This is a deliverable summary spreadsheet attachment detailing the required deliverables across 10 topic areas for the 2025 Distributed Wind Turbine Competitiveness Improvement Project (CIP). The spreadsheet contains separate tables for each topic area: Prototype Design Development, Prototype Manufacture, Prototype Installation and Testing, Component Innovation, System Optimization, Small Wind Certification/Listing, Inverter Listing, Type Certification and Listing, Manufacturing Process Innovation, and Technology Commercialization.

Each table outlines specific deliverables with associated timing requirements over a 21-month period, including quarterly reports, work summaries, design reviews, testing reports, and LCOE (Levelized Cost of Energy) analyses. The tables include columns for NREL portion, subcontractor portion, and total costs, though no actual costs are filled in. Quarterly reports across all topic areas have minimum values of $2,000-$4,000 and maximum values of $4,000-$10,000. The spreadsheet notes that deliverables may be split into sub-deliverables and additional ones may be added subject to NREL approval.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Prototype Design Development

Attachment 6
Deliverable Summary Table
Prototype Design Development Topic Area
OccurrenceTaskOccurrences/Deliverables - DescriptionNREL PortionSubcontractor PortionTotalMonths
16.1Summary of Work Effort$0.00$0.00$0.001
26.8Q1 report$0.00$0.00$0.003
36.2Design Evaluation$0.00$0.00$0.003
46.8Q2 Report$0.00$0.00$0.006
56.3Evaluation Response Plan$0.00$0.00$0.006
66.8Q3 Report$0.00$0.00$0.009
76.4Problem Resolution Report$0.00$0.00$0.0011
86.8Q4 Report$0.00$0.00$0.0012
96.5Final Design Development Plan$0.00$0.00$0.0013
106.8Q5 Report$0.00$0.00$0.0015
116.8Q6 Report$0.00$0.00$0.0018
126.6Final Design and Testing Report$0.00$0.00$0.0019
136.8Q7 Report$0.00$0.00$0.0021
146.7Final Project Report and LCOE$0.00$0.00$0.0021
$0.00$0.00$0.00
$0.00$0.00$0.00
Total Price$0.00$0.00$0.00
Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval.
Quarterly reports should be at least $2,000 each and not more than $4,000.

Prototype Manuf. & Install.

Attachment 6
Deliverable Summary Table
Prototype Manufacture Topic Area
OccurrenceTaskOccurrences/Deliverables - DescriptionNREL PortionSubcontractor PortionTotalMonths
16.1Summary of Work Effort$0.00$0.00$0.001
26.7Q1 report$0.00$0.00$0.003
36.2Design Evaluation$0.00$0.00$0.003
46.7Q2 Report$0.00$0.00$0.006
56.3Manufacturing and Tooling Plan$0.00$0.00$0.006
66.7Q3 report$0.00$0.00$0.009
76.7Q4 Report$0.00$0.00$0.0012
86.7Q5 Report$0.00$0.00$0.0015
96.4Turbine Manufacturing Report$0.00$0.00$0.0015
106.7Q6 Report$0.00$0.00$0.0018
116.7Q7 Report$0.00$0.00$0.0021
126.5LCOE Report$0.00$0.00$0.0021
$0.00$0.00$0.00
Total Price$0.00$0.00$0.00
Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval.
Quarterly reports should be at least $2,000 each and not more than $5,000.

Prototype Install. & Testing

Attachment 6
Deliverable Summary Table
Prototype Installation and Testing Topic Area
OccurrenceTaskOccurrences/Deliverables - DescriptionNREL PortionSubcontractor PortionTotalMonths
16.1Summary of Work Effort$0.00$0.00$0.001
26.5Q1 report$0.00$0.00$0.003
36.2Design Review$0.00$0.00$0.003
46.3Testing Specification$0.00$0.00$0.005
56.5Q2 Report$0.00$0.00$0.006
66.5Q3 report$0.00$0.00$0.009
76.5Q4 Report$0.00$0.00$0.0012
86.5Q5 Report$0.00$0.00$0.0015
96.5Q6 Report$0.00$0.00$0.0018
106.5Q7 Report$0.00$0.00$0.0021
116.4Testing Results$0.00$0.00$0.0021
Total Price$0.00$0.00$0.00
Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval.
Quarterly reports should be at least $2,000 each and not more than $5,000.

