratioin

Clinic Buildout Duration

Final Inspections

6/9

Final Punchlist

Work Off Punchlist

Cut / Fill Site

Storm Water Piping

2/9

2/9

Fine Grade Site (Stone for Crane)

Clear Site Phase 2

F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

VA Tampa Mental Health Clinic and Domicilary

Cullinan Properties, LTD

Leo A Daly

Prosser Inc.

Hoar Construction

Wed 2/16/22 Page 1 VA/GSA

Task Name Start Finish Duration

105 Install Sanitary Sewer Piping Tue 3/1/22 Mon 3/21/22 15 days

106 Grading Retention/Detention Ponds Fri 3/11/22 Thu 3/24/22 10 days

107 Bulkhead @ Ponds Fri 3/25/22 Thu 5/5/22 30 days

108 Domestic Water / Fire Main Piping Tue 3/22/22 Mon 4/18/22 20 days

109 Install Lift Station Tue 4/19/22 Wed 4/20/22 2 days

110 Install Phone Lines/Conduits Tue 4/19/22 Mon 4/25/22 5 days

111 Install Gas Line Tue 4/19/22 Mon 5/2/22 10 days

112 Install New Primary & Secondary Electrical Lines Tue 4/19/22 Mon 5/2/22 10 days

113 Install Site Lighting Tue 5/3/22 Tue 6/14/22 30 days

114 Curb and Gutter @ Perimeter Wed 6/15/22 Thu 7/28/22 30 days

115 Install Grease Interceptor Mon 8/1/22 Fri 8/5/22 5 days

116 Stone Base / Fine Grade Fri 7/15/22 Thu 8/18/22 25 days

117 Install Base for Paving Fri 8/19/22 Fri 9/9/22 15 days

118 Install Curb and Gutter / Sidewalks/ Bike Rack Pads Tue 12/20/22 Thu 1/26/23 25 days

119 Irrigation Thu 1/12/23 Fri 2/24/23 30 days

120 Hardscapes Fri 1/27/23 Fri 3/24/23 40 days

121 Landscaping Fri 2/10/23 Fri 4/7/23 40 days

122 Install Basketball Court & Goal Fri 1/27/23 Fri 2/24/23 20 days

123 Light Poles & Bases Fri 1/27/23 Fri 2/24/23 20 days

124 Paint Basketball Court Mon 2/27/23 Tue 2/28/23 2 days

125 Install Pavilions & Sheds Mon 3/27/23 Fri 4/14/23 15 days

126 Site Furnishings & Bike Racks & Flag Poles Mon 3/27/23 Fri 4/14/23 15 days

127 Install Site Fencing Mon 4/10/23 Fri 5/5/23 20 days

128 Install Lift Gates & Arms Mon 3/27/23 Wed 3/29/23 3 days

129 Install Monument Sign Thu 3/30/23 Wed 4/5/23 5 days

130 Patch / Clean Base Mon 3/13/23 Fri 4/14/23 25 days

131 Final Asphalt Paving Wed 3/29/23 Tue 4/18/23 15 days

132 Cure Asphalt Wed 4/19/23 Tue 5/2/23 10 days

133 Striping / Signage Wed 5/3/23 Tue 5/9/23 5 days

134 Punchlist / Inspections Wed 5/10/23 Tue 5/23/23 10 days

136 TEMPLE TERRACE OFFSITE ROADWAY WORK Thu 6/23/22 Fri 1/6/23 135 days

137 TECO Power Pole Relocation Thu 6/23/22 Thu 7/7/22 10 days

138 Permitting Mon 10/10/22 Fri 10/14/22 5 days

139 Lane Closures/Signage Mon 10/17/22 Tue 10/18/22 2 days

140 Erosion Control Mon 10/17/22 Tue 10/18/22 2 days

141 Demo/Regrade Wed 10/19/22 Tue 11/1/22 10 days

142 Storm Drain Modifications Wed 11/2/22 Tue 11/8/22 5 days

143 Curbs/Gutters/Sidewalks Wed 11/9/22 Mon 11/14/22 3 days

Install Sanitary Sewer Piping

Grading Retention/Detention Ponds

Bulkhead @ Ponds

Domestic Water / Fire Main Piping

Install Lift Station

Install Phone Lines/Conduits

Install Gas Line

Install New Primary & Secondary Electrical Lines

Install Site Lighting

Curb and Gutter @ Perimeter

Install Grease Interceptor

Stone Base / Fine Grade

Install Base for Paving

Install Curb and Gutter / Sidewalks/ Bike Rack Pads

Irrigation

Hardscapes

Landscaping

Install Basketball Court & Goal

Light Poles & Bases

Paint Basketball Court

Install Pavilions & Sheds

Site Furnishings & Bike Racks & Flag Poles

Install Site Fencing

Install Lift Gates & Arms

Install Monument Sign

Patch / Clean Base

Final Asphalt Paving

Cure Asphalt

Striping / Signage

Punchlist / Inspections

TECO Power Pole Relocation

Permitting

Lane Closures/signage

Erosion Control

Demo/Regrade

Storm Drain Modifications

Curbs/Gutters/Sidewalks

F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

VA Tampa Mental Health Clinic and Domicilary

Cullinan Properties, LTD

Leo A Daly

Prosser Inc.

