Attachment J.17 CPFMD Integrated Program Schedule (CPFMD IPS).pdf
PDF 452 KB Posted
- Attached to
- DC Courts Program Management Services
- Solicitation number
- Not on record
- Issued by
- District of Columbia Government
About this file
This integrated program schedule outlines various construction, renovation, and infrastructure upgrade projects for the District of Columbia Courts over a multi-year period. Key projects include the historic recorder of deeds restoration, Moultrie courthouse addition construction, Indiana level east court room renovations, 4th floor east juror's lounge renovation, C level NW room C-300 renovation, migration from the gallery place modernization including buildings A and B, life safety and code compliance upgrades including the 4th floor east magistrate judge's renovation and suite 3120 & 3130 US attorney and security renovation. The schedule also includes chilled water upgrades, budget milestones, design, permitting, construction, contract closeout, and project closeout activities extending into 2026. Primary responsibilities are assigned to various project management groups, architects, contractors, and District agencies for completing the work on schedule and within budget to modernize and improve court facilities.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Remaining Duration
Start Finish Primary Responsibility
CPFMD INTEGRATED PROGRAM SCHEDULECPFMD INTEGRATED PROGRAM SCHEDULE 852 01-Apr-21 A 12-Jun-26
Budget MilestonesBudget Milestones 668 01-Apr-21 A 30-Sep-25
FY21 BudgetFY21 Budget 0 01-Apr-21 A 28-Feb-23
BMI-FY21-MIL-1010 Receipt of FY21 Funds 0 01-Apr-21 A BUDGET
BMI-FY21-MIL-1020 Obligation Deadline of FY21 Funds 0 28-Feb-23* BUDGET
FY22 BudgetFY22 Budget 0 15-Apr-22 A 29-Sep-23
BMI-FY22-MIL-1010 Receipt of FY22 Funds 0 15-Apr-22 A BUDGET
BMI-FY22-MIL-1020 Obligation Deadline of FY22 Funds 0 29-Sep-23* BUDGET
FY23 BudgetFY23 Budget 383 03-Apr-23 30-Sep-24
BMI-FY23-MIL-1010 Receipt of FY23 Funds 0 03-Apr-23* BUDGET
BMI-FY23-MIL-1020 Obligation Deadline of FY23 Funds 0 30-Sep-24* BUDGET
FY24 BudgetFY24 Budget 391 01-Apr-24 30-Sep-25
BMI-FY24-MIL-1010 Receipt of FY24 Funds 0 01-Apr-24* BUDGET
BMI-FY24-MIL-1020 Obligation Deadline of FY24 Funds 0 30-Sep-25* BUDGET
Renovations, Improvements & Expansions (RIE)Renovations, Improvements & Expansions (RIE) 852 27-Sep-21 A 12-Jun-26
Historic Recorder of Deeds Restoration (D/B)Historic Recorder of Deeds Restoration (D/B) 852 06-Jan-23 A 12-Jun-26
Pre-DesignPre-Design 95 06-Jan-23 A 14-Jul-23
RIE-RDR-PLN-1010 Award Task Order for Industrial Hygenist Survey 0 06-Jan-23 A ASD
RIE-RDR-PLN-1020 Conduct Hazmat Material Survey 15 02-Mar-23* 22-Mar-23 AE - SG
RIE-RDR-PLN-1030 Submit Hazmat Report 0 29-Mar-23 AE - SG
RIE-RDR-PLN-1040 Develop Task Order for FCA 10 02-Mar-23 15-Mar-23 PgM
RIE-RDR-PLN-1050 Review Task Order for FCA 5 16-Mar-23 22-Mar-23 COTR
RIE-RDR-PLN-1060 Revise Task Order for FCA 5 23-Mar-23 29-Mar-23 PgM
RIE-RDR-PLN-1070 Release Task Order for FCA 0 29-Mar-23 ASD
RIE-RDR-PLN-1080 Award Task Order for FCA 0 19-Apr-23 ASD
RIE-RDR-PLN-1090 Conduct Facility Condition Assessment (FCA) 10 20-Apr-23 03-May-23 AE - SG
RIE-RDR-PLN-1100 Prepare DRAFT FCA Report 15 04-May-23 24-May-23 AE - SG
RIE-RDR-PLN-1110 Submit DRAFT FCA Report 0 24-May-23 AE - SG
RIE-RDR-PLN-1120 Review DRAFT FCA Report 10 25-May-23 08-Jun-23 PgM
RIE-RDR-PLN-1130 Revise DRAFT FCA Report 10 09-Jun-23 22-Jun-23 AE - SG
RIE-RDR-PLN-1140 Submit FINAL FCA Report 0 23-Jun-23 23-Jun-23 AE - SG
RIE-RDR-PLN-1150 Prepare DRAFT IGE 10 02-Jun-23 15-Jun-23 PgM
RIE-RDR-PLN-1160 Submit DRAFT IGE 5 09-Jun-23 15-Jun-23 PgM
RIE-RDR-PLN-1170 Review DRAFT IGE 10 16-Jun-23 29-Jun-23 COTR
