The document is an Asbestos and Lead Survey Report prepared by Blackburn Consulting for the State Route 99/120 Interchange Phase 1B Project in Manteca, California. The report documents a limited asbestos survey conducted by Entek Consulting Group on two westbound SR120 bridge structures located over Van Ryn Avenue and Moffat Boulevard. The survey was performed on October 16, 2023, with the primary objective of inspecting bridge components for potential asbestos-containing materials (ACM) prior to planned widening and modification work. Due to safety concerns with oncoming traffic, the inspection was limited to accessible areas of the bridges.
The survey results indicate that none of the sampled concrete materials from the bridge structures (including parapets, abutments, side rail slabs, and decks) contained asbestos above the reporting limit. Consequently, the contractor is not required to file a pre-demolition notification with the San Joaquin Valley Air Pollution Control District. However, the report recommends additional sampling of traffic striping and other coatings during a future road closure, as these areas could not be safely accessed during the initial survey. The report also notes that yellow traffic stripes may contain heavy metals like lead and chromium, potentially exceeding hazardous waste thresholds, and recommends a project-specific Lead Compliance Plan for any work impacting these materials.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT K
ASBESTOS & LEAD SURVEY REPORT
Fresno Office:
4186 W. Swift Avenue, Ste 107 Fresno, CA 93722 Auburn (530) 887‐1494
(559) 438‐8411 West Sacramento (916) 375‐8706
File No. 4283.x January 9, 2024
Mark Thomas & Company, Inc.
Mr. Gary Horton, PE 701 University Avenue, Suite 200 Sacramento, CA 95825
Subject: ASBESTOS AND LEAD SURVEY REPORT
State Route 99/120 Interchange Phase 1B Project Moffat Boulevard Overhead (Left) Widen Bent Foundation Excavations Manteca, California
Dear Mr. Horton, Blackburn Consulting (Blackburn) prepared this Asbestos and Lead Survey report for the State Route 99/120 Interchange Phase 1B Project (Project) located in Manteca, California. This report addresses the asbestos and lead assessment at the existing Moffat Boulevard Overhead Left structure and Van Ryne Overhead Left (aka Spreckles Road Undercrossing) structures. Blackburn prepared this summary in accordance with our proposal dated January 4, 2023.
Blackburn appreciates the opportunity to be part of your team. Please call if you have questions or require additional information.
Sincerely, BLACKBURN CONSULTING
Brian Carey, PG Laura Long Senior Project Geologist Environmental Project Manager
ASBESTOS AND LEAD SURVEY REPORT
State Route 99/120 Interchange Phase 1B Project, Manteca, CA ii
Table of Contents
1 INTRODUCTION
2 ASBESTOS AND LEAD SURVEY
Asbestos Containing Material
Lead Coatings
3 LIMITATIONS
Figure 1 – Vicinity Map Figure 2 – Site Plan
Appendix A ‐ Limited Asbestos Survey by Entek Consulting Group, Inc.
1 INTRODUCTION
Blackburn prepared this Asbestos and Lead Survey report for the State Route 99/120 Interchange Phase 1B Project (Project) located in Manteca, California.
This report presents the findings of the Limited Asbestos Survey (Survey) performed at the existing Moffat Boulevard Overhead Left structure and Van Ryne Overhead Left (aka Spreckles Road Undercrossing) structure. Blackburn contracted Entek Consulting (Entek) to conduct the Survey. Entek is a California Occupational Safety Health Administration (Cal/OSHA) Certified Asbestos Consultant (CAC) and State of California Department of Public Health (CDPH) Certified Lead Inspector (CLI). The Survey evaluated the presence of asbestos containing material (ACM) and lead in the bridge structures. Figure 1 is the Vicinity Map and Figure 2 is the Site Plan.
