Attachment_M_Training_and_Lab_Building_100%_Cost_Estimate_-_11-01-2021.pdf
PDF 316 KB Posted
- Attached to
- VSD Campus Master Plan Analysis
- Solicitation number
- 2025-RFP-009
- Issued by
- Riverside County, Huntington Beach City, California
About this file
This document is a Design Development Cost Estimate prepared by SGH Architects for the Valley Sanitary District, located at 45-100 Van Buren St. in Indio, California. The project involves constructing new Training, Office, and Laboratory Buildings, with a total site area of 28,613 square feet. The estimated total project consists of two primary buildings: a Training & Office Building of 8,068 square feet and a Laboratory Building of 2,156 square feet. The cost estimate is dated November 1, 2021, with a project job number of 20-40101-00, suggesting the document represents a comprehensive preliminary budget for the proposed facility.
The total estimated construction cost for the project is $9,902,149, broken down as $6,691,666 for the Training & Office Building and $3,210,483 for the Laboratory Building. The estimate includes detailed line-item costs across multiple construction categories such as foundations, superstructure, enclosure, interior construction, plumbing, HVAC, electrical, fire protection, equipment, and site improvements. The cost estimate incorporates various contingencies, including general conditions (7%), contractor overhead and profit (4%), bonds and insurance (2.075%), design contingency (8%), and cost escalation to the midpoint of construction (9%) at a 6% per annum rate. The projected midpoint of construction is May 1, 2023, indicating a comprehensive financial planning document for the Valley Sanitary District's new facility development.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Estimate Provided By
Diversified Service Center, LLC 6801 Avenida De Galvez, Navarre FL 32566
T & F 850-710-3663 / C 760-505-2223 a394sam@yahoo.com dsc1939@yahoo.com
On Behalf Of
SGH Architects
707 Brookside Ave. / Redlands, CA 92373 / T 909.375.3030 / www.sgharch.com
Design Development Cost Estimate
New Training, Office and Laboratory Buildings
Valley Sanitary District
45-100 Van Buren St., Indio, CA 92201
November 1, 2021
Job #: 20-40101-00
Design Development Cost Estimate
New Training, Office and Laboratory Buildings
Valley Sanitary District
45-100 Van Buren St., Indio, CA 92201
November 1, 2021
SGH Job No. 20-40101-00
Overall Summaries
New Training, Office and Laboratory Buildings November 1, 2021
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Overall Areas
Enclosed Covered Gross*
Training & Office Building 8,068 793 8,068 SF
Laboratory Building Details 2,156 0 2,156 SF
Total Building Area 10,224 793 10,224 SF
Total Site Area (including Building footprint) 27,620 0 28,613 SF
* Gross floor area is calculated as the full enclosed area plus one-half of the covered area.
Valley Sanitary District
45-100 Van Buren St., Indio, CA 92201
November 1, 2021
SGH Job No. 20-40101-00
Training & Office Building
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Areas and Control Quantities
Areas Enclosed Covered Gross*
Corridor 315 0 315 SF
Quiet Rm 136 0 136 SF
Plan RM 385 0 385 SF
Laundry 106 0 106 SF
Corridor 718 0 718 SF
Mens LKR 663 0 663 SF
Womens LKR 570 0 570 SF
Storage 205 0 205 SF
Server 60 0 60 SF
Field Stations 1,144 0 1,144 SF
Office 171 0 171 SF
Office 175 0 175 SF
Office 174 0 174 SF
Office 171 0 171 SF
Conf Rm 257 0 257 SF
Trn'g RM 1,238 0 1,238 SF
Tbls/Chairs 328 0 328 SF
AV 36 0 36 SF
Kitchen 259 0 259 SF
Break RM 380 0 380 SF
Unisex 58 0 58 SF
Unisex 57 0 57 SF
Janitor 62 0 62 SF
Storage 211 0 211 SF
Electrical 29 0 29 SF
Mech/FR 58 0 58 SF
Corridor 102 0 102 SF
Covered Area 793
Total Building Area 8,068 793 8,068 SF
Total Site Area, including building footprint 27,620 28,613 SF
Control Quantities Quantity Unit Ratio to Gross
Gross Floor Area 8,068 SF 1.000
Enclosed Area 8,068 SF 1.000
Covered Area 793 SF 0.098
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Summary $/SF Total $
A10 Foundations 32.10 258,969
A20 Basement Construction 0.00 0
B10 Superstructure 114.69 925,355
B20 Enclosure 46.25 373,121
B30 Roofing 33.50 270,288
C10 Interior Construction 99.84 805,508
C20 Stairs 0.00 0
C30 Interior Finishes 44.06 355,454
D10 Conveying 0.00 0
D20 Plumbing 30.78 248,343
D30 HVAC 51.96 419,216
D40 Fire Protection 7.49 60,414
D50 Electrical 53.33 430,294
D51 Technology 0.77 6,225
D52 Fire Alarm 5.55 44,792
E10 Equipment 5.11 41,200
E20 Furnishings 7.00 56,465
F10 Special Construction 19.95 160,920
F20 Selective Building Demolition 0.00 0
G10 Site Preparation 13.47 108,714
G20 Site Improvement 18.58 149,897
G30 Site Mechanical Utilities 21.76 175,569
G40 Site Electrical Utilities 11.53 93,004
G41 Site Technology Utilities 2.55 20,600
G90 Off Site Construction 0.00 0
Direct Construction Cost 620.27 5,004,348
Gen Conditions 7.0% 43.42 350,304
Gen Contractor OH&P 4.0% 26.55 214,186
Bonds and Insurance 2.1% 14.32 115,553
Design Contingency 8.0% 56.36 454,751
Cost Escalation to Midpoint of Construction* 9.0% 68.48 552,523
Total Construction Cost $829.41 $6,691,666
* Cost escalation to midpoint of construction in May 1, 2023 - 18 months at 6.0 % per annum.
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Trade Summary $/SF Total $
02 Existing Conditions 1.01 8,149
03 Concrete 31.97 257,937
04 Masonry 64.76 522,490
05 Metals 53.49 431,521
06 Wood, Plastics and Composites 6.24 50,369
07 Thermal and Moisture Protection 39.95 322,301
08 Openings 48.08 387,901
09 Finishes 117.63 949,038
10 Specialties 8.19 66,106
11 Equipment 5.11 41,200
12 Furnishings 7.00 56,465
13 Special Construction 19.95 160,920
14 Conveying Equipment 0.00 0
21 Fire Suppression 7.49 60,414
22 Plumbing 30.78 248,343
23 Heating, Ventilating and Air Conditioning 51.96 419,216
26 Electrical 53.33 430,294
27 Technology 0.77 6,225
28 Fire Alarm 5.55 44,792
31 Earthwork 12.46 100,565
32 Exterior Improvements 18.71 150,929
33 Utilities 33.29 268,573
34 Site Technology 2.55 20,600
36 Off Site Construction 0.00 0
Direct Construction Cost 620.27 5,004,348
Gen Conditions 7.0% 43.42 350,304
Gen Contractor OH&P 4.0% 26.55 214,186