RIE-RDR-PLN-1180 Revise DRAFT IGE 10 30-Jun-23 14-Jul-23 PgM
RIE-RDR-PLN-1190 Submit FINAL IGE 0 14-Jul-23 PgM
RIE-RDR-PLN-1200 Develop DRAFT Performance Requirements 20 04-May-23 01-Jun-23 AE - SG
RIE-RDR-PLN-1210 Submit DRAFT Performance Requirements 0 08-Jun-23 AE - SG
RIE-RDR-PLN-1220 Review DRAFT Performance Requirements 10 09-Jun-23 22-Jun-23 PgM
RIE-RDR-PLN-1230 Revise DRAFT Performance Requirements 10 23-Jun-23 07-Jul-23 AE - SG
RIE-RDR-PLN-1240 Submit FINAL Performance Requirements 0 07-Jul-23 AE - SG
ProcurementProcurement 152 20-Jan-23 A 02-Oct-23
RIE-RDR-PRO-1010 Develop Acquisition Strategy 10 20-Jan-23 A 13-Mar-23 PgM
RIE-RDR-PRO-1020 Develop RFP 30 14-Mar-23 24-Apr-23 PgM
RIE-RDR-PRO-1030 Review RFP 20 25-Apr-23 22-May-23 COTR
RIE-RDR-PRO-1040 Revise RFP 10 23-May-23 06-Jun-23 PgM
RIE-RDR-PRO-1050 Release RFP for Bid 0 07-Jul-23 ASD
RIE-RDR-PRO-1055 Pre-proposal meeting 0 21-Jul-23* COTR
RIE-RDR-PRO-1060 Submit Bids 0 25-Aug-23 DB
RIE-RDR-PRO-1070 Conduct SSEB 15 28-Aug-23 18-Sep-23 COTR
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2023 2024 2025 2026
Obligation Deadline of FY21 Funds
Receipt of FY22 Funds
Obligation Deadline of FY22 Funds
Receipt of FY23 Funds
Obligation Deadline of FY23 Funds
Receipt of FY24 Funds
Obligation Deadline of FY24 Funds
Award Task Order for Industrial Hygenist Survey
Submit Hazmat Report
Release Task Order for FCA
Award Task Order for FCA
Prepare DRAFT FCA Report
Submit DRAFT FCA Report
Review DRAFT FCA Report
Revise DRAFT FCA Report
Submit FINAL FCA Report
Prepare DRAFT IGE
Submit DRAFT IGE
Review DRAFT IGE
Revise DRAFT IGE
Submit FINAL IGE
Submit DRAFT Performance Requirements
Submit FINAL Performance Requirements
Develop Acquisition Strategy
Develop RFP
Review RFP
Revise RFP
Release RFP for Bid
Pre-proposal meeting
Submit Bids
CPFMD: INTEGRATED PROGRAM SCHEDULE
Data Date: 28-Feb-23 Project ID: CPFMD IPS - Feb 2023
Start Finish Primary Responsibility
RIE-RDR-PRO-1080 Negotiate Contract 10 19-Sep-23 02-Oct-23 ASD
RIE-RDR-PRO-1090 Award Contract 0 02-Oct-23 ASD
DesignDesign 245 31-Jul-23 12-Jul-24
RIE-RDR-DGN-1010 Issue Design NTP 0 02-Oct-23* ASD
RIE-RDR-DGN-1020 Issue/Award TO for FF&E 0 31-Jul-23*
RIE-RDR-DGN-1030 Submit Design Intent Drawings (DID-I) 0 15-Nov-23 DB
RIE-RDR-DGN-1040 Review Design Intent Drawings (DID-I) 10 16-Nov-23 30-Nov-23 CM
RIE-RDR-DGN-1050 Submit Design Intent Drawings (DID-II) 0 15-Nov-23 DB
RIE-RDR-DGN-1060 Review Design Intent Drawings (DID-II) 10 16-Nov-23 30-Nov-23 CM
RIE-RDR-DGN-1070 Submit Finalized DID I&II drawings 0 14-Dec-23 DB
RIE-RDR-DGN-1080 Submit 35% Design 0 26-Jan-24 DB
RIE-RDR-DGN-1090 Review 35% Design 10 29-Jan-24 09-Feb-24 CM
RIE-RDR-DGN-1100 Submit 65% Design 0 22-Mar-24 DB
RIE-RDR-DGN-1110 Review 65% Design 10 25-Mar-24 05-Apr-24 CM
RIE-RDR-DGN-1120 Submit Final (95%) Design 0 17-May-24 DB
RIE-RDR-DGN-1130 Review Final (95%) Design 10 20-May-24 31-May-24 CM
RIE-RDR-DGN-1140 DOB Review Construction Documents (95%) 30 20-May-24 28-Jun-24 DOB
RIE-RDR-DGN-1150 Submit IFC/100% (corrected 95%) Construction Documents 0 12-Jul-24 DB
PermittingPermitting 55 08-Nov-23 26-Jan-24
RIE-RDR-PER-1010 Submit documents for Building Permit 15 08-Nov-23 30-Nov-23 DB
RIE-RDR-PER-1020 DOB Review of Permit Documents 40 01-Dec-23 26-Jan-24 DOB
RIE-RDR-PER-1030 Building Permit Approval 0 26-Jan-24 DB
ConstructionConstruction 792 28-Feb-23 20-Mar-26
RIE-RDR-CON-1010 Issue Construction NTP 0 29-Jan-24 ASD
RIE-RDR-CON-1020 Start Construction 0 29-Jan-24 DB
RIE-RDR-CON-1030 Substantial Completion 0 08-Aug-25 DB
RIE-RDR-CON-1040 Complete Punchlist Items 0 12-Dec-25 CM
RIE-RDR-CON-1050 Turnover Space to CPFMD 0 26-Dec-25 DB