2 ASBESTOS AND LEAD SURVEY
The EPA, National Emission Standards for Hazardous Air Pollutants (NESHAP), 40 DVR Part 61 – Nov. 20, 1990, requires an owner or operator of a demolition or renovation project to “thoroughly inspect the affected facility or part of the facility where the demolition or renovation operation will occur for the presence of ACM prior to the commencement of that project”. Structures proposed for demolition or modification must be surveyed by a properly certified inspector for ACM. In addition, Cal/OSHA regulates all construction activities involving materials containing lead. These regulations are found in CCR, Title 8 (§1532.1) Lead in Construction, and require an inspection by a properly certified inspector for Lead prior to construction activities. Blackburn therefore contracted with Entek to complete the survey.
Asbestos Containing Material
Blackburn reviewed the Limited Asbestos Survey report prepared by Entek (November 15, 2023). We attach Entek’s report as Appendix A. Blackburn summarizes Entek’s results below. Refer to Entek’s report for additional regulatory requirements and a full description of their observations, conclusions and recommendations, and limitations.
Test results indicate that asbestos was not detected above the reporting limit in the materials sampled from the Moffat Boulevard Overhead Left and Van Ryne Overhead Left (aka Spreckles Road Undercrossing) structures. The contractor is not required to file a pre‐demolition notification with the San Joaquin Valley Air Pollution Control District (SJVAPCD).
Lead Coatings
Entek was scheduled to collect samples for the presence of lead from traffic striping or other coatings at the bridges. However, safety issues due to oncoming traffic prevented sample collection. We recommend sampling and testing of the traffic striping when safe to do so during a future road closure.
Moffat Boulevard Overhead (Left) Widen Bent Foundation Excavations January 9, 2024
Please notify us when the Project team plans a road closure, and we will schedule Entek to return to the site.
Yellow traffic stripes are known to contain heavy metals, such as lead and chromium, at concentrations exceeding the hazardous waste thresholds established by the California Code of Regulations and may produce toxic fumes when heated. Any disturbance of lead‐containing paint (LCP) and LCP materials is considered “lead related construction work.” Any contractor performing work which will impact the Yellow Traffic Striping must utilize properly trained personnel and comply with all Cal/OSHA regulations and requirements including a project specific Lead Compliance Plan.
In addition, Caltrans Standard Special Provision (SSP) 2018:14‐11.12, 84‐9.03B, Remove Traffic Stripes and Pavement Markings Containing Lead, requires a project specific Lead Compliance Plan for removal and disposal of traffic stripes where lead concentrations are determined to be non‐hazardous (<1,000 milligrams per kilogram total lead).
3 LIMITATIONS
Blackburn prepared this memo to transmit Entek’s Limited Asbestos Survey report. We did not perform any engineering calculations, interpretation of data, or provide any conclusions or recommendations related to presence of ACM/LCP materials. Blackburn is not a CAC or LCI. Refer to Entek’s report for state and federal regulations addressing ACM/LCP materials during construction.
Blackburn does not warranty our services or Entek’s specifications. Blackburn performed these services in accordance with generally accepted environmental engineering principles and practices currently used in Northern California.
Our scope does not include evaluation of hazardous materials other than those specified herein. This report is not a comprehensive site characterization and shall not be so construed. This report is not intended to fully characterize the site for future development.
State Route 99/120 Interchange Phase 1B Moffat Boulevard Overhead (Left) Widen Bent
Foundation Excavations
January 2024
FIGURES
Figure 1: Vicinity Map
Figure 2: Site Plan
© 2023 Microsoft Corporation © 2023 TomTom
/6
/2
.x F ig .1
V ic
M ap
_S R
-1
_A sb es to s.
dw g
Figure 1
DISTANCE, FEET
0 20000 40000 60000 80000
SCALE: 1"= 40,000'
PROJECT
LOCATION
December 2023
File No. 4283.xVICINITY MAP Asbestos and Lead Survey Moffat Blvd. Overhead (Left)
Widen Bent Foundation Excavations SP99/120 Interchange Improvements - Phase 1B
/1
3/
.x F
IG
.2
S ite
P la n_
SR
-1
_A
C M
.d w g
Figure 2
Source: SR 99 / 120 Interchange Connector, Geometric Approval Drawings, Sheet 2, Mark Thomas, CalTrans 10-SJ-99/120 dated: 02/09/2021
L E G E N D
December 2023
File No. 4283.xSITE PLAN Asbestos and Lead Survey
Moffat Boulevard Overhead (Left) Widen Bent Foundation Excavations
SR99/120 Interchange Improvements - Phase 1B
MOFFAT BLVD.
