This document includes an attachment for a federal solicitation seeking peer review services. The Federal Aviation Administration requires a Structural Peer Review Panel to verify the Engineer of Record's submittals for the replacement of the existing Airport Traffic Control Tower and Terminal Radar Approach Control facility at Ted Stevens International Airport in Anchorage, Alaska. Offerors must be registered in the System for Award Management database and submit proposals in accordance with the solicitation instructions by March 5, 2021 to be considered for award of this requirement. The peer review services are needed to verify the accuracy, completeness, and acceptability of structural designs for the airport infrastructure project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ATTACHMENT J-3 FINANICAL CAPABILITY Amendment 0001.pdf | ||
| 697DCK-21-R-00044 Amendment 0001.pdf | ||
| 697DCK-21-R-00044 Amend 0001.pdf | ||
| ATTACHMENT J-2 INFORMATION ON OFFEROR_Amendment 0001.pdf | ||
| ATTACHMENT J-5 KEY PERSONNEL EXPERIENCE_Amendment 0001.pdf | ||
| 697DCK-21-R-00044.pdf | ||
| Questions and Responses_Feb 26 2021.pdf | ||
| 697DCK-21-R-00044.pdf | ||
| 697DCK-21-R-00044.pdf | ||
| 697DCK-21-R-00044.pdf | ||
| 697DCK-21-R-00044.pdf | ||
| 697DCK-21-R-00044.pdf | ||
| Attachment J-1 STATEMENT OF WORK.pdf | ||
| Attachment J-4 PAST PERFORMANCE QUESTIONNAIRE.pdf | ||
| ATTACHMENT J-3 FINANICAL CAPABILITY.pdf | ||
| ATTACHMENT J-2 INFORMATION ON OFFEROR.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT J-5 KEY PERSONNEL EXPERIENCE
1. List a minimum of one (1), but no more than three (3) Relevant Facilities in the last 7 years from the date of the solicitation in the United States designed by the Designer of Record.
Names and references must be current and verifiable. (Copy for additional sheets)
Project Name/Location: _____________________________________________
POC Name and Telephone Number: _______________________________
Description of Work Performed: ___________________________
Project Delivery (Design-Build; Design-Bid-Build; etc.): ____________________________
Final Contract Cost: $______________________________
Original Contract Cost: $____________________________
Reason(s) for change in cost: _________________________
Percentage of Project Design Performed by A/E: ___________
Original Completion Date: ___________________________________________
Actual Date of Completion: ___________________________________________________
Reason(s) for time extension: __________________________________________________
Key Team Members critical to project success and is proposed for this FAA Project (if applicable):
Name/Title: ____________________________________________
Name/Title: _____________________________________________
2. List a minimum of one (1), but no more than three (3) projects of any type constructed by the Designer of Record in locations with similar site and environmental conditions in the last 7 years from date of this solicitation. Projects similar in size and scope to this FAA’s project preferred, including office facilities.
Names and references must be current and verifiable. (Copy for additional sheets)
Project Name/Location: _____________________________________________
POC Name and Telephone Number: _______________________________
Description of Work Performed: ___________________________
Project Delivery (Design-Build; Design-Bid-Build; etc.): ____________________________
Final Contract Cost: $______________________________
Original Contract Cost: $____________________________
Reason(s) for change in cost: _________________________
Percentage of Project Design Performed by A/E: ___________
Original Completion Date: ___________________________________________
Actual Date of Completion: ___________________________________________________
Reason(s) for time extension: __________________________________________________
Key Team Members critical to project success and is proposed for this FAA Project (if applicable):
Name/Title: ____________________________________________
Name/Title: _____________________________________________
3. List a minimum of one (1), but no more than three (3) Relevant Facilities designed by the Architect of Record in the last 7 years anywhere in the United States.
Names and references must be current and verifiable. (Copy for additional sheets)
Project Name/Location: _____________________________________________
POC Name and Telephone Number: _______________________________
Description of Work Performed: ___________________________
Project Delivery (Design-Build; Design-Bid-Build