This is a deliverable summary spreadsheet attachment detailing the required deliverables across 10 topic areas for the 2025 Distributed Wind Turbine Competitiveness Improvement Project (CIP). The spreadsheet contains separate tables for each topic area: Prototype Design Development, Prototype Manufacture, Prototype Installation and Testing, Component Innovation, System Optimization, Small Wind Certification/Listing, Inverter Listing, Type Certification and Listing, Manufacturing Process Innovation, and Technology Commercialization.
Each table outlines specific deliverables with associated timing requirements over a 21-month period, including quarterly reports, work summaries, design reviews, testing reports, and LCOE (Levelized Cost of Energy) analyses. The tables include columns for NREL portion, subcontractor portion, and total costs, though no actual costs are filled in. Quarterly reports across all topic areas have minimum values of $2,000-$4,000 and maximum values of $4,000-$10,000. The spreadsheet notes that deliverables may be split into sub-deliverables and additional ones may be added subject to NREL approval.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Prototype Design Development
| Attachment 6 | ||||||
| Deliverable Summary Table | ||||||
| Prototype Design Development Topic Area | ||||||
| Occurrence | Task | Occurrences/Deliverables - Description | NREL Portion | Subcontractor Portion | Total | Months |
| 1 | 6.1 | Summary of Work Effort | $0.00 | $0.00 | $0.00 | 1 |
| 2 | 6.8 | Q1 report | $0.00 | $0.00 | $0.00 | 3 |
| 3 | 6.2 | Design Evaluation | $0.00 | $0.00 | $0.00 | 3 |
| 4 | 6.8 | Q2 Report | $0.00 | $0.00 | $0.00 | 6 |
| 5 | 6.3 | Evaluation Response Plan | $0.00 | $0.00 | $0.00 | 6 |
| 6 | 6.8 | Q3 Report | $0.00 | $0.00 | $0.00 | 9 |
| 7 | 6.4 | Problem Resolution Report | $0.00 | $0.00 | $0.00 | 11 |
| 8 | 6.8 | Q4 Report | $0.00 | $0.00 | $0.00 | 12 |
| 9 | 6.5 | Final Design Development Plan | $0.00 | $0.00 | $0.00 | 13 |
| 10 | 6.8 | Q5 Report | $0.00 | $0.00 | $0.00 | 15 |
| 11 | 6.8 | Q6 Report | $0.00 | $0.00 | $0.00 | 18 |
| 12 | 6.6 | Final Design and Testing Report | $0.00 | $0.00 | $0.00 | 19 |
| 13 | 6.8 | Q7 Report | $0.00 | $0.00 | $0.00 | 21 |
| 14 | 6.7 | Final Project Report and LCOE | $0.00 | $0.00 | $0.00 | 21 |
| $0.00 | $0.00 | $0.00 | ||||
| $0.00 | $0.00 | $0.00 | ||||
| Total Price | $0.00 | $0.00 | $0.00 | |||
| Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval. | ||||||
| Quarterly reports should be at least $2,000 each and not more than $4,000. |
Prototype Manuf. & Install.
