This pre-solicitation notice seeks initial outfitting, transition, and activation services for a new Lakeland Community Based Outpatient Clinic located in Tampa, Florida. The Department of Veterans Affairs intends to solicit quotes for non-personal services to help bring the new Lakeland CBOC into full planned operations by January 30, 2024 to provide healthcare services to Veterans. Required services include comprehensive project management, furniture/equipment planning support, acquisition, transition planning, warehousing, activation, acquisition package development, and post-occupancy training. The firm-fixed-price contract is estimated at 27 months. The solicitation targeted for April 16, 2021 posting will be 100% set aside for verified Service-Disabled Veteran-Owned Small Businesses. Questions are due by email by May 7, 2021 anticipated closing date.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Duration Start Finish
VA Outpatient Clinic - Lakeland FLVA Outpatient Clinic - Lakeland FL 814 28-Jan-21 21-Apr-23
PROPOSAL & AWARDPROPOSAL & AWARD 0 28-Jan-21 28-Jan-21
A1020 No ce to Proceed 0 28-Jan-21 DESIGNDESIGN 132 11-Feb-21 18-Aug-21
LEVEL 1 DIDLEVEL 1 DID 38 11-Feb-21 06-Apr-21 D1000 Design Intent Drawing Workshop 2 11-Feb-21 12-Feb-21 D1020 Design Intent Drawings 21 16-Feb-21 16-Mar-21 D1010 DID Approval 15 17-Mar-21 06-Apr-21
SITE INVESTIGATIONSITE INVESTIGATION 25 16-Feb-21 22-Mar-21 D1011 Preliminary Geotechnical 10 16-Feb-21 01-Mar-21 D1021 Site Survey 20 16-Feb-21 15-Mar-21 D1001 Prepare/Issue Final Geotechnical 15 02-Mar-21 22-Mar-21
LEVEL 2 DIDLEVEL 2 DID 42 07-Apr-21 04-Jun-21 A6100 DID2 Plumbing 25 07-Apr-21 11-May-21 A6090 DID2 Fire Protec on 25 07-Apr-21 11-May-21 A6080 DID2 Electrical/Fire Alarm/Low Voltage 25 07-Apr-21 11-May-21 A6070 DID2 Mechanical 25 07-Apr-21 11-May-21 A6060 DID2 Architecture 25 07-Apr-21 11-May-21 A6110 VA Review of DID2 15 12-May-21 02-Jun-21 A6120 DID2 Package Review Mee ng 2 03-Jun-21 04-Jun-21
90% TI90% TI 30 07-Jun-21 19-Jul-21 A6220 100% Site 16 07-Jun-21 28-Jun-21 A6200 90% Interior Design 16 07-Jun-21 28-Jun-21 A6180 90% Plumbing 16 07-Jun-21 28-Jun-21 A6170 90% Fire Protec on 16 07-Jun-21 28-Jun-21 A6160 90% Electrical/Fire Alarm/Low Voltage 16 07-Jun-21 28-Jun-21 A6150 90% Mechanical 16 07-Jun-21 28-Jun-21 A6140 90% Architecture 16 07-Jun-21 28-Jun-21 A6210 90% Package Internal Technical Review 2 29-Jun-21 30-Jun-21 A6190 VA Review of 90% 10 01-Jul-21 15-Jul-21 A6130 90% Package Review Mee ng 2 16-Jul-21 19-Jul-21 A5390 NTP Site / Civil Package 0 19-Jul-21
100% TI100% TI 22 20-Jul-21 18-Aug-21 D4050 100% Interior Design 6 20-Jul-21 27-Jul-21 D4040 100% Plumbing 6 20-Jul-21 27-Jul-21 D4030 100% Fire Protec on 6 20-Jul-21 27-Jul-21 D4020 100% Electrical/Fire Alarm/Low Voltage 6 20-Jul-21 27-Jul-21 D4010 100% Mechanical 6 20-Jul-21 27-Jul-21 D4000 100% Architectural 6 20-Jul-21 27-Jul-21