Component Innovation

Attachment 6
Deliverable Summary Table
Component Innovation Topic Area
OccurrenceTaskOccurrences/Deliverables - DescriptionNREL PortionSubcontractor PortionTotalMonths
16.1Summary of Work Effort$0.00$0.00$0.001
26.2Analysis of Opportunity$0.00$0.00$0.002
36.6Q1 Report$0.00$0.00$0.003
46.3Product Development Plan$0.00$0.00$0.003
56.6Q2 Report$0.00$0.00$0.006
66.6Q3 report$0.00$0.00$0.009
76.6Q4 Report$0.00$0.00$0.0012
86.6Q5 Report$0.00$0.00$0.0015
96.6Q6 Report$0.00$0.00$0.0018
106.4Final Analysis Report$0.00$0.00$0.0019
116.6Q7 Report$0.00$0.00$0.0021
126.5LCOE Report$0.00$0.00$0.0021
$0.00$0.00$0.00
Total Price$0.00$0.00$0.00
Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval.
Quarterly reports should be at least $2,000 each and not more than $5,000.

System Opt.

Attachment 6
Deliverable Summary Table
System Optimization Topic Area
OccurrenceTaskOccurrences/Deliverables - DescriptionNREL PortionSubcontractor PortionTotalMonths
16.1Summary of Work Effort$0.00$0.00$0.001
26.2Analysis of Opportunity$0.00$0.00$0.002
36.6Q1 Report$0.00$0.00$0.003
46.3Product Development Plan$0.00$0.00$0.003
56.6Q2 Report$0.00$0.00$0.006
66.6Q3 report$0.00$0.00$0.009
76.6Q4 Report$0.00$0.00$0.0012
86.6Q5 Report$0.00$0.00$0.0015
96.6Q6 Report$0.00$0.00$0.0018
106.4Final Analysis Report$0.00$0.00$0.0019
116.6Q7 Report$0.00$0.00$0.0021
126.5LCOE Report$0.00$0.00$0.0021
$0.00$0.00$0.00
Total Price$0.00$0.00$0.00
Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval.
Quarterly reports should be at least $2,000 each and not more than $5,000.

Small Wind Cert. List

Attachment 6
Deliverable Summary Table
Small Wind Certification and/or Listing Topic Area
OccurrenceTaskOccurrences/Deliverables - DescriptionNREL PortionSubcontractor PortionTotalMonths
16.1Summary of Work Effort$0.00$0.00$0.001
26.7Q1 report$0.00$0.00$0.003
36.2Design Review$0.00$0.00$0.003
46.3.1Installation and Commissioning Report$0.00$0.00$0.005
56.3.2Listing: Certification Application$0.00$0.00$0.006
66.7Q2 Report$0.00$0.00$0.006
76.3.3Listing: Construction Review Report and Test Plan$0.00$0.00$0.009
86.7Q3 report$0.00$0.00$0.009
96.7Q4 Report$0.00$0.00$0.0012
106.4Commercialization Plan$0.00$0.00$0.0013
116.7Q5 Report$0.00$0.00$0.0015
126.7Q6 Report$0.00$0.00$0.0018
136.5Design Load Document (Listing: Testing Report)$0.00$0.00$0.0019
146.7Q7 Report$0.00$0.00$0.0021
156.6Certification Documents and Experience Report$0.00$0.00$0.0021
Total Price$0.00$0.00$0.00
Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval.
Quarterly reports should be at least $2,000 each and not more than $4,000.

Inverter Listing

Attachment 6
Deliverable Summary Table
Inverter Listing Topic Area
OccurrenceTaskOccurrences/Deliverables - DescriptionNREL PortionSubcontractor PortionTotalMonths
16.1Summary of Work Effort$0.00$0.00$0.001
26.8Q1 report$0.00$0.00$0.003
36.2aNRTL quotation$0.00$0.00$0.006
46.2bPre-listing effort report$0.00$0.00$0.006
56.8Q2 Report$0.00$0.00$0.006
66.3Design Review$0.00$0.00$0.008
76.8Q3 report$0.00$0.00$0.009
86.4.1Certification application$0.00$0.00$0.0010
96.4.2Construction review report$0.00$0.00$0.0012
106.8Q4 Report$0.00$0.00$0.0012
116.5Commercialization Plan$0.00$0.00$0.0013
126.8Q5 Report$0.00$0.00$0.0015
136.8Q6 Report$0.00$0.00$0.0018
146.6Testing Report$0.00$0.00$0.0019
156.8Q7 Report$0.00$0.00$0.0021
156.7Certification/Listing Documents and Experience Report$0.00$0.00$0.0021
Total Price$0.00$0.00$0.00
Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval.
Quarterly reports should be at least $2,000 each and not more than $4,000.

