This document is a Scope of Work (SOW) for the Valley Sanitary District (VSD) Campus Master Plan Analysis. The project involves developing three alternative master plan options for the VSD campus, which includes a Water Reclamation Facility and administrative buildings. The alternatives range from constructing new lab and training facilities according to preliminary designs to a complete campus rebuild. The consultant will conduct a kick-off meeting, develop master plan alternatives, hold a workshop to review options, provide renderings, and prepare budget-level cost estimates. The project timeline is expedited, with key milestones including board approval on December 9, 2025, a notice to proceed on December 16, 2025, and a final technical memorandum due by February 16, 2026.

The scope of work is a desktop master plan that does not include geotechnical or hazardous material analyses. The existing campus buildings were constructed in the 1960s and 1970s and renovated in 2011, with the assumption that hazardous materials are present. The project requires developing alternatives that include a relocated certified laboratory, new office and training building, expanded parking, additional solar panel areas, and improved campus security. VSD will provide cost estimate templates and previous project costs, which the consultant will escalate to present-day values. The alternatives include renovating existing facilities to current building codes and potentially demolishing all existing structures to create a state-of-the-art campus.

View the file

Other files

File Type Posted
VSD_Campus_Master_Plan_Analysis.pdf PDF
VSD_Campus_Master_Plan_Analysis.pdf PDF
VSD_Campus_Master_Plan_Analysis.pdf PDF
VSD_Campus_Master_Plan_Analysis_RFP.pdf PDF
VSD_Campus_Master_Plan_Analysis_RFP.pdf PDF
VSD_Campus_Master_Plan_Analysis_RFP.pdf PDF
Attachment_D_VSD_Site_CAD_File_-_Work_in_Progress.dwg DWG drawing
Attachment_H_Leighton_Geotechnical_Report_-_11-20-2020.pdf PDF
Attachment_K_Lab_Bldg_Schematic_Design_Package_-_4-8-21.pdf PDF
Attachment_L_Lab_Furnishing_and_Equipment_Plan_-_9-2-21.pdf PDF
Attachment_M_Training_and_Lab_Building_100%_Cost_Estimate_-_11-01-2021.pdf PDF
Attachment_F_Geotech_Report_-_Lab_Building_2021.pdf PDF
Attachment_I_50%_Design_Plans_-_11-19-21.pdf PDF
Attachment_M_Training_and_Lab_Building_100%_Cost_Estimate_-_11-01-2021.pdf PDF
Attachment_E_Earth_Systems_Geotechnical_Report_Jan_2022.pdf PDF
Attachment_M_Training_and_Lab_Building_100%_Cost_Estimate_-_11-01-2021.pdf PDF
Attachment_C_VSD_WRF_Master_Plan_2025_-_Draft.pdf PDF
Attachment_A_Scope_of_Work.pdf PDF
Attachment_D_VSD_Site_CAD_File_-_Work_in_Progress.dwg DWG drawing
Attachment_A_Scope_of_Work.pdf PDF
Attachment_F_Geotech_Report_-_Lab_Building_2021.pdf PDF
Attachment_I_50%_Design_Plans_-_11-19-21.pdf PDF
Attachment_K_Lab_Bldg_Schematic_Design_Package_-_4-8-21.pdf PDF
Attachment_I_50%_Design_Plans_-_11-19-21.pdf PDF
Attachment_J_Lab_Bldg_Schematic_Design_Cost_Estimate_-_4-19-21.pdf PDF
Attachment_C_VSD_WRF_Master_Plan_2025_-_Draft.pdf PDF
Attachment_E_Earth_Systems_Geotechnical_Report_Jan_2022.pdf PDF
Attachment_K_Lab_Bldg_Schematic_Design_Package_-_4-8-21.pdf PDF
Attachment_C_VSD_WRF_Master_Plan_2025_-_Draft.pdf PDF
Attachment_G_Geotech_Report_for_Lystek_2024-12-11.pdf PDF
Attachment_H_Leighton_Geotechnical_Report_-_11-20-2020.pdf PDF
Attachment_J_Lab_Bldg_Schematic_Design_Cost_Estimate_-_4-19-21.pdf PDF
Attachment_L_Lab_Furnishing_and_Equipment_Plan_-_9-2-21.pdf PDF
Attachment_E_Earth_Systems_Geotechnical_Report_Jan_2022.pdf PDF
Attachment_F_Geotech_Report_-_Lab_Building_2021.pdf PDF
Attachment_G_Geotech_Report_for_Lystek_2024-12-11.pdf PDF
VSD_SAMPLE_CONTRACT.pdf PDF
Attachment_G_Geotech_Report_for_Lystek_2024-12-11.pdf PDF
Attachment_H_Leighton_Geotechnical_Report_-_11-20-2020.pdf PDF
Attachment_J_Lab_Bldg_Schematic_Design_Cost_Estimate_-_4-19-21.pdf PDF
Attachment_L_Lab_Furnishing_and_Equipment_Plan_-_9-2-21.pdf PDF
VSD_SAMPLE_CONTRACT.pdf PDF
Attachment_D_VSD_Site_CAD_File_-_Work_in_Progress.dwg DWG drawing
VSD_SAMPLE_CONTRACT.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT A