Jan F M Apr M J Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F Mar A M Jun Jul A S Oct N D
2021 2022 2023
21-Apr-23, VA Outpa ent Clinic - Lakeland FL
28-Jan-21, PROPOSAL & AWARD
No ce to Proceed 18-Aug-21, DESIGN
06-Apr-21, LEVEL 1 DID Design Intent Drawing Workshop
Design Intent Drawings DID Approval
22-Mar-21, SITE INVESTIGATION Preliminary Geotechnical
Site Survey Prepare/Issue Final Geotechnical
04-Jun-21, LEVEL 2 DID DID2 Plumbing DID2 Fire Protec on DID2 Electrical/Fire Alarm/Low Voltage DID2 Mechanical DID2 Architecture
VA Review of DID2 DID2 Package Review Mee ng
19-Jul-21, 90% TI 100% Site 90% Interior Design 90% Plumbing 90% Fire Protec on 90% Electrical/Fire Alarm/Low Voltage 90% Mechanical 90% Architecture 90% Package Internal Technical Review
VA Review of 90% 90% Package Review Mee ng NTP Site / Civil Package
18-Aug-21, 100% TI 100% Interior Design 100% Plumbing 100% Fire Protec on 100% Electrical/Fire Alarm/Low Voltage 100% Mechanical 100% Architectural
VA Outpatient Clinic - Lakeland FL 20-Jan-21
Remaining Level of Effort
Remaining Work
Critical Remaining Work
Milestone
Summary
Page: 1 of 6
D4060 100% Package Internal Technical Review 2 28-Jul-21 29-Jul-21 D4070 VA Review 100% Package 10 30-Jul-21 12-Aug-21 D4080 100% Package Review Mee ng 2 13-Aug-21 16-Aug-21 D5120 Gov. Issues NTP on 100% Construc on Documents 0 16-Aug-21 D5130 100% Package Print and Ship 2 17-Aug-21 18-Aug-21
PERMITTINGPERMITTING 54 20-Jul-21 11-Sep-21
A1210 Early Grading Permit 30 20-Jul-21 18-Aug-21 A1200 Building Permit 30 13-Aug-21 11-Sep-21
PROCUREMENTPROCUREMENT 188 28-Jan-21 25-Oct-21
SUBCONTRACT AWARDSUBCONTRACT AWARD 153 28-Jan-21 02-Sep-21 SA1060 Award Fire Protec on 15 28-Jan-21 18-Feb-21 SA1050 Award Plumbing 15 28-Jan-21 18-Feb-21 SA1040 Award Electrical 15 28-Jan-21 18-Feb-21 SA1030 Award Mechanical 15 28-Jan-21 18-Feb-21 SA1070 Award Concrete / Rebar 10 20-Jul-21 02-Aug-21 SA1020 Award Earthwork 10 20-Jul-21 02-Aug-21 SA1200 Award U li es 10 13-Aug-21 26-Aug-21 SA1190 Award Elevator 10 13-Aug-21 26-Aug-21 SA1170 Award Flooring 10 13-Aug-21 26-Aug-21 SA1120 Award Metal Studs and Drywall 10 13-Aug-21 26-Aug-21 SA1160 Award Casework 10 13-Aug-21 26-Aug-21 SA1180 Award Special es 10 13-Aug-21 26-Aug-21 SA1150 Award Doors, Frames and Hardware 10 13-Aug-21 26-Aug-21 SA1140 Award Paint 10 13-Aug-21 26-Aug-21 SA1090 Award Windows / Storefronts 10 13-Aug-21 26-Aug-21 SA1000 Award Metal Panels 10 13-Aug-21 26-Aug-21 SA1110 Award Roofing 10 13-Aug-21 26-Aug-21 SA1080 Award Tilt Up Concrete 15 13-Aug-21 02-Sep-21 SA1010 Award Structural Steel 15 13-Aug-21 02-Sep-21