Type Cert. & List

Attachment 6
Deliverable Summary Table
Type Certification and Listing Topic Area
OccurrenceTaskOccurrences/Deliverables - DescriptionNREL PortionSubcontractor PortionTotalMonths
16.1Summary of Work Effort$0.00$0.00$0.001
26.9Q1 report$0.00$0.00$0.003
36.2.1Design Basis Review Report$0.00$0.00$0.004
46.3.2Listing: Certification Application$0.00$0.00$0.004
56.9Q2 Report$0.00$0.00$0.006
66.2.2Design Basis Evaluation Conformity$0.00$0.00$0.006
76.3.3Listing: Construction Review Report and Test Plan$0.00$0.00$0.008
86.2.3Design Evaluation Conformity$0.00$0.00$0.008
96.9Q3 report$0.00$0.00$0.009
106.9Q4 Report$0.00$0.00$0.0012
116.3.1Installation and Commissioning Report$0.00$0.00$0.0012
126.4Commercialization Plan$0.00$0.00$0.0013
136.9Q5 Report$0.00$0.00$0.0015
146.5Manufacturing Evaluation Conformity$0.00$0.00$0.0015
156.9Q6 Report$0.00$0.00$0.0018
166.6Testing Complete Conformity Report$0.00$0.00$0.0019
176.7Final Evaluation Report$0.00$0.00$0.0020
186.9Q7 Report$0.00$0.00$0.0021
196.8Type Certification and Listing Document$0.00$0.00$0.0021
Total Price$0.00$0.00$0.00
Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval.
Quarterly reports should be at least $4,000 each and not more than $10,000.

Manuf. Innovation

Attachment 6
Deliverable Summary Table
Manufacturing Process Innovation Topic Area
OccurrenceTaskOccurrences/Deliverables - DescriptionNREL PortionSubcontractor PortionTotalMonths
16.1Summary of Work Effort$0.00$0.00$0.001
26.2Current State of Manufacturing Report$0.00$0.00$0.002
36.6Q1 Report$0.00$0.00$0.003
46.3Implementation Plan$0.00$0.00$0.003
56.6Q2 Report$0.00$0.00$0.006
66.6Q3 report$0.00$0.00$0.009
76.6Q4 Report$0.00$0.00$0.0012
86.6Q5 Report$0.00$0.00$0.0015
96.6Q6 Report$0.00$0.00$0.0018
106.4Final Report Documenting Implementation$0.00$0.00$0.0019
116.6Q7 Report$0.00$0.00$0.0021
126.5LCOE Report$0.00$0.00$0.0021
Total Price$0.00$0.00$0.00
Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval.
Quarterly reports should be at least $2,000 each and not more than $4,000.

Tech Commercialization

Attachment 6
Deliverable Summary Table
Technology Commercialization Topic Area
OccurrenceTaskOccurrences/Deliverables - DescriptionNREL PortionSubcontractor PortionTotalMonths
16.1Summary of Work Effort$0.00$0.00$0.001
26.5Q1 report$0.00$0.00$0.003
36.2Market Development Plan Outline$0.00$0.00$0.003
56.5Q2 Report$0.00$0.00$0.006
66.3Commercialization Implementation Plan$0.00$0.00$0.009
76.5Q3 report$0.00$0.00$0.009
86.5Q4 Report$0.00$0.00$0.0012
96.5Q5 Report$0.00$0.00$0.0015
106.5Q6 Report$0.00$0.00$0.0018
116.5Q7 Report$0.00$0.00$0.0021
126.4Final Implementation Report$0.00$0.00$0.0021
Total Price$0.00$0.00$0.00
Deliverables may be split into sub-deliverables and additional deliverables may be added by subcontractor subject to NREL approval.
Quarterly reports should be at least $2,000 each and not more than $5,000.