This document is a cost estimate form for a federal contract opportunity related to the design, fabrication, and installation of wayside exhibits for the Cuyahoga Valley National Park (CUVA).
The key details are:
- The federal contract opportunity is solicitation number 140P2124R0070, titled "HAFC_CUVA_Wayside Exhibit Plan, DESIGN, FAB & INST", issued by the Department of the Interior National Park Service.
- The cost estimate form provides a detailed breakdown of potential costs for project management, proposals and layouts, proofs/samples, exhibit structures, display objects, graphic panels, audio description, project closeout, shipping, and installation. Labor hours and material costs are included for each category.
- The total estimated cost is $0.00, indicating this is a template form rather than a completed cost proposal.
- The required products and services include the design, fabrication, and installation of various types of wayside exhibits and interpretive elements for the Cuyahoga Valley National Park.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Gov't Est
| CUVA - Planning/Design/Fabrication/Installation | |||
| PROJECT MANAGEMENT | $0.00 | ||
| PROPOSALS and LAYOUTS | $0.00 | ||
| PROOFS/SAMPLES/PROTOTYPE | $0.00 | ||
| EXHIBIT STRUCTURES | $0.00 | ||
| DISPLAY OBJECTS & SPECIALTY | $0.00 | ||
| GRAPHIC PANELS | $0.00 | ||
| AUDIO DESCRIPTION | $0.00 | ||
| PROJECT CLOSEOUT | $0.00 | ||
| SHIPPING | $0.00 | ||
| INSTALLATION | $0.00 | ||
| TRAVEL | $0.00 | ||
| TOTAL | $0.00 |
| PROJECT MANAGEMENT (excluding travel) | |||||
| LABOR | hours | x | rate | amount | |
| Project Manager | hours @ | $0.00 | $0.00 |
$0.00
TOTAL Project Management $0.00
| PROPOSALS and LAYOUTS | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| Miscellaneous | job | $0.00 | $0.00 |
| SUBTOTAL MATERIALS | $0.00 | |
| MARK-UP on materials | percent | $0.00 |
| TOTAL ALL MATERIALS | $0.00 | ||||
| LABOR | hours | x | rate | amount | |
| Designer | hours @ | $0.00 | $0.00 | ||
| Writer | hours @ | $0.00 | $0.00 |
TOTAL ALL LABOR $0.00
TOTAL Proposals and Layouts $0.00
| Proofs/Samples/Mock-ups/Prototypes | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| Full Size Proofs (2 per Ex: 1 for park + 1 for COR) | ea | $0.00 | $0.00 | ||
| Sample Materials | sets | $0.00 | $0.00 | ||
| SUBTOTAL MATERIALS | $0.00 | ||||
| MARK-UP on materials | percent | $0.00 |
| TOTAL ALL MATERIALS | $0.00 | ||||
| LABOR | hours | x | rate | amount | |
| Exhibit Specialist - Fabrication | hours @ | $0.00 | $0.00 |
TOTAL ALL LABOR $0.00
TOTAL Samples $0.00
| Exhibit Structures/Bases | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| Tri-Sided Kiosk | ea | $0.00 | $0.00 | ||
| 36x48 Upright In-Ground | ea | $0.00 | $0.00 | ||
| 36x48 Wall-Mounted Frame | ea | $0.00 | $0.00 | ||
| 48x24 Low-Profile In-Ground | ea | $0.00 | $0.00 | ||
| 36x24 Low-Profile In-Ground | ea | $0.00 | $0.00 | ||
| 24x24 Low-Profile In-Ground | ea | $0.00 | $0.00 | ||
| 36x48 Bulletin Case | ea | $0.00 | $0.00 | ||
| SUBTOTAL MATERIALS | $0.00 | ||||
| MARK-UP on materials | percent | $0.00 |
TOTAL ALL MATERIALS $0.00
| LABOR | hours | x | rate | amount | |
| Exhibit Specialist - Fabrication | hours @ | $0.00 | $0.00 |
TOTAL ALL LABOR $0.00
TOTAL Exhibit Structures $0.00
| Display Objects and Specialty Elements | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| Illustration | ea | $0.00 | $0.00 | ||
| Photos or Graphic Stock Purchases | ea | $0.00 | $0.00 | ||
| Bronze Tactile - At or Below 10" x 10" | ea | $0.00 | $0.00 | ||
| Interactive Flipbook Tactile | ea | $0.00 | $0.00 | ||
| SUBTOTAL MATERIALS | $0.00 | ||||
| MARK-UP on materials | percent | $0.00 |
| TOTAL ALL MATERIALS | $0.00 | ||||