PREPARE SUBMITTALSPREPARE SUBMITTALS 163 19-Feb-21 08-Oct-21 PS1060 Submit Fire Protec on 25 19-Feb-21 25-Mar-21 PS1050 Submit Plumbing 25 19-Feb-21 25-Mar-21 PS1040 Submit Electrical 25 19-Feb-21 25-Mar-21 PS1030 Submit Mechanical 25 19-Feb-21 25-Mar-21 PS1070 Submit Concrete / Rebar 5 03-Aug-21 09-Aug-21 PS1020 Submit Earthwork 15 20-Jul-21 09-Aug-21 PS1200 Submit U li es 15 13-Aug-21 02-Sep-21 PS1190 Submit Elevator 15 27-Aug-21 17-Sep-21 PS1170 Submit Flooring 15 27-Aug-21 17-Sep-21
Jan F M Apr M J Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F Mar A M Jun Jul A S Oct N D
2021 2022 2023
100% Package Internal Technical Review VA Review 100% Package 100% Package Review Mee ng Gov. Issues NTP on 100% Construc on Documents 100% Package Print and Ship
11-Sep-21, PERMITTING
Early Grading Permit Building Permit
25-Oct-21, PROCUREMENT
02-Sep-21, SUBCONTRACT AWARD Award Fire Protec on Award Plumbing Award Electrical Award Mechanical
Award Concrete / Rebar Award Earthwork
Award U li es Award Elevator Award Flooring Award Metal Studs and Drywall Award Casework Award Special es Award Doors, Frames and Hardware Award Paint Award Windows / Storefronts Award Metal Panels Award Roofing Award Tilt Up Concrete Award Structural Steel
08-Oct-21, PREPARE SUBMITTALS Submit Fire Protec on Submit Plumbing Submit Electrical Submit Mechanical
Submit Concrete / Rebar Submit Earthwork
Submit U li es Submit Elevator Submit Flooring
VA Outpatient Clinic - Lakeland FL 20-Jan-21
Remaining Level of Effort
Remaining Work
Critical Remaining Work
Milestone
Page: 2 of 6
PS1120 Submit Metal Studs and Drywall 15 27-Aug-21 17-Sep-21 PS1160 Submit Casework 15 27-Aug-21 17-Sep-21 PS1180 Submit Special es 15 27-Aug-21 17-Sep-21 PS1150 Submit Doors, Frames and Hardware 15 27-Aug-21 17-Sep-21 PS1140 Submit Paint 15 27-Aug-21 17-Sep-21 PS1090 Submit Windows / Storefronts 15 27-Aug-21 17-Sep-21 PS1080 Submit Metal Panels 15 27-Aug-21 17-Sep-21 PS1110 Submit Roofing 15 27-Aug-21 17-Sep-21 PS1010 Submit Structural Steel 25 03-Sep-21 08-Oct-21
REVIEW SUBMITTALSREVIEW SUBMITTALS 143 26-Mar-21 18-Oct-21 CRS1150 Review Fire Protec on 10 26-Mar-21 08-Apr-21 CRS1050 Review Plumbing 10 26-Mar-21 08-Apr-21 CRS1040 Review Electrical 10 26-Mar-21 08-Apr-21 CRS1030 Review Mechanical 10 26-Mar-21 08-Apr-21 CRS1020 Review Concrete / Rebar 5 10-Aug-21 16-Aug-21 CRS1010 Review Earthwork 5 10-Aug-21 16-Aug-21 CRS1180 Review U li es 5 03-Sep-21 10-Sep-21 CRS1140 Review Elevator 5 20-Sep-21 24-Sep-21 CRS1130 Review Flooring 5 20-Sep-21 24-Sep-21 CRS1120 Review Metal Studs and Drywall 5 20-Sep-21 24-Sep-21 CRS1110 Review Casework 5 20-Sep-21 24-Sep-21 CRS1100 Review Special es 5 20-Sep-21 24-Sep-21 CRS1090 Review Doors, Frames and Hardware 5 20-Sep-21 24-Sep-21 CRS1080 Review Paint 5 20-Sep-21 24-Sep-21 CRS1160 Review Windows / Storefronts 5 20-Sep-21 24-Sep-21 CRS1070 Review Metal Panels 5 20-Sep-21 24-Sep-21 CRS1060 Review Roofing 5 20-Sep-21 24-Sep-21 CRS1170 Review Structural Steel 5 12-Oct-21 18-Oct-21