Wed 2/16/22 Page 2 VA/GSA

Task Name Start Finish Duration

144 Asphalt Base Wed 11/2/22 Fri 11/4/22 3 days

145 Install Asphalt Wed 11/9/22 Thu 11/10/22 2 days

146 Cure Asphalt Mon 11/14/22 Thu 11/17/22 4 days

147 Striping/Signage Fri 11/18/22 Mon 11/21/22 2 days

148 Inspections Tue 11/22/22 Tue 11/22/22 1 day

150 DAVIS ROAD OFFSITE WORK Wed 11/23/22 Fri 1/6/23 30 days

151 Permitting Wed 11/23/22 Tue 11/29/22 5 days

152 Lane Closures/Signage Wed 11/30/22 Thu 12/1/22 2 days

153 Erosion Control Wed 11/30/22 Thu 12/1/22 2 days

154 Demo/Regrade Fri 12/2/22 Thu 12/15/22 10 days

155 Storm Drain Modifications Fri 12/16/22 Thu 12/22/22 5 days

156 Curbs/Gutters/Sidewalks Fri 12/23/22 Wed 12/28/22 3 days

157 Asphalt Base Fri 12/16/22 Tue 12/20/22 3 days

158 Install Asphalt Fri 12/23/22 Tue 12/27/22 2 days

159 Cure Asphalt Wed 12/28/22 Tue 1/3/23 4 days

160 Striping/Signage Wed 1/4/23 Thu 1/5/23 2 days

161 Inspections Fri 1/6/23 Fri 1/6/23 1 day

163 STRUCTURE Thu 2/10/22 Fri 9/23/22 157 days

164 Layout Thu 2/10/22 Wed 2/16/22 5 days

165 Install Spread Footing (Start Col Line 1 Moving East) Mon 2/14/22 Mon 3/28/22 30 days

166 Continuous Footings Tue 2/22/22 Mon 4/4/22 30 days

167 Set Stem Wall with Brick Ledge Tue 3/22/22 Mon 4/11/22 15 days

168 Dig/Form/Pour Elev Pit 1 Tue 2/22/22 Mon 2/28/22 5 days

169 Dig/Form/Pour Elev Pit 2-4 Tue 3/1/22 Mon 3/21/22 15 days

170 Waterproofing @ Elevator Pits Tue 3/22/22 Thu 3/24/22 3 days

171 Underground Plbg R-ins Area 1 Fri 3/18/22 Mon 4/4/22 12 days

172 Underground Elec Area 1 Tue 3/29/22 Thu 4/7/22 8 days

173 Prep/Pour Clinic SOG Area 1 Fri 4/8/22 Thu 4/14/22 5 days

174 Underground Plbg R-ins Area 2 Mon 4/4/22 Tue 4/19/22 12 days

175 Underground Elec Area 2 Mon 4/11/22 Fri 4/22/22 10 days

176 Prep/Pour Clinic SOG Area 2 Mon 4/25/22 Fri 4/29/22 5 days

177 Underground Plbg R-ins Area 3 Wed 4/20/22 Tue 5/3/22 10 days

178 Underground Elec Area 3 Wed 4/27/22 Fri 5/6/22 8 days

179 Prep/Pour Clinic SOG Area 3 Mon 5/9/22 Fri 5/13/22 5 days

180 Undeground Plbg R-ins Domiciliary Area 1 Wed 5/4/22 Tue 5/17/22 10 days

181 Underground Elec Domiciliary Area 1 Wed 5/11/22 Fri 5/20/22 8 days

182 Erect Structural Steel/Deck/Detail/Stairs Mon 5/2/22 Wed 8/24/22 80 days

183 Clinic Steel Phase 1 Complete Mon 6/13/22 Mon 6/13/22 0 days

Asphalt Base

Install Asphalt

Cure Asphalt

Striping/Signage

Inspections

Permitting

Lane Closures/signage

Erosion Control

Demo/Regrade

Storm Drain Modifications

Curbs/Gutters/Sidewalks

Asphalt Base

Install Asphalt

Cure Asphalt

Striping/Signage

Inspections

Layout

Install Spread Footing (Start Col Line 1 Moving East)

Continuous Footings

Set Stem Wall with Brick Ledge

Dig/Form/Pour Elev Pit 1

Dig/Form/Pour Elev Pit 2-4

Waterproofing @ Elevator Pits

Underground Plbg R-ins Area 1

Underground Elec Area 1

Prep/Pour Clinic SOG Area 1

Underground Plbg R-ins Area 2

Underground Elec Area 2

Prep/Pour Clinic SOG Area 2

Underground Plbg R-ins Area 3

Underground Elec Area 3

Prep/Pour Clinic SOG Area 3

Undeground Plbg R-ins Domiciliary Area 1

Underground Elec Domiciliary Area 1

Erect Structural Steel/Deck/Detail/Stairs

6/13

F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

VA Tampa Mental Health Clinic and Domicilary

Cullinan Properties, LTD

Leo A Daly

Prosser Inc.

