This is a Statement of Work (SOW) for construction services to improve an existing rail bed into a Tactical Vehicle Maneuver Lane (TVML) at Camp James A. Garfield Joint Military Training Center (CJAG) in northeast Ohio. The project, identified as Project Number 3926003, is Phase 3 of the maneuver trail improvement initiative and spans 365 days from the notice to proceed. The base contract (CLIN 1) covers 450 feet of improvements between stations 78+50 to 74+00, including earthwork, fence demolition, culvert installation and replacement (60-inch CMP to RCP culvert and 24-inch RCP culvert), site restoration, and stone surface hardening. The work must accommodate tractor-trailers hauling heavy tracked military equipment and support the weight of M1A1 Abrams battle tanks at 80 tons. Four options (CLINs 2-5) each cover 500-foot sections extending west, with Option 4 requiring removal of a 36-inch CMP culvert. All work must comply with U.S. Army Corps of Engineers Nationwide Permit #3, Ohio EPA requirements, and the attached Erosion and Sediment Control Plans and Storm Water Pollution Prevention Plans.
The contractor is responsible for all personnel, transportation, equipment, tools, materials, supervision, and quality control, with work performed Monday-Friday, 0730-1630 hours, at CJAG in coordination with military training activities. The contractor must obtain a Pre-Construction Notification (PCN) and water quality certification for culvert work, prepare an environmental work plan, submit a Notice of Intent for NPDES permit coverage, and attend a pre-construction meeting. Deliverables include hard and digital copies of as-built drawings, SWP3 forms and inspection reports, construction documents, surveying and mapping data, grass seed tags, and waste disposal documentation. All contractor personnel require background clearance, AT Level 1 and OPSEC training within 30 days, iWATCH training, and proper installation identification. The contractor must maintain workforce stability and continuity, ensure employees possess required equipment operation licenses, and comply with all installation access, security, and environmental regulations, with stricter regulations taking precedence in conflicts.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
8 April 2026
Statement of Work
FOR
CAMP JAMES A. GARFIELD JOINT MILITARY TRAINING CENTER
TACTICAL VEHICLE MANEUVER LANE (TVML) Phase 3
MANEUVER TRAIL IMPROVEMENT CONSTRUCTION SERVICES
PROJECT NUMBER 3926003
1.0 General:
1.1 Scope: The contractor shall provide all personnel, transportation, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to perform Improvement Construction Services, as defined in this PWS.
1.2 Background: The Camp James A. Garfield Joint Military Training Site (CJAG) is a 21,683 acre training site located in northeast Ohio used by the Ohio Army National Guard (OHARNG) and other military and civil agencies. The purpose of this project is to improve an existing rail bed, the Tactical Vehicle Maneuver Lane (TVML), extending west from Paris-Windham Rd., west of the Engineer Dig Site North and on the north side of Smalley Rd., running parallel to it. Once fully completed and all phases constructed the improvements will provide better maneuverability across CJAG from east to west within training areas. The improvements will also contribute to long term sustainable use of training areas and will help avoid and/or minimize negative impacts to the environment and associated costs.
The maneuver trail will have a surface hardened with stone. Some culvert replacement and installation is required as well as other drainage improvements such as ditches and rock check dams. No turn pads are required for this construction project, they have already been installed. The trail must be able to accommodate a tractor trailer hauling heavy, tracked military equipment (tanks, bulldozers, etc.) and support the weight and movement of an M1A1 Abrams battle tank at 80 tons.
1.3 Period of Performance (PoP): The Period of Performance shall be 365 days from the date of the notice to proceed (NTP).
1.4 General Information:
1.4.1 Place and Performance of Services: The contractor shall provide services between the hours of 0730-1630 on Monday through Friday, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. The contractor shall coordinate their work schedule with CJAG to avoid conflicts with military training activities. If a conflict exists, training activity has priority over contractor activity. If Contractor desires to perform work outside of that schedule, a request must be made and coordinated with Range Ops at 614-336-6041. Performance shall be at the area described above in Section 1.2. The contractor shall at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential. Teleworking is not authorized.
1.4.1.1 Telework: The Government does not permit the contractor to telework in support of this requirement. In furtherance of Continuity of Operations Planning (COOP), a telework program may be enacted to ensure that the Government's mission-critical operations stay operational during times of national emergency or incidents of national significance. Telework shall be at no additional cost to the Government.