4. Scope of Work

4.1 Work VSD Campus Master Plan Analysis

4.1.1 Background and Project Purpose

Valley Sanitary District (VSD) has a unique campus which includes both the Water Reclamation Facility (WRF) and the VSD administration, maintenance, and other ancillary buildings. VSD has recently completed a preliminary design for two building projects: the relocation of the Certified Laboratory and a new Office and Training Building. However, as part of the next phase VSD is requesting an expedited process to prepare several overall Campus Master Plan alternatives which emphasize an overall plan to site the following components and/or criteria:

• Relocated Certified Laboratory

• New Office and Training Building

• Expanded Parking Lot which doubles the capacity (all must be covered)

• Additional Solar Panel Areas

• Maintain security of WRF facilities with public access limited to gate access

• Increased ingress and egress

VSD will have a Kick off meeting to provide input prior to the development of the Campus Master Plan alternatives and once several alternatives are developed then conduct a workshop. At the workshop, the CONSULTANT shall present renderings and preliminary cost estimates of all three alternatives

The assumed alternatives are as follows:

1. Alternative 1 - Construct the new Lab and Ops/training facility as per the preliminary designs

2. Alternative 2 - Construct the new Lab and Ops/training facility including upgrades and renovations to the existing buildings (see Assumptions/Exclusions section)

3. Alternative 3 - Entire new VSD campus this would include the complete demolition of all existing buildings and constructing a state-of-the-art campus that includes all new facilities for Administration, Board Room, Operations, Maintenance, Collections, Laboratory, Engineering, Development, Locker rooms with showers, etc. (Note, the existing Certified Laboratory and Operations and Training facility’s preliminary drawings will be used as the baseline for both of those departments).

4.1.2 Reference Documents

• The District has completed preliminary design for two buildings included in the District Campus.

These include the relocation of the Certified Laboratory and a new Office and Training Building

• VSD has the CADD files which will be made available to the selected CONSULTANT to layout an overall siting plan for the entire campus.

• VSD has CADD files for the proposed building footprints for the relocation of the Certified Laboratory and a new Office and Training Building

• A tentative plan for the expansion of the proposed project titled, “Additional Parking for Customers and Staff”

• Stantec prepared a Water Reclamation Facility Master Plan, dated September 2025 as part of the “VALLEY SANITARY DISTRICT WATER RECLAMATION FACILITY MASTER PLAN”. Figure 2-1 – Site Phasing Layout shows the entire VSD Campus and shows various future phases.

4.1.3 Proposed Scope of Services

The following task list is a general preliminary Scope of Services to communicate the District's expectations. Proposers should identify any additional services required to meet the District's expectations, provide a price, and document the reasons for the additional services. It is at the District's discretion to decide which services are ultimately included in the final Scope of Services.

• Review existing reports and drawings.

• Develop three alternatives for a VSD Campus wide master plan

• Conduct one workshop to review the VSD Campus Master Plan alternatives

• Provide renderings for the selected VSD Campus Master Plan alternative

• Provide budget level cost estimates for the selected Campus Master Plan and for standalone building alternatives (such as the Office and Training Building & Certified Laboratory Building)

• Prepare both a DRAFT and FINAL Technical memorandum summarizing the findings of the Campus Master Plan analysis

• Project study shall begin to address environmental compliance regulations (both NEPA & CEQA requirements).

Assumptions and Exclusions

The following are clarifications to the scope of work and exclusions:

• This scope does not include geotechnical reconnaissance and/or hazardous material analyses.

This is a desktop master plan.

• The building footprints for the Certified Laboratory and the Office and Training Building have been established and these footprints are to be utilized in the various alternatives of the Campus Master Plan

• Project study will not address environmental compliance regulations (both NEPA & CEQA requirements).

• The Administration Building, Laboratory Building, Operations Building, and the shop buildings were built in the 1960’s and 1970’s and renovated in 2011. For the purposes of cost, it shall be assumed that hazardous materials are present.

• VSD will provide the cost estimate template with the costs from the previous building projects and escalate these costs to present day value for the cost estimate

• VSD will provide the estimated costs prepared for the previous building projects. The CONSULTANT shall escalate these costs to present day value for the cost estimate.

Alternative 2 for the existing building renovations should be based on plans to bring the facilities to current building codes. This also includes general upgrades to existing office spaces including new men's and women's restroom facilities and converting the existing lab into a usable office space.

4.1.4 Schedule

Time is of the essence. The CONSULTANT shall ensure that the budget-level cost estimate is completed by February 16, 2026, per the following timeline. Since this project is an expedited contract, the following schedule must be met and/or exceeded:

1. Board Approval December 9, 2025

2. Notice of Award December 10, 2025

3. Notice to Proceed December 16, 2025

4. Kick off Meeting December 17, 2025

5. Workshop to Review Alternatives January 12, 2026

6. DRAFT TM for Campus Master Plan January 30, 2026

7. FINAL TM for Campus Master Plan February 16, 2026

The awarded CONSULTANT shall be prepared to provide all required insurance certificates and executed contract documents immediately following the Notice of Award to maintain the schedule. CONSULTANT shall provide an example Certificate of Insurance showing that it currently can meet all insurance requirements.