Wed 2/16/22 Page 3 VA/GSA

Task Name Start Finish Duration

184 Clinic Phase 2 Complete Wed 7/27/22 Wed 7/27/22 0 days

185 Stair Systems Complete Wed 8/10/22 Wed 8/10/22 0 days

186 Domiciliary Area 1 Steel Complete Wed 8/10/22 Wed 8/10/22 0 days

187 Domiciliary Area 2 Steel Complete Wed 8/24/22 Wed 8/24/22 0 days

188 Set Clinic RTU Curbs Wed 8/17/22 Wed 8/17/22 0 days

189 Set Domiciliary RTU Curbs Thu 9/8/22 Thu 9/8/22 0 days

190 Prep/Pour Domiciliary SOG Area 1 Mon 5/23/22 Thu 6/2/22 8 days

191 Underground Plbg Domiciliary Area 2 Wed 5/18/22 Wed 6/1/22 10 days

192 Underground Elec Domiciliary Area 2 Wed 5/25/22 Mon 6/6/22 8 days

193 Prep/Pour Domiciliary SOG Area 2 Tue 6/7/22 Mon 6/13/22 5 days

194 Prep/Pour 2nd Flr. Clinic SOM Area 1 Fri 6/10/22 Thu 6/16/22 5 days

195 Prep/Pour 2nd Flr. Clinic SOM Area 2 Thu 7/28/22 Wed 8/3/22 5 days

196 Prep/Pour 2nd Flr. Clinic SOM Area 3 Tue 8/2/22 Mon 8/8/22 5 days

197 Install Equipment Pads @ Loading Dock Area Tue 8/9/22 Tue 9/20/22 30 days

198 Install Dock Leveler & Scissor Lift Wed 9/21/22 Fri 9/23/22 3 days

200 ENCLOSURE CLINIC Thu 4/14/22 Fri 3/10/23 226 days

201 Exterior Mockup Wall Complete Thu 4/14/22 Thu 4/14/22 0 days

202 Exterior Studs/Sheathing 1st Floor Clinic Tue 6/21/22 Tue 7/26/22 25 days

203 Exterior Studs/Sheathing 2nd Flr. Clinic Thu 6/23/22 Thu 7/28/22 25 days

204 Deliver Exterior Hollow Metal Door Frames Tue 6/21/22 Tue 6/21/22 0 days

205 Install Early Test Windows & Waterproofing Wed 7/13/22 Thu 7/14/22 2 days

206 Water Test Early Window Install Fri 7/29/22 Fri 7/29/22 1 day

207 Exterior Sheathing Punchlist Fri 7/29/22 Mon 8/1/22 2 days

208 Waterproofing Wed 7/6/22 Tue 8/9/22 25 days

209 Install Canopy/Awning/Building Signage Structural Ties/All threads Wed 7/20/22 Tue 7/26/22 5 days

210 Waterproofing Punchlist Wed 8/10/22 Thu 8/11/22 2 days

211 Install Window Systems & Curtainwalls Wed 7/20/22 Wed 9/7/22 35 days

212 Window Punchlist Thu 9/22/22 Fri 9/23/22 2 days

213 Install Brick Wed 7/20/22 Wed 9/14/22 40 days

214 Install Dumpster Enclosure Walls - CMU/Brick Thu 9/15/22 Thu 10/13/22 20 days

215 Water Test Remaining Windows Thu 10/6/22 Thu 10/6/22 0 days

216 Install Roof Wood Blocking Clinic Thu 7/28/22 Wed 8/10/22 10 days

217 Install 2nd Floor Roof System Clinic Thu 8/4/22 Thu 9/15/22 30 days

218 Measure/Fab Panels Area 1 Wed 8/17/22 Wed 10/5/22 35 days

219 Install Fiber Cement Siding Plank Thu 9/15/22 Tue 10/25/22 28 days

220 Measure/Fab Panels Area 2 Thu 9/15/22 Thu 11/3/22 35 days

221 Install Metal Panels Area 1 Thu 10/6/22 Thu 10/27/22 15 days

222 Measure/Fab Panels Area 3 Thu 10/6/22 Mon 11/28/22 35 days

7/27

8/10

8/10

8/24

8/17

9/8

Prep/Pour Domiciliary SOG Area 1

Underground Plbg Domiciliary Area 2

Underground Elec Domiciliary Area 2

Prep/Pour Domiciliary SOG Area 2

Prep/Pour 2nd Flr. Clinic SOM Area 1

Prep/Pour 2nd Flr. Clinic SOM Area 2

Prep/Pour 2nd Flr. Clinic SOM Area 3

Install Equipment Pads @ Loading Dock Area

Install Dock Leveler & Scissor Lift

4/14

Exterior Studs/Sheathing 1st Floor Clinic

Exterior Studs/Sheathing 2nd Flr. Clinic

6/21

Install Early Test Windows & Waterproofing

Water Test Early Window Install

Exterior Sheathing Punchlist

Waterproofing

Install Canopy/Awning/Building Signage Structural Ties/All threads

Waterproofing Punchlist

Install Window Systems

Window Punchlist

Install Brick

Install Dumpster Enclosure Walls - CMU/Brick

10/6

Install Roof Wood Blocking Clinic

Install 2nd Floor Roof System Clinic

Measure/Fab Panels Area 1

Install Hardie Plank

Measure/Fab Panels Area 2

Install Metal Panels Area 1

Measure/Fab Panels Area 3

F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

VA Tampa Mental Health Clinic and Domicilary

Cullinan Properties, LTD

Leo A Daly

Prosser Inc.

Wed 2/16/22 Page 4 VA/GSA

Task Name Start Finish Duration

223 Install Metal Panels Area 2 Fri 11/4/22 Mon 11/28/22 15 days

224 Install Metal Panels Area 3 Tue 11/29/22 Mon 12/19/22 15 days

225 Install Storefront Doors & Aluminum Entry Slides Tue 12/20/22 Wed 1/11/23 15 days

226 Install Screenwall Metal Panels Tue 12/20/22 Wed 1/4/23 10 days

227 Install Building Signage Tue 12/20/22 Wed 1/11/23 15 days

228 Install Canopies/Awnings Tue 12/20/22 Thu 1/19/23 20 days

229 Install Coping Cap Fri 2/3/23 Thu 2/16/23 10 days

230 Install Overhead Doors Tue 12/20/22 Wed 1/11/23 15 days

231 Exterior Skin (Metal Panel & Brick )Punchlist Fri 2/17/23 Fri 3/10/23 15 days

233 ENCLOSURE DOMICILARY AREA 1 & 2 Fri 7/29/22 Fri 3/24/23 163 days

234 Exterior Studs / Sheathing Domicilary Area 1 Fri 7/29/22 Thu 8/11/22 10 days

235 Install Roof Wood Blocking Domicilary Area 1 Fri 8/12/22 Fri 8/19/22 6 days

236 Exterior Studs / Sheathing Domicilary Area 2 Fri 8/12/22 Thu 8/25/22 10 days

237 Install Domiciliary Waterproofing Area 1 & 2 Fri 8/19/22 Thu 9/1/22 10 days

238 Install Brick Thu 9/15/22 Thu 10/13/22 20 days

239 Install Domiciliary Windows Area 1 & 2 Fri 9/2/22 Fri 9/16/22 10 days

240 Install Roof System Domicilary Area 1 Fri 9/9/22 Thu 9/22/22 10 days

241 Install Roof Wood Blocking Domicilary Area 2 Fri 9/23/22 Fri 9/30/22 6 days

242 Install Roof System Domicilary Area 2 Mon 10/3/22 Mon 10/17/22 10 days

243 Water Test Window Fri 9/23/22 Fri 9/23/22 0 days

244 Measure/Fab Panels Area 1 Fri 10/14/22 Mon 12/5/22 35 days

245 Install Hardie Plank Wed 10/26/22 Mon 11/21/22 18 days

246 Measure/Fab Panels Area 2 Wed 10/26/22 Thu 12/15/22 35 days

247 Install Metal Panels Area 1 Tue 12/20/22 Wed 1/4/23 10 days

248 Install Metal Panels Area 2 Thu 1/5/23 Thu 1/19/23 10 days

249 Install Screenwall Metal Panels Fri 1/20/23 Thu 2/2/23 10 days

250 Install Coping Cap Fri 2/17/23 Fri 3/3/23 10 days

251 Exterior Skin Punchlist Mon 3/6/23 Fri 3/24/23 15 days

253 BUILDOUT Tue 6/21/22 Tue 6/27/23 255 days

254 BUILDOUT CLINIC FIRST FLOOR AREA 1 Tue 6/21/22 Wed 3/1/23 173 days

255 Layout Walls Tue 6/21/22 Thu 6/30/22 8 days

256 Deliver Interior Clinic Door Frames Tue 6/21/22 Tue 6/21/22 0 days

257 Install Hangers / Z Plates Fri 7/1/22 Fri 7/8/22 5 days

258 Frame / Top Out Priority Walls ( Densarmor ) Mon 7/11/22 Thu 7/21/22 9 days

259 Electrical Rooms (Main and Subs) Ready for Gear Wed 7/20/22 Wed 7/20/22 0 days

260 MEP / FP Above Ceiling Rough-Ins Mon 7/18/22 Fri 8/26/22 30 days

261 Interior Metal Studs Mon 7/25/22 Fri 8/12/22 15 days

262 MEP In Wall Rough-Ins Mon 8/1/22 Wed 8/24/22 18 days

Install Metal Panels Area 2

Install Metal Panels Area 3

Install Storefront Doors & Aluminum Entry Slides

Install Screenwall Metal Panels

Install Building Signage

Install Canopies/Awnings

Install Coping Cap

Install Overhead Doors

Exterior Skin Punchlist

Exterior Studs / Sheathing Domicilary Area 1

Install Roof Wood Blocking Domicilary Area 1

Exterior Studs / Sheathing Domicilary Area 2

Install Domiciliary Waterproofing

Install Brick

Install Domiciliary Windows

Install Roof System Domicilary Area 1

Install Roof Wood Blocking Domicilary Area 2

Install Roof System Domicilary Area 2

9/23

Measure/Fab Panels Area 1

Install Hardie Plank

Measure/Fab Panels Area 2

Install Metal Panels Area 1

Install Metal Panels Area 2

Install Screenwall Metal Panels

Install Coping Cap

Exterior Skin Punchlist

Layout Walls

6/21

Install Hangers / Z Plates

Frame / Top Out Priority Walls ( Densarmor )

7/20

MEP / FP Above Ceiling Rough-Ins

Interior Metal Studs

MEP In Wall Rough-Ins

F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

VA Tampa Mental Health Clinic and Domicilary

Cullinan Properties, LTD

Leo A Daly

Prosser Inc.