RIE-RDR-CON-1060 Install FF&E 30 29-Dec-25 06-Feb-26 FF&E
RIE-RDR-CON-1070 Tenant Move-in 20 09-Feb-26 06-Mar-26 ASD
RIE-RDR-CON-1080 Certificate of Occupancy 5 28-Feb-23 06-Mar-23 CM
RIE-RDR-CON-1090 100% Occupancy 0 06-Mar-26 CPFMD
RIE-RDR-CON-1100 De-Commission Vacated Space 10 09-Mar-26 20-Mar-26 CPFMD
Contract Close-OutContract Close-Out 0 17-Apr-26 17-Apr-26
RIE-RDR-CCL-1010 Submit As-Builts 0 17-Apr-26 DB
RIE-RDR-CCL-1020 Submit O&M Manuals 0 17-Apr-26 DB
RIE-RDR-CCL-1030 Contract Complete/Last day of Period of Performance 0 17-Apr-26 COTR
Project Close-OutProject Close-Out 220 08-Aug-25 12-Jun-26
RIE-RDR-PCL-1010 Deliver Completed Close-out Documents 0 12-Jun-26 CM
RIE-RDR-PCL-1020 Enter Fixed Assets into Manager Plus 0 12-Jun-26 CPFMD-O&M
RIE-RDR-PCL-1030 Enter Architectural and Furniture shop drawings to FM systems 0 12-Jun-26 IPT
RIE-RDR-PCL-1040 One Year Warranty Period Begins 0 08-Aug-25 CPFMD-O&M
RIE-RDR-PCL-1050 Conduct a 9-month Warranty Walk/Inspection 190 11-Aug-25 01-May-26 CPFMD-O&M
RIE-RDR-PCL-1060 One Year Warranty Period Ends 0 01-May-26 CPFMD-O&M
Moultrie Courthouse AdditionMoultrie Courthouse Addition 242 24-May-22 A 09-Feb-24
HCMC Construct C Street Addition - Phase 2B (D/B/B)HCMC Construct C Street Addition - Phase 2B (D/B/B) 144 01-Jul-22 A 20-Sep-23
ConstructionConstruction 15 01-Jul-22 A 20-Sep-23
RIE-MCA-CSA-CON-1010 Turnover Space to CPFMD 0 31-Aug-22 A GC
RIE-MCA-CSA-CON-1020 Install FF&E 0 01-Jul-22 A 31-Aug-22 A FF&E
RIE-MCA-CSA-CON-1030 Tenant Move-in 0 01-Sep-22 A 30-Sep-22 A ASD
RIE-MCA-CSA-CON-1040 Certificate of Occupancy 0 30-Aug-23* CM
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2023 2024 2025 2026
Award Contract
Issue Design NTP
Issue/Award TO for FF&E
Submit Design Intent Drawings (DID-I)
Review Design Intent Drawings (DID-I)
Submit Design Intent Drawings (DID-II)
Submit Finalized DID I&II drawings
Submit 35% Design
Review 35% Design
Submit 65% Design
Review 65% Design
Submit Final (95%) Design
Review Final (95%) Design
DOB Review Construction Documents (95%)
Submit IFC/100% (corrected 95%) Construction Documents
Building Permit Approval
Issue Construction NTP
Start Construction
Substantial Completion
Complete Punchlist Items
Turnover Space to CPFMD
Certificate of Occupancy
100% Occupancy
Submit As-Builts
Submit O&M Manuals
Contract Complete/Last day of Period of Performance
Deliver Completed Close-out Documents
Enter Fixed Assets into Manager Plus
Enter Architectural and Furniture shop drawings to FM systems
One Year Warranty Period Begins
One Year Warranty Period Ends
Turnover Space to CPFMD
Install FF&E
Tenant Move-in
Certificate of Occupancy
CPFMD: INTEGRATED PROGRAM SCHEDULE
Data Date: 28-Feb-23
Start Finish Primary Responsibility
RIE-MCA-CSA-CON-1050 100% Occupancy 0 30-Aug-23* CPFMD
RIE-MCA-CSA-CON-1070 De-Commission Vacated Space 0 13-Sep-23 CPFMD
RIE-MCA-CSA-CON-1080 Commissioning 5 14-Sep-23 20-Sep-23* GC
Contract Close-OutContract Close-Out 0 10-May-23 10-May-23
RIE-MCA-CSA-CCL-1010 Submit As-Builts 0 10-May-23 GC
RIE-MCA-CSA-CCL-1020 Submit O&M Manuals 0 10-May-23 GC
RIE-MCA-CSA-CCL-1030 Contract Complete/Last day of Period of Performance 0 10-May-23* COTR
Project Close-OutProject Close-Out 86 31-Aug-22 A 28-Jun-23
RIE-MCA-CSA-PCL-1010 Deliver Completed Close-out Documents 0 10-May-23 CM
RIE-MCA-CSA-PCL-1020 Enter Fixed Assets into Manager Plus 0 10-May-23 CPFMD-O&M
RIE-MCA-CSA-PCL-1030 Enter Architectural and Furniture shop drawings to FM systems 0 10-May-23 IPT
RIE-MCA-CSA-PCL-1040 One Year Warranty Period Begins 0 31-Aug-22 A CPFMD-O&M
RIE-MCA-CSA-PCL-1050 Conduct a 9-month Warranty Walk/Inspection 86 01-Sep-22 A 28-Jun-23 CPFMD-O&M