| Attachment 6 | ||||||
| Deliverable Summary Table | ||||||
| Prototype Manufacture Topic Area | ||||||
| Occurrence | Task | Occurrences/Deliverables - Description | NREL Portion | Subcontractor Portion | Total | Months |
| 1 | 6.1 | Summary of Work Effort | $0.00 | $0.00 | $0.00 | 1 |
| 2 | 6.7 | Q1 report | $0.00 | $0.00 | $0.00 | 3 |
| 3 | 6.2 | Design Evaluation | $0.00 | $0.00 | $0.00 | 3 |
| 4 | 6.7 | Q2 Report | $0.00 | $0.00 | $0.00 | 6 |
| 5 | 6.3 | Manufacturing and Tooling Plan | $0.00 | $0.00 | $0.00 | 6 |
| 6 | 6.7 | Q3 report | $0.00 | $0.00 | $0.00 | 9 |
| 7 | 6.7 | Q4 Report | $0.00 | $0.00 | $0.00 | 12 |
| 8 | 6.7 | Q5 Report | $0.00 | $0.00 | $0.00 | 15 |
| 9 | 6.4 | Turbine Manufacturing Report | $0.00 | $0.00 | $0.00 | 15 |
| 10 | 6.7 | Q6 Report | $0.00 | $0.00 | $0.00 | 18 |
| 11 | 6.7 | Q7 Report | $0.00 | $0.00 | $0.00 | 21 |
| 12 | 6.5 | LCOE Report | $0.00 | $0.00 | $0.00 | 21 |
| $0.00 | $0.00 | $0.00 | ||||
| Total Price | $0.00 | $0.00 | $0.00 | |||
| Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval. | ||||||
| Quarterly reports should be at least $2,000 each and not more than $5,000. |
Prototype Install. & Testing
| Attachment 6 | ||||||
| Deliverable Summary Table | ||||||
| Prototype Installation and Testing Topic Area | ||||||
| Occurrence | Task | Occurrences/Deliverables - Description | NREL Portion | Subcontractor Portion | Total | Months |
| 1 | 6.1 | Summary of Work Effort | $0.00 | $0.00 | $0.00 | 1 |
| 2 | 6.5 | Q1 report | $0.00 | $0.00 | $0.00 | 3 |
| 3 | 6.2 | Design Review | $0.00 | $0.00 | $0.00 | 3 |
| 4 | 6.3 | Testing Specification | $0.00 | $0.00 | $0.00 | 5 |
| 5 | 6.5 | Q2 Report | $0.00 | $0.00 | $0.00 | 6 |
| 6 | 6.5 | Q3 report | $0.00 | $0.00 | $0.00 | 9 |
| 7 | 6.5 | Q4 Report | $0.00 | $0.00 | $0.00 | 12 |
| 8 | 6.5 | Q5 Report | $0.00 | $0.00 | $0.00 | 15 |
| 9 | 6.5 | Q6 Report | $0.00 | $0.00 | $0.00 | 18 |
| 10 | 6.5 | Q7 Report | $0.00 | $0.00 | $0.00 | 21 |
| 11 | 6.4 | Testing Results | $0.00 | $0.00 | $0.00 | 21 |
| Total Price | $0.00 | $0.00 | $0.00 | |||
| Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval. | ||||||
| Quarterly reports should be at least $2,000 each and not more than $5,000. |
Component Innovation
| Attachment 6 | ||||||
| Deliverable Summary Table | ||||||
| Component Innovation Topic Area | ||||||
| Occurrence | Task | Occurrences/Deliverables - Description | NREL Portion | Subcontractor Portion | Total | Months |
| 1 | 6.1 | Summary of Work Effort | $0.00 | $0.00 | $0.00 | 1 |
| 2 | 6.2 | Analysis of Opportunity | $0.00 | $0.00 | $0.00 | 2 |
| 3 | 6.6 | Q1 Report | $0.00 | $0.00 | $0.00 | 3 |
| 4 | 6.3 | Product Development Plan | $0.00 | $0.00 | $0.00 | 3 |
| 5 | 6.6 | Q2 Report | $0.00 | $0.00 | $0.00 | 6 |
| 6 | 6.6 | Q3 report | $0.00 | $0.00 | $0.00 | 9 |
| 7 | 6.6 | Q4 Report | $0.00 | $0.00 | $0.00 | 12 |
| 8 | 6.6 | Q5 Report | $0.00 | $0.00 | $0.00 | 15 |
| 9 | 6.6 | Q6 Report | $0.00 | $0.00 | $0.00 | 18 |
| 10 | 6.4 | Final Analysis Report | $0.00 | $0.00 | $0.00 | 19 |
| 11 | 6.6 | Q7 Report | $0.00 | $0.00 | $0.00 | 21 |
| 12 | 6.5 | LCOE Report | $0.00 | $0.00 | $0.00 | 21 |
| $0.00 | $0.00 | $0.00 | ||||
| Total Price | $0.00 | $0.00 | $0.00 | |||
| Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval. | ||||||
| Quarterly reports should be at least $2,000 each and not more than $5,000. |
System Opt.