SITE PLAN
NOT TO SCALE
Distance, feet
100 200 300 400
SCALE: 1"= 200'
Moffat Boulevard and Van Ryn Avenue Bridges
State Route 99/120 Interchange Phase 1B Moffat Boulevard Overhead (Left) Widen Bent
Foundation Excavations
January 2024
APPENDIX A
Limited Asbestos Survey by Entek Consulting Group, Inc.
ENTEK
CONSULTING GROUP, INC.
4200 Rocklin Road, Suite 7, Rocklin, CA 95677 Phone (916) 632-6800 Fax (916) 632-6812 www.entekgroup.com
ASBESTOS LEAD MOLD INDOOR AIR QUALITY SILICA TRAINING SAFETY AUDITS
November 15, 2023
Ms. Laura Long Environmental Project Manager Blackburn Consulting 2491 Boatman Avenue West Sacramento, CA 95691
Re: Limited Asbestos Survey – 4283.x SR99/120 Interchange Phase 1B Project – Two
Westbound SR120 Bridge Structures over Van Ryn Avenue and Moffat Boulevard in
Dear Ms., Long:
Entek Consulting Group, Inc. (Entek) is pleased to provide the results for the limited asbestos survey of the two westbound SR120 bridge structures over Van Ryn Avenue and Moffat Boulevard in Manteca, California.
It is Entek’s understanding that both bridge structures are planned to be widened, therefore Entek was requested to conduct an asbestos and lead inspection prior to the demolition work beginning.
Entek was requested by you to conduct an asbestos and lead inspection specific to the two bridge structures for regulatory requirements. At the time of the inspection the middle of the highway/bridges was inaccessible due to safety concerns with oncoming traffic. Nick Vasquez with Balckburn Consulting was advised of the limitations and directed Entek to proceed with sampling of the accessible materials.
Therefore, Entek was limited to collecting asbestos samples from the two bridges at the accessible locations at the medium. Entek observed asphalt and coatings located in the middle of the highway/bridges that were excluded in this survey. It is recommended that additional sampling of the coatings be conducted in order to meet Title 8 1532.1. Lead regulations requirements.
This report provides results for the asbestos bulk samples collected on October 16, 2023, by Mr. Jose Hernandez who is a Cal/OSHA Certified Asbestos Consultant (CAC).
Asbestos Bulk Sampling and Results
Entek collected 14 bulk samples from the accessible areas of the two bridges mentioned in this report. The samples were submitted to Asbestech Laboratory located in Rancho Cordova, California and analyzed by Polarized Light Microscopy (PLM) with dispersion staining. Asbestech is accredited by the National Voluntary Accreditation Program (NVLAP) for this analysis. Entek relayed the following asbestos bulk lab results via email to the project team on October 17, 2023.
Suspect Materials Found NOT TO Contain Asbestos Two westbound SR120 bridge structures over Van Ryn Ave and Moffat Blvd in
Manteca, California
Sample ID#’s
Suspect Material
Asbestos Content
Location
01A-B Concrete Parapet None Detected Bridge over Moffat Boulevard
02A-B Concrete Abutment None Detected Bridge over Moffat Boulevard
03A-B Concrete Side Rail Slab None Detected Bridge over Moffat Boulevard
Ms. Laura Long ENTEK Blackburn Consulting
2 | P a g e
Suspect Materials Found NOT TO Contain Asbestos Two westbound SR120 bridge structures over Van Ryn Ave and Moffat Blvd in
Manteca, California
Sample ID#’s
Suspect Material
Asbestos Content
Location
04A-B Concrete Deck None Detected Bridge over Moffat Boulevard
05A-B Concrete Parapet None Detected Bridge over Van Ryn Avenue
06A-B Concrete Deck None Detected Bridge over Van Ryn Avenue
07A-B Concrete Abutment None Detected Bridge over Van Ryn Avenue
The surveyed materials were determined to be none detected for asbestos. Specifics pertaining to the materials sampled can be found in Appendix A of this report. All other suspect materials were inaccessible since the highway was still operational and no traffic control was made available to safely inspect the middle of the highway/bridges.