RIE-MCA-CSA-PCL-1060 One Year Warranty Period Ends 0 28-Jun-23 CPFMD-O&M
HCMC Indiana Level East Court Room 115 RenovationHCMC Indiana Level East Court Room 115 Renovation 171 01-Sep-22 A 30-Oct-23
ConstructionConstruction 10 28-Feb-23 13-Mar-23
RIE-MCA-INE-CON-1010 De-Commission Vacated Space 10 28-Feb-23 13-Mar-23 CPFMD
Contract Close-OutContract Close-Out 0 31-Aug-23 31-Aug-23
RIE-MCA-INE-CCL-1010 Submit As-Builts 0 31-Aug-23 GC
RIE-MCA-INE-CCL-1020 Submit O&M Manuals 0 31-Aug-23 GC
RIE-MCA-INE-CCL-1030 Contract Complete/Last day of Period of Performance 0 31-Aug-23* COTR
Project Close-OutProject Close-Out 161 01-Sep-22 A 30-Oct-23
RIE-MCA-INE-PCL-1010 Deliver Completed Close-out Documents 0 30-Oct-23 CM
RIE-MCA-INE-PCL-1020 Enter Fixed Assets into Manager Plus 0 30-Oct-23 CPFMD-O&M
RIE-MCA-INE-PCL-1030 Enter Architectural and Furniture shop drawings to FM systems 0 30-Oct-23 IPT
RIE-MCA-INE-PCL-1040 One Year Warranty Period Begins 0 01-Sep-22 A CPFMD-O&M
RIE-MCA-INE-PCL-1050 Conduct a 9-month Warranty Walk/Inspection 78 02-Sep-22 A 30-Jun-23 CPFMD-O&M
RIE-MCA-INE-PCL-1060 One Year Warranty Period Ends 0 30-Jun-23 CPFMD-O&M
HCMC 4th Floor East Juror’s Lounge Renovation (D/B)HCMC 4th Floor East Juror’s Lounge Renovation (D/B) 143 24-May-22 A 30-Oct-23
ConstructionConstruction 45 24-May-22 A 09-Jun-23
RIE-MCA-H4J-CON-1010 Turnover Space to CPFMD 0 24-May-22 A GC
RIE-MCA-H4J-CON-1020 Partition Procurement and Installation 0 07-Apr-23* GC
RIE-MCA-H4J-CON-1030 AV Matrix Procurement and Installation 0 25-May-23 GC
RIE-MCA-H4J-CON-1040 Install FF&E 0 01-Dec-22 A 30-Dec-22 A FF&E
RIE-MCA-H4J-CON-1050 Tenant Move-in 0 30-Dec-22 A 20-Jan-23 A ASD
RIE-MCA-H4J-CON-1060 100% Occupancy 0 20-Jan-23 A CPFMD
RIE-MCA-H4J-CON-1070 De-Commission Vacated Space 10 26-May-23 09-Jun-23 CPFMD
Contract Close-OutContract Close-Out 0 01-Sep-23 01-Sep-23
RIE-MCA-H4J-CCL-1010 Submit As-Builts 0 01-Sep-23 GC
RIE-MCA-H4J-CCL-1020 Submit O&M Manuals 0 01-Sep-23 GC
RIE-MCA-H4J-CCL-1030 Contract Complete/Last day of Period of Performance 0 01-Sep-23* COTR
Project Close-OutProject Close-Out 98 23-Jan-23 A 30-Oct-23
RIE-MCA-H4J-PCL-1010 Deliver Completed Close-out Documents 0 30-Oct-23 CM
RIE-MCA-H4J-PCL-1020 Enter Fixed Assets into Manager Plus 0 30-Oct-23 CPFMD-O&M
RIE-MCA-H4J-PCL-1030 Enter Architectural and Furniture shop drawings to FM systems 0 30-Oct-23 IPT
RIE-MCA-H4J-PCL-1040 One Year Warranty Period Begins 0 23-Jan-23 A CPFMD-O&M
RIE-MCA-H4J-PCL-1050 Conduct a 9-month Warranty Walk/Inspection 92 23-Jan-23 A 20-Oct-23 CPFMD-O&M
RIE-MCA-H4J-PCL-1060 One Year Warranty Period Ends 0 20-Oct-23 CPFMD-O&M
HCMC C Level NW Room C-300 RenovationHCMC C Level NW Room C-300 Renovation 242 10-Nov-22 A 09-Feb-24
PermittingPermitting 0 10-Nov-22 A 10-Nov-22 A
RIE-MCA-300-PER-1010 DOB Permit Approval 0 10-Nov-22 A DOB
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2023 2024 2025 2026
100% Occupancy
De-Commission Vacated Space
Submit As-Builts
Submit O&M Manuals
Contract Complete/Last day of Period of Performance
Deliver Completed Close-out Documents
Enter Fixed Assets into Manager Plus
Enter Architectural and Furniture shop drawings to FM systems
One Year Warranty Period Begins
Conduct a 9-month Warranty Walk/Inspection
One Year Warranty Period Ends
De-Commission Vacated Space
Submit As-Builts
Submit O&M Manuals
Contract Complete/Last day of Period of Performance
Deliver Completed Close-out Documents
Enter Fixed Assets into Manager Plus
Enter Architectural and Furniture shop drawings to FM systems
One Year Warranty Period Begins
Conduct a 9-month Warranty Walk/Inspection
One Year Warranty Period Ends
Turnover Space to CPFMD
Partition Procurement and Installation