Bonds and Insurance 2.1% 14.32 115,553
Design Contingency 8.0% 56.36 454,751
Cost Escalation to Midpoint of Construction* 9.0% 68.48 552,523
Total Construction Cost $829.41 $6,691,666
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Detail Quantity Unit Rate Subtotal $ Total $
A10 Foundations 258,969
Standard foundations 71,071
CMU footing, 2'-0" w x 1'-6" d 40 cy 954.00 38,088
CMU footing, 2'-0" w x 2'-6" d 4 cy 1,132.00 4,606
CMU footing, 3'-0" w x 2'-6" d 10 cy 1,132.00 11,232
CMU footing, 3'-6" w x 2'-6" d 8 cy 1,132.00 9,575
Pad footing, 4'-0" x 4'-0" w x 1'-0" d, 8 cy 954.00 7,570
* 0
Special foundations 1,032
Pilaster, 1'-3" dia. 3'-4" deep 1 cy 1,132.00 1,032
* 0
Slab on grade 186,866
5" SOG, #4 @ 18" ocew, vb, 4" crushed rock, ovr compacted soil (natural of fill) 9,177 sf 15.10 138,573
Add for depressed slabs 910 sf 5.15 4,687
Concrete curbs @ restrooms 0'-6" W x 0'-6" H 369 lf 30.80 11,355
Add for thickened edge 28 cy 1,132.00 31,652
Slab surface column blockouts 7 ea 19.90 139
Patch back at blockouts 7 ea 65.70 460
* 0
B10 Superstructure 925,355
Walls 591,308
CMU, split face, 8816, full grout 2,270 sf 59.00 133,920
CMU, precision, 8816, full grout 7,818 sf 49.70 388,570
HSS3-1/2x3-1/2x3/8 1,629 lbs 4.05 6,598
HSS4x4x1/4 183 lbs 4.05 741
HSS6x0.25 1,232 lbs 4.05 4,990
Base plate 122 lbs 5.20 636
Top plate 122 lbs 5.20 636
Miscellaneous material 10% pct 552,173.75 55,217
* 0
Roof construction 170,849
W10x12 @ extr. @ metal deck canopies 2,208.750 lbs 4.70 10,381
5.125 x 28.5 GLB ridge beam 2.209 mbf 4,285.20 9,465
5.125 x 18 GLB ridge beam 0.58 mbf 4,285.20 2,475
PWJ-16 3,201 fl 18.20 58,252
PWJ-12 1,159 lf 21.80 25,258
4x10 ledger 0.431 mbf 8,438.95 3,635
5/8" struct 1 plywood sheathing 8.9 msf 4,853.00 43,069
Plaster soffit framing 143 sf 16.50 2,360
Miscellaneous labor & material 10% pct 159,541.85 15,954
* 0
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Detail Quantity Unit Rate Subtotal $ Total $
Metal deck canopy @ entry,elec, mech & exit 69,948
W10x12 858 lbs 4.05 3,475
C15x33.9 4,481 lbs 4.70 21,059
C12x20.7 3,910 lbs 4.70 18,379
L4x4x1/4 585 lbs 5.60 3,277
HSS12x6x1/4 1,732 lbs 4.70 8,139
Roof deck, ,18 ga., Q-3, 1-1/2" simple, galvanized & primed 732 sf 6.45 4,721
Canopy, paint 732 sf 2.10 1,537
Misc. labor & material, metal deck canopies 15% pct 62,404.65 9,361
* 0
Mechanical screen 93,250
HSS 3"x2"x1/4" 1,802 lbs 4.70 8,469
HSS 3"x3"x5/16" 429 lbs 4.70 2,017
HSS 3.500 x.300 180 lbs 4.20 757
1/4" bent U plate, 26" L x 7-3/4" h x 4" w x 7-
3/4" h 6,073 lbs 5.70 34,616
L2-1/2"x2-1/2"x1/4", vertical 174 lbs 5.60 974
L5"x4"x1/4"x7" 60 lbs 5.60 336
10"x10"x3/4" cap plate, drilled 3/4" dia x 4 ea 590 lbs 7.15 4,220
3"x3"x1/4", cap plate 1,285 lbs 7.15 9,189
Perforated mtl wall panel, baked enamel finish 286 sf 83.70 23,964
Miscellaneous labor & material 10% pct 87,078.30 8,708
* 0
B20 Enclosure 373,121
Exterior walls 93,124
Exterior gypsum sheathing, 5/8" 81 sf 5.55 450
Weather barrier 81 sf 0.65 53
Corrugated metal wall panel 81 sf 53.60 4,342
Framing 81 sf 16.25 1,316
Tyvek fluid applied water barrier 81 sf 4.75 385
Exterior plaster soffit 15.9 syd 287.35 4,566
Paint plaster soffit 143 sf 2.35 336
Sun shades 90 sf 85.00 7,650
Miscellaneous labor & material 10% pct 19,670.95 1,967
Metal deck canopy @ entry
W10x12 858 lbs 3.70 3,175
C15x33.9 3,771 lbs 4.70 17,725
C12x20.7 3,249 lbs 4.70 15,268
L4x4x1/4 473 lbs 5.60 2,649
HSS12x6x1/4 1,400 lbs 7.00 9,801
Roof deck, ,18 ga., Q-3, 1-1/2" simple, galvanized & primed 732 sf 6.45 4,721
Canopy, paint 732 sf 12.40 9,077
Misc. labor & material, metal deck canopies 15% pct 64,288.50 9,643
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Detail Quantity Unit Rate Subtotal $ Total $
Exterior windows 236,100
Aluminum windows, dual pane, low E 187 sf 136.00 25,459
Aluminum storefront 700 sf 292.55 204,785
Adder for seismic bracing 887 sf 6.60 5,856
* 0
Exterior doors 43,897
Storefront door, 6070, w/hardware 1 set 7,321.80 7,322
Storefront door, 3070, w/hardware 3 ea 4,067.70 12,203
3070 HM frame 4 ea 283.40 1,134
3070 HM door 4 ea 439.90 1,760
VSD standard hardware 6 ea 1,012.50 6,075
Add for threshold 4 ea 82.85 331
Add for kick plate 4 ea 165.60 662
Panic hardware, single 4 ea 2,299.45 9,198
Panic hardware, double 1 set 4,697.00 4,697
Paint door & frame, single 4 ea 128.75 515
* 0
B30 Roofing 270,288
Roof coverings 253,031
Multi-ply membrane roof 9,464 sf 10.75 101,738
Sheet metal & accessories 9,464 sf 6.20 58,677
6" rigid insulation 9,464 sf 7.25 68,614
Roof walk pads 600 sf 12.40 7,440
R30 Insulation to U.S.R. 9,464 sf 1.75 16,562
* 0
Roof openings 17,257
Roof ladder 1 ea 2,642.35 2,642
Roof ladder cage 1 ea 2,565.95 2,566
Roof hatch / scuttle 1 ea 2,723.45 2,723
Skylight 13 ea 717.35 9,326
* 0
C10 Interior Construction 805,508
Interior partitions 623,874
Metal stud interior furring, 4" 5,862 sf 14.45 84,699
Metal stud interior furring, 6" 273 sf 14.45 3,951
Metal stud interior partition, 6" 8,579 sf 16.25 139,403
Tyvek fluid applied water barrier 5,364 sf 4.75 25,479
5/8" Type WR dywl, intr on xtr wall 5,364 sf 7.45 39,962
Drywall on metal studs, both sides 17,157 sf 14.10 241,917
Drywall on metal studs, one side 4,903 sf 7.05 34,565
Type 'X' glass mat moisture resistant dywl 644 sf 7.45 4,796
Glass mat water-resistance tile backing board 498 syd 12.40 6,175
Insulation, interior walls, R13 8,579 sf 2.10 18,015
Insulation, ceilings, R30 8,006 sf 2.00 16,012
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Detail Quantity Unit Rate Subtotal $ Total $
Blocking and backing, ceiling 8,006 sf 0.30 2,402
Blocking and backing, walls 14,440 sf 0.45 6,498
* 0
Interior glazing 35,652
Glass sliding partition 14 lf 319.30 4,470
Aluminum storefront 247 sf 119.50 29,550
Aluminum windows, dual pane, low E 0 sf 91.35 0
Adder for seismic bracing 247 sf 6.60 1,632
* 0
Interior doors, frames, hardware 79,876
Storefront, 6070, aluminum & glass 1 set 6,170.65 6,171
Storefront, 6081, aluminum & glass 2 set 6,170.65 12,341
Retractable glass door, aluminum 1 set 6,817.40 6,817
Sliding pocket door, ctr opening, 9'-6" wide 1 set 3,408.70 3,409
3070 HM frame 17 ea 343.90 5,846
6070 HM frame 3 ea 464.90 1,395
3070 HM door 17 ea 533.80 9,075