All sample numbers noted in the table above start with ECG-23-6868-
Materials commonly excluded from being suspected for containing asbestos include, but are not limited to:
unwrapped pink and yellow fiberglass insulating materials or products, foam insulation, wood, metal, plastic, or glass. All other types of building materials or coatings on the materials listed above are commonly listed as “suspect” and must be tested prior to impact by a Contractor. Work impacting these untested or newly discovered materials must cease until an investigation can be completed.
US EPA
The bridge structures included in this survey report are located in San Joaquin County. The San Joaquin Valley Air Pollution Control District (SJVAPCD) has been given authority for enforcement of the NESHAP regulations by means of their own rules (Rule 4002).
Since the materials sampled were determined to not contain asbestos, a 10-day notification to the SJVAPCD is not required prior to starting work for asbestos reasons.
Cal/OSHA
Disturbance of any ACM or ACCM could generate airborne asbestos fibers and would be regulated by Cal/OSHA. Cal/OSHA worker health and safety regulations apply during any disturbance of ACM or ACCM by a person while in the employ of another. This is true regardless of friability or quantity disturbed.
Since it has been determined the materials sampled did not contain any asbestos, a licensed asbestos contractor who is registered with Cal/OSHA will not be required for the removal and/or disturbance of the sampled materials. Although the concrete materials sampled did not contain asbestos, additional sampling will be required prior to removing and/or disturbing any other suspect material that might be associated with the two westbound SR120 bridge structures since Entek could not access the middle of the highway/bridges for safety reasons.
Ms. Laura Long ENTEK Blackburn Consulting
3 | P a g e
Limitations
This asbestos survey is limited to the accessible concrete components found on the two westbound SR120 bridge structures over Van Ryn Avenue and Moffat Boulevard in Manteca, California.
If any other suspect materials not listed as having been sampled in this or previous reports are discovered, which will be impacted during the project, those materials must be assumed to contain asbestos until properly inspected and tested for asbestos content.
Entek’s policy is to retain a full copy of these written documents for three (3) years once the file is closed.
At the end of the three (3) year period the written files will be destroyed without further notice. It is suggested copies of the file(s) are maintained as per your policy.
Entek will be providing only this electronic copy of the report and its attachments for your use. However, if you would like a hard copy of this report, a copy will be mailed upon request. Thank you for choosing Entek for your hazardous materials needs.
Sincerely, Reviewed By:
Jose Hernandez, CAC Project Manager
Richard Beall, CIH, CSP, CAC
CEO
Enclosures
APPENDIX A
ASBESTOS RELATED DOCUMENTS
� Bulk Asbestos Analysis Report From Asbestech
� Bulk Asbestos Material Analysis Request Form for Entek
� Asbestos Bulk Sample Location Drawing
ASBESTECH
11151 Sun Center Drive, Suite B Rancho Cordova, California 95670 Tel.(916) 481-8902 asbestech@sbcglobal.net
THE ANALYSIS USES POLARIZED LIGHT MICROSCOPY AND DISPERSION STAINING FOLLOWING E.P.A. METHOD 600/R-93/116. NON-FRIABLE MATERIALS WERE ANALYZED APPLYING THE SAME METHOD. THE LOWER DETECTION LIMIT IS <1 % WITH THE PROVISO THAT PLM MAY NOT DETECT FIBERS <0.25 MICRONS IN DIAMETER THAT MAY BE PRESENT IN SAMPLES SUCH AS FLOOR TILES. IN ACCORDANCE WITH TITLE 22, CCR, SECTION 66261.24(a)(2)(A),THE MCL IS 1 %. SAMPLES WERE NOT COLLECTED BY ASBESTECH. THIS REPORT MUST NOT BE REPRODUCED EXCEPT IN FULL WITHOUT THE APPROVAL OF ASBESTECH. THIS REPORT RELATES ONLY TO THE ITEMS TESTED. THIS REPORT MUST NOT BE USED TO CLAIM PRODUCT ENDORSEMENT BY N.V.L.A.P. OR ANY AGENCY OF THE U.S. GOVERNMENT. ASBESTECH ACCEPTS
TECHNICAL RESPONSIBILITY FOR THIS REPORT AND DATE OF ISSUE.