Wed 2/16/22 Page 5 VA/GSA

Task Name Start Finish Duration

263 MEP In Wall Inspections Thu 8/25/22 Mon 8/29/22 3 days

264 Pull Wire Mon 8/29/22 Mon 9/12/22 10 days

265 Test / Insulate Duct Mon 8/29/22 Mon 9/12/22 10 days

266 Hang Drywall Thu 9/1/22 Thu 9/29/22 20 days

267 Frame Drywall Soffits / Ceilings Fri 9/9/22 Thu 9/15/22 5 days

268 Firetape / Finish Drywall Tue 9/13/22 Fri 10/14/22 23 days

269 Rough-In Soffits / Ceilings Wed 9/14/22 Tue 9/20/22 5 days

270 Soffit / Ceiling R-In Inspections Wed 9/21/22 Thu 9/22/22 2 days

271 Hang Soffits / Ceilings Fri 9/23/22 Tue 9/27/22 3 days

272 Install Low Voltage Cabling Fri 9/30/22 Fri 10/14/22 10 days

273 Install Elevators Fri 9/30/22 Tue 12/13/22 50 days

274 Prime/1st Coat Finish ( Spray, Backroll ) Thu 10/13/22 Fri 10/28/22 12 days

275 Firestopping / Accoustical Sealant Mon 10/17/22 Tue 10/25/22 7 days

276 Operable Partitions Wed 10/26/22 Tue 11/1/22 5 days

277 Ceiling Grid Thu 10/27/22 Wed 11/23/22 20 days

278 Lights / Grilles / Diffusers / Sprinkler Drops Thu 11/3/22 Fri 12/2/22 20 days

279 Float Floors/Level Fri 11/25/22 Tue 12/6/22 8 days

280 Flooring Wed 12/7/22 Wed 12/28/22 15 days

281 Terrazo @ Monument Stair Thu 12/29/22 Fri 1/20/23 15 days

282 Install Interior Glass @ Monument Stair Mon 1/23/23 Fri 1/27/23 5 days

283 Casework Thu 12/29/22 Fri 1/20/23 15 days

284 Install Wall Protection Recievers Mon 10/31/22 Mon 11/14/22 10 days

285 Ceramic Tile @ Toilets Mon 12/5/22 Thu 12/29/22 18 days

286 Above Ceiling Punchlist / Inspections Mon 12/5/22 Fri 12/9/22 5 days

287 Energize Lights Fri 12/2/22 Fri 12/2/22 0 days

288 Install Plumbing Fixtures Wed 1/11/23 Thu 1/26/23 12 days

289 Ceiling Tile Mon 12/12/22 Tue 12/20/22 7 days

290 Finish Paint Wed 12/21/22 Mon 1/9/23 12 days

291 Toilet Partitions / Toilet Accessories Thu 12/22/22 Fri 1/6/23 10 days

292 Doors and Hardware Thu 12/29/22 Thu 1/12/23 10 days

293 Install Wall Protection/Handrail/Crashrail Thu 12/29/22 Thu 1/12/23 10 days

294 Install Interior Glass & Firelites Fri 1/13/23 Thu 1/19/23 4 days

295 Install Blinds & Window Shades Thu 12/29/22 Thu 1/5/23 5 days

296 MEP Trim Out Tue 1/3/23 Tue 1/17/23 10 days

297 Install Interior Signage Tue 1/10/23 Tue 1/17/23 5 days

298 Install Owner Furnished Equipment Tue 1/10/23 Tue 1/24/23 10 days

299 Carpet and Base Tue 1/10/23 Tue 1/24/23 10 days

300 Hoar Punchlist Wed 1/25/23 Wed 1/25/23 1 day

MEP In Wall Inspections

Pull Wire

Test / Insulate Duct

Hang Drywall

Frame Drywall Soffits / Ceilings

Firetape / Finish Drywall

Rough-In Soffits / Ceilings

Soffit / Ceiling R-In Inspections

Hang Soffits / Ceilings

Install Low Voltage Cabling

Install Elevators

Prime/1st Coat Finish ( Spray,Backroll )

Firestopping / Accoustical Sealant

Operable Partitions

Ceiling Grid

Lights / Grilles / Diffusers / Sprinkler Drops

Float Floors/Level

Flooring

Terrazo @ Monument Stair

Install Interior Glass & Monument Stair

Casework

Install Wall Protection Recievers

Ceramic Tile @ Toilets

Above Ceiling Punchlist / Inspections

12/2

Install Plumbing Fixtures

Ceiling Tile

Finish Paint

Toilet Partitions / Toilet Accessories

Doors and Hardware

Install Wall Protection/Handrail/Crashrail

Install Interior Glass & Firelites

Install Blinds & Window Shades

MEP Trim Out

Install Interior Signage

Install Owner Furnished Equipment

Carpet and Base

Hoar Punchlist

F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

VA Tampa Mental Health Clinic and Domicilary

Cullinan Properties, LTD

Leo A Daly

Prosser Inc.