AV Matrix Procurement and Installation
Install FF&E
Tenant Move-in
100% Occupancy
De-Commission Vacated Space
Submit As-Builts
Submit O&M Manuals
Contract Complete/Last day of Period of Performance
Deliver Completed Close-out Documents
Enter Fixed Assets into Manager Plus
Enter Architectural and Furniture shop drawings to FM systems
One Year Warranty Period Begins
Conduct a 9-month Warranty Walk/Inspection
One Year Warranty Period Ends
DOB Permit Approval
CPFMD: INTEGRATED PROGRAM SCHEDULE
Data Date: 28-Feb-23
Start Finish Primary Responsibility
ConstructionConstruction 142 28-Feb-23 18-Sep-23
RIE-MCA-300-CON-1010 Issue Construction NTP 0 28-Feb-23* ASD
RIE-MCA-300-CON-1020 Start Construction 0 28-Feb-23 GC
RIE-MCA-300-CON-1030 Substantial Completion 0 11-May-23* GC
RIE-MCA-300-CON-1040 Complete Punchlist Items 0 22-Jun-23 GC
RIE-MCA-300-CON-1050 Turnover Space to CPFMD 0 22-Jun-23 GC
RIE-MCA-300-CON-1060 Install FF&E 0 04-Aug-23 FF&E
RIE-MCA-300-CON-1070 Tenant Move-in 0 18-Aug-23 ASD
RIE-MCA-300-CON-1080 Certificate of Occupancy 0 01-Sep-23 CM
RIE-MCA-300-CON-1090 100% Occupancy 0 18-Sep-23 CPFMD
RIE-MCA-300-CON-1100 De-Commission Vacated Space 0 18-Sep-23 CPFMD
Contract Close-OutContract Close-Out 0 31-Oct-23 31-Oct-23
RIE-MCA-300-CCL-1010 Submit As-Builts 0 31-Oct-23 GC
RIE-MCA-300-CCL-1020 Submit O&M Manuals 0 31-Oct-23 GC
RIE-MCA-300-CCL-1030 Contract Complete/Last day of Period of Performance 0 31-Oct-23 COTR
Project Close-OutProject Close-Out 190 11-May-23 09-Feb-24
RIE-MCA-300-PCL-1010 Deliver Completed Close-out Documents to O&M Team 0 29-Dec-23 CM
RIE-MCA-300-PCL-1020 Enter Fixed Assets into Manager Plus 0 29-Dec-23 CPFMD-O&M
RIE-MCA-300-PCL-1030 Enter Architectural and Furniture shop drawings to FM systems 0 29-Dec-23 IPT
RIE-MCA-300-PCL-1040 One Year Warranty Period Begins 0 11-May-23 CPFMD-O&M
RIE-MCA-300-PCL-1050 Conduct a 9-month Warranty Walk/Inspection 190 11-May-23 09-Feb-24 CPFMD-O&M
RIE-MCA-300-PCL-1060 One Year Warranty Period Ends 0 09-Feb-24 CPFMD-O&M
HCMC Sixth Floor East Library Remote Hearing Room RenovationsHCMC Sixth Floor East Library Remote Hearing Room Renovations 0 30-Sep-22 A 28-Feb-23
Pre-DesignPre-Design 0 30-Sep-22 A 28-Feb-23
RIE-MCA-6EL-REN-1010 Submit Survey Report 0 30-Sep-22 A 12-Oct-22 A GC
RIE-MCA-6EL-REN-1020 Review / Sign off Test Fit 0 13-Oct-22 A 26-Oct-22 A GC
RIE-MCA-6EL-REN-1030 Complete Reconfiguration 0 28-Feb-23* GC
Migration from Gallery Place ModernizationMigration from Gallery Place Modernization 621 18-Oct-21 A 24-Jul-25
Migration from Gallery Place (Bldg.'s A & B) (D/B)Migration from Gallery Place (Bldg.'s A & B) (D/B) 621 18-Oct-21 A 24-Jul-25
ProcurementProcurement 21 09-Jan-23 A 12-May-23
RIE-MGP-BAB-PRO-1010 Award Furniture Task Order 0 09-Jan-23 A ASD
RIE-MGP-BAB-PRO-1020 Negotiate Phase 2 Construction 20 14-Apr-23 11-May-23 GC
RIE-MGP-BAB-PRO-1030 Award Phase 2 Construction 0 12-May-23* ASD
DesignDesign 41 14-Apr-23 12-Jun-23
RIE-MGP-BAB-DGN-1010 Accept 95% Design 0 14-Apr-23* CPFMD
RIE-MGP-BAB-DGN-1020 DOB Review Construction Documents (95%) 0 11-May-23 DOB
RIE-MGP-BAB-DGN-1030 Submit IFC/100% (corrected 95%) Construction Documents 0 26-May-23 GC
RIE-MGP-BAB-DGN-1040 Accept IFC/100% (corrected 95%) Construction Documents 0 12-Jun-23 CPFMD
PermittingPermitting 33 28-Feb-23 14-Apr-23
RIE-MGP-BAB-PER-1010 Submit documents for Building Permit 0 14-Apr-23 GC
RIE-MGP-BAB-PER-1020 DOB Review of Permit Documents 20 28-Feb-23 27-Mar-23 DOB
RIE-MGP-BAB-PER-1030 Building Permit Approval 0 27-Mar-23 DOB
ConstructionConstruction 432 18-Oct-21 A 16-Jan-25
RIE-MGP-BAB-CON-1010 Issue NTP - Phase 1 (Pre-Construction) 0 18-Oct-21 A ASD
RIE-MGP-BAB-CON-1020 Issue NTP - Phase 2 (Full Construction) 0 12-May-23 ASD