1.4.1.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
1.4.1.3 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times, and shall be subject to such checks as may be deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The Government reserves the right to direct the removal of an employee from Government property or revoke access to Government systems for misconduct, security reasons, or any overt evidence of communicable disease. Removal of contractor employees for reasons stated above does not relieve the Contractor from responsibility for total performance of this contract.
1.4.2 Recognized Holidays: The following are recognized United States (US) holidays. The contractor shall not perform services on these days. Keep in mind that in situations when a holiday falls on a weekend, the holiday will then be observed on the preceding Friday or following Monday:
1.4.2.1 New Year’s Day: January 1st
1.4.2.2 Martin Luther King, Jr.’s Birthday
1.4.2.3 President’s Day
1.4.2.4 Memorial Day
1.4.2.5 Juneteenth National Independence Day: June 19th
1.4.2.6 Independence Day: July 4th
1.4.2.7 Labor Day
1.4.2.8 Columbus Day
1.4.2.9 Veteran’s Day: November 11th
1.4.2.10 Thanksgiving Day
1.4.2.11 Christmas Day: December 25th
1.4.3 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).
1.4.4 Installation Access and Security Requirements. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the COR. The contractor and all associated subcontractor employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services, or Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by Department of Defense (DoD), Headquarters Department of Army (HQDA) and/or local policy (see PWS 6.0). Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
1.4.4.1 For contractors that do not require a CAC, but require access to a DoD facility or installation: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05), and applicable installation, facility and area commander installation/facility access, and local security policies and procedures (provided by a Government representative).
1.4.4.2 Awareness Training (AT) Level 1: All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level 1 training within 30 calendar days after contract start date and within 30 calendar days of new employees commencing performance. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee to the COR within 15 calendar days after completion of training by each employee or subcontractor personnel. AT Level 1 awareness training is available at the following website: https://jko.jten.mil/courses/atl1/launch.html.
1.4.4.3 iWATCH Training: The contractor and all associated subcontractors with an area of performance within an Army-controlled installation, facilities or area shall brief all employees on the local iWATCH program (training standards provided by the requiring activity Antiterrorism Officer (ATO)). This local developed training shall be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR or the KO. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance. The contractor shall report completion for each contractor employee and subcontractor employee to the COR within 15 calendar days after completion of training.
1.4.4.4 Communications Security/Information Technology (COMSEC/IT) Security. All communications with DoD organizations are subject to COMSEC review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations. Therefore, the contractor is advised that any time contractor personnel place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DoD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.
1.4.4.5 Protection of Personally Identifiable Information (PII). The contractor shall protect all PII encountered in the performance of services in accordance with Defense Federal Acquisition Regulation Supplement (DFARS) 224.103 Personally Identifiable Information and Department of Defense Directive (DoDD) 5400.11, Department of Defense Privacy Program, and DoD 5400.11-R. If a PII breach results from the contractor’s violation of the aforementioned policies, the contractor shall bear all notification costs, call-center support costs, and credit monitoring service costs for all individuals whose PII has been compromised.
1.4.4.6 OPSEC Training: In accordance with AR 530-1, Operations Security, new contractor employees shall complete Level I OPSEC training within 30 calendar days of their reporting for duty and annually thereafter. The contractor shall submit certificates of completion for each contractor employee to the within 15 calendar days after completion of training. Level 1 OPSEC training is available at https://securityawareness.usalearning.gov/opsec/index.htm.
1.4.5 Special Qualifications: The contractor shall ensure all employees possess all required licenses for operating equipment/machinery used in the performance of this contract. This does not include education or other qualifications for the position in which the contractor employee is performing, dress codes, or other information. (NOTE: The Government does not provide training to contractors. Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified, and otherwise qualified to provide services.)
1.4.6 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with FAR 42.5. The KO, COR and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the KO will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.
1.4.7 Contract Manager (CM): The contractor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.
1.4.8 Combating Trafficking in Persons: The United States Government has adopted a zero-tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.
1.4.9 Data Rights: The Government has unlimited rights to all documents/materials produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the KO. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.4.10 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.