6070 HM door, set 3 ea 1,067.60 3,203
Standard VSD hardware 25 ea 906.25 22,656
Add for transom lite 1 ea 197.90 198
Add for kick plate 10 ea 165.60 1,656
Paint door & frame, single 17 ea 281.25 4,781
Paint door & frame, double 3 set 500.00 1,500
Paint sliding pocket door & frame 1 ea 828.15 828
* 0
Fittings 66,106
Signage, building 1 allow 5,150.00 5,150
Signage, interior, code 37 ea 206.00 7,622
Signage, exterior, code 4 ea 360.50 1,442
Toilet partition, ADA, floor mtd. 2 ea 1,729.65 3,459
Toilet partition, standard, floor mtd. 4 ea 1,383.75 5,535
Urinal partition 1 ea 610.95 611
Grab bar, set 4 ea 215.15 861
Toilet paper dispenser, surface mount, single 5 ea 56.75 284
Toilet paper dispenser, surface mount, double 2 ea 93.55 187
Toilet paper dispenser, recessed, single 4 ea 93.55 374
Seat cover dispenser, surface mount 8 ea 201.30 1,610
Seat cover dispenser, recessed 2 ea 201.30 403
Sanitary napkin disposal, surface 5 ea 360.10 1,801
Sanitary napkin disposal, recessed 3 ea 360.10 1,080
Liquid soap dispenser, surface mounted 7 ea 110.65 775
Utility shelf & mop holder 1 ea 142.70 143
Mirror, 18" x 30" w/shelf 6 ea 209.65 1,258
Install accessories 46 ea 48.30 2,222
Electric hand dryer 4 ea 2,279.55 9,118
Fire extinguisher 8 ea 276.35 2,211
Fire extinguisher semi-recessed cabinet, stainless 6 ea 589.25 3,536
White board 128 sf 17.30 2,214
Tackable wall panel 64 sf 20.80 1,331
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Detail Quantity Unit Rate Subtotal $ Total $
Lockers, 12 x 12 x 24, 3 tier 24 ea 402.50 9,660
Corner guards 25 ea 128.75 3,219
* 0
C30 Interior Finishes 355,454
Wall finishes 129,533
Painted gypsum board 26,722 sf 1.15 30,731
Fiberglass reinforced plastic (FRP) 589 sf 12.40 7,300
Ceramic tile 4,034 sf 21.95 88,538
Acoustical wall panels (allowance) 116 sf 23.20 2,691
Acoustical wall panel furring (hat channel) 116 lf 2.35 273
* 0
Floor finishes 67,557
Carpet 3,526 sf 4.95 17,454
Ceramic tile 1,348 sf 21.85 29,454
Ceramic tile base 358 lf 21.75 7,795
Sealed concrete 1,294 sf 1.15 1,488
Sealed & polished concrete 1,900 sf 3.10 5,890
Rubber topset base, 4" 1,404 lf 3.90 5,476
* 0
Ceiling finishes 158,364
Suspended 2x4 ACT 5,381 sf 9.40 50,581
Suspended 2x2 ACT 132 sf 9.40 1,241
Design Flex, Allowance 400 sf 66.95 26,780
Gypsum soffitt, framed 885 sf 17.40 15,399
Gypsum soffitt face, framed 1,530 sf 17.40 26,620
Gypsum hardlid, framed, 5/8" 560 sf 17.40 9,744
Gypsum hardlid, framed, Type X, 5/8" 1,410 sf 18.25 25,733
Paint gypsum board ceiling 1,970 sf 1.15 2,266
* 0
D20 Plumbing 248,343
Plumbing fixtures 87,248
Water heater, unscheduled 1 aw 10,200.00 10,200
HW circulating pump, 1 hp 2 ea 1,213.80 2,428
Expansion tank, 19 gallon 2 ea 605.90 1,212
Specialties (wha, rfbp, etc.) 1 ea 8,343.60 8,344
Sanitary Fixtures
Water closet, floor, flush valve 8 ea 872.10 6,977
Urinal, flush valve 2 ea 811.95 1,624
Lavatory, counter, faucet 4 ea 968.00 3,872
Lavatory, wall, faucet 2 ea 968.00 1,936
Sink, counter, faucet, double-basin 1 ea 1,129.15 1,129
Sink, wall, faucet - laundry 1 ea 819.10 819
Shower, valve, head 6 ea 902.70 5,416
Service sink, floor 1 ea 976.15 976
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Detail Quantity Unit Rate Subtotal $ Total $
Drinking fountain, dual 1 ea 2,692.80 2,693
Floor drain 10 ea 205.05 2,051
Floor sink 1 ea 562.05 562
Hose bibb, interior 5 ea 191.80 959
Wall hydrant 4 ea 473.30 1,893
Rough-ins
Local rough-in per fixture 26 ea 931.30 24,214
Local rough-in, washer box 1 ea 803.80 804
Rough-in at floor sink or floor drain 11 ea 383.55 4,219
Adds
Add for sensor flush valve 10 ea 281.55 2,816
Add for sensor flush faucet 6 ea 266.25 1,598
Garbage disposal 1 ea 505.95 506
* 0
Domestic water distribution 33,602
Cold
3/4" pipe, cu type L 450 lf 23.10 10,395
1" pipe, cu type L 25 lf 28.30 708
1-1/4" pipe, cu type L 50 lf 34.80 1,740
1-1/2" pipe, cu type L 100 lf 40.60 4,060
2" pipe, cu type L 25 lf 54.40 1,360
2-1/2" pipe, cu type L, in bldg 25 lf 67.45 1,686
Hot
3/4" pipe, cu type L 300 lf 28.30 8,490
1" pipe, cu type L 15 lf 34.80 522
1-1/4" pipe, cu type L 25 lf 40.60 1,015
1-1/2" pipe, cu type L 50 lf 7.75 388
Pipe insulation, 3/4" pipe 300 lf 8.05 2,415
Pipe insulation, 1" pipe 15 lf 9.90 149
Pipe insulation, 1-1/4" pipe 25 lf 10.05 251
Pipe insulation, 1-1/2" pipe 50 lf 8.45 423
* 0
Sanitary waste 39,827
Waste / Vent
2" pipe, ci, no-hub, below grade 290 lf 22.55 6,540
3" pipe, ci, no-hub, below grade 50 sf 25.50 1,275
4" pipe, ci, no-hub, below grade 160 lf 29.60 4,736
Trench excavate, backfill, compact 240 lf 37.45 8,988
2" pipe, ci, no-hub, in bldg 325 lf 38.60 12,545
3" pipe, ci, no-hub, in bldg 25 lf 42.85 1,071
4" pipe, ci, no-hub, in bldg 10 sf 48.90 489
4" clean out, floor type 2 lf 350.90 702
4" clean out, wall type 8 lf 187.70 1,502
2" vent through roof 4 lf 299.90 1,200
4" vent through roof 2 lf 389.65 779
* 0
Rain water drainage 19,564
Roof receptor, 3" 2 ea 301.95 604
Roof drain, 4" 14 ea 305.00 4,270
4" pipe, ci, no-hub, below grade 70 lf 29.60 2,072
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Detail Quantity Unit Rate Subtotal $ Total $
Trench excavate, backfill, compact 35 cy 37.45 1,311
4" pipe, ci, no-hub, in bldg 245 lf 46.15 11,307
* 0
Gas piping 20,939
2" seismic shut off valve 1 ea 3,529.20 3,529
2" pressure regulator 1 ea 2,050.20 2,050
3/4" pipe, steel sched 40, t&c 250 lf 22.85 5,713
1" pipe, steel sched 40, t&c 25 lf 26.75 669
1-1/4" pipe, steel sched 40, t&c 50 lf 31.65 1,583
1-1/2" pipe, steel sched 40, t&c 25 lf 35.40 885
2" pipe, steel sched 40, t&c 25 lf 41.95 1,049
Gas turret 8 ea 191.80 1,534
Rough-in at AC unit, 3/4" 6 ea 388.65 2,332
Rough-in at hot water heater, 1-1/4" 2 ea 797.65 1,595
* 0
Condensate piping 4,299
Trap and equipment connect 6 lf 310.10 1,861
3/4" pipe, cu type M 150 lf 16.25 2,438
* 0
Piping accessories 42,864
Access panels 15 ea 191.80 2,877
Labeling, identification, valve tags 200 ea 13.30 2,660
Seismic requirements 10 ea 383.55 3,836
Flush, chlorinization & testing 40 hr 125.50 5,020
Start-up/check-out 40 hr 131.60 5,264
Commissioning assistance 24 hr 124.45 2,987
Penetrations, sleeving and firestopping 1 ls 3,570.00 3,570