RIE-MGP-BAB-CON-1030 Substantial Completion, Building A 0 01-Mar-24* GC
RIE-MGP-BAB-CON-1040 Substantial Completion, Building B 0 01-Nov-24* GC
RIE-MGP-BAB-CON-1050 Complete Punchlist Items 5 01-Nov-24 07-Nov-24 GC
RIE-MGP-BAB-CON-1060 Turnover Space to CPFMD 0 07-Nov-24* GC
RIE-MGP-BAB-CON-1070 Install FF&E 0 19-Dec-24 FF&E
RIE-MGP-BAB-CON-1080 Tenant Move-in 0 02-Jan-25 ASD
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2023 2024 2025 2026
Issue Construction NTP
Start Construction
Substantial Completion
Complete Punchlist Items
Turnover Space to CPFMD
Install FF&E
Tenant Move-in
Certificate of Occupancy
100% Occupancy
De-Commission Vacated Space
Submit As-Builts
Submit O&M Manuals
Contract Complete/Last day of Period of Performance
Deliver Completed Close-out Documents to O&M Team
Enter Fixed Assets into Manager Plus
Enter Architectural and Furniture shop drawings to FM systems
One Year Warranty Period Begins
Conduct a 9-month Warranty Walk/Inspection
One Year Warranty Period Ends
Submit Survey Report
Review / Sign off Test Fit
Complete Reconfiguration
Award Furniture Task Order
Award Phase 2 Construction
Accept 95% Design
DOB Review Construction Documents (95%)
Submit IFC/100% (corrected 95%) Construction Documents
Accept IFC/100% (corrected 95%) Construction Documents
Submit documents for Building Permit
Building Permit Approval
Issue NTP - Phase 2 (Full Construction)
Substantial Completion, Building A
Substantial Completion, Building B
Turnover Space to CPFMD
Install FF&E
Tenant Move-in
CPFMD: INTEGRATED PROGRAM SCHEDULE
Data Date: 28-Feb-23
Start Finish Primary Responsibility
RIE-MGP-BAB-CON-1090 Certificate of Occupancy 0 16-Jan-25 CM
RIE-MGP-BAB-CON-1100 100% Occupancy 0 16-Jan-25 CPFMD
RIE-MGP-BAB-CON-1110 De-Commission Vacated Space 0 16-Jan-25 CPFMD
Contract Close-OutContract Close-Out 15 27-Dec-24 16-Jan-25
RIE-MGP-BAB-CCL-1010 Submit As-Builts 0 16-Jan-25 GC
RIE-MGP-BAB-CCL-1020 Submit O&M Manuals 0 16-Jan-25 GC
RIE-MGP-BAB-CCL-1030 Contract Complete/Last day of Period of Performance 0 27-Dec-24* COTR
Project Close-OutProject Close-Out 190 01-Nov-24 24-Jul-25
RIE-MGP-BAB-PCL-1010 Deliver Completed Close-out Documents 0 20-Feb-25 CM
RIE-MGP-BAB-PCL-1020 Enter Fixed Assets into Manager Plus 0 20-Feb-25 CPFMD-O&M
RIE-MGP-BAB-PCL-1030 Enter Architectural and Furniture shop drawings to FM systems 0 20-Feb-25 IPT
RIE-MGP-BAB-PCL-1040 One Year Warranty Period Begins 0 01-Nov-24 CPFMD-O&M
RIE-MGP-BAB-PCL-1050 Conduct a 9-month Warranty Walk/Inspection 190 01-Nov-24 24-Jul-25 CPFMD-O&M
RIE-MGP-BAB-PCL-1060 One Year Warranty Period Ends 0 24-Jul-25 CPFMD-O&M
Life Safety and Code Compliance UpgradesLife Safety and Code Compliance Upgrades 471 27-Sep-21 A 26-Dec-24
HCMC 4th Floor East Magistrate Judge's Renovation (D/B/B)HCMC 4th Floor East Magistrate Judge's Renovation (D/B/B) 471 27-Sep-21 A 26-Dec-24
PermittingPermitting 10 19-Oct-22 A 13-Mar-23
RIE-LSC-4MJ-PER-1010 Submit documents for Building Permit - Phase 2 0 19-Oct-22 A DB
RIE-LSC-4MJ-PER-1020 DOB Review of Permit Documents 10 20-Oct-22 A 13-Mar-23 DOB
RIE-LSC-4MJ-PER-1030 Building Permit Approval 0 13-Mar-23 DOB
ConstructionConstruction 285 27-Sep-21 A 10-Apr-24
RIE-LSC-4MJ-CON-1010 Issue Construction NTP 0 12-Oct-21 A ASD
RIE-LSC-4MJ-CON-1020 Construction - Phase 1A 0 27-Sep-21 A 31-Aug-22 A DB
RIE-LSC-4MJ-CON-1030 Construction - Phase 1B 28 11-Jul-22 A 06-Apr-23 DB
RIE-LSC-4MJ-CON-1040 Construction - Phase 2A 173 17-Jan-23 A 01-Nov-23 DB
RIE-LSC-4MJ-CON-1050 Construction - Phase 2B 171 03-Aug-23* 04-Apr-24 DB
RIE-LSC-4MJ-CON-1060 Substantial Completion 0 04-Apr-24 DB
RIE-LSC-4MJ-CON-1070 Complete Punchlist Items 0 04-Apr-24 DB