NVLAP LAB CODE 101442-0 LAB DIRECTOR: TOM CONLON ANALYST: JIM JUNGLES
Client: Job:
Entek Consulting Group, Inc. 23-6868 Blackburn 4200 Rocklin Rd., Suite 7 Bridge on Hwy. 120 Westbound Rocklin, CA 95677 37.783431,-121.196096, Manteca, Ca
BULK ASBESTOS ANALYSIS REPORT
LAB JOB # 70777 NVLAP Lab Code 101442-0 Date/Time Collected: 10/16/23 CDPH # 1153 Date Received: 10/16/23 Date Analyzed: 10/17/23
Sample No. Color/Description % Type Asbestos Other Materials
ECG-23-6868-
01A Gray concrete parapet, south parapet NONE DETECTED Granular Mins.
east side
01B Gray concrete parapet, south parapet NONE DETECTED Granular Mins.
east side
02A Gray concrete abutment, east abutment NONE DETECTED Granular Mins.
south side
02B Gray concrete abutment, east abutment NONE DETECTED Granular Mins.
03A Gray concrete slide rail slab, SE side NONE DETECTED Granular Mins.
rail slab
03B Gray concrete slide rail slab, SE side NONE DETECTED Granular Mins.
rail slab
04A Gray concrete deck, SE side of bridge NONE DETECTED Granular Mins.
deck
04B Gray concrete deck, SE side of bridge NONE DETECTED Granular Mins.
deck zDz11 AE rr BULK ASBESTOS MATERIAL AnatysisRequest
Errex CottsullHe Gnoup, lnc.
4200 RocruN Rono, Sulre 7 Rocxuru, CA 95677
(916) 632-6800 PHorue
(916) 632-6812 Fnx m a i noffice@entekg rou p. co m
Date of Sampling: 10-16-23 Lab: Asbestech
Job Number: 23-6868 Collected by: Jose Hernandez client Name: Blackburn Turnaround rime: 2-Day Turnaround Time
Site Address: Bridge on Highway 120 Westbound ANALYSIS REQUESTED: Asbestos by PLM
37.7g9431, _121.196096 with Dispersion Staining
Manteca, CA
Special lnstructions: Sfop analysis upon first positive result (>1%) for sample rn a series. A/so stop analysis upon first positive result (>1%) in the joint compound for sample series.
Please e-mail results at mainoffice@entekqroup.com and ihernandez@entekqroup.com as soon as available and include copv of submittalwith those results.
t'
SAMPLE # MATERIAL DESCRIPTIONILOCATION
ECG-23-6868-0'tA Concrete Parapet / South Parapet, East Side
ECG-23-6868-018 Concrete Parapet / South Parapet, East Side
ECG-23-6868-024 Concrete Abutment / East Abutment. South Side
ECG-23-6868-028 Concrete Abutment / East Abutment, South Side
ECG-23-6868-03A Concrete Side Rail Slab / Southeast Side Rail Slab
ECG-23-6868-03B Concrete Side Rail Slab / Southeast Side Rail Slab
ECG-23-6868-04A Concrete Deck / Southeast Side of Bridge Deck
ECG-23-6868-048 Concrete Deck / Southeast Side of Bridge Deck
Httpsi//entekgroupinc.sharepoint.com/sites/Entekgroup/Shared Documents/Clients/Blackburn/23-6868 Manteca Hwy 1 2O-99 Bridges/Bulk Asb/Bulk Asb Rqst 10-16-23 Bridge 1.docx
Delivered by:
Received by:
Date: llLGLa rime: /,^ae o*@ Date: /t?Jh-? r.net /Z-L aM/pM
Entek Consulting Group, Inc.