2.0 Definitions and Acronyms:
2.1 Definitions:
2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
2.1.2 Defective Service: A service output that does not meet the standard of performance associated with the PWS.
2.1.3 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.
2.1.4 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.5 Physical Security: Actions that prevent the loss or damage of Government property.
2.1.6 Quality Assurance: The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.7 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.8 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.
2.1.9 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.2 Acronyms:
| AEI | Army Enterprise Infostructure |
| AR | Army Regulation |
| AT/OPSEC | Antiterrorism/Operational Security |
| BI | Background Investigation |
CLIN Contract Line Item
| CM | Contract Manager | |
| COR | Contracting Officer Representative | |
| DA | Department of the Army | |
| DD254 | Department of Defense Contract Security Classification Specification | |
| DFARS | Defense Federal Acquisition Regulation Supplement | |
| DoD | Department of Defense | |
| DSCA | Defense Counterintelligence and Security Agency | |
| EPA | Environmental Protection Agency | |
| FAR | Federal Acquisition Regulation | |
| GFP/M/E/S | Government Furnished Property/Material/Equipment/Services | |
| HQDA | Headquarters, Department of the Army | |
| HSPD | Homeland Security Presidential Directive | |
| IA | Information Assurance | |
| IS | Information System(s) | |
| KO | Contracting Officer | |
| NGB | National Guard Bureau | |
| OCI | Organizational Conflict of Interest | |
| OHARNG | Ohio Army National Guard | |
| PCN | Pre-Construction Notification | |
| PII | Personally Identifiable Information | |
| PIPO | Phase In/Phase Out | |
| POC | Point of Contact | |
| PRS | Performance Requirements Summary | |
| PWS | Performance Work Statement | |
| QA | Quality Assurance | |
| QASP | Quality Assurance Surveillance Plan | |
| SCR | Service Contract Reporting | |
| SSN | Social Security Number | |
| TE | Technical Exhibit | |
| USACE | United States Army Corps of Engineers | |
| USD(I) | Under Secretary of Defense for Intelligence | |
| WQC | Water Quality Certification |
3.0 Requirements: The contractor shall:
3.1 CLIN 1 Base Bid, Develop TVML Maneuver Trail Improvement – (450 ft.)
Improve an existing rail bed extending west from Paris-Windham Rd., just south of the North Dig Site for use by tanks and Bradley Fighting Vehicles. This task is for construction by a contractor, as shown on construction drawing sheet C-127. The work area will be between stations 78+50 to 74+00. The task includes all associated earth work, fence demolition, culvert installation, and site restoration. This section includes the replacement of a 60” CMP culvert with a 60” RCP culvert pipe with full-height headwall at the north end and a half-height headwall at the south end, rip-rap installed at both ends, and the installation of a 24” RCP culvert pipe with half-height headwalls and rip-rap at both ends between Stations 74+00 and 75+00. A Pre-Construction Notification (PCN) is required for culvert removal/replacement and all associated fees for application and Water Quality Certification (WQC) is the responsibility of the Contractor (see Section 4.5.1). The PCN will include culvert removal/replacement for the base bid and all Options that are awarded with this Contract as described in this PWS and the provided drawing plans.
3.2 CLIN 2 Option 1, Develop TVML Maneuver Trail Improvement – (500 ft.)
Improve an existing rail bed extending west from Paris-Windham Rd., just south of the North Dig Site for use by tanks and Bradley Fighting Vehicles. This task is for construction by a contractor, as shown on construction drawing sheet C-127. The work area will be between stations 74+00 to 69+00. The task includes all associated earth work, fence demolition, culvert installation, and site restoration. This section includes the installation of a 24” RCP culvert with half-height headwalls and rip-rap at both ends at Station 72+00.
3.3 CLIN 3 Option 2, Develop TVML Maneuver Trail Improvement – (500 ft.)
Improve an existing rail bed extending west from Paris-Windham Rd., just south of the North Dig Site for use by tanks and Bradley Fighting Vehicles. This task is for construction by a contractor, as shown on construction drawing sheets C-127 and C-126. The work area will be between stations 69+00 to 64+00. The task includes all associated earth work, fence demolition, and site restoration.