RIE-LSC-4MJ-CON-1080 Turnover Space to CPFMD 0 04-Apr-24 DB
RIE-LSC-4MJ-CON-1090 Install FF&E 0 04-Apr-24 FF&E
RIE-LSC-4MJ-CON-1100 Tenant Move-in 0 04-Apr-24 ASD
RIE-LSC-4MJ-CON-1110 Certificate of Occupancy 0 04-Apr-24 CM
RIE-LSC-4MJ-CON-1120 100% Occupancy 0 04-Apr-24 CPFMD
RIE-LSC-4MJ-CON-1130 De-Commission Vacated Space 0 10-Apr-24 CPFMD
Contract Close-OutContract Close-Out 0 10-Apr-24 10-Apr-24
RIE-LSC-4MJ-CCL-1010 Submit As-Builts 0 10-Apr-24 DB
RIE-LSC-4MJ-CCL-1020 Submit O&M Manuals 0 10-Apr-24 DB
RIE-LSC-4MJ-CCL-1030 Contract Complete/Last day of Period of Performance 0 10-Apr-24* COTR
Project Close-OutProject Close-Out 190 04-Apr-24 26-Dec-24
RIE-LSC-4MJ-PCL-1010 Deliver Completed Close-out Documents 0 04-Jun-24 CM
RIE-LSC-4MJ-PCL-1020 Enter Fixed Assets into Manager Plus 0 04-Jun-24 CPFMD-O&M
RIE-LSC-4MJ-PCL-1030 Enter Architectural and Furniture shop drawings to FM systems 0 04-Jun-24 IPT
RIE-LSC-4MJ-PCL-1040 One Year Warranty Period Begins 0 04-Apr-24 CPFMD-O&M
RIE-LSC-4MJ-PCL-1050 Conduct a 9-month Warranty Walk/Inspection 190 05-Apr-24 26-Dec-24 CPFMD-O&M
RIE-LSC-4MJ-PCL-1060 One Year Warranty Period Ends 0 26-Dec-24 CPFMD-O&M
HCMC Suite 3120 & 3130 US Attorney and Security RenovationHCMC Suite 3120 & 3130 US Attorney and Security Renovation 61 18-Mar-22 A 23-May-23
DesignDesign 30 18-Mar-22 A 10-Apr-23
RIE-LSC-UAS-DGN-1010 Issue Design NTP 0 18-Mar-22 A ASD
RIE-LSC-UAS-DGN-1020 Submit 65% Design 0 15-Sep-22 A 05-Oct-22 A AE - SG
RIE-LSC-UAS-DGN-1030 Submit Final (95%) Design 0 23-Nov-22 A AE - SG
RIE-LSC-UAS-DGN-1040 DOB Review Construction Documents (95%) 30 28-Feb-23 10-Apr-23 DOB
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2023 2024 2025 2026
Certificate of Occupancy
100% Occupancy
De-Commission Vacated Space
Submit As-Builts
Submit O&M Manuals
Contract Complete/Last day of Period of Performance
Deliver Completed Close-out Documents
Enter Fixed Assets into Manager Plus
Enter Architectural and Furniture shop drawings to FM systems
One Year Warranty Period Begins
One Year Warranty Period Ends
Submit documents for Building Permit - Phase 2
DOB Review of Permit Documents
Building Permit Approval
Construction - Phase 1A
Construction - Phase 1B
Construction - Phase 2A
Substantial Completion
Complete Punchlist Items
Turnover Space to CPFMD
Install FF&E
Tenant Move-in
Certificate of Occupancy
100% Occupancy
De-Commission Vacated Space
Submit As-Builts
Submit O&M Manuals
Contract Complete/Last day of Period of Performance
Deliver Completed Close-out Documents
Enter Fixed Assets into Manager Plus
Enter Architectural and Furniture shop drawings to FM systems
One Year Warranty Period Begins
Conduct a 9-month Warranty Walk/Inspection
One Year Warranty Period Ends
Submit 65% Design
Submit Final (95%) Design
DOB Review Construction Documents (95%)
CPFMD: INTEGRATED PROGRAM SCHEDULE
Data Date: 28-Feb-23
Start Finish Primary Responsibility
RIE-LSC-UAS-DGN-1050 Submit IFC/100% (corrected 95%) Construction Documents 0 28-Feb-23 AE - SG
DemolitionDemolition 21 14-Oct-22 A 28-Mar-23
RIE-LSC-UAS-DEM-1010 Issue Letter Directive 0 14-Oct-22 A ASD
RIE-LSC-UAS-DEM-1020 Prepare pricing and Negotiate Change Order 18 17-Oct-22 A 23-Mar-23 GC
RIE-LSC-UAS-DEM-1030 Aquire Demolition Permit 0 14-Dec-22 A GC
RIE-LSC-UAS-DEM-1040 30-day Abatement Notification to Tenants 0 12-Jan-23 A CPFMD
RIE-LSC-UAS-DEM-1050 Demolition Phase 21 28-Feb-23 28-Mar-23 GC
ConstructionConstruction 61 28-Feb-23 23-May-23
RIE-LSC-UAS-CON-1010 Issue Construction NTP 0 28-Feb-23 ASD
RIE-LSC-UAS-CON-1020 Start Construction 0 29-Mar-23 GC
RIE-LSC-UAS-CON-1030 Substantial Compeltion 5 28-Feb-23 06-Mar-23 GC