Wed 2/16/22 Page 6 VA/GSA

Task Name Start Finish Duration

301 Work Off Punchlist Thu 1/26/23 Wed 2/15/23 15 days

302 Final Clean Thu 2/16/23 Wed 3/1/23 10 days

304 BUILDOUT CLINIC FIRST FLOOR AREA 2 Thu 8/11/22 Tue 4/25/23 176 days

305 Layout Walls Thu 8/11/22 Mon 8/22/22 8 days

306 Install Hangers / Z Plates Tue 8/23/22 Mon 8/29/22 5 days

307 Frame / Top Out Priority Walls ( Densarmor ) Tue 8/30/22 Mon 9/12/22 9 days

308 Electrical Rooms Ready for Gear Thu 9/22/22 Thu 9/22/22 0 days

309 MEP / FP Above Ceiling Rough-Ins Tue 9/13/22 Tue 10/25/22 30 days

310 Interior Metal Studs Tue 9/20/22 Tue 10/11/22 15 days

311 MEP In Wall Rough-Ins Tue 9/27/22 Fri 10/21/22 18 days

312 MEP In Wall Inspections Mon 10/24/22 Wed 10/26/22 3 days

313 Pull Wire Wed 10/26/22 Tue 11/8/22 10 days

314 Test / Insulate Duct Wed 10/26/22 Tue 11/8/22 10 days

315 Hang Drywall Thu 10/27/22 Fri 11/25/22 20 days

316 Frame Drywall Soffits / Ceilings Thu 11/3/22 Wed 11/9/22 5 days

317 Firetape / Finish Drywall Mon 11/7/22 Fri 12/9/22 23 days

318 Rough-In Soffits / Ceilings Tue 11/8/22 Tue 11/15/22 5 days

319 Soffit / Ceiling R-In Inspections Wed 11/16/22 Thu 11/17/22 2 days

320 Hang Soffits / Ceilings Fri 11/18/22 Tue 11/22/22 3 days

321 Install Low Voltage Cabling Mon 11/28/22 Fri 12/9/22 10 days

322 Prime/1st Coat Finish ( Spray, Backroll ) Thu 12/8/22 Fri 12/23/22 12 days

323 Firestopping / Accoustical Sealant Mon 12/12/22 Tue 12/20/22 7 days

324 Install Wall Protection Recievers Tue 12/27/22 Tue 1/10/23 10 days

325 Operable Partitions Tue 12/27/22 Tue 1/3/23 5 days

326 Ceiling Grid Thu 12/22/22 Wed 1/18/23 20 days

327 Set/Install Kitchen Equipment Thu 1/19/23 Wed 2/1/23 10 days

328 Lights / Grilles / Diffusers / Sprinkler Drops Fri 12/30/22 Mon 1/30/23 20 days

329 Float Floors/Level Thu 1/19/23 Mon 1/30/23 8 days

330 Flooring Tue 1/31/23 Tue 2/21/23 15 days

331 Casework Wed 2/22/23 Tue 3/14/23 15 days

332 Ceramic Tile @ Toilets Tue 1/31/23 Wed 2/15/23 12 days

333 Quarry Tile in Kitchen Thu 2/16/23 Thu 3/9/23 15 days

334 Above Ceiling Punchlist / Inspections Tue 1/31/23 Mon 2/6/23 5 days

335 Energize Lights Mon 1/30/23 Mon 1/30/23 0 days

336 Install Plumbing Fixtures Mon 3/6/23 Tue 3/21/23 12 days

337 Ceiling Tile Tue 2/7/23 Wed 2/15/23 7 days

338 Finish Paint Thu 2/16/23 Mon 3/6/23 12 days

339 Toilet Partitions / Toilet Accessories Thu 2/9/23 Thu 2/23/23 10 days

Work Off Punchlist

Final Clean

Layout Walls

Install Hangers / Z Plates

Frame / Top Out Priority Walls ( Densarmor )

9/22

MEP / FP Above Ceiling Rough-Ins

Interior Metal Studs

MEP In Wall Rough-Ins

MEP In Wall Inspections

Pull Wire

Test / Insulate Duct

Hang Drywall

Frame Drywall Soffits / Ceilings

Firetape / Finish Drywall

Rough-In Soffits / Ceilings

Soffit / Ceiling R-In Inspections

Hang Soffits / Ceilings

Install Low Voltage Cabling

Prime/1st Coat Finish ( Spray,Backroll )

Firestopping / Accoustical Sealant

Install Wall Protection Recievers

Operable Partitions

Ceiling Grid

Set/Install Kitchen Equipment

Lights / Grilles / Diffusers / Sprinkler Drops

Float Floors/Level

Flooring

Casework

Ceramic Tile @ Toilets

Quarry Tile in Kitchen

Above Ceiling Punchlist / Inspections

1/30

Install Plumbing Fixtures

Ceiling Tile

Finish Paint

Toilet Partitions / Toilet Accessories

F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

VA Tampa Mental Health Clinic and Domicilary

Cullinan Properties, LTD

Leo A Daly

Prosser Inc.

Wed 2/16/22 Page 7 VA/GSA

Task Name Start Finish Duration

340 Doors and Hardware Wed 2/22/23 Tue 3/7/23 10 days

341 Install Wall Protection/Handrail/Crashrail Tue 1/31/23 Mon 2/13/23 10 days

342 Install Interior Glass & Firelites Wed 3/8/23 Mon 3/13/23 4 days

343 Install Blinds & Window Shades Wed 2/22/23 Tue 2/28/23 5 days

344 MEP Trim Out Tue 2/28/23 Mon 3/13/23 10 days

345 Install Interior Signage Tue 3/7/23 Mon 3/13/23 5 days

346 Install Owner Furnished Equipment Tue 3/7/23 Mon 3/20/23 10 days

347 Carpet and Base Tue 3/7/23 Mon 3/20/23 10 days

348 Hoar Punchlist Tue 3/21/23 Tue 3/21/23 1 day

349 Work Off Punchlist Wed 3/22/23 Tue 4/11/23 15 days

350 Final Clean Wed 4/12/23 Tue 4/25/23 10 days

352 BUILDOUT CLINIC SECOND FLOOR AREA 1 Thu 7/28/22 Mon 5/8/23 195 days

353 Layout Walls Thu 7/28/22 Mon 8/8/22 8 days

354 Install Hangers / Z Plates Mon 8/1/22 Tue 8/16/22 12 days

355 Frame / Top Out Priority Walls ( Densarmor ) Mon 8/8/22 Fri 8/26/22 15 days

356 Electrical Rooms Ready for Gear Thu 9/8/22 Thu 9/8/22 0 days

357 MEP / FP Above Ceiling Rough-Ins Mon 8/29/22 Thu 10/13/22 32 days

358 Interior Metal Studs Tue 9/6/22 Mon 9/26/22 15 days

359 MEP In Wall Rough-Ins Tue 9/13/22 Tue 10/18/22 25 days

360 MEP In Wall Inspections Wed 10/19/22 Fri 10/21/22 3 days

361 Pull Wire Fri 10/14/22 Thu 10/27/22 10 days

362 Test / Insulate Duct Fri 10/14/22 Thu 10/27/22 10 days

363 Hang Drywall Mon 10/24/22 Tue 11/29/22 25 days

364 Frame Drywall Soffits / Ceilings Mon 10/31/22 Fri 11/4/22 5 days

365 Firetape / Finish Drywall Mon 10/31/22 Tue 12/13/22 30 days

366 Rough-In Soffits / Ceilings Thu 11/3/22 Wed 11/9/22 5 days

367 Soffit / Ceiling R-In Inspections Thu 11/10/22 Mon 11/14/22 2 days

368 Hang Soffits / Ceilings Tue 11/15/22 Thu 11/17/22 3 days

369 Install Low Voltage Cabling Wed 11/30/22 Tue 12/13/22 10 days

370 Prime/1st Coat Finish ( Spray, Backroll ) Mon 12/12/22 Wed 12/28/22 12 days

371 Firestopping / Accoustical Sealant Wed 12/14/22 Thu 12/22/22 7 days

372 Operable Partitions Thu 12/29/22 Thu 1/5/23 5 days

373 Ceiling Grid Mon 12/26/22 Fri 1/20/23 20 days

374 Lights / Grilles / Diffusers / Sprinkler Drops Wed 1/4/23 Wed 2/1/23 20 days

375 Float Floors/Level Mon 1/23/23 Wed 2/1/23 8 days

376 Flooring Thu 2/2/23 Thu 2/23/23 15 days

377 Casework Fri 2/24/23 Thu 3/16/23 15 days

378 Install Wall Protection Recievers Thu 12/29/22 Thu 1/12/23 10 days

Doors and Hardware

Install Wall Protection/Handrail/Crashrail

Install Interior Glass & Firelites

Install Blinds & Window Shades

MEP Trim Out

Install Interior Signage

Install Owner Furnished Equipment

Carpet and Base

Hoar Punchlist

Work Off Punchlist

Final Clean

Layout Walls

Install Hangers / Z Plates

Frame / Top Out Priority Walls ( Densarmor )

9/8

MEP / FP Above Ceiling Rough-Ins

Interior Metal Studs

MEP In Wall Rough-Ins

MEP In Wall Inspections

Pull Wire

Test / Insulate Duct

Hang Drywall

Frame Drywall Soffits / Ceilings

Firetape / Finish Drywall

Rough-In Soffits / Ceilings

Soffit / Ceiling R-In Inspections

Hang Soffits / Ceilings

Install Low Voltage Cabling

Prime/1st Coat Finish ( Spray,Backroll )

Firestopping / Accoustical Sealant

Operable Partitions

Ceiling Grid

Lights / Grilles / Diffusers / Sprinkler Drops

Float Floors/Level

Flooring

Casework

Install Wall Protection Recievers

F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

VA Tampa Mental Health Clinic and Domicilary

Cullinan Properties, LTD

Leo A Daly

Prosser Inc.