3.4 CLIN 4 Option 3, Develop TVML Maneuver Trail Improvement – (500 ft.)
Improve an existing rail bed extending west from Paris-Windham Rd., just south of the North Dig Site for use by tanks and Bradley Fighting Vehicles. This task is for construction by a contractor, as shown on construction drawing sheets C-126. The work area will be between stations 64+0 to 59+00. The task includes all associated earth work, fence demolition, and site restoration.
3.5 CLIN 5 Option 4, Develop TVML Maneuver Trail Improvement – (500 ft.)
Improve an existing rail bed extending west from Paris-Windham Rd., just south of the North Dig Site for use by tanks and Bradley Fighting Vehicles. This task is for construction by a contractor, as shown on construction drawing sheets C-126. The work area will be between stations 59+00 to 54+00. The task includes all associated earth work, fence demolition, and site restoration. This section includes the removal of a 36” CMP culvert between Stations 58+00 and 59+00.
4.0 Additional Requirements
4.1 The contractor shall comply with all applicable U.S. Army, Federal, state, and local laws, regulations, and safety requirements. The contractor shall supply their personnel with safety protection as required by OSHA regulations. If a discrepancy exists between regulations, the more stringent of the conflicting regulations shall take precedence.
4.2 The contractor shall comply with the CJAG access and security policies and shall provide a roster of all personnel who require access a minimum of two business days in advance of access. Access rooster will be submitted to the OHARNG project manager who will route them through Security for approval.
4.3 All construction activity must follow the construction drawings and specifications, Erosion and Sediment Control (ESC) Plans (Attachment 1), and Storm Water Pollution Prevention Plans (SWP3’s) provided by CJAG and created by Michael-Baker International. Any amendments or changes must first be approved by the OHARNG and noted on the SWP3 Amendment Log.
4.4 The contractor must comply with applicable portions of the attached Environmental Procedures (Attachment 2), dated 3 April 2024. Of particular applicability are the requirements in Section 2.0 on environmental work plans, Section 3.0 on spill prevention and response, Section 4.0 on erosion and storm water control, and Sections 1.6 and 6.0 on recycling and tracking waste.
4.5 Culvert Replacements and Wetland Requirements:
4.5.1 General Wetland Requirements:
Culvert replacements must be done in accordance with the terms and conditions of U.S. Army Corps of Engineers (USACE) Nationwide Permit #3 (NWP3) and the associated Nationwide Permits Regional General Conditions, Corps NWP Specific Regional Conditions, Ohio 401 Certification Special Limitations and Conditions, and General Limitations and Conditions for all Ohio EPA Clean Water Act Sec 401 Certified Nationwide Permits. The Contractor will obtain a copy of the above listed permit conditions and will include them in their Environmental Work Plan. The Contractor will integrate permit conditions into their work process to ensure compliance.
When a Pre-Construction Notification (PCN) or Individual Sec 401 Water Quality Certification (WQC) is required or an evaluation is needed to determine if a WQC is required, the Contractor will use a qualified Wetland Consultant to do this work. The qualified wetland consultant will perform all work, except as noted in this section, necessary to develop a complete PCN to include a Sec 401 WQC evaluation and Individual Sec 401 WQC application if/as required. The PCN and/ or WQC application must be reviewed and approved by the OHARNG prior to submittal.
PCN’s and WQC will be developed for signature by the OHARNG as the landowner. The Contractor will pay the cost for PCN and WQC development and submittal. Neither the Contractor nor the Contractor’s Wetland Consultant will contact the USACE or the Ohio EPA without written authorization from the OHARNG or the Adjutant General’s Department to do so.
If more than one culvert is replaced as part of a single project, one PCN may be developed and submitted that includes all the culverts. If a partial award is made and a later additional award is made, an additional PCN is required for any culverts not included in the initial award PCN. Project delays caused by Contractor failure to prioritize development and submittal of a PCN/WQC or the need to develop more than one PCN/WQC application will not be cause for a project extension or a cost increase.
The OHARNG Environmental Department will provide the required ESA Sec 7 consultation and the NHPA Sec 106 consultation for the PCN. The Contractor is required to provide a project description and details necessary for the OHARNG to complete these.
4.5.2 Sec 401 Water Quality Certification (WQC)
The Ohio EPA General Sec 401 Water Quality Certification is valid for NWP3 in all locations so a determination of eligibility using Ohio EPA Sec 401 WQC eligibility map is not required and an Individual Sec 401 WQC is not required.