Shop-drawings / CAD / As-built plans / BIM 120 hr 138.75 16,650
* 0
D30 HVAC 419,216
96,603
Air-conditioning unit, 4 ton 3 ea 8,615.95 25,848
Air-conditioning unit, 5 ton 1 ea 10,323.45 10,323
Air-conditioning unit, 7-1/2 1 ea 15,607.05 15,607
Air-conditioning unit, 10 ton 1 ea 19,628.90 19,629
Dehumidification, premium Not anticipated
Split system, 2 ton w/refr piping 1 ea 10,200.00 10,200
Exhaust fan, 500 cfm - restroom & janitor's closet 1 ea 1,522.90 1,523
Air-Side Equipment
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Detail Quantity Unit Rate Subtotal $ Total $
Exhaust fan, 200 cfm - laundry & breakroom 2 ea 885.40 1,771
Vav box 12 ea 975.15 11,702
* 0
Distribution systems 149,330
Ductwork, galvanized steel - supply (medium pressure) 2,500 lb 12.15 30,375
Ductwork, galvanized steel - supply (low pressure) 3,000 lb 12.15 36,450
Ductwork, galvanized steel - return (ducted) 3,750 lb 12.15 45,563
Ductwork, galvanized steel - exhaust 500 lb 12.15 6,075
Duct insulation, wrap 5,550 sf 2.35 13,043
Flexible duct, insulated, various sizes 105 lf 17.05 1,790
Manual volume damper 21 ea 59.00 1,239
Ceiling diffuser 40 ea 137.70 5,508
Return grille 25 ea 130.60 3,265
Exhaust grille 6 ea 107.10 643
Sidewall grille 2 ea 162.20 324
Fire/smoke damper 4 ea 1,060.80 4,243
Louvers 8 sf 101.50 812
* 0
Controls and instrumentation 95,560
DDC Controls - air-conditioning unit 6 ea 6,966.60 41,800
DDC Controls - split-system 1 ea 2,937.60 2,938
DDC Controls - vav box 12 ea 1,938.00 23,256
DDC Controls - exhaust fan 3 ea 1,654.45 4,963
DDC Controls - front-end/programming/training 1 ls 22,603.20 22,603
* 0
Systems testing and balancing 7,060
Test / balance HVAC 40 hr 176.50 7,060
* 0
Other HVAC systems and equipment 70,663
Access panels, furnish 20 ea 103.05 2,061
Start-up and testing 40 hr 131.60 5,264
Commissioning assistance 24 hr 123.45 2,963
Rigging, hoisting and cranes 1 ls 16,749.45 16,749
Labeling, identification, valve tags 140 ea 13.90 1,946
Seismic requirements 7 ea 531.45 3,720
Penetrations, sleeving and firestopping 1 ls 3,549.60 3,550
Shop-drawings / CAD / As-built plans / BIM 248 hr 138.75 34,410
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Detail Quantity Unit Rate Subtotal $ Total $
D40 Fire Protection 60,414
Sprinklers 60,414
Wet-pipe sprinklers, office 9,177 sf 6.05 55,521
Standpipe / connection to civil 1 ls 4,892.50 4,893
* 0
D50 Electrical 481,311
Electrical service and distribution 187,277
Main switchboard, 1200 amp, 480/277v, 3ph, 4w 1 ea 56,223.55 56,224
Distribution board, 800 amp, 480/277v, 3ph, 4w 1 ea 35,392.70 35,393
Panelboard, 225 amp, 120/208v, 3ph, 4w 2 ea 2,991.95 5,984
Panelboard, 400 amp, 480/277v, 3ph, 4w 1 ea 3,394.80 3,395
Transformer, 112.5kVA, 480-120/208v, 3ph, 4w 1 ea 10,018.85 10,019
Feeder, 225 amp, emt 30 lf 117.75 3,533
Feeder, 400 amp, emt 30 lf 209.05 6,272
Feeder, 800 amp, emt 30 lf 467.05 14,012
Feeder, 1200 amp, PVC 60 lf 671.25 40,275
Transformer primary emt feeder, 112.5kVA 20 lf 93.90 1,878
Transformer secondary flex feeder, 112.5kVA 20 lf 514.60 10,292
* 0
HVAC and equipment connections 79,634
Connection ot circulating pump 1 ea 237.50 238
Connection to water founatin 1 ea 196.35 196
Connection to air condition unit 6 ea 572.05 3,432
Connection to exhaust fan 5 ea 221.15 1,106
Connection to VAV 12 ea 196.35 2,356
Connection to garbage disposal 1 lf 196.35 196
Disconnect switch, motor rated N1 13 lf 142.50 1,853
Disconnect switch, motor rated N3R 5 lf 257.30 1,287
Disconnect switch, 30/3 fused N3R 1 lf 1,031.50 1,032
Disconnect switch, 100/3 fused N3R 6 lf 1,966.70 11,800
Equipment feeder, 20 amp 665 lf 17.95 11,937
Equipment feeder, 30 amp 45 lf 19.85 893
Equipment feeder, 100 amp 720 lf 60.15 43,308
* 0
Lighting and lighting control 116,691
2' x 4' layin LED troffer 76 ea 339.00 25,764
1' x 4' surface mount LED 29 ea 249.45 7,234
Recessed downlight 23 ea 215.10 4,947
Low voltage switch 2 ea 196.10 392
Digital room controller/power pack 24 ea 277.05 6,649
Dimmer switch, low voltage 24 ea 159.75 3,834
Occupancy sensor, ceiling mounted 24 ea 317.05 7,609
Occupancy sensor, wall mounted 5 ea 269.15 1,346
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Detail Quantity Unit Rate Subtotal $ Total $
Lighting branch power, fixtures 1,920 lf 16.85 32,352
Conduit, 3/4" emt 1,975 lf 9.25 18,269
Lighting control cable 2,370 lf 3.50 8,295
* 0
Convenience Power 46,692
Duplex receptacle, 20 amp 56 ea 112.60 6,306
Double duplex receptacle, 20 amp 5 ea 149.10 746
Duplex receptacle, 20 amp GFCI 11 ea 132.00 1,452
Duplex receptacle, 20 amp flush floor 7 ea 468.00 3,276
Junction box, 120v furniture connection 3 ea 123.05 369
Branch power, 20 amp 2,050 lf 16.85 34,543
* 0
Voice and Data system 6,225
Tele/data outlet, 4 port 12 ea 156.65 1,880
Junction box, furniture connection 3 ea 132.25 397
Conduit, 1" emt 225 lf 11.05 2,486
Conduit, 2" emt 60 lf 23.20 1,392
CAT-6, 4 pair 23 AWG, CMP 48 lf 1.45 70
* 0
Fire alarm system 44,792
FA control panel 1 ea 5,752.35 5,752
FA pull station 5 ea 162.90 815
FA smoke detector 37 ea 137.00 5,069
FA speaker strobe unit, wall mount 5 ea 368.30 1,842
FA strobe unit, wall mount 15 ea 298.05 4,471
Conduit, 3/4" emt 2,170 lf 9.25 20,073
Fire alarm cable rated, 2C 2,604 lf 2.60 6,770
* 0
E10 Equipment 41,200
Institutional equipment 41,200
Kitchen equipment 1 allow 41,200.00 41,200
* 0
E20 Furnishings 56,465
Fixed furnishings 54,980
Items Not Noted Below Furnished by Owner OFOI
Base cabinets 44 lf 528.00 23,056
Wall cabinets 29 lf 440.00 12,575
Countertop, solid surface, kitchen 34 lf 182.50 6,190
Knee space, w/countertop 12 lf 138.95 1,667
Countertop, laminate 12 lf 104.00 1,248
Window shades, mechanical 724 sf 14.15 10,244
Window shades, motorized 0 sf 3.90 0
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Detail Quantity Unit Rate Subtotal $ Total $
Movable furnishings 1,485
Folding partion wall 30 lf 49.90 1,485
F10 Special Construction 160,920
Special construction systems 160,920
Photo Votalic system, allow for 21.6 kW DC 21,600 W DC 7.45 160,920
* 0
G10 Site Preparation 108,714
Site clearing 7,743
Clear site 17,100 sf 0.25 4,275
Load & haul spoils 63 cy 15.75 998
Disposal of spoils 63 cy 39.00 2,470
* 0