| Attachment 6 | ||||||
| Deliverable Summary Table | ||||||
| System Optimization Topic Area | ||||||
| Occurrence | Task | Occurrences/Deliverables - Description | NREL Portion | Subcontractor Portion | Total | Months |
| 1 | 6.1 | Summary of Work Effort | $0.00 | $0.00 | $0.00 | 1 |
| 2 | 6.2 | Analysis of Opportunity | $0.00 | $0.00 | $0.00 | 2 |
| 3 | 6.6 | Q1 Report | $0.00 | $0.00 | $0.00 | 3 |
| 4 | 6.3 | Product Development Plan | $0.00 | $0.00 | $0.00 | 3 |
| 5 | 6.6 | Q2 Report | $0.00 | $0.00 | $0.00 | 6 |
| 6 | 6.6 | Q3 report | $0.00 | $0.00 | $0.00 | 9 |
| 7 | 6.6 | Q4 Report | $0.00 | $0.00 | $0.00 | 12 |
| 8 | 6.6 | Q5 Report | $0.00 | $0.00 | $0.00 | 15 |
| 9 | 6.6 | Q6 Report | $0.00 | $0.00 | $0.00 | 18 |
| 10 | 6.4 | Final Analysis Report | $0.00 | $0.00 | $0.00 | 19 |
| 11 | 6.6 | Q7 Report | $0.00 | $0.00 | $0.00 | 21 |
| 12 | 6.5 | LCOE Report | $0.00 | $0.00 | $0.00 | 21 |
| $0.00 | $0.00 | $0.00 | ||||
| Total Price | $0.00 | $0.00 | $0.00 | |||
| Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval. | ||||||
| Quarterly reports should be at least $2,000 each and not more than $5,000. |
Small Wind Cert. List
| Attachment 6 | ||||||
| Deliverable Summary Table | ||||||
| Small Wind Certification and/or Listing Topic Area | ||||||
| Occurrence | Task | Occurrences/Deliverables - Description | NREL Portion | Subcontractor Portion | Total | Months |
| 1 | 6.1 | Summary of Work Effort | $0.00 | $0.00 | $0.00 | 1 |
| 2 | 6.7 | Q1 report | $0.00 | $0.00 | $0.00 | 3 |
| 3 | 6.2 | Design Review | $0.00 | $0.00 | $0.00 | 3 |
| 4 | 6.3.1 | Installation and Commissioning Report | $0.00 | $0.00 | $0.00 | 5 |
| 5 | 6.3.2 | Listing: Certification Application | $0.00 | $0.00 | $0.00 | 6 |
| 6 | 6.7 | Q2 Report | $0.00 | $0.00 | $0.00 | 6 |
| 7 | 6.3.3 | Listing: Construction Review Report and Test Plan | $0.00 | $0.00 | $0.00 | 9 |
| 8 | 6.7 | Q3 report | $0.00 | $0.00 | $0.00 | 9 |
| 9 | 6.7 | Q4 Report | $0.00 | $0.00 | $0.00 | 12 |
| 10 | 6.4 | Commercialization Plan | $0.00 | $0.00 | $0.00 | 13 |
| 11 | 6.7 | Q5 Report | $0.00 | $0.00 | $0.00 | 15 |
| 12 | 6.7 | Q6 Report | $0.00 | $0.00 | $0.00 | 18 |
| 13 | 6.5 | Design Load Document (Listing: Testing Report) | $0.00 | $0.00 | $0.00 | 19 |
| 14 | 6.7 | Q7 Report | $0.00 | $0.00 | $0.00 | 21 |
| 15 | 6.6 | Certification Documents and Experience Report | $0.00 | $0.00 | $0.00 | 21 |
| Total Price | $0.00 | $0.00 | $0.00 | |||
| Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval. | ||||||
| Quarterly reports should be at least $2,000 each and not more than $4,000. |
Inverter Listing
| Attachment 6 | ||||||
| Deliverable Summary Table | ||||||