4.5.3 Pre-Construction Notification (PCN)
4.5.3.1 A PCN is required for the culvert replacement.
4.5.3.2 Using a qualified wetland consultant, the Contractor will prepare and submit a PCN(s) in accordance with the General Wetland Requirements above.
4.5.3.3 The PCN will be submitted to: U.S. Army corps of Engineers, Pittsburgh District, William S. Moorhead Federal Building, 1000 Liberty Avenue, Pittsburgh, Pennsylvania 15222-4186,412-395-7155.
Prior approval must be obtained from the CJAG Environmental Office for all correspondence with external regulatory agencies.
4.6 The contractor will develop and submit a Notice of Intent (NOI) for coverage under the Ohio EPA General NPDES Permit for Storm Water Discharges Associated with Construction Activity for project locations that disturb one or more acres. Any minor editing to finalize the Storm Water Pollution Prevention Plans (SWP3) will also be included as part of this contract. Cost for these items, including the NOI fees and any other permit fees, are the contractor’s responsibility to pay. See Section 3.0 of the attached Supplemental Conditions Environmental for specific requirements.
4.7 The contractor is required to develop an environmental work plan applicable to their work activities. This work plan should be very simple and focused. It must identify points of contact and identify who is responsible for environmental compliance for the project. The plan must include the CJAG emergency notification and spill response form. It must identify where contractor spill kits are located. It must identify fuel locations and contractor emergency response procedures. It must identify how storm water will be managed, how spoil piles will be managed, vegetation removal, types of waste and their management, recycling of materials, concrete outwash, hazardous materials on site and their management, and any other applicable environmental issues. The intent of the plan is to identify issues and determine how they will be managed before work starts. See Section 2 of the Supplemental Conditions Environmental.
4.8 The awarded contractor must attend a Pre-Construction Meeting (PRECON) with the CJAG personnel to discuss access procedures, intended schedule, and other issues to ensure successful completion of the work.
4.9 Contractor will provide the OHARNG with one construction schedule to cover all work under the contract. The schedule will be kept current and updated with any changes.
4.10 If any portion of fence will need to be removed, disposal and/or recycling of the removed parts of fencing must be performed according to Environmental Procedures, Section 4.
4.11 Any and all vegetation clearing including mowing, trimming, and tree removal must be done between 1 October and 31 March, unless otherwise authorized by the CJAG Environmental Office. Culvert replacements must comply with USACE Nationwide Permit #3. Downstream flow must be maintained at all times. Hardwood material four inches and greater in diameter will be cut into eight-foot lengths and neatly stacked in an accessible area near the work location and approved by the OHARNG. All other plant material will be removed from site and processed for recycling if possible or otherwise properly disposed.
4.12 Excess soil may be kept on site for later use or future phases of the project. In order to remain, the soil must be approved via submittal to the CJAG Environmental Office. Soil that is determined to be unacceptable must be removed at the expense of the contractor. If it is determined that any soil will be kept the storage location will be determined by CJAG Environmental. Any damage done to the paved roads or debris left behind will be the responsibility of the Contractor to repair/clean up. Silt fence will be placed around the stockpiled soil, and it must be stabilized with vegetation to protect the surrounding area from sediment runoff.
5.0 Deliverables:
5.1 All deliverables must be in English. All measurements must be in Standard English units (inches, feet, yards, acres, etc.).
5.2 All electronic data deliverables must be submitted in accordance with the guidelines outlined in the attached memorandum, OHARNG Specifications for Facility Management Electronic Data Deliverables (Attachment 3).
5.3 Hard and digital copies of the SWP3 and all completed SWP3 forms, inspection reports, and corrective action reports will be submitted to CJAG prior to receipt of final payment.
5.4 Hard and digital copies of all construction-related documents will be submitted to CJAG prior to receipt of final payment.
5.5 The contractor will submit one (1) full sized hard copy, one (1) 11” X 17” copy and a sharable digital copy of as-built drawings to CJAG prior to final payment
5.6 All surveying, mapping, photographs, plans, drawings, reports and other data gathered or developed while performing this SOW will be submitted to the OHARNG in an appropriate digital and hard copy format.