Site demolition and relocations 8,149
Sawcut AC 49 lf 38.30 1,877
Add for water vacuum 49 lf 19.15 938
Remove asphalt & base 980 sf 2.75 2,695
Load & haul excess soils 23 cy 26.00 602
Disposal fee 23 cy 54.05 1,252
Sawcut PCC 21 lf 38.30 785
* 0
Site earthwork 92,822
SWPPP 17,100 sf 0.25 4,275
Building
Over-ex 5'-0" below bottom of lowest footing &
5' out 461 cy 15.25 7,037
Spread & recompact native soil less SOG thickness 319 cy 8.70 2,773
Excavate for foundations 70 cy 27.50 1,933
Load & haul excess soils 213 cy 26.00 5,540
Disposal of excess soils 213 cy 42.40 9,034
Site grading, rough 11,327 sf 0.55 6,230
Site grading, finish 11,327 sf 0.80 9,062
Asphalt paving
Over-ex 1'-6" 221 cy 15.25 3,365
Spread & recompact 1'-0" native soil 139 cy 8.70 1,213
Load & haul excess soils 81 cy 26.00 2,111
Disposal of excess soils 81 cy 42.40 3,443
Site grading, rough 3,457 sf 0.55 1,901
Site grading, finish 3,457 sf 0.80 2,766
Hardscape
Over-ex 1'-6" 167 cy 15.25 2,542
Spread & recompact 1'-0" native soil 111 cy 8.70 967
Load & haul excess soils 56 cy 26.00 1,445
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Detail Quantity Unit Rate Subtotal $ Total $
Disposal of excess soils 56 cy 42.40 2,356
Site grading, rough 2,858 sf 0.55 1,572
Site grading, finish 2,858 sf 0.80 2,286
Landscape
Over-ex 1'-6" 318 cy 15.25 4,850
Spread & recompact 1'-0" native soil 212 cy 8.70 1,845
Load & haul excess soils 106 cy 26.00 2,756
Disposal of excess soils 106 cy 42.40 4,495
Site grading, rough 5,204 sf 0.55 2,862
Site grading, finish 5,204 sf 0.80 4,163
* 0
Hazardous waste remediation 0
Not Included 0.00 0
* 0
G20 Site Improvement 149,897
Vehicular paving 38,160
Grind & overlay AC 848 sf 1.30 1,103
AC, 3.5" over 4" AB
AC, 2" over 4" AB 1,746 sf 6.55 11,436
Add per 1.5" of asphaltic concrete 1,746 sf 2.70 4,714
AC, 4" over 6" AB
AC, 2" over 6" AB 1,711 sf 7.45 12,747
Add per 2" of asphaltic concrete 1,711 sf 3.60 6,160
Curb & gutter 53 lf 37.50 2,000
* 0
Pedestrian paving 37,184
4" conc #4 @ 18" ocew ovr 4" compacted subgrd 2,858 sf 11.45 32,724
Thickened edge 770 lf 5.25 4,040
Dowels 8 ea 52.50 420
* 0
Site development 17,529
CMU footing, 5'-6" w x 1'-4" d 9 cy 954.00 8,343
CMU wall 150 sf 50.65 7,611
Prep & repaint (E) bollards 15 ea 105.00 1,575
* 0
Landscaping 57,024
Soil prep 5,204 sf 7.55 39,290
Seeding, 12-lbs/1000 sf 5,204 sf 2.35 12,229
90 day maintenance 3 mo 1,835.00 5,505
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Detail Quantity Unit Rate Subtotal $ Total $
G30 Site Mechanical Utilities 175,569
Water supply, domestic 12,239
2-1/2" PVC water pipe, sch80 200 lf 33.40 6,680
1" PVC water pipe, sch80 100 lf 24.40 2,440 o elbow, 2" 4 ea 35.45 142 o elbow, 1" 1 ea 26.15 26
Shut off gate valve, 2" 1 ea 297.40 297
Valve box, gate valve 1 ea 140.45 140
Hot tap, POC to existing 1 ea 2,513.50 2,514
* 0
Water supply, fire supply 93,054
6" Class 235 DR-14 C900 PVC, incld'g trench 637 lf 73.60 46,902
Fire hydrant 1 ea 3,569.45 3,569
Fire hydrant, bury 3 vlf 1,006.45 3,019
Fire department connection, Croker 6510 or equal 1 ea 1,943.80 1,944
Gate valve 3 ea 1,530.10 4,590
Valve box 3 ea 376.15 1,128
Add for each extra foot depth 6 lf 112.60 676
Post indicator valve, 6" 1 ea 2,254.70 2,255
6" 45 elbow 8 ea 491.30 3,930
6" 90 ELL 1 ea 449.95 450
Silent wafer check valve 1 ea 796.10 796
Thrust blocks 13 ea 1,531.60 19,911
Fire line hot tap to existing 1 ea 3,884.30 3,884
* 0
Sanitary sewer 12,320
6" sewer pipe, SDR-35 50 lf 55.60 2,780
4" sewer pipe, SDR-35 125 lf 49.90 6,238
45 ELL, 6" 3 ea 64.05 192
45 ELL, 4" 4 ea 35.70 143
45 ELL, reducing 6" to 4" 1 ea 64.05 64
Sewer cleanout 4 ea 690.60 2,762
POC to existing 1 ea 141.30 141
* 0
Storm drainage 42,206
6" PVC storm drain pipe, SDR-35 342 lf 47.20 16,148
Reducing Wye, 6 6 4 7 ea 154.35 1,080
Catch basin, 12" x 12" prefab 12 ea 1,499.05 17,989
Cleanout 8 ea 690.60 5,525
POC to existing 12" line 1 ea 1,464.15 1,464
* 0
Fuel distribution 15,750
Natural gas 1 allow 15,750.00 15,750
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Training & Office Building
Component Detail Quantity Unit Rate Subtotal $ Total $
G40 Site Electrical Utilities 113,604
Electrical distribution 42,604
Power to bld'g (excludes upgrade to (E) transformers) 8,115 sf 5.25 42,604
* 0
Site lighting 50,400
Exterior lighting 12,000 sf 4.20 50,400
* 0
Site communications and security 20,600
Feed to building 1 allow 20,600.00 20,600
Valley Sanitary District
45-100 Van Buren St., Indio, CA 92201
November 1, 2021
RC Job No. 20-40101-00
Laboratory Building Details
DRAFT
Valley Sanitary District RC Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Laboratory Building Details
Areas and Control Quantities
Areas Enclosed Covered Gross*
First Floor 2,156 2,156 SF
Total Building Area 2,156 0 2,156 SF
Control Quantities Quantity Unit Ratio to Gross
Gross Floor Area 2,156 SF 1.000
Enclosed Area 2,156 SF 1.000
Valley Sanitary District RC Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Component Summary $/SF Total $
A10 Foundations 44.74 96,456
A20 Basement Construction 0.00 0
B10 Superstructure 136.07 293,373
B20 Enclosure 42.12 90,807
B30 Roofing 29.84 64,329
C10 Interior Construction 72.85 157,069
C20 Stairs 0.00 0
C30 Interior Finishes 155.27 334,764
D10 Conveying 0.00 0
D20 Plumbing 117.81 254,008
D30 HVAC 132.03 284,658
D40 Fire Protection 9.42 20,300
D50 Electrical 128.72 277,518
D51 Technology 38.22 82,409
D52 Fire Alarm 8.37 18,040
E10 Equipment 8.30 17,900
E20 Furnishings 77.98 168,128
F10 Special Construction 0.00 0
F20 Selective Building Demolition 0.00 0
G10 Site Preparation 37.53 80,917
G20 Site Improvement 14.51 31,277
G30 Site Mechanical Utilities 20.41 44,000
G40 Site Electrical Utilities 39.42 85,000
G41 Site Technology Utilities 0.00 0
G90 Off Site Construction 0.00 0
Direct Construction Cost 1,113.61 2,400,953
Gen Conditions 7.0% 77.95 168,067
Gen Contractor OH&P 4.0% 47.66 102,761
Bonds and Insurance 2.075% 25.71 55,439
Design Contingency 8.0% 101.20 218,178
Cost Escalation to Midpoint of Construction* 9.0% 122.95 265,086
Total Construction Cost $1,489.09 $3,210,483
* Cost escalation to midpoint of construction in May 1, 2023 - 18 months at 6.0 % per annum.