| Inverter Listing Topic Area | ||||||
| Occurrence | Task | Occurrences/Deliverables - Description | NREL Portion | Subcontractor Portion | Total | Months |
| 1 | 6.1 | Summary of Work Effort | $0.00 | $0.00 | $0.00 | 1 |
| 2 | 6.8 | Q1 report | $0.00 | $0.00 | $0.00 | 3 |
| 3 | 6.2a | NRTL quotation | $0.00 | $0.00 | $0.00 | 6 |
| 4 | 6.2b | Pre-listing effort report | $0.00 | $0.00 | $0.00 | 6 |
| 5 | 6.8 | Q2 Report | $0.00 | $0.00 | $0.00 | 6 |
| 6 | 6.3 | Design Review | $0.00 | $0.00 | $0.00 | 8 |
| 7 | 6.8 | Q3 report | $0.00 | $0.00 | $0.00 | 9 |
| 8 | 6.4.1 | Certification application | $0.00 | $0.00 | $0.00 | 10 |
| 9 | 6.4.2 | Construction review report | $0.00 | $0.00 | $0.00 | 12 |
| 10 | 6.8 | Q4 Report | $0.00 | $0.00 | $0.00 | 12 |
| 11 | 6.5 | Commercialization Plan | $0.00 | $0.00 | $0.00 | 13 |
| 12 | 6.8 | Q5 Report | $0.00 | $0.00 | $0.00 | 15 |
| 13 | 6.8 | Q6 Report | $0.00 | $0.00 | $0.00 | 18 |
| 14 | 6.6 | Testing Report | $0.00 | $0.00 | $0.00 | 19 |
| 15 | 6.8 | Q7 Report | $0.00 | $0.00 | $0.00 | 21 |
| 15 | 6.7 | Certification/Listing Documents and Experience Report | $0.00 | $0.00 | $0.00 | 21 |
| Total Price | $0.00 | $0.00 | $0.00 | |||
| Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval. | ||||||
| Quarterly reports should be at least $2,000 each and not more than $4,000. |
Type Cert. & List
| Attachment 6 | ||||||
| Deliverable Summary Table | ||||||
| Type Certification and Listing Topic Area | ||||||
| Occurrence | Task | Occurrences/Deliverables - Description | NREL Portion | Subcontractor Portion | Total | Months |
| 1 | 6.1 | Summary of Work Effort | $0.00 | $0.00 | $0.00 | 1 |
| 2 | 6.9 | Q1 report | $0.00 | $0.00 | $0.00 | 3 |
| 3 | 6.2.1 | Design Basis Review Report | $0.00 | $0.00 | $0.00 | 4 |
| 4 | 6.3.2 | Listing: Certification Application | $0.00 | $0.00 | $0.00 | 4 |
| 5 | 6.9 | Q2 Report | $0.00 | $0.00 | $0.00 | 6 |
| 6 | 6.2.2 | Design Basis Evaluation Conformity | $0.00 | $0.00 | $0.00 | 6 |
| 7 | 6.3.3 | Listing: Construction Review Report and Test Plan | $0.00 | $0.00 | $0.00 | 8 |
| 8 | 6.2.3 | Design Evaluation Conformity | $0.00 | $0.00 | $0.00 | 8 |
| 9 | 6.9 | Q3 report | $0.00 | $0.00 | $0.00 | 9 |
| 10 | 6.9 | Q4 Report | $0.00 | $0.00 | $0.00 | 12 |
| 11 | 6.3.1 | Installation and Commissioning Report | $0.00 | $0.00 | $0.00 | 12 |
| 12 | 6.4 | Commercialization Plan | $0.00 | $0.00 | $0.00 | 13 |
| 13 | 6.9 | Q5 Report | $0.00 | $0.00 | $0.00 | 15 |
| 14 | 6.5 | Manufacturing Evaluation Conformity | $0.00 | $0.00 | $0.00 | 15 |
| 15 | 6.9 | Q6 Report | $0.00 | $0.00 | $0.00 | 18 |
| 16 | 6.6 | Testing Complete Conformity Report | $0.00 | $0.00 | $0.00 | 19 |