FABRICATION & DELIVERFABRICATION & DELIVER 138 09-Apr-21 25-Oct-21 FD1150 F&D Fire Protec on 20 09-Apr-21 06-May-21 FD1140 F&D Plumbing 20 09-Apr-21 06-May-21 FD1130 F&D Electrical 20 09-Apr-21 06-May-21 FD1120 F&D Mechanical 20 09-Apr-21 06-May-21 FD1010 F&D Concrete / Rebar 10 17-Aug-21 30-Aug-21 FD1000 F&D U li es 20 13-Sep-21 08-Oct-21 FD1110 F&D Elevator 20 27-Sep-21 25-Oct-21 FD1100 F&D Flooring 20 27-Sep-21 25-Oct-21 FD1090 F&D Metal Studs and Drywall 20 27-Sep-21 25-Oct-21 FD1080 F&D Casework 20 27-Sep-21 25-Oct-21
Jan F M Apr M J Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F Mar A M Jun Jul A S Oct N D
2021 2022 2023
Submit Metal Studs and Drywall Submit Casework Submit Special es Submit Doors, Frames and Hardware Submit Paint Submit Windows / Storefronts Submit Metal Panels Submit Roofing
Submit Structural Steel 18-Oct-21, REVIEW SUBMITTALS
Review Fire Protec on Review Plumbing Review Electrical Review Mechanical
Review Concrete / Rebar Review Earthwork
Review U li es Review Elevator Review Flooring Review Metal Studs and Drywall Review Casework Review Special es Review Doors, Frames and Hardware Review Paint Review Windows / Storefronts Review Metal Panels Review Roofing
Review Structural Steel 25-Oct-21, FABRICATION & DELIVER
F&D Fire Protec on F&D Plumbing F&D Electrical F&D Mechanical
F&D Concrete / Rebar F&D U li es
F&D Elevator F&D Flooring F&D Metal Studs and Drywall F&D Casework
VA Outpatient Clinic - Lakeland FL 20-Jan-21
Remaining Level of Effort
Remaining Work
Critical Remaining Work
Milestone
Page: 3 of 6
FD1070 F&D Special es 20 27-Sep-21 25-Oct-21 FD1060 F&D Doors Frames and Hardware 20 27-Sep-21 25-Oct-21 FD1050 F&D Paint 20 27-Sep-21 25-Oct-21 FD1040 F&D Windows / Storefronts 20 27-Sep-21 25-Oct-21 FD1030 F&D Metal Panels 20 27-Sep-21 25-Oct-21 FD1020 F&D Roofing 20 27-Sep-21 25-Oct-21
CONSTRUCTIONCONSTRUCTION 523 23-Sep-21 27-Feb-23
MOBILIZATIONMOBILIZATION 12 23-Sep-21 04-Oct-21 A5970 Mobilize to Project Site 2 23-Sep-21 24-Sep-21 A1170 Conduct Pre-Construc on Conference 1 27-Sep-21 27-Sep-21 A1190 Setup Site Trailers 2 27-Sep-21 28-Sep-21 A1270 Install Erosion Control Measures 2 28-Sep-21 30-Sep-21 A1160 Locate Exis ng U li es 2 28-Sep-21 30-Sep-21 A1180 Install Temporary Construc on Fence & Barriers 2 01-Oct-21 04-Oct-21
SITEWORKSITEWORK 215 27-Sep-21 23-Sep-22 A3300 Site Layout 2 27-Sep-21 28-Sep-21 A3690 Clearing & Grubbing 2 05-Oct-21 06-Oct-21 A3700 Cut / Fill 10 01-Oct-21 15-Oct-21 A3780 Test Piling 3 18-Oct-21 20-Oct-21 A3310 Earthwork / Grading 10 07-Oct-21 22-Oct-21 A3790 Fabricate Piling 7 22-Oct-21 02-Nov-21 A3800 Install Piling 20 03-Nov-21 06-Dec-21 A3340 Site Water Lines 5 06-Jan-22 13-Jan-22 A3320 Site Storm Sewer 5 06-Jan-22 13-Jan-22 A2360 Site Natural Gas Line 5 14-Jan-22 21-Jan-22 A3330 Site Sanitary Sewer 10 06-Jan-22 21-Jan-22 A3600 UG Electric Service 5 24-Jan-22 28-Jan-22 A3610 UG Communica on Lines 5 31-Jan-22 04-Feb-22 A2270 Mechanical Equipment Housekeeping Pads 2 21-Jul-22 22-Jul-22 A2130 Pipe Bollards 2 21-Jul-22 22-Jul-22 A3590 Sidewalks & Curbs 8 21-Jul-22 02-Aug-22 A3560 Site Fencing & Gates 5 04-Aug-22 11-Aug-22 A2420 Parking Lot Pavement 8 04-Aug-22 16-Aug-22 A3570 Site Seeding 10 18-Aug-22 06-Sep-22 A3580 Landscaping 20 18-Aug-22 23-Sep-22