Laboratory Building Details
Valley Sanitary District RC Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Laboratory Building Details
Trade Summary $/SF Total $
02 Existing Conditions 7.42 15,998
03 Concrete 44.74 96,456
04 Masonry 103.17 222,428
05 Metals 119.05 256,666
06 Wood, Plastics and Composites 28.14 60,679
07 Thermal and Moisture Protection 29.90 64,474
08 Openings 30.06 64,807
09 Finishes 120.69 260,211
10 Specialties 5.14 11,077
11 Equipment 8.30 17,900
12 Furnishings 77.98 168,128
13 Special Construction 0.00 0
14 Conveying Equipment 0.00 0
21 Fire Suppression 9.42 20,300
22 Plumbing 117.81 254,008
23 Heating, Ventilating and Air Conditioning 132.03 284,658
26 Electrical 128.72 277,518
27 Technology 38.22 82,409
28 Fire Alarm 8.37 18,040
31 Earthwork 30.11 64,919
32 Exterior Improvements 14.51 31,277
33 Utilities 59.83 129,000
34 Site Technology 0.00 0
36 Off Site Construction 0.00 0
Direct Construction Cost 1,113.61 2,400,953
Gen Conditions 7.0% 77.95 168,067
Gen Contractor OH&P 4.0% 47.66 102,761
Bonds and Insurance 2.075% 25.71 55,439
Design Contingency 8.0% 101.20 218,178
Cost Escalation to Midpoint of Construction* 9.0% 122.95 265,086
Total Construction Cost $1,489.09 $3,210,483
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Laboratory Building Details
Component Detail Quantity Unit Rate Subtotal $ Total $
A10 Foundations 96,456
Standard foundations 60,981
CMU footing 187' x 4' x 2', includes trenching 57 cy 903.05 51,537
Continuous footing, 1'-0" w x 2'-0" d, interior 0 cy 954.00 0
Continuous footing, 1'-2" w x 2'-0" d 0 cy 954.00 0
CMU footing, 1'-6" w x 2'-0" d 10 cy 954.00 9,444
Continuous footing, 2'-0" w x 2'-0" d 0 cy 954.00 0
Continuous footing, 2'-6" w x 2'-0" d 0 cy 954.00 0
Continuous footing, 3'-0" w x 1'-6"' d 0 cy 954.00 0
* 0
Special foundations 0
Auger holes, 24" dia. 25' deep 0 lf 15.45 0
CIP cassions, 24" dia. 25' deep 0 lf 77.35 0
Auger holes, 30" dia. 30' deep 0 lf 17.60 0
CIP cassions, 30" dia. 30' deep 0 lf 106.50 0
Cassion cap, 24" x 24" x 18" 0 cy 1,001.70 0
* 0
Slab on grade 35,475
SOG, 6", 6" rock, memb, #4 @ 18" on center each way 0 sf 16.75 0
5" SOG, #4 @ 18" ocew, vb, 4" crushed rock, ovr 1,907 sf 15.85 30,226
Add for depressed slabs 0 lf 10.20 0
Conc curb @ janitor & restroom 0'-6" W x 0'-6" H 53 lf 23.10 1,219
Add for thickened edge 3.6 cy 1,132.00 4,030
Slab surface column blockouts 0 ea 19.90 0
Patch back at blockouts 0 ea 65.70 0
* 0
A20 Basement Construction 0
Basement excavation 0
* 0.00 0
* 0
Basement walls 0
* 0.00 0
* 0
B10 Superstructure 293,373
Walls 222,428
CMU, precision, accent 1 1,604 sf 49.70 79,719
CMU, precision, accent 2 247 sf 49.70 12,276
CMU, split face 1,868 sf 59.00 110,212
HSS4x4x1/4 0 lbs 4.05 0
HSS3-1/2x3-1/2x3/8 0 lbs 4.05 0
Connections 0 ea 875.55 0
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Laboratory Building Details
Component Detail Quantity Unit Rate Subtotal $ Total $
HSS4x4x3/8 0 lbs 4.05 0
Connections 0 ea 875.55 0
HSS5x5x1/4 0 lbs 4.05 0
Connections 0 ea 875.55 0
HSS4x4x1/4 0 lbs 4.05 0
HSS5x5x3/8 0 lbs 4.05 0
HSS6x4x3/8 0 lbs 4.05 0
HSS7x7x3/8 0 lbs 4.05 0
Miscellaneous lintels, anchors, columns, etc 10% pct 202,207.00 20,221
* 0
Roof construction 56,451
High roof
W18x50 0 lbs 2.85 0
W18x40 0 lbs 2.85 0
W18x40 c = 1-1/4" 0 lbs 3.90 0
W14x22 0 lbs 2.85 0
W12x26 0 lbs 2.85 0
W12x16 0 lbs 2.85 0
W12x14 0 lbs 2.85 0
W8x18 0 lbs 3.35 0
W8x10 0 lbs 3.35 0
HSS5x5x3/8 0 lbs 4.05 0
HSS5x4x3/8 0 lbs 4.05 0
C6x8.2 0 lbs 4.05 0
L5x3x1/4 0 lbs 5.60 0
Trusses
WT7x26.5 0 lbs 3.35 0
2L4x4x1/4 0 lbs 5.60 0
Bolts, connector plates, stiffeners, etc 0 ls 5.60 0
3/8x10x14" truss connection 0 lbs 4.45 0
3/8x10x30" truss connection 0 lbs 4.45 0
3/8x5x3" truss connection 0 lbs 4.45 0
Epic "ER2R" 2" deep acoustical roof deck, ,18 0 sf 14.80 0
Closure plate 0 lbs 0.00 0
Red-I65-24" @ 24" o.c. 1,019 lf 29.75 30,308
2x12 Red-I-joist blocking, 24" oc 489 lf 12.60 6,161
Sheathing, 5/8" 2,039 sf 9.80 19,982
W18x50 0 lbs 2.85 0
W18x40 0 lbs 2.85 0
W12x16 0 lbs 2.85 0
W12x14 0 lbs 2.85 0
W8x18 0 lbs 3.35 0
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Laboratory Building Details
Component Detail Quantity Unit Rate Subtotal $ Total $
W8x10 0 lbs 3.35 0
HSS6x6x3/8 0 lbs 4.05 0
L5x3x1/4 0 lbs 5.60 0
Verco "B deck" 1-1/2" x 18 ga 0 sf 19.00 0
Closure plate 0 lbs 0.00 0
Lightweight concrete fill cyd 300.05 0
Pump concrete, 1st 50 cyd cyd 0.00 0
Pump concrete, 50 to 150 cyd 0 cyd 0.00 0
Miscellaneous labor & material 20% pct 0.00 0
* 0
Canopy framing 14,494
W10x12, column 416 lbs 6.60 2,747
HSS8x3x1/8, beam 333 lbs 4.05 1,349
C3x5 x 5'-10" L @ 16" oc 869 lbs 3.25 2,825
Sheathing, 5/8", top & bottom 431 sf 9.80 4,228
1/4" cap plate 0 lbs 7.00 0
HSS 2x2x1/8 0 lbs 7.15 0
Perforated metal wall panel 0 sf 50.25 0
Miscellaneous clips, anchors, bolts, etc 30% pct 11,149.00 3,345
* 0
B20 Enclosure 90,807
Exterior walls 47,520
Exterior gypsum sheathing, 5/8" 0 sf 5.55 0
Weather barrier 0 sf 0.65 0
Lath & plaster, 3 coat application 0 syd 342.15 0
Tyvek fluid applied water barrier 0 sf 4.75 0
Linear metal ceiling 0 sf 26.80 0
Canopy, Tyvek, or similar, water barrier 216 sf 4.75 1,026
Type 'X' glass mat mold resistant drywall, u.s. canopy 216 sf 7.45 1,607
Frame canopy 0 sf 18.70 0
Lath & plaster, 3 coat application to u.s. of canopy 216 sf 31.95 6,892
Canopy, paint plaster & fascia 306 sf 2.35 720
Corrugated metal wall panel, canopy siding 90 sf 53.60 4,850
Canopy, paint plaster & fascia 3,809 sf 2.35 8,952
Graffiti coating on CMU 3,719 sf 5.15 19,153
Miscellaneous labor & material 10% pct 43,200.00 4,320
* 0
Exterior windows 25,248
Aluminum windows, 1" tempered, tinted, fixed 163 sf 136.00 22,154
Aluminum storefront, 1" tempered, tinted 14 sf 144.20 2,019
Adder for seismic bracing 163 sf 6.60 1,075
* 0
Exterior doors 18,039
Storefront door & frame, std. hdwr, 6070 0 set 8,885.70 0
Storefront door & frame, 3070 0 set 4,936.50 0
3070 HM frame 2 ea 343.90 688
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Laboratory Building Details
Component Detail Quantity Unit Rate Subtotal $ Total $
4070 HM frame 1 ea 362.90 363
6070 HM frame 1 ea 464.90 465
3070 HM door 2 ea 533.80 1,068
4070 HM door 1 ea 724.35 724
6070 HM door set 1 ea 533.80 534
VSD Standard hardware 5 ea 906.25 4,531
Add for 180 swing 0 ea 289.40 0
Add for opening under 4 sf 2 ea 152.70 305
Add for vision lite 1 ea 197.90 198
Add for louver 1 ea 158.80 159
Add for threshold 5 ea 82.85 414
Add for kick plate 4 ea 165.60 662
Panic hardware, single 3 ea 2,299.45 6,898
Panic hardware, double 0 set 4,697.00 0
Paint door & frame, single 3 ea 206.00 618
Paint door & frame, double 1 set 412.00 412
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Laboratory Building Details
Component Detail Quantity Unit Rate Subtotal $ Total $
B30 Roofing 64,329
Roof coverings 56,398
Single-ply membrane roof, including canopies 2,372 sf 10.75 25,499
Sheet metal & accessories 2,372 sf 3.10 7,353
