The document is a Past Performance Information Form (PPIF), a standardized template for contractors to document their previous contract experience when bidding on federal contracts. The form requires detailed information about past contracts, including contract specifics (customer, contract number, type, performance period, pricing), description of work performed, self-assessment of performance, contract status, and primary customer points of contact. The form is designed to help evaluate a contractor's historical performance and capability to execute future work, with specific sections for describing problems encountered, corrective actions taken, and technical issues relevant to the current solicitation.
The PPIF is associated with a specific federal contract opportunity (Solicitation Number FA302925R0005) for an electrical distribution resilience project at Vance AFB in Enid, Oklahoma. The project is a 100% Small Business Set-Aside with a project magnitude between $500,000 and $1,000,000, involving installation of electrical distribution equipment including a pad mounted distribution switch, sectionalizing cabinets, duct bank construction, and medium voltage cable installation. Key dates include a site visit on July 9, 2025, and a Q&A due date of July 16, 2025. The project is under the Department of the Air Force, with NAICS code 238210 and a size standard of $19 Million.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment FA302925R00050001 SF 30.pdf | ||
| Attachment 5_Site Visit Sign-in Sheet.pdf | ||
| Attachment 6_Question and Answers.pdf | ||
| Attachment L2_Bond Checklist.pdf | ||
| Attachment L7_Consent Form.pdf | ||
| Section M - Evaluation Factors for Award.pdf | ||
| Attachment 1_Specifications.pdf | ||
| Attachment L3_Financial Responsibility Worksheet.pdf | ||
| Solicitation - FA302925R0005.pdf | ||
| Attachment 2_Drawings.pdf | ||
| Section L- Instruction Conditions and Notices to Offerors.pdf | ||
| Attachment 3_Vance AFB Map.pdf | ||
| Attachment 4_Wage Determination OK20250038.pdf | ||
| Attachment L1_Bid Form.pdf | ||
| Attachment L5_Questionnaire Cover Letter.pdf | ||
| Attachment L6_Past Performance Questionnaire.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment L4 - PAST
PERFORMANCE INFORMATION
FORM (PPIF)
Past Performance Reference No.
Provide the information requested in this form for each one of the present or past contracts you have identified. Provide a separate completed form for each contract identified. Attach a separate sheet if additional space is needed.
A. Current Offeror (Company/Division):
CAGE Code:
UEI Number:
(NOTE: If the company or division performing this past or present effort is different from the current Offeror, note this fact below. Refer to the "Organizational Structure Change History" you provided as part of your Past Performance Volume).
B. Project Title:
C. Contract Specifics:
1. Complete Name of Customer:
2. Customer Address and Telephone #:
3. Contract Number or Citation:
4. Type of Contract:
5. Period of Performance:
6. Initial Contract Price: $
7. Final Amount Invoiced/Amount Invoiced to Date: $
8. Original completion date:
9. Current scheduled completion date:
10. Estimated completion date:
OR Estimated Percent Completion:
11. Number of contract modifications:
12. Enter primary cause for contract changes below:
D. Description of Work Prime or Subcontractor.
E. Describe how the work under this contract relates to the experience cited by the Offeror in its present proposal.
F. Self-Assessment of past performance record. Provide information of any problems encountered and your corrective actions.
G. Address below any technical (or other) issues about this contract considered particularly relevant to the current solicitation.
H. Summarize contract issues relative to the number and severity of quality deficiencies recorded/contract discrepancy reports issued, cure notices, show cause letters, termination for default or cause, disputes, claims, latent defects; and corrective actions taken for this contract reference.
I. Current Status of Contract (Select as applicable):
[ ] Work Continuing – On Schedule
[ ] Work Continuing – Behind Schedule
[ ] Work Completed – Litigation Pending or Underway
[ ] Work Completed – No Further Action Pending or Underway
[ ] Work Completed – Routine Administrative Action Pending or Underway
[ ] Request For Equitable Adjustment(s) Negotiations Pending or Underway
[ ] Claims Negotiations Pending or Underway
[ ] Terminated for Convenience
[ ] Terminated for Default
[ ] Other (Explain)
J. Primary customer points of contact. (For Government contracts/orders, provide current information on all three individuals. For commercial contracts, provide points of contact filling these same roles.)
1. Program Manager and/or Site Manager
2. Procurement Contracting Officer
3. Administrative Contracting Officer
Name:
Office:
Address:
Telephone:
FAX #:
E-Mail:
Additionally, for those efforts where the offeror is cognizant of unfavorable and/or marginal past performance ratings/reports previously assessed by customers or clients, but feel that significant progress has been made but not yet credited or formally documented, provide the program name, contract number, customer location and a narrative explaining "fixes" made to date, or any other information regarding the unfavorable/marginal assessment.
It is not presumed that the offeror's performance has been perfect. Rather, the proposal should contain evidence of the offeror's ability to isolate the root causes of problems and should describe programs or actions taken to resolve those causes. Demonstrated corrective actions (not just planned or promised), and the overall work record will be considered. Problems not addressed by the offeror, but found by the Government during the evaluation of the information in this volume, will be assumed to still exist. Note: In the case of Contractor Performance Assessment Report System (CPARS), if your input has already been provided and the rationale/circumstances have not changed, DO NOT repeat them here.
File details come from the government source that posted it. Updated .