5.7 The contractor will submit tags from grass seed mixes used on the project. See Section 4.5 of Supplemental Conditions Environmental for approved grass seed mixes on CJAG.
5.8 The contractor will submit completed OHARNG Construction/Demolition Diversion and Waste Disposal Form(s) and will provide supporting documentation (weight tickets, manifests, etc.).
6.0 List of Attachments
6.1 Attachment 1 – Construction Drawings
6.2 Attachment 2 – Environmental Procedures
6.3 Attachment 3 - OHARNG Specifications for Facility Management Electronic Data Deliverables
7.0 Applicable Publications: Publications applicable to this PWS are listed below:
Publication (Chapter/Page)
| Date of Publication |
| Mandatory or Advisory |
| Website |
Federal Acquisition Regulation https://www.acquisition.gov/?q=browsefar
Defense Federal Acquisition Regulation Supplement http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html or https://www.acquisition.gov/dfars
Joint Travel Regulation (JTR) https://www.defensetravel.dod.mil/site/travelreg.cfm
DoDM 1000.13-M-V1 DoD Identification (ID) Cards (Enclosure 2, paragraph 3.b) 01/23/2014 (Change 1: 07/28/2020) http://www.esd.whs.mil/Directives/issuances/dodm
Federal Information Processing Standards (FIPS) Publication 201-2 Personal Identity Verification (PIV) of Federal Employees and Contractors (paragraph 9) August 2013 http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.201-2.pdf
| DoDM 5200.2 Procedures for the DoD Personnel Security Program (PSP) |
| 04/03/2017 |
https://www.esd.whs.mil/Directives/issuances/dodm/
DoDI 5200.46 DoD Investigative and Adjudicative Guidance for Issuing the Common Access Card (CAC) 09/09/14 (Change 1: 05/04/2018) https://www.esd.whs.mil/Directives/issuances/dodi/
Homeland Security Presidential Directive (HSPD)-12 Policy for a Common Identification Standard for Federal Employees and Contractors 08/27/2004 https://www.dhs.gov/homeland-security-presidential-directive-12
DoDI 5400.11 Department of Defense Privacy and Civil Liberties Programs 01/29/2019 https://www.esd.whs.mil/Directives/issuances/dodi/
DoD 5400.11-R Department of Defense Privacy Program 05/14/2007 https://www.esd.whs.mil/Directives/issuances/dodm/
DoDD 8140.01 Cyberspace Workforce Management
10/05/2020 https://www.esd.whs.mil/Directives/issuances/dodd/
DoD 8570.01-M Information Assurance Workforce Improvement Program 12/19/2005 (Change 4: 11/10/2015) https://www.esd.whs.mil/Directives/issuances/dodm/
DoD 5220.22-M National Industrial Security Program Operating Manual (NISPOM) 02/28/2006 (Change 2: 05/18/2016) https://www.esd.whs.mil/Directives/issuances/dodm/
Army Directive 2014-05 Policy and Implementation Procedures for Common Access Card Credentialing and Installation Access for Uncleared Contractors 03/07/2014 https://armypubs.army.mil/ProductMaps/PubForm/ArmyDir.aspx
AR 25-2
Information Assurance 04/04/2019 http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx
AR 530-1
Operations Security 09/26/2014 http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx
AR 525-13
Antiterrorism 12/09/2019 http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx
AR 381-12
Threat Awareness and Reporting Program (TARP) (Section II, ¶ 2-4.b) 06/01/2016 http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx
5.1 Applicable Forms: Forms applicable to the PWS are listed below:
| Form |
| Date |
| Website |
DD 1172-2
Application for Identification Card/DEERS Enrollment
| Mar 2017 |
| http://www.dtic.mil/whs/directives/forms/index.htm |
I-9 Employment Eligibility Verification 10/21/2019 https://www.uscis.gov/sites/default/files/files/form/i-9.pdf
DD 441
Department of Defense Security Agreement Feb 2020 http://www.dtic.mil/whs/directives/forms/dd/ddforms0001-0499.htm
DD 250
Material Inspection and Receiving Report
| Aug 2000 |
| https://www.esd.whs.mil/Directives/forms/dd0001_0499/ |
Ver. October 2022