90# cap sheet, parapet walls 186 sf 4.35 808
6" rigid insulation 2,372 sf 6.95 16,485
Roof walk pads 200 sf 12.40 2,480
R30 Insulation to U.S.R. 2,156 sf 1.75 3,773
* 0
Roof openings 7,931
Roof ladder 1 ea 2,642.35 2,642
Roof ladder cage 1 ea 2,565.95 2,566
Roof hatch / scuttle 1 ea 2,723.45 2,723
Skylight 0 ea 717.35 0
* 0
C10 Interior Construction 157,069
Interior partitions 121,588
Hat channel on intr of extr walls, 3/4" x 3/4" 1,550 sf 14.45 22,402
Metal stud interior furring, 4" 0 sf 0.00 0
Metal stud wall framing, 1-5/8", 16 ga., 6" 1,304 sf 16.25 21,186
5/8" Type WR dywl, intr on xtr metal wall furring 0 sf 7.55 0
5/8" dywl on hat channel & metal studs 4,056 sf 7.75 31,438
Add for 2nd layer, electrical room 355 sf 7.85 2,784
5/8" Type 'X' drywall, mold resistant 4,056 sf 8.75 35,494
5/8" impact glass matt drywall 0 sf 7.55 0
Type 'X' glass mat moisture resistant dywl 0 sf 7.55 0
Glass mat water-resistance tile backing board 0 syd 12.40 0
Insulation, walls, R13 1,304 sf 2.10 2,738
Insulation, ceilings, R19 2,156 sf 2.00 4,312
Blocking and backing, walls 1,304 sf 0.45 587
Blocking and backing, ceiling 2,156 sf 0.30 647
* 0
Interior glazing 224
Aluminum windows, 1/2", fixed 0 sf 91.35 0
Adder for seismic bracing 34 sf 6.60 224
Entrance, 3070, aluminum & glass, hidden closer 0 ea 4,067.70 0
Adder for seismic bracing 0 sf 6.60 0
* 0
Interior doors, frames, hardware 24,180
Storefront door & frame, 6070 0 set 8,885.70 0
3070 HM frame 8 ea 343.90 2,751
3670 HM frame 1 ea 347.25 347
4070 HM frame 0 ea 362.90 0
6070 HM frame 0 ea 464.90 0
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Laboratory Building Details
Component Detail Quantity Unit Rate Subtotal $ Total $
3070 HM door 8 ea 533.80 4,270
3670 HM door 1 ea 634.35 634
4070 HM door 0 ea 724.35 0
6070 HM door, set 0 ea 1,067.60 0
6070 WD door, set 0 ea 1,067.60 0
Standard VSD hardware 10 ea 906.25 9,063
Add for opening under 4 sf 0 ea 152.70 0
Add for vision lite 0 ea 197.90 0
Add for threshold 0 ea 82.85 0
Add for kick plate 4 ea 165.60 662
Add for louver 0 ea 158.80 0
Add for 180 swing 0 ea 289.40 0
Panic hardware, single 2 ea 2,299.45 4,599
Panic hardware, double 0 set 4,697.00 0
Paint door & frame, single 9 ea 206.00 1,854
Paint door & frame, double 0 set 412.00 0
* 0
Fittings 11,077
Signage, building 0 ls 2,060.00 0
Signage, interior, code 14 ea 206.00 2,884
Signage, exterior, code 5 ea 360.50 1,803
Toilet partition, ADA, floor mtd. 0 ea 1,729.65 0
Toilet partition, standard, floor mtd. 0 ea 1,383.75 0
Urinal partition 0 ea 610.95 0
Grab bar, set 1 ea 215.15 215
Toilet paper dispenser, surface mount, single 0 ea 56.75 0
Toilet paper dispenser, surface mount, double 1 ea 93.55 94
Seat cover dispenser, surface mount 1 ea 201.30 201
Sanitary napkin disposal 1 ea 360.10 360
Liquid soap dispenser, surface mounted 1 ea 110.65 111
Paper towel dispenser, & waste 0 ea 861.30 0
Utility shelf & mop holder 1 ea 142.70 143
Mirror, 18" x 30" w/shelf 1 ea 209.65 210
Coat hooks 11 ea 20.25 223
Install accessories 17 ea 48.30 821
Electric hand dryer 1 ea 2,279.55 2,280
Fire extinguisher 2 ea 276.35 553
Fire extinguisher semi-recessed cabinet, stainless 2 ea 589.25 1,179
Marker board 0 sf 17.30 0
Tackable wall panel 0 sf 20.80 0
Handrail, wall mounted 0 lf 72.60 0
Handrail, floor mounted 0 lf 138.75 0
Projection mounts, screen & projector 0 ea 4,120.00 0
Lockers, 12 x 12 x 24, 3 tier 0 ea 402.50 0
Corner guards 0 ea 128.75 0
* 0
C20 Stairs 0
Stair construction 0
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Laboratory Building Details
Component Detail Quantity Unit Rate Subtotal $ Total $
Concrete stairs on grade 0 lft 39.80 0
* 0
Stair finishes 0
Nosing 0 lf 29.70 0
Concrete sealer 0 lf 1.15 0
* 0
C30 Interior Finishes 334,764
Wall finishes 243,684
Paint gypsum board 582 sf 2.25 1,310
Paint CMU interior walls, water/lab storage, electrical 617 sf 2.25 1,387
Epoxy paint 0 sf 7.15 0
Stainless steel, .0625", #3 finish 7,098 lbs 32.40 229,964
Stainless steel delivery charge 1 ls 3,655.30 3,655
Fiberglass reinforced plastic (FRP) 594 sf 12.40 7,368
Wall protection panel 0 sf 19.90 0
Armstrong, WoodWorks channeled plank 0 sf 9.15 0
Ceramic tile 0 sf 21.95 0
Acoustical wall panels, painted 0 sf 21.70 0
Acoustical wall panel furring (hat channel) 0 sf 2.35 0
* 0
Floor finishes 44,639
Epoxy coating, troweled 1,874 sf 18.65 34,950
Epoxy coating, wall base 512 sf 18.65 9,552
Carpet 0 sf 7.95 0
Rubber flooring, 12" x 12", various colors 0 sf 11.35 0
Ceramic tile 0 sf 21.85 0
Ceramic tile base 0 lf 21.75 0
Sealed concrete, electrical room 33 sf 1.15 38
Sealed & polished concrete 0 sf 3.10 0
Rubber topset base, 4", electrical room 25 lf 3.90 99
* 0
Ceiling finishes 46,441
Suspended 2x4 ACT, washable vinyl face, small qty, each room divided 1,772 sf 25.05 44,389
Linear metal ceiling 0 sf 66.95 0
Gypsum soffitt, framed 0 sf 19.85 0
Gypsum hardlid, framed 102 sf 18.55 1,892
Gypsum hardlid, framed, GB-4 0 sf 18.15 0
Paint gypsum board ceiling 102 sf 1.15 117
Paint acoutical deck ceiling 0 sf 1.20 0
Paint open to ceiling 33 sf 1.30 43
* 0
D10 Conveying 0
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Laboratory Building Details
Component Detail Quantity Unit Rate Subtotal $ Total $
Elevators and lifts 0
Elevator, 2500# hydraulic 0 ea 144,200.00 0
Interior finish, allowance 0 ea 10,300.00 0
* 0
Escalators and moving walks 0
* 0.00 0
* 0
Other conveying systems 0
* 0.00 0
* 0
D20 Plumbing 254,008
Plumbing fixtures 89,392
General Plumbing Equipment
Water heater, gas-fired, unscheduled 1 ea 10,200.00 10,200
Water heater, electric, unscheduled 1 ea 5,100.00 5,100
HW circulating pump, 1 hp 2 ea 1,213.80 2,428
Expansion tank, 2.1 gallon 2 ea 605.90 1,212
Expansion tank, 6.4 gallon 2 ea 605.90 1,212
Water softening system Not anticipated
RO/DI system Not anticipated
Laboratory safety system, unscheduled 1 ea 15,300.00 15,300
Acid neutralization tank 1 ea 7,411.35 7,411
Specialties (wha, rfbp, etc.) 1 ea 8,343.60 8,344
Sanitary Fixtures
Water closet, floor, flush valve 1 ea 872.10 872
Lavatory, counter, faucet 1 ea 968.00 968
Sink, wall/counter, lab, ofci 6 ea 458.00 2,748
Emergency eyewash/shower 1 ea 2,560.20 2,560
Service sink, floor 1 ea 976.15 976
Drinking fountain, dual 1 ea 2,692.80 2,693
Eyewash, counter 1 ea 753.80 754
Cup sink, counter Not anticipated
DI water polisher (lab sink) Not anticipated
Floor drain 2 ea 205.05 410
Floor sink 2 ea 562.05 1,124
Hose bibb, interior 2 ea 191.80 384
Wall hydrant 2 ea 473.30 947
Trap primer valve 4 ea 339.70 1,359
Rough-ins
Local rough-in per fixture 10 ea 931.30 9,313
Local rough-in per fixture, lab 6 ea 1,591.20 9,547
Local rough-in per fixture, fume hood 1 ea 1,448.40 1,448
Local rough-in per fixture, bio-safety cabinet Future
Rough-in at floor sink or floor drain 4 ea 383.55 1,534
Adds
Add for sensor flush valve 1 ea 281.55 282
Add for sensor flush faucet 1 ea 266.25 266