STRUCTURESTRUCTURE 100 30-Nov-21 22-Apr-22 A3720 Underslab U lity Rough In 15 01-Dec-21 21-Dec-21 A3710 Pile Caps & Founda ons 25 30-Nov-21 05-Jan-22 A3730 Form & Place Slab on Grade 10 29-Dec-21 12-Jan-22
Jan F M Apr M J Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F Mar A M Jun Jul A S Oct N D
2021 2022 2023
F&D Special es F&D Doors Frames and Hardware F&D Paint F&D Windows / Storefronts F&D Metal Panels F&D Roofing
27-Feb-23, CONSTRUCTION
04-Oct-21, MOBILIZATION Mobilize to Project Site Conduct Pre-Construc on Conference Setup Site Trailers Install Erosion Control Measures Locate Exis ng U li es Install Temporary Construc on Fence & Barriers
23-Sep-22, SITEWORK Site Layout Clearing & Grubbing
Cut / Fill Test Piling Earthwork / Grading
Fabricate Piling Install Piling
Site Water Lines Site Storm Sewer Site Natural Gas Line Site Sanitary Sewer UG Electric Service UG Communica on Lines
Mechanical Equipment Housekeeping Pads Pipe Bollards
Sidewalks & Curbs Site Fencing & Gates Parking Lot Pavement
Site Seeding Landscaping
22-Apr-22, STRUCTURE Underslab U lity Rough In
Pile Caps & Founda ons Form & Place Slab on Grade
VA Outpatient Clinic - Lakeland FL 20-Jan-21
Remaining Level of Effort
Remaining Work
Critical Remaining Work
Milestone
Page: 4 of 6
A3740 Form & Place Tilt Up Panels 20 13-Jan-22 10-Feb-22 A3750 Erect Tilt Up Panels 4 14-Feb-22 17-Feb-22 A3760 Erect Steel 25 18-Feb-22 25-Mar-22 A6040 Erect 2nd Floor & Roof Deck 20 07-Mar-22 01-Apr-22 A3830 Place 2nd Floor Raised Slab 15 04-Apr-22 22-Apr-22
EXTERIOREXTERIOR 75 04-Apr-22 19-Jul-22 A3910 Steel Canopy & Roof 15 04-Apr-22 22-Apr-22 A3900 Caulk Panels 5 25-Apr-22 29-Apr-22 A3820 Roof Insula on & Membrane Roof 30 04-Apr-22 13-May-22 A3850 Exterior Curtain Wall 30 25-Apr-22 06-Jun-22 A3860 Metal Panels 20 16-May-22 13-Jun-22 A3870 Flashing & Sheetmetal 15 14-Jun-22 05-Jul-22 A6050 Exterior Glass 25 07-Jun-22 12-Jul-22 A3890 Paint Exterior 5 13-Jul-22 19-Jul-22
BUILDING INTERIORBUILDING INTERIOR 210 25-Apr-22 27-Feb-23 1st FLOOR1st FLOOR 180 25-Apr-22 12-Jan-23 1B2000 1st Flr Overhead MEPFp Rough-In 50 25-Apr-22 05-Jul-22 1B2030 1st Flr Plumbing Rough In 40 11-May-22 07-Jul-22 1B2020 1st Flr Interior Metal Stud Wall Framing 50 09-May-22 19-Jul-22 1B2050 1st Flr Mechanical Rough In 50 11-May-22 21-Jul-22 1B2040 1st Flr Electrical Rough In 50 11-May-22 21-Jul-22 1B2060 1st Flr Drywall & Taping 60 16-May-22 09-Aug-22 1B2210 1st Floor