Attachment H Financial Mgmt Reporting 1.pdf

PDF 66 KB Posted

Attached to
Final RFP Geostationary Extended Observations (GeoXO) Lightning Mapper (LMX) Instrument Implementation Federal contract opportunity
Solicitation number
80GSFC23R0013
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

This document outlines financial management reporting requirements for a federal contract. The contractor must submit monthly and quarterly cost reports using NASA Form 533, providing a summary of total contract costs by work breakdown structure level one element. The reports must include a breakdown of direct labor hours and costs by labor category for both prime and subcontractor effort. The contractor is required to provide a narrative explanation for variances exceeding 10% from the prior month's estimated to the current month's actual total direct labor hours and costs. Reports are due to the contracting officer and other addresses specified in the contract by the 10th day of each month for the prior month's activities and the 15th day prior to the start of the quarter for quarterly reporting.

View the file

Other files for this federal contract opportunity

Other files attached to Final RFP Geostationary Extended Observations (GeoXO) Lightning Mapper (LMX) Instrument Implementation, newest first.
File Type Posted
FRFP Q_A.pdf PDF
Enclosure B LMX FRFP PPQ1.pdf PDF
Attachment F CDRL 418 XO LMXCDRL 0068 Version 1.00.pdf PDF
Attachment S CONOPS 410 XO CONOPS 0004 V1.00.pdf PDF
Attachment Q GRDDP 418 XO RPT 0039 Version 1.00.pdf PDF
Attachment G EU PU EDU Risk Mitigation Efforts1.pdf PDF
80GSFC23R0013 LMX FRFP Cost Exhibits R1-7C.pdf PDF
Enclosure B LMX FRFP PPQ1.pdf PDF
LMX FRFP 80GSFC23R0013.pdf PDF
Attachment C GIRD 418 XO GIRD 0041 Version 2.3.pdf PDF
Attachment A SOW 418 XO LMXSOW 0116 Version 1.00.pdf PDF
Attachment T DEIA Plan DRD1.pdf PDF
Enclosure A ITSMP Template 1.pdf PDF
LMX FRFP Cover Letter 1.pdf PDF
Enclosure C LMX PEP1.pdf PDF
Attachment E IMAR 418 XO IMAR 0026 Version 2.20.pdf PDF
Attachment U FPGA 418 XO RPT 0045 Version 1.00.pdf PDF
Attachment D LMXUIID 418 XO LMXUIID 0067 Version 1 40.pdf PDF
Attachment I - OCI Plan DRD1.pdf PDF
Attachment W OCI Plan 1.pdf PDF
LMX SF33.pdf PDF
Attachment R RPT 418 XO RPT 0042 Version 1.20.pdf PDF
Attachment B LMXPORD 418 XOLMXPORD 0120 Version 1.0.pdf PDF
Attachment X DEIA Plan 1.pdf PDF
Attachment V Requirements Statements List1.0.pdf PDF
Attachment O LMX CWBS1.pdf PDF
Attachment M IT Security ADL1.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT H

FINANCIAL MANAGEMENT REPORTING

REQUIREMENTS

RFP 80GSFC23R0013

CONTRACT TBD

Contract TBD

Attachment H

(06/2014) 2

FINANCIAL MANAGEMENT REPORTING REQUIREMENTS

Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA

Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial

Management Reporting,” dated May 27, 2011, and additional instructions issued by the

Contracting Officer.

a. Level of Detail

The Contractor’s 533 Reports shall contain a summary of total contract costs, for Work

Breakdown Structure (WBS) Level 1element of the Statement of Work. The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in

Section d below.

b. Variance Narrative Reporting

In accordance with Section 3.6 of NPR 9501.2, the Contractor shall include a narrative explanation for variances exceeding plus or minus 10 percent (+/- 10%) between the

Total Direct Labor Hours (prime and subcontractors) and/or Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and/or Actual Total

Cost amount shown in the current month at the total contract level. (For example, the

Total Estimated Cost amount shown for June in column 8a in the May NF 533M and the

Actual June Total Cost amount shown in column 7a in the June NF 533M.)

Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the

Core baseline and/or each individual task order, and (3) specific corrective action(s) being taken or to be taken.

c. Distribution

The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533Q format within 30 working days after contract award.

After the initial report, the NF 533M reports shall be distributed not later than the tenth

(10th) working day following the close of the contractors' monthly accounting period.

The 533Q reports shall be distributed not later than the fifteenth (15th) day of the month preceding the quarter being reported. The NF 533M need not be submitted in months in which an NF 533Q is submitted.

d. Reporting Requirements

Each individual report shall, at a minimum, provide cost data by the following elements of cost categories:

(06/2014) 3

1. Prime Direct Labor Hours:

(List applicable labor categories)

Total Prime Direct Labor Hours

2. Subcontractor Direct Labor Hours:

Subcontractor A Direct Labor Hours

Subcontractor B Direct Labor Hours

Subcontractor C Direct Labor Hours

Total Subcontractors Direct Labor Hours

3. Total Prime and Subcontractors Direct Labor Hours

4. Prime Direct Labor Costs:

Total Prime Direct Labor Costs

5. Prime Overhead Expense

6. Other Direct Costs (ODCs):

a. Subcontracts (list separately, Subcontractor A, B, C, etc.)

b. Material

c. Travel

d. Other (specify)

Total ODCs

7. Subtotal (Direct Labor, Overhead & ODCs)

8. G&A Expense

9. Total Estimated Cost

(06/2014) 4

10. Provisionally Billed Award Fee

11. Award Fee Earned

12. Total Cost-Plus-Award-Fee (CPAF)