4200 Rocklin Road, Suite 7
Rocklin, CA 95677 Map Not to Scale
Blackburn 4283.x SR99/120 Interchange Phase 1B Project
37.783431, -121.196096 Manteca, CA
Bulk Asbestos Sampling Locations Collected by Jose Hernandez
On October 16, 2023 Project Number 23-6868
01B01A 03A 03B
02A 02B
04A 04B
ASBESTECH
11151 Sun Center Drive, Suite B Rancho Cordova, California 95670 Tel.(916) 481-8902 asbestech@sbcglobal.net
THE ANALYSIS USES POLARIZED LIGHT MICROSCOPY AND DISPERSION STAINING FOLLOWING E.P.A. METHOD 600/R-93/116. NON-FRIABLE MATERIALS WERE ANALYZED APPLYING THE SAME METHOD. THE LOWER DETECTION LIMIT IS <1 % WITH THE PROVISO THAT PLM MAY NOT DETECT FIBERS <0.25 MICRONS IN DIAMETER THAT MAY BE PRESENT IN SAMPLES SUCH AS FLOOR TILES. IN ACCORDANCE WITH TITLE 22, CCR, SECTION 66261.24(a)(2)(A),THE MCL IS 1 %. SAMPLES WERE NOT COLLECTED BY ASBESTECH. THIS REPORT MUST NOT BE REPRODUCED EXCEPT IN FULL WITHOUT THE APPROVAL OF ASBESTECH. THIS REPORT RELATES ONLY TO THE ITEMS TESTED. THIS REPORT MUST NOT BE USED TO CLAIM PRODUCT ENDORSEMENT BY N.V.L.A.P. OR ANY AGENCY OF THE U.S. GOVERNMENT. ASBESTECH ACCEPTS
TECHNICAL RESPONSIBILITY FOR THIS REPORT AND DATE OF ISSUE.
NVLAP LAB CODE 101442-0 LAB DIRECTOR: TOM CONLON ANALYST: JIM JUNGLES
Client: Job:
Entek Consulting Group, Inc. 23-6868 Blackburn 4200 Rocklin Rd., Suite 7 Bridge on Hwy. 120 Westbound Rocklin, CA 95677 37.783435,-121.200619, Manteca, Ca
BULK ASBESTOS ANALYSIS REPORT
LAB JOB # 70778 NVLAP Lab Code 101442-0 Date/Time Collected: 10/16/23 CDPH # 1153 Date Received: 10/16/23 Date Analyzed: 10/17/23
Sample No. Color/Description % Type Asbestos Other Materials
ECG-23-6868-
05A Gray concrete parapet, south parapet NONE DETECTED Granular Mins.
west side
05B Gray concrete parapet, south parapet NONE DETECTED Granular Mins.
west side
06A Gray concrete deck, SW side of NONE DETECTED Granular Mins.
bridge deck
06B Gray concrete deck, SW side of NONE DETECTED Granular Mins.
bridge deck
07A Gray concrete abutment, west abutment NONE DETECTED Granular Mins.
07B Gray concrete abutment, west abutment NONE DETECTED Granular Mins.
7D 7A E, AE rr BULK ASBESTOS MATERIAL AnatysisResuest
ENTEK Consumre GRoup, lr.rc.