Wed 2/16/22 Page 8 VA/GSA

Task Name Start Finish Duration

379 Ceramic Tile @ Toilets Thu 2/2/23 Tue 2/28/23 18 days

380 Above Ceiling Punchlist / Inspections Thu 2/2/23 Wed 2/8/23 5 days

381 Energize Lights Wed 2/1/23 Wed 2/1/23 0 days

382 Install Plumbing Fixtures Wed 3/8/23 Thu 3/23/23 12 days

383 Ceiling Tile Thu 2/9/23 Wed 2/22/23 10 days

384 Finish Paint Thu 2/23/23 Wed 3/15/23 15 days

385 Toilet Partitions / Toilet Accessories Wed 2/22/23 Tue 3/7/23 10 days

386 Doors and Hardware Fri 2/24/23 Thu 3/9/23 10 days

387 Install Wall Protection/Handrail/Crashrail Fri 2/24/23 Thu 3/9/23 10 days

388 Install Interior Glass & Firelites Fri 3/10/23 Wed 3/15/23 4 days

389 Install Blinds & Window Shades Fri 2/24/23 Thu 3/2/23 5 days

390 MEP Trim Out Thu 3/9/23 Wed 3/22/23 10 days

391 Install Interior Signage Thu 3/16/23 Wed 3/22/23 5 days

392 Install Owner Furnished Equipment Thu 3/16/23 Wed 3/29/23 10 days

393 Carpet and Base Thu 3/16/23 Fri 3/31/23 12 days

394 Hoar Punchlist Mon 4/3/23 Mon 4/3/23 1 day

395 Work Off Punchlist Tue 4/4/23 Mon 4/24/23 15 days

396 Final Clean Tue 4/25/23 Mon 5/8/23 10 days

398 BUILDOUT CLINIC SECOND FLOOR AREA 2 Mon 8/29/22 Tue 6/27/23 207 days

399 Layout Walls Mon 8/29/22 Thu 9/8/22 8 days

400 Install Hangers / Z Plates Fri 9/9/22 Tue 9/20/22 8 days

401 Frame / Top Out Priority Walls ( Densarmor ) Wed 9/21/22 Wed 10/12/22 15 days

402 Electrical Rooms Ready for Gear Mon 10/24/22 Mon 10/24/22 0 days

403 MEP / FP Above Ceiling Rough-Ins Thu 10/13/22 Tue 11/29/22 32 days

404 Interior Metal Studs Thu 10/20/22 Wed 11/9/22 15 days

405 MEP In Wall Rough-Ins Thu 10/27/22 Fri 12/2/22 25 days

406 MEP In Wall Inspections Mon 12/5/22 Wed 12/7/22 3 days

407 Pull Wire Wed 11/30/22 Tue 12/13/22 10 days

408 Test / Insulate Duct Wed 11/30/22 Tue 12/13/22 10 days

409 Hang Drywall Thu 12/8/22 Fri 1/13/23 25 days

410 Frame Drywall Soffits / Ceilings Thu 12/15/22 Wed 12/21/22 5 days

411 Firetape / Finish Drywall Thu 12/15/22 Mon 1/30/23 30 days

412 Rough-In Soffits / Ceilings Tue 12/20/22 Tue 12/27/22 5 days

413 Soffit / Ceiling R-In Inspections Wed 12/28/22 Thu 12/29/22 2 days

414 Hang Soffits / Ceilings Fri 12/30/22 Wed 1/4/23 3 days

415 Install Low Voltage Cabling Tue 1/17/23 Mon 1/30/23 10 days

416 Prime/1st Coat Finish ( Spray, Backroll ) Fri 1/27/23 Mon 2/13/23 12 days

417 Firestopping / Accoustical Sealant Tue 1/31/23 Wed 2/8/23 7 days

Ceramic Tile @ Toilets

Above Ceiling Punchlist / Inspections

2/1

Install Plumbing Fixtures

Ceiling Tile

Finish Paint

Toilet Partitions / Toilet Accessories

Doors and Hardware

Install Wall Protection/Handrail/Crashrail

Install Interior Glass & Firelites

Install Blinds & Window Shades

MEP Trim Out

Install Interior Signage

Install Owner Furnished Equipment

Carpet and Base

Hoar Punchlist

Work Off Punchlist

Final Clean

Layout Walls

Install Hangers / Z Plates

Frame / Top Out Priority Walls ( Densarmor )

10/24

MEP / FP Above Ceiling Rough-Ins

Interior Metal Studs

MEP In Wall Rough-Ins

MEP In Wall Inspections

Pull Wire

Test / Insulate Duct

Hang Drywall

Frame Drywall Soffits / Ceilings

Firetape / Finish Drywall

Rough-In Soffits / Ceilings

Soffit / Ceiling R-In Inspections

Hang Soffits / Ceilings

Install Low Voltage Cabling

Prime/1st Coat Finish ( Spray,Backroll )

Firestopping / Accoustical Sealant

F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

VA Tampa Mental Health Clinic and Domicilary

Cullinan Properties, LTD

Leo A Daly

Prosser Inc.