Elevator Equipment 20 20-Jul-22 16-Aug-22 1B2090 1st Flr Pain ng and Wall Finish 30 20-Jul-22 30-Aug-22 1B2070 1st Flr Electrical Switchgear 15 10-Aug-22 30-Aug-22 1B2120 1st Flr Mechanical Trim Out 30 27-Jul-22 07-Sep-22 1B2100 1st Flr Acous cal Ceiling Grid 25 03-Aug-22 07-Sep-22 1B2160 1st Flr Acous cal Ceiling Pads 20 08-Sep-22 05-Oct-22 1B2220 1st Floor Elevator Cabs 40 17-Aug-22 13-Oct-22 1B2080 1st Flr Plumbing Fixtures & Trim Out 30 31-Aug-22 13-Oct-22 1B2110 1st Flr Electric Trim Out 30 31-Aug-22 13-Oct-22 1B2140 1st Flr Flooring 30 31-Aug-22 13-Oct-22 1B2170 1st Flr Fire Protec on System Trim Out 25 09-Sep-22 14-Oct-22 1B2130 1st Flr Install Interior Doors & Door Hardware 40 15-Sep-22 10-Nov-22 1B2180 1st Flr Install Cabinets & Counters 30 14-Oct-22 29-Nov-22 1B2200 1st Flr Install Special es 30 14-Nov-22 28-Dec-22 1B1210 1st Flr Final Clean-up 10 29-Dec-22 12-Jan-23
2nd FLOOR2nd FLOOR 200 09-May-22 27-Feb-23 2B1000 2nd Flr Overhead MEPFp Rough-In 50 09-May-22 19-Jul-22
Jan F M Apr M J Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F Mar A M Jun Jul A S Oct N D
2021 2022 2023
Form & Place Tilt Up Panels Erect Tilt Up Panels
Erect Steel Erect 2nd Floor & Roof Deck
Place 2nd Floor Raised Slab 19-Jul-22, EXTERIOR
Steel Canopy & Roof Caulk Panels
Roof Insula on & Membrane Roof Exterior Curtain Wall Metal Panels
Flashing & Sheetmetal Exterior Glass Paint Exterior
27-Feb-23, BUILDING INTERIOR 12-Jan-23, 1st FLOOR
1st Flr Overhead MEPFp Rough-In 1st Flr Plumbing Rough In
1st Flr Interior Metal Stud Wall Framing 1st Flr Mechanical Rough In 1st Flr Electrical Rough In
1st Flr Drywall & Taping 1st Floor Elevator Equipment
1st Flr Pain ng and Wall Finish 1st Flr Electrical Switchgear 1st Flr Mechanical Trim Out 1st Flr Acous cal Ceiling Grid
1st Flr Acous cal Ceiling Pads 1st Floor Elevator Cabs 1st Flr Plumbing Fixtures & Trim Out 1st Flr Electric Trim Out 1st Flr Flooring 1st Flr Fire Protec on System Trim Out
1st Flr Install Interior Doors & Door Hardware 1st Flr Install Cabinets & Counters
1st Flr Install Special es 1st Flr Final Clean-up
27-Feb-23, 2nd FLOOR 2nd Flr Overhead MEPFp Rough-In
VA Outpatient Clinic - Lakeland FL 20-Jan-21
Remaining Level of Effort
Remaining Work
Critical Remaining Work
Milestone
Page: 5 of 6
2B1030 2nd Flr Plumbing Rough In 40 02-Jun-22 28-Jul-22 2B1020 2nd Flr Interior Metal Stud Wall Framing 50 31-May-22 09-Aug-22 2B1050 2nd Flr Mechanical Rough In 50 09-Jun-22 18-Aug-22 2B1040 2nd Flr Electrical Rough In 50 09-Jun-22 18-Aug-22 2B1060 2nd Flr Drywall & Taping 60 14-Jun-22 07-Sep-22 2B1090 2nd Flr Pain ng and Wall Finish 30 17-Aug-22 28-Sep-22 2B1100 2nd Flr Acous cal Ceiling Grid 25 08-Sep-22 13-Oct-22 2B1120 2nd Flr Mechanical Trim Out 30 08-Sep-22 20-Oct-22 2B1110 2nd Flr Electric Trim Out 30 08-Sep-22 20-Oct-22 2B1160 2nd Flr Acous cal Ceiling Pads 20 