4200 Rocxuru Roeo, Surre 7 RocxltN, CA 95677 (91 6) 632-6800 PHoNe (91 6) 632-681 2 Fnx mainoff ice@entekqrouo.com
Date of Sampling: 10-16-23
Job Number: 23-6868
Client Name: Blackburn
Site Address: Bridge on Highway 120 Westbound
37.783435, -121.200619
Manteca, CA
Lab: Asbestech
Collected by: Jose Hernandez
Turnaround Time: 2-Day Turnaround Time
ANALYSIS REQUESTED: Asbestos by PLM with Dispersion Staining
Speciallnstructions: Stop analysis upon first positive result (>1%) for sample rn a series. A/so sfop analysis upon first positive result (>1%) in the joint compound for sample series.
Please e-mail results at mainoffice@entekqroup.com and ihernandez@entekqrouo.com as soon as available and include copv of submittal with those results.
Https://entekgroupinc.sharepoint.com/sites/Entekgroup/Shared Documents/Clients/Blackburn/23-6868 Manteca Hwy 1 20-99 Bridges/Bulk Asb/Bulk Asb Rqst 10-16-23 Bridge 2.docx
Delivered by:
Received by:
llLttLX rime: /-:-!!-o*t@ /9fbtz7 ri^", / De AM/,MDate:
Page 1 of I
SAMPLE # MATERIAL DESCRIPTIONILOCATION
ECG-2s-6868-05A Concrete Parapet / South Parapet, West Side
ECG-23-6868-058 Concrete Parapet / South Parapet, West Side
ECG-23-6868-06A Concrete Deck / Southwest Side of Bridge Deck
ECG-23-6868-O6B Concrete Deck / Southwest Side of Bridge Deck
ECG-23-6868-07A Concrete Abutment / West Abutment, South Side
ECG-23-6868-078 Concrete Abutment / West Abutment. South Side
Rocklin, CA 95677 Map Not to Scale
Blackburn 4283.x SR99/120 Interchange Phase 1B Project
37.783435, -121.200619 Manteca, CA
Bulk Asbestos Sampling Locations Collected by Jose Hernandez
On October 16, 2023 Project Number 23-6868
07A 07B
05A 05B
06A 06B
APPENDIX B
BACK UP DOCUMENTATION
� Site Map
� Photo Log
� Inspector Accreditations and Certifications
� Laboratory Accreditations for Asbestos Analysis
Rocklin, CA 95677 Map Not to Scale
Blackburn 4283.x SR99/120 Interchange Phase 1B Project
Two westbound SR120 bridge structures over Van Ryn Avenue and Moffat Boulevard
Manteca, CA
Site Map Project Number 23-6868
Location of Bridge over Moffat Boulevard
Location of Bridge over Van Ryn Avenue
Photo Log Job Number: 23-6868 Date: 10-16-23 Client: Blackburn Site Address: Two westbound SR120 bridge structures over Van Ryn Avenue and Moffat Boulevard in
View of the bridge structure over Moffat
Boulevard in Manteca, CA.
View of the bridge structure over Moffat Boulevard in Manteca, CA.
View of the bridge structure over Van Ryn Avenue in Manteca, CA.
View of the bridge structure over Van Ryn Avenue in Manteca, CA.
| 4283.X ACM-Lead Report.pdf |
| 4283.X ACM-Lead Report Figures.pdf |
| 4283.x Fig.1 Vic Map_SR99-120_ACM |
| Sheets and Views |
| 1 |
| 4283.x FIG.2 Site Plan_SR99-120_ACM-2 |
| Sheets and Views |
| 2 |
| 4283.X ACM-Lead Report Appendices.pdf |
| 4283.x Fig.1 Vic Map_SR99-120_ACM.pdf |
| Sheets and Views |
| 1 |
| 4283.x Fig.2 Site Plan_SR99-120_ACM.pdf |
| Sheets and Views |
| 2 |
| 4283.X ACM-Lead Report Figures.pdf |
| 4283.x Fig.1 Vic Map_SR99-120_ACM |
| Sheets and Views |
| 1 |
| 4283.x FIG.2 Site Plan_SR99-120_ACM-2 |
| Sheets and Views |
| 2 |
File details come from the government source that posted it. Updated .