Wed 2/16/22 Page 9 VA/GSA

Task Name Start Finish Duration

418 Operable Partitions Tue 2/14/23 Tue 2/21/23 5 days

419 Ceiling Grid Fri 2/10/23 Mon 3/13/23 22 days

420 Lights / Grilles / Diffusers / Sprinkler Drops Fri 2/17/23 Tue 3/21/23 22 days

421 Float Floors/Level Tue 3/14/23 Thu 3/23/23 8 days

422 Flooring Fri 3/24/23 Thu 4/13/23 15 days

423 Casework Fri 4/14/23 Thu 5/4/23 15 days

424 Install Wall Protection Recievers Tue 2/14/23 Tue 2/28/23 10 days

425 Ceramic Tile @ Toilets Wed 3/22/23 Fri 4/14/23 18 days

426 Above Ceiling Punchlist / Inspections Wed 3/22/23 Tue 3/28/23 5 days

427 Energize Lights Tue 3/21/23 Tue 3/21/23 0 days

428 Install Plumbing Fixtures Wed 4/26/23 Thu 5/11/23 12 days

429 Ceiling Tile Wed 3/29/23 Tue 4/11/23 10 days

430 Finish Paint Wed 4/12/23 Tue 5/2/23 15 days

431 Toilet Partitions / Toilet Accessories Mon 4/10/23 Fri 4/21/23 10 days

432 Doors and Hardware Fri 4/14/23 Thu 4/27/23 10 days

433 Install Wall Protection/Handrail/Crashrail Fri 3/24/23 Thu 4/6/23 10 days

434 Install Interior Glass & Firelites Fri 4/28/23 Wed 5/3/23 4 days

435 Install Blinds & Window Shades Fri 4/14/23 Thu 4/20/23 5 days

436 MEP Trim Out Wed 4/26/23 Tue 5/9/23 10 days

437 Install Interior Signage Wed 5/3/23 Tue 5/9/23 5 days

438 Install Owner Furnished Equipment Wed 5/3/23 Tue 5/16/23 10 days

439 Carpet and Base Wed 5/3/23 Thu 5/18/23 12 days

440 Hoar Punchlist Fri 5/19/23 Tue 5/23/23 3 days

441 Work Off Punchlist Wed 5/24/23 Tue 6/13/23 15 days

442 Final Clean Wed 6/14/23 Tue 6/27/23 10 days

444 DOMICILIARY 1 Fri 9/9/22 Fri 4/14/23 149 days

445 Layout Walls Fri 9/9/22 Thu 9/15/22 5 days

446 Install Hangers / Z Plates Tue 9/13/22 Mon 9/19/22 5 days

447 Frame / Top Out Priority Walls ( Densarmor ) Tue 9/20/22 Mon 9/26/22 5 days

448 Electrical Rooms Ready for Gear Thu 10/6/22 Thu 10/6/22 0 days

449 MEP / FP Above Ceiling Rough-Ins Tue 9/27/22 Fri 10/21/22 18 days

450 Interior Metal Studs Tue 10/4/22 Tue 10/18/22 10 days

451 MEP In Wall Rough-Ins Wed 10/12/22 Tue 11/1/22 15 days

452 MEP In Wall Inspections Wed 11/2/22 Fri 11/4/22 3 days

453 Pull Wire Mon 10/24/22 Fri 11/4/22 10 days

454 Test / Insulate Duct Mon 10/24/22 Fri 11/4/22 10 days

455 Hang Drywall Mon 11/7/22 Tue 11/29/22 15 days

456 Frame Drywall Soffits / Ceilings Tue 11/15/22 Mon 11/21/22 5 days

Operable Partitions

Ceiling Grid

Lights / Grilles / Diffusers / Sprinkler Drops

Float Floors/Level

Flooring

Casework

Install Wall Protection Recievers

Ceramic Tile @ Toilets

Above Ceiling Punchlist / Inspections

3/21

Install Plumbing Fixtures

Ceiling Tile

Finish Paint

Toilet Partitions / Toilet Accessories

Doors and Hardware

Install Wall Protection/Handrail/Crashrail

Install Interior Glass & Firelites

Install Blinds & Window Shades

MEP Trim Out

Install Interior Signage

Install Owner Furnished Equipment

Carpet and Base

Hoar Punchlist

Work Off Punchlist

Final Clean

Layout Walls

Install Hangers / Z Plates

Frame / Top Out Priority Walls ( Densarmor )

10/6

MEP / FP Above Ceiling Rough-Ins

Interior Metal Studs

MEP In Wall Rough-Ins

MEP In Wall Inspections

Pull Wire

Test / Insulate Duct

Hang Drywall

Frame Drywall Soffits / Ceilings

F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

VA Tampa Mental Health Clinic and Domicilary

Cullinan Properties, LTD

Leo A Daly

Prosser Inc.

Wed 2/16/22 Page 10 VA/GSA

Task Name Start Finish Duration

457 Firetape / Finish Drywall Wed 11/23/22 Thu 12/22/22 21 days

458 Rough-In Soffits / Ceilings Wed 11/16/22 Fri 11/25/22 7 days

459 Soffit / Ceiling R-In Inspections Mon 11/28/22 Fri 12/2/22 5 days

460 Hang Soffits / Ceilings Mon 12/5/22 Fri 12/16/22 10 days

461 Install Low Voltage Cabling Wed 11/30/22 Tue 12/13/22 10 days

462 Prime/1st Coat Finish ( Spray, Backroll ) Wed 12/21/22 Thu 1/5/23 10 days

463 Firestopping / Accoustical Sealant Wed 12/14/22 Thu 12/22/22 7 days

464 Install Cubicle Curtain Track Fri 1/6/23 Wed 1/18/23 8 days

465 Ceiling Grid Fri 1/6/23 Thu 1/12/23 5 days

466 Lights / Grilles / Diffusers / Sprinkler Drops Fri 1/13/23 Fri 1/27/23 10 days

467 Float Floors/Level Fri 1/13/23 Wed 1/25/23 8 days

468 Flooring Thu 1/26/23 Wed 2/8/23 10 days

469 Casework Thu 2/9/23 Thu 2/23/23 10 days

470 Install Wall Protection Recievers Fri 1/6/23 Tue 1/17/23 7 days

471 Ceramic Tile @ Toilets Mon 1/30/23 Thu 2/23/23 18 days

472 Above Ceiling Punchlist / Inspections Mon 1/30/23 Fri 2/3/23 5 days

473 Energize Lights Fri 1/27/23 Fri 1/27/23 0 days

474 Install Plumbing Fixtures Wed 2/22/23 Thu 3/9/23 12 days

475 Ceiling Tile Mon 2/6/23 Thu 2/9/23 4 days

476 Finish Paint Fri 2/3/23 Tue 2/21/23 12 days

477 Toilet Partitions / Toilet Accessories Thu 2/16/23 Thu 3/2/23 10 days

478 Doors and Hardware Thu 2/9/23 Thu 2/16/23 6 days

479 Install Wall Protection/Handrail/Crashrail Thu 2/9/23 Thu 2/23/23 10 days

480 Install Interior Glass & Firelites Fri 2/17/23 Wed 2/22/23 3 days

481 Install Blinds & Window Shades & Shower Curtains Thu 2/9/23 Wed 2/15/23 5 days

482 MEP Trim Out Tue 2/14/23 Thu 3/2/23 12 days

483 Install Interior Signage Wed 2/22/23 Tue 2/28/23 5 days

484 Install Owner Furnished Equipment Wed 2/22/23 Thu 3/9/23 12 days

485 Carpet and Base Wed 2/22/23 Thu 3/9/23 12 days

486 Hoar Punchlist Fri 3/10/23 Fri 3/10/23 1 day

487 Work Off Punchlist Mon 3/13/23 Fri 3/31/23 15 days

488 Final Clean Mon 4/3/23 Fri 4/14/23 10 days

490 DOMICILIARY 2 Fri 9/16/22 Wed 5/3/23 157 days

491 Layout Walls Fri 9/16/22 Thu 9/22/22 5 days

492 Install Hangers / Z Plates Tue 9/20/22 Mon 9/26/22 5 days

493 Frame / Top Out Priority Walls ( Densarmor ) Tue 9/27/22 Mon 10/3/22 5 days

494 Electrical Rooms Ready for Gear Fri 10/14/22 Fri 10/14/22 0 days

495 MEP / FP Above Ceiling Rough-Ins Mon 10/17/22 Wed 11/9/22 18 days

Firetape / Finish Drywall

Rough-In Soffits / Ceilings

Soffit / Ceiling R-In Inspections

Hang Soffits / Ceilings

Install Low Voltage Cabling

Prime/1st Coat Finish ( Spray,Backroll )