| 17 | 6.7 | Final Evaluation Report | $0.00 | $0.00 | $0.00 | 20 |
| 18 | 6.9 | Q7 Report | $0.00 | $0.00 | $0.00 | 21 |
| 19 | 6.8 | Type Certification and Listing Document | $0.00 | $0.00 | $0.00 | 21 |
| Total Price | $0.00 | $0.00 | $0.00 | |||
| Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval. | ||||||
| Quarterly reports should be at least $4,000 each and not more than $10,000. |
Manuf. Innovation
| Attachment 6 | ||||||
| Deliverable Summary Table | ||||||
| Manufacturing Process Innovation Topic Area | ||||||
| Occurrence | Task | Occurrences/Deliverables - Description | NREL Portion | Subcontractor Portion | Total | Months |
| 1 | 6.1 | Summary of Work Effort | $0.00 | $0.00 | $0.00 | 1 |
| 2 | 6.2 | Current State of Manufacturing Report | $0.00 | $0.00 | $0.00 | 2 |
| 3 | 6.6 | Q1 Report | $0.00 | $0.00 | $0.00 | 3 |
| 4 | 6.3 | Implementation Plan | $0.00 | $0.00 | $0.00 | 3 |
| 5 | 6.6 | Q2 Report | $0.00 | $0.00 | $0.00 | 6 |
| 6 | 6.6 | Q3 report | $0.00 | $0.00 | $0.00 | 9 |
| 7 | 6.6 | Q4 Report | $0.00 | $0.00 | $0.00 | 12 |
| 8 | 6.6 | Q5 Report | $0.00 | $0.00 | $0.00 | 15 |
| 9 | 6.6 | Q6 Report | $0.00 | $0.00 | $0.00 | 18 |
| 10 | 6.4 | Final Report Documenting Implementation | $0.00 | $0.00 | $0.00 | 19 |
| 11 | 6.6 | Q7 Report | $0.00 | $0.00 | $0.00 | 21 |
| 12 | 6.5 | LCOE Report | $0.00 | $0.00 | $0.00 | 21 |
| Total Price | $0.00 | $0.00 | $0.00 | |||
| Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval. | ||||||
| Quarterly reports should be at least $2,000 each and not more than $4,000. |
Tech Commercialization
| Attachment 6 | ||||||
| Deliverable Summary Table | ||||||
| Technology Commercialization Topic Area | ||||||
| Occurrence | Task | Occurrences/Deliverables - Description | NREL Portion | Subcontractor Portion | Total | Months |
| 1 | 6.1 | Summary of Work Effort | $0.00 | $0.00 | $0.00 | 1 |
| 2 | 6.5 | Q1 report | $0.00 | $0.00 | $0.00 | 3 |
| 3 | 6.2 | Market Development Plan Outline | $0.00 | $0.00 | $0.00 | 3 |
| 5 | 6.5 | Q2 Report | $0.00 | $0.00 | $0.00 | 6 |
| 6 | 6.3 | Commercialization Implementation Plan | $0.00 | $0.00 | $0.00 | 9 |
| 7 | 6.5 | Q3 report | $0.00 | $0.00 | $0.00 | 9 |
| 8 | 6.5 | Q4 Report | $0.00 | $0.00 | $0.00 | 12 |
| 9 | 6.5 | Q5 Report | $0.00 | $0.00 | $0.00 | 15 |
| 10 | 6.5 | Q6 Report | $0.00 | $0.00 | $0.00 | 18 |
| 11 | 6.5 | Q7 Report | $0.00 | $0.00 | $0.00 | 21 |
| 12 | 6.4 | Final Implementation Report | $0.00 | $0.00 | $0.00 | 21 |
| Total Price | $0.00 | $0.00 | $0.00 | |||
| Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval. | ||||||
| Quarterly reports should be at least $2,000 each and not more than $5,000. |