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Laboratory Building Details
Component Detail Quantity Unit Rate Subtotal $ Total $
* 0
Domestic water distribution 17,648
Domestic Cold Water Piping
3/4" pipe, cu type L 150 lf 23.10 3,465
1" pipe, cu type L 10 lf 28.30 283
1-1/4" pipe, cu type L 25 lf 34.80 870
1-1/2" pipe, cu type L 25 lf 40.60 1,015
2" pipe, cu type L 25 lf 54.40 1,360
2-1/2" pipe, cu type L, in bldg 50 lf 67.45 3,373
Domestic Hot Water Piping
3/4" pipe, cu type L 100 lf 23.10 2,310
1" pipe, cu type L 15 lf 28.30 425
1-1/4" pipe, cu type L 25 lf 34.80 870
1-1/2" pipe, cu type L 50 lf 40.60 2,030
Pipe insulation, 3/4" pipe 100 lf 7.75 775
Pipe insulation, 1" pipe 15 lf 8.05 121
Pipe insulation, 1-1/4" pipe 25 lf 9.90 248
Pipe insulation, 1-1/2" pipe 50 lf 10.05 503
Purified water Not anticipated
* 0
Waste / Vent 15,721
2" pipe, ci, no-hub, below grade 100 lf 22.55 2,255
3" pipe, ci, no-hub, below grade 15 lf 25.50 383
4" pipe, ci, no-hub, below grade 60 lf 29.60 1,776
Trench excavate, backfill, compact 165 cy 37.45 6,179
2" pipe, ci, no-hub, in bldg 50 lf 38.60 1,930
3" pipe, ci, no-hub, in bldg 10 lf 42.85 429
4" pipe, ci, no-hub, in bldg 10 lf 48.90 489
4" clean out, floor type 1 ea 350.90 351
4" clean out, wall type 5 ea 187.70 939
2" vent through roof 2 ea 299.90 600
4" vent through roof 1 ea 389.65 390
* 0
Lab Waste/Vent 22,106
2" pipe, PP sch 40, below ground 125 lf 31.85 3,981
3" pipe, PP sch 40, below ground 10 lf 38.60 386
4" pipe, PP sch 40, below ground 65 lf 52.55 3,416
Trench excavate, backfill, compact 95 cy 37.45 3,558
2" pipe, PP sch 40, in building 150 lf 51.35 7,703
3" pipe, PP sch 40, in building 10 lf 65.20 652
4" pipe, PP sch 40, in building 15 lf 85.10 1,277
4" PP floor clean out 1 ea 675.25 675
4" vent through roof, lab 1 ea 458.00 458
* 0
Industrial Water
Industrial Cold 10,616
3/4" pipe, cu type L 100 lf 23.10 2,310
1" pipe, cu type L 50 lf 28.30 1,415
1-1/4" pipe, cu type L 25 lf 34.80 870
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Laboratory Building Details
Component Detail Quantity Unit Rate Subtotal $ Total $
Industrial Hot
3/4" pipe, cu type L 100 lf 23.10 2,310
1" pipe, cu type L 50 lf 28.30 1,415
1-1/4" pipe, cu type L 25 lf 34.80 870
Pipe insulation, 3/4" pipe 100 lf 7.75 775
Pipe insulation, 1" pipe 50 lf 8.05 403
Pipe insulation, 1-1/4" pipe 25 lf 9.90 248
* 0
Lab & natural gas 47,124
DI water generator, "Centra", ofci 1 ea 2,262.40 2,262
3/4" pipe, stainless steel 125 lf 34.30 4,288
1" pipe, stainless steel 50 lf 40.10 2,005
Vacuum pump, ofci 2 ea 10,200.00 20,400
Compressed Air Not anticipated
Nitrogen Not anticipated
Natural Gas
2" seismic shut off valve 1 ea 3,529.20 3,529
2" pressure regulator 1 ea 2,050.20 2,050
3/4" pipe, steel sched 40, t&c 150 lf 22.85 3,428
1" pipe, steel sched 40, t&c 25 lf 26.75 669
1-1/4" pipe, steel sched 40, t&c 50 lf 31.65 1,583
1-1/2" pipe, steel sched 40, t&c 25 lf 35.40 885
2" pipe, steel sched 40, t&c 50 lf 41.95 2,098
Gas turret 8 ea 191.80 1,534
Rough-in at AC unit, 1-1/4" 1 ea 797.65 798
Rough-in at hot water heater, 1-1/4" 2 ea 797.65 1,595
* 0
Roof Drainage 7,104
Roof receptor, 3" 1 ea 301.95 302
Roof drain, 4" 4 ea 305.00 1,220
4" pipe, ci, no-hub, below grade 20 lf 29.60 592
Trench excavate, backfill, compact 10 cy 37.45 375
4" pipe, ci, no-hub, in bldg 100 lf 46.15 4,615
* 0
Condensate Drainage 1,433
Trap and equipment connect 2 ea 310.10 620
3/4" pipe, cu type M 50 lf 16.25 813
* 0
Miscellaneous Plumbing 42,864
Access panels 15 ea 191.80 2,877
Labeling, identification, valve tags 200 ea 13.30 2,660
Seismic requirements 10 ea 383.55 3,836
Flush, chlorinization & testing 40 hr 125.50 5,020
Start-up/check-out 40 hr 131.60 5,264
Commissioning assistance 24 hr 124.45 2,987
Penetrations, sleeving and firestopping 1 ls 3,570.00 3,570
Shop-drawings / CAD / As-built plans / BIM 120 hr 138.75 16,650
* 0 jrivera Rectangle jrivera Text Box $28,955
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Laboratory Building Details
Component Detail Quantity Unit Rate Subtotal $ Total $
D30 HVAC 284,658
Air-Side Equipment 104,103
Air-conditioning unit, 10 ton, evaporative (lab) 1 aw 51,000.00 51,000
Hepa filtration, ac unit 4,000 cfm 0.55 2,200
Dehumidification, premium Not anticipated
Split system, 2 ton w/refr piping 1 ea 10,200.00 10,200
Exhaust fan, 100 cfm - restroom & janitor's closet 1 ea 648.75 649
Exhaust fan, 500 cfm - hood 1 ea 2,182.80 2,183
Exhaust fan, 250 cfm - lab (fume hood) 2 ea 2,784.60 5,569
Vav box 8 ea 975.15 7,801
Venturi valve 2 ea 4,732.80 9,466
Exhaust hood 1 ea 10,200.00 10,200
Fume hood, ofci 2 ea 2,417.40 4,835
* 0
Air Distribution 62,840
Ductwork, galvanized steel - supply (medium pressure) 850 lb 12.15 10,328
Ductwork, galvanized steel - supply (low pressure) 1,100 lb 12.15 13,365
Ductwork, galvanized steel - return (ducted) 1,300 lb 12.15 15,795
Ductwork, galvanized steel - exhaust 300 lb 12.15 3,645
Ductwork, stainless steel - hood exhaust 250 lb 13.90 3,475
Ductwork, stainless steel, welded - lab exhaust 100 lb 22.05 2,205
Duct insulation, wrap 1,950 sf 2.35 4,583
Flexible duct, insulated, various sizes 125 lf 17.05 2,131
Manual volume damper 25 ea 59.00 1,475
Ceiling diffuser 12 ea 137.70 1,652
Return grille 9 ea 130.60 1,175
Exhaust grille 3 ea 107.10 321
Sidewall grille 1 ea 162.20 162
Fire/smoke damper 2 ea 1,060.80 2,122
Louvers 4 sf 101.50 406
* 0
HVAC Controls 69,695
DDC Controls - air-conditioning unit 1 ea 23,460.00 23,460
DDC Controls - split-system 1 ea 2,937.60 2,938
DDC Controls - vav box 8 ea 1,938.00 15,504
DDC Controls - venturi valve 2 ea 1,764.60 3,529
DDC Controls - exhaust fan 4 ea 1,654.45 6,618
DDC Controls - "Aircuity" system Not anticipated
DDC Controls - metering (cw, hw, icw, ihw, ng, mu) Not anticipated
DDC Controls - front-end/programming/training 1 ls 17,646.00 17,646
* 0
Miscellaneous 48,020
Access panels, furnish 10 ea 103.05 1,031
Test / balance HVAC 40 hr 176.50 7,060
Valley Sanitary District SGH Job No. 20-40101-00
45-100 Van Buren St., Indio, CA 92201
Laboratory Building Details
Component Detail Quantity Unit Rate Subtotal $ Total $
Start-up and testing 28 hr 131.60 3,685
Commissioning assistance 24 hr 123.45 2,963
Rigging, hoisting and cranes 1 ls 9,200.40 9,200
Labeling, identification, valve tags 110 ea 13.90 1,529
Seismic requirements 6 ea 531.45 3,189
Penetrations, sleeving and firestopping 1 ls 2,713.20 2,713
Shop-drawings / CAD / As-built plans / BIM 120 hr 138.75 16,650
* 0
D40 Fire Protection 20,300
Sprinklers 13,475
Wet-pipe sprinklers, laboratory 2,156 sf 6.25 13,475
* 0
Standpipes 4,845
Standpipe / connection to civil 1 ls 4,845.00 4,845
FDC 0 ea 0.00 0
Alarm & valve riser, 6" 0 ea 49.95 0
* 0
Other fire protection systems 1,980
Canopy 300 sf 6.60 1,980
Pre-action system, premium Not anticipated
* 0
D50 Electrical 377,967
Electrical service and distribution 187,277 Main switchboard,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .