About this file

This document contains a Contractor Work Breakdown Structure (CWBS) and CWBS dictionary for the GeoXO Flight Project Lightning Mapper (LMX). The CWBS establishes a product-oriented framework for reporting program cost, schedule, and technical performance. It provides a logical subdivision of all project work to be completed, including the element title and number for each subdivision. The CWBS dictionary briefly describes the work content of each element and relevant efforts such as design, development, and manufacturing. The structure includes five levels with Level 1 defining the total contract effort and Level 2 defining major contract activities such as engineering, flight models, special tasks, and mission operations. Level 3 further subdivides work content and Level 4 is defined by the Contractor.

The related federal contract opportunity is a final RFP for the Geostationary Extended Observations (GeoXO) Lightning Mapper (LMX) Instrument Implementation from the National Aeronautics and Space Administration Goddard Space Center. The solicitation number and opportunity type are provided.

View the file

Other files for this federal contract opportunity

Other files attached to Final RFP Geostationary Extended Observations (GeoXO) Lightning Mapper (LMX) Instrument Implementation, newest first.
File Type Posted
FRFP Q_A.pdf PDF
Enclosure B LMX FRFP PPQ1.pdf PDF
Attachment F CDRL 418 XO LMXCDRL 0068 Version 1.00.pdf PDF
Attachment S CONOPS 410 XO CONOPS 0004 V1.00.pdf PDF
Attachment Q GRDDP 418 XO RPT 0039 Version 1.00.pdf PDF
Attachment G EU PU EDU Risk Mitigation Efforts1.pdf PDF
Attachment H Financial Mgmt Reporting 1.pdf PDF
LMX FRFP Cover Letter 1.pdf PDF
Enclosure C LMX PEP1.pdf PDF
Attachment E IMAR 418 XO IMAR 0026 Version 2.20.pdf PDF
Attachment U FPGA 418 XO RPT 0045 Version 1.00.pdf PDF
Attachment D LMXUIID 418 XO LMXUIID 0067 Version 1 40.pdf PDF
Attachment I - OCI Plan DRD1.pdf PDF
Attachment W OCI Plan 1.pdf PDF
80GSFC23R0013 LMX FRFP Cost Exhibits R1-7C.pdf PDF
Enclosure B LMX FRFP PPQ1.pdf PDF
LMX FRFP 80GSFC23R0013.pdf PDF
Attachment C GIRD 418 XO GIRD 0041 Version 2.3.pdf PDF
Attachment A SOW 418 XO LMXSOW 0116 Version 1.00.pdf PDF
Attachment T DEIA Plan DRD1.pdf PDF
Enclosure A ITSMP Template 1.pdf PDF
LMX SF33.pdf PDF
Attachment R RPT 418 XO RPT 0042 Version 1.20.pdf PDF
Attachment B LMXPORD 418 XOLMXPORD 0120 Version 1.0.pdf PDF
Attachment X DEIA Plan 1.pdf PDF
Attachment V Requirements Statements List1.0.pdf PDF
Attachment M IT Security ADL1.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Heather Matthews Digitally signed by Heather Matthews Date: 2023.03.16 12:54:26 -04'00'

Candace Carlisle Digitally signed by Candace Carlisle Date: 2023.03.16 13:53:54 -04'00'

Geostationary eXtended Observations (GeoXO) Flight Project Lightning Mapper (LMX)

Contractor Work Breakdown Structure

(CWBS)

March, 2023

Prepared by:

Heather Matthews GeoXO Flight Deputy Project Manager/Resources

Approved by:

Candace Carlisle GeoXO Flight Project Manager

Attachment O: Contractor Work Breakdown Structure (CWBS) and CWBS Dictionary

1. DESCRIPTION / PURPOSE

The CWBS establishes a product-oriented framework for reporting program cost, schedule, and technical performance and provides a basis for uniform planning, reporting status, program visibility, and assignment of responsibilities. Additionally, the CWBS provides a product-oriented logical subdivision of hardware, software, services, facilities, etc., that contribute to and/or make up the total project scope of effort and work. The CWBS dictionary provides a narrative description of the work tasks and effort to be performed in each CWBS element.

2. PREPARATION INFORMATION

Contents:

The CWBS and CWBS dictionary are two distinct project documents used for defining the approved project scope of work. The contents of each document are detailed in the following paragraphs:

CWBS – A logical, hierarchical display of the subdivision of all project work to be completed.

The CWBS shall include the approved element title and element number.

CWBS dictionary – The CWBS dictionary shall briefly describe and document the work content of every CWBS element and relevant efforts associated with each element (e.g., design, development, and manufacturing).

The CWBS levels shall be governed by the Following. The actual letter and number designations can be adapted to meet the needs of the Contractor’s systems

Level 1 - Total contract effort

Level 2 Definitions: Major contract activity as described below

A. Engineering Unit / Non-Recurring Activities – All effort to plan and manage the design of the instrument including detailed design activities, design reviews, risk reduction (engineering models, etc), software development, ground support equipment (GSE) development, verification planning, etc.

B. Flight Model (FM) -1 – All effort related to fabrication, assembly, test, launch operations and on-orbit testing of the satellite

C. FM-2

D. FM-3

E. FM-4

F. Special Tasks – all un-issued special task funds remain in this level 2 WBS G. Mission Operations - Long term mission support including any management, business management support, systems engineering etc that is not unique to a particular mission

Level 3 Definitions (Note: X denotes the Level 2 Contract Activity) – the work content as described is not necessarily all inclusive.

X.01 Program Management – Including program leadership, resource management, program planning (schedule), data management, configuration management, support for major design reviews

X.02 Systems Engineering - Including system engineering leadership, interface management (instrument, launch vehicle, ground), system specification definition and flow-down, verification planning, system level analysis and modeling

X.03 Mission Assurance - Including mission assurance leadership, quality engineering, subcontract surveillance, safety, reliability, parts and materials management

X.04 Hardware / Software – All subsystem hardware and software effort including parts and materials which should be accounted for in a separate line. Effort included in each level 2 WBS

X.05 Integration & Test - Including instrument baseline testing and environmental testing and post environment test activities including instrument packing and shipping.

X.06 GSE – design, fabrication, procurement assembly, test and maintenance of electrical, mechanical GSE and mission simulation and GSE software

X.07 Post Delivery Support (PDS) – Any support required after the Pre-Ship Review/Pre- Storage Review including satellite integration and testing and if needed storage costs or testing during storage prior to shipping to spacecraft vendor

X.08 Launch and Post Launch Testing– support for pre-launch planning, launch site support, support for mission unique or special launch services, launch-vehicle integration (spacecraft portion), and the first 6 months of post-launch testing prior to the handoff to NOAA.

X.09 Special Tasks – Actual and projected cost of special tasks issued for a specific level 2

WBS.

X.10 Long Term Support – Long term mission support including any management, business management support, systems engineering etc. that is not unique to a particular mission

Level 4 – The Contractor shall define WBS level within each level 3 and provide a brief description of the work content. For example, A.04.01 C&DH