Firestopping / Accoustical Sealant

Install Cubicle Curtain Track

Ceiling Grid

Lights / Grilles / Diffusers / Sprinkler Drops

Float Floors/Level

Flooring

Casework

Install Wall Protection Recievers

Ceramic Tile @ Toilets

Above Ceiling Punchlist / Inspections

1/27

Install Plumbing Fixtures

Ceiling Tile

Finish Paint

Toilet Partitions / Toilet Accessories

Doors and Hardware

Install Wall Protection/Handrail/Crashrail

Install Interior Glass & Firelites

Install Blinds & Window Shades & Shower Curtains

MEP Trim Out

Install Interior Signage

Install Owner Furnished Equipment

Carpet and Base

Hoar Punchlist

Work Off Punchlist

Final Clean

Layout Walls

Install Hangers / Z Plates

Frame / Top Out Priority Walls ( Densarmor )

10/14

MEP / FP Above Ceiling Rough-Ins

F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

VA Tampa Mental Health Clinic and Domicilary

Cullinan Properties, LTD

Leo A Daly

Prosser Inc.

Wed 2/16/22 Page 11 VA/GSA

Task Name Start Finish Duration

496 Interior Metal Studs Mon 10/24/22 Fri 11/4/22 10 days

497 MEP In Wall Rough-Ins Mon 10/31/22 Mon 11/21/22 15 days

498 MEP In Wall Inspections Tue 11/22/22 Fri 11/25/22 3 days

499 Pull Wire Thu 11/10/22 Fri 11/25/22 10 days

500 Test / Insulate Duct Thu 11/10/22 Fri 11/25/22 10 days

501 Hang Drywall Mon 11/28/22 Fri 12/16/22 15 days

502 Frame Drywall Soffits / Ceilings Mon 12/5/22 Fri 12/9/22 5 days

503 Firetape / Finish Drywall Tue 12/13/22 Thu 1/12/23 21 days

504 Rough-In Soffits / Ceilings Tue 12/6/22 Wed 12/14/22 7 days

505 Soffit / Ceiling R-In Inspections Thu 12/15/22 Wed 12/21/22 5 days

506 Hang Soffits / Ceilings Thu 12/22/22 Fri 1/6/23 10 days

507 Install Low Voltage Cabling Mon 12/19/22 Tue 1/3/23 10 days

508 Prime/1st Coat Finish ( Spray, Backroll ) Wed 1/11/23 Wed 1/25/23 10 days

509 Firestopping / Accoustical Sealant Wed 1/4/23 Thu 1/12/23 7 days

510 Install Cubicle Curtain Track Thu 1/26/23 Mon 2/6/23 8 days

511 Ceiling Grid Thu 1/26/23 Wed 2/1/23 5 days

512 Lights / Grilles / Diffusers / Sprinkler Drops Thu 2/2/23 Wed 2/15/23 10 days

513 Float Floors/Level Thu 2/2/23 Mon 2/13/23 8 days

514 Flooring Tue 2/14/23 Tue 2/28/23 10 days

515 Casework Wed 3/1/23 Tue 3/14/23 10 days

516 Install Wall Protection Recievers Thu 1/26/23 Fri 2/3/23 7 days

517 Ceramic Tile @ Toilets Thu 2/16/23 Tue 3/14/23 18 days

518 Above Ceiling Punchlist / Inspections Thu 2/16/23 Thu 2/23/23 5 days

519 Energize Lights Wed 2/15/23 Wed 2/15/23 0 days

520 Install Plumbing Fixtures Mon 3/13/23 Tue 3/28/23 12 days

521 Ceiling Tile Fri 2/24/23 Wed 3/1/23 4 days

522 Finish Paint Thu 2/23/23 Fri 3/10/23 12 days

523 Toilet Partitions / Toilet Accessories Wed 3/8/23 Tue 3/21/23 10 days

524 Doors and Hardware Wed 3/1/23 Wed 3/8/23 6 days

525 Install Wall Protection/Handrail/Crashrail Wed 3/1/23 Tue 3/14/23 10 days

526 Install Interior Glass & Firelites Thu 3/9/23 Mon 3/13/23 3 days

527 Install Blinds & Window Shades & Shower Curtains Wed 3/1/23 Tue 3/7/23 5 days

528 MEP Trim Out Mon 3/6/23 Tue 3/21/23 12 days

529 Install Interior Signage Mon 3/13/23 Fri 3/17/23 5 days

530 Install Owner Furnished Equipment Mon 3/13/23 Tue 3/28/23 12 days

531 Carpet and Base Mon 3/13/23 Tue 3/28/23 12 days

532 Hoar Punchlist Wed 3/29/23 Wed 3/29/23 1 day

533 Work Off Punchlist Thu 3/30/23 Wed 4/19/23 15 days

Interior Metal Studs

MEP In Wall Rough-Ins

MEP In Wall Inspections

Pull Wire

Test / Insulate Duct

Hang Drywall

Frame Drywall Soffits / Ceilings

Firetape / Finish Drywall

Rough-In Soffits / Ceilings

Soffit / Ceiling R-In Inspections

Hang Soffits / Ceilings

Install Low Voltage Cabling

Prime/1st Coat Finish ( Spray,Backroll )

Firestopping / Accoustical Sealant

Install Cubicle Curtain Track

Ceiling Grid

Lights / Grilles / Diffusers / Sprinkler Drops

Float Floors/Level

Flooring

Casework

Install Wall Protection Recievers

Ceramic Tile @ Toilets

Above Ceiling Punchlist / Inspections

2/15

Install Plumbing Fixtures

Ceiling Tile

Finish Paint

Toilet Partitions / Toilet Accessories

Doors and Hardware

Install Wall Protection/Handrail/Crashrail

Install Interior Glass & Firelites

Install Blinds & Window Shades & Shower Curtains

MEP Trim Out

Install Interior Signage

Install Owner Furnished Equipment

Carpet and Base

Hoar Punchlist

Work Off Punchlist

F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

VA Tampa Mental Health Clinic and Domicilary

Cullinan Properties, LTD

Leo A Daly

Prosser Inc.

Wed 2/16/22 Page 12 VA/GSA

Task Name Start Finish Duration

534 Final Clean Thu 4/20/23 Wed 5/3/23 10 days Final Clean F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J

Half 1, 2021 Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024

VA Tampa Mental Health Clinic and Domicilary

Cullinan Properties, LTD

Leo A Daly

Prosser Inc.

Wed 2/16/22 Page 13 VA/GSA