14-Oct-22 10-Nov-22 2B1170 2nd Flr Fire Protec on System Trim Out 25 17-Oct-22 21-Nov-22 2B1080 2nd Flr Plumbing Fixtures & Trim Out 30 14-Oct-22 29-Nov-22 2B1140 2nd Flr Flooring 30 14-Oct-22 29-Nov-22 2B1130 2nd Flr Install Interior Doors & Door Hardware 40 28-Oct-22 28-Dec-22 2B1180 2nd Flr Install Cabinets & Counters 30 30-Nov-22 12-Jan-23 2B1200 2nd Flr Install Special es 30 29-Dec-22 10-Feb-23 2B1190 2nd Flr Final Clean-up 10 13-Feb-23 27-Feb-23
CLOSEOUTCLOSEOUT 99 30-Nov-22 21-Apr-23
C1000 Red Zone Mee ng 0 30-Nov-22 C1020 Commissioning 15 29-Dec-22 20-Jan-23 C1010 Tes ng & Balancing 15 29-Dec-22 20-Jan-23 C1040 Owner Training 5 23-Jan-23 27-Jan-23 C1120 Review & Approve Comm Reports 15 23-Jan-23 10-Feb-23 C1090 Prepare & Submit As-Builts 60 30-Nov-22 27-Feb-23 C1080 Prepare & Submit O&Ms 60 30-Nov-22 27-Feb-23 C1110 Contractor Pre-Final Punchlist 2 28-Feb-23 01-Mar-23 C1140 Contractor Complete Pre-Final Punchlist 15 02-Mar-23 22-Mar-23 C1150 Contractor Final Punchlist 1 23-Mar-23 23-Mar-23 C1190 Contractor Complete Final Punchlist 15 24-Mar-23 13-Apr-23 C1200 Owner Final Punchlist 1 14-Apr-23 14-Apr-23 C1030 Substan al Comple on/BOD 0 14-Apr-23 C1210 Complete Government Final Punchlist 5 17-Apr-23 21-Apr-23 C1220 Project Complete 0 21-Apr-23
DURATIONSDURATIONS 814 28-Jan-21 21-Apr-23
A5280 Contract Award to Design Comp. 201 28-Jan-21 16-Aug-21 A6230 Ftg Start to Int Finishes Comp 455 30-Nov-21 27-Feb-23 A5250 Construc on Dura on 576 23-Sep-21 21-Apr-23 A5240 Contract Award to Final Comp. 814 28-Jan-21 21-Apr-23
Jan F M Apr M J Jul A S Oct N D Jan F M Apr M Jun Jul A S Oct N D Jan F Mar A M Jun Jul A S Oct N D
2021 2022 2023
2nd Flr Plumbing Rough In 2nd Flr Interior Metal Stud Wall Framing
2nd Flr Mechanical Rough In 2nd Flr Electrical Rough In
2nd Flr Drywall & Taping 2nd Flr Pain ng and Wall Finish
2nd Flr Acous cal Ceiling Grid 2nd Flr Mechanical Trim Out 2nd Flr Electric Trim Out
2nd Flr Acous cal Ceiling Pads 2nd Flr Fire Protec on System Trim Out 2nd Flr Plumbing Fixtures & Trim Out 2nd Flr Flooring
2nd Flr Install Interior Doors & Door Hardware 2nd Flr Install Cabinets & Counters
2nd Flr Install Special es 2nd Flr Final Clean-up
21-Apr-23, CLOSEOUT
Red Zone Mee ng Commissioning Tes ng & Balancing Owner Training
Review & Approve Comm Reports Prepare & Submit As-Builts Prepare & Submit O&Ms Contractor Pre-Final Punchlist
Contractor Complete Pre-Final Punchlist Contractor Final Punchlist
Contractor Complete Final Punchlist Owner Final Punchlist Substan al Comple on/BOD Complete Government Final Punchlist Project Complete 21-Apr-23, DURATIONS
Contract Award to Design Comp.
Ftg Start to Int Finishes Comp
Construc on Dura on Contract Award to Final Comp.
VA Outpatient Clinic - Lakeland FL 20-Jan-21
Remaining Level of Effort
Remaining Work
Critical Remaining Work
Milestone
Page: 6 of 6