| LABOR | hours | x | rate | amount | |
| Cartographer | hours @ | $0.00 | $0.00 | ||
| Exhibits Specialist Fabarication | hours @ | $0.00 | $0.00 | ||
| TOTAL ALL LABOR | $0.00 |
TOTAL DO and SE $0.00
| Graphic Panels | |||||
| MATERIALS: | qty. | unit | dig output | amount | |
| 36x48 Upright In-Ground | ea | $0.00 | $0.00 | ||
| 48x24 Low-Profile In-Ground | ea | $0.00 | $0.00 | ||
| 36x24 Low-Profile In-Ground | ea | $0.00 | $0.00 | ||
| 24x24 Low-Profile In-Ground | ea | $0.00 | $0.00 | ||
| SUBTOTAL MATERIALS | $0.00 | ||||
| MARK-UP on materials | percent | $0.00 |
| TOTAL ALL MATERIALS | $0.00 | ||||
| LABOR | hours | x | rate | amount | |
| Exhibits Specialist Fabrication | hours @ | $0.00 | $0.00 |
TOTAL ALL LABOR $0.00
TOTAL Graphics $0.00
| Audio Description | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| Misc. | ea | $0.00 | $0.00 | ||
| SUBTOTAL MATERIALS | $0.00 | ||||
| MARK-UP on materials | percent | $0.00 |
| TOTAL ALL MATERIALS | $0.00 | |||
| LABOR | x | rate | amount | |
| Audio Describer 4 hours per exhibits | hours @ | $0.00 | $0.00 |
TOTAL ALL LABOR $0.00
TOTAL Audio Description $0.00
| PROJECT CLOSEOUT | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| Misc. | job | $0.00 | $0.00 |
| SUBTOTAL MATERIALS | $0.00 | |
| MARK-UP on materials | percent | $0.00 |
| TOTAL ALL MATERIALS | $0.00 | ||||
| LABOR | hours | x | rate | amount | |
| Project Manager | hours @ | $0.00 | $0.00 | ||
| TOTAL ALL LABOR | $0.00 |
TOTAL Project Closeout $0.00
| SHIPPING | |||||
| MATERIALS: | qty. | unit | unit cost | amount | |
| Packing | job @ | $0.00 | $0.00 | ||
| Shipping | job @ | $0.00 | $0.00 |
TOTAL MATERIALS $0.00
| LABOR | hours | x | rate | amount | |
| Exhibit Spec - Fabrication | hours @ | $0.00 | $0.00 |
TOTAL ALL LABOR $0.00
Total Shipping $0.00
INSTALLATION
| MATERIALS: | qty. | unit | unit cost | amount | |
| Air Fare | job @ | $0.00 | $0.00 | ||
| Per Diem (Akron, Ohio) | days @ | $0.00 | $0.00 | ||
| Per Diem (Travel Days) | days @ | $0.00 | $0.00 | ||
| Lodging | days @ | $0.00 | $0.00 | ||
| Rental Car and Gas | days @ | $0.00 | $0.00 | ||
| Travel Time - Project Manager | hours @ | $0.00 | $0.00 | ||
| Travel Time - Exhibit Spec - Fabricator | hours @ | $0.00 | $0.00 | ||
| Travel Time - Exhibit Spec - Fabricator | hours @ | $0.00 | $0.00 | ||
| Travel Time - Audio Describer | hours @ | $0.00 | $0.00 | ||
| Misc. concrete, weights, and equipment rental - Explain | job @ | $0.00 | $0.00 |
TOTAL MATERIALS crew $0.00
| LABOR - CONTRACTOR SHALL PROPOSE | hours | x | rate | amount | |
| Project Manager | hours @ | $0.00 | $0.00 | ||
| Exhibit Spec - Fabricator | hours @ | $0.00 | $0.00 | ||
| Exhibit Spec - Fabricator | hours @ | $0.00 | $0.00 | ||
| Audio Describer | hours @ | $0.00 | $0.00 |
TOTAL ALL LABOR $0.00
Total Installation $0.00
| TRAVEL | |||||
| Post Award | |||||
| qty. | unit | unit cost | amount | ||
| Air Fare | job @ | $0.00 | $0.00 | ||
| Per Diem (Akron, Ohio) | days @ | $0.00 | $0.00 | ||
| Per Diem (Travel Days) | days @ | $0.00 | $0.00 | ||
| Lodging | days @ | $0.00 | $0.00 | ||
| Rental Car and Gas | days @ | $0.00 | $0.00 | ||
| Travel Time - Project Manager | hours @ | $0.00 | $0.00 | ||
| Travel Time - Writer | hours @ | $0.00 | $0.00 | ||
| Travel Time - Exhibit Designer | hours @ | $0.00 | $0.00 | ||
| Misc. - Explain | job @ | $0.00 | $0.00 |
TOTAL MATERIALS team $0.00
| LABOR | hours | x | rate | amount | |
| Project Manager | hours @ | $0.00 | $0.00 | ||
| Writer | hours @ | $0.00 | $0.00 | ||
| Exhibit Designer | hours @ | $0.00 | $0.00 | ||
| hours @ | $0.00 | $0.00 | |||
| TOTAL ALL LABOR | $0.00 |
Total Travel $0.00
File details come from the government source that posted it. Updated .