RIE-LSC-UAS-CON-1040 Complete Punchlist Items 20 26-Apr-23 23-May-23 GC
RIE-LSC-UAS-CON-1050 Turnover Space to CPFMD 5 28-Feb-23 06-Mar-23 GC
RIE-LSC-UAS-CON-1060 Install FF&E 20 29-Mar-23 25-Apr-23 FF&E
RIE-LSC-UAS-CON-1070 Tenant Move-in 0 23-May-23 ASD
RIE-LSC-UAS-CON-1080 Certificate of Occupancy 5 28-Feb-23 06-Mar-23 CM
RIE-LSC-UAS-CON-1090 100% Occupancy 5 28-Feb-23 06-Mar-23 CPFMD
RIE-LSC-UAS-CON-1100 De-Commission Vacated Space 5 28-Feb-23 06-Mar-23 CPFMD
Contract Close-OutContract Close-Out 0 28-Feb-23 28-Feb-23
RIE-LSC-UAS-CCL-1010 Submit As-Builts 0 28-Feb-23 GC
RIE-LSC-UAS-CCL-1020 Submit O&M Manuals 0 28-Feb-23 GC
RIE-LSC-UAS-CCL-1030 Contract Complete/Last day of Period of Performance 0 28-Feb-23 COTR
Project Close-OutProject Close-Out 5 28-Feb-23 06-Mar-23
RIE-LSC-UAS-PCL-1010 Deliver Completed Close-out Documents 0 28-Feb-23 CM
RIE-LSC-UAS-PCL-1020 Enter Fixed Assets into Manager Plus 0 28-Feb-23 CPFMD-O&M
RIE-LSC-UAS-PCL-1030 Enter Architectural and Furniture shop drawings to FM systems 0 28-Feb-23 IPT
RIE-LSC-UAS-PCL-1040 One Year Warranty Period Begins 0 28-Feb-23 CPFMD-O&M
RIE-LSC-UAS-PCL-1050 Conduct a 9-month Warranty Walk/Inspection 5 28-Feb-23 06-Mar-23 CPFMD-O&M
RIE-LSC-UAS-PCL-1060 One Year Warranty Period Ends 0 06-Mar-23 CPFMD-O&M
Maintain Exising Infrastructure (MEI)Maintain Exising Infrastructure (MEI) 190 16-Nov-22 A 08-Feb-24
General ImprovementsGeneral Improvements 190 16-Nov-22 A 08-Feb-24
HCMC MR-1000 Chilled Water Upgrade (D/B/B)HCMC MR-1000 Chilled Water Upgrade (D/B/B) 190 16-Nov-22 A 08-Feb-24
ConstructionConstruction 0 16-Nov-22 A 09-May-23
MEI-GIM-CWU-CON-1010 Issue NTP 0 16-Nov-22 A ASD
MEI-GIM-CWU-CON-1020 Substantial Completion 0 09-May-23 CM
Contract Close-OutContract Close-Out 0 26-May-23 26-May-23
MEI-GIM-CWU-CCL-1010 Submit As-Builts 0 26-May-23 DB
MEI-GIM-CWU-CCL-1020 Submit O&M Manuals 0 26-May-23 DB
MEI-GIM-CWU-CCL-1030 Contract Complete/Last day of Period of Performance 0 26-May-23* COTR
Project Close-OutProject Close-Out 190 09-May-23 08-Feb-24
MEI-GIM-CWU-PCL-1010 Deliver Completed Close-out Documents 0 24-Jul-23 CM
MEI-GIM-CWU-PCL-1020 Enter Fixed Assets into Manager Plus 0 24-Jul-23 CPFMD-O&M
MEI-GIM-CWU-PCL-1030 Enter Architectural and Furniture shop drawings to FM systems 0 24-Jul-23 IPT
MEI-GIM-CWU-PCL-1040 One Year Warranty Period Begins 0 09-May-23 CPFMD-O&M
MEI-GIM-CWU-PCL-1050 Conduct a 9-month Warranty Walk/Inspection 190 10-May-23 08-Feb-24 CPFMD-O&M
MEI-GIM-CWU-PCL-1060 One Year Warranty Period Ends 0 08-Feb-24 CPFMD-O&M
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2023 2024 2025 2026
Submit IFC/100% (corrected 95%) Construction Documents
Issue Letter Directive
Prepare pricing and Negotiate Change Order
Aquire Demolition Permit
30-day Abatement Notification to Tenants
Demolition Phase
Issue Construction NTP
Start Construction
Substantial Compeltion
Complete Punchlist Items
Turnover Space to CPFMD
Install FF&E
Tenant Move-in
Certificate of Occupancy
100% Occupancy
De-Commission Vacated Space
Submit As-Builts
Submit O&M Manuals
Contract Complete/Last day of Period of Performance
Deliver Completed Close-out Documents
Enter Fixed Assets into Manager Plus
Enter Architectural and Furniture shop drawings to FM systems
One Year Warranty Period Begins
Conduct a 9-month Warranty Walk/Inspection
One Year Warranty Period Ends
Issue NTP
Substantial Completion
Submit As-Builts
Submit O&M Manuals
Contract Complete/Last day of Period of Performance
Deliver Completed Close-out Documents
Enter Fixed Assets into Manager Plus
Enter Architectural and Furniture shop drawings to FM systems
One Year Warranty Period Begins
Conduct a 9-month Warranty Walk/Inspection
One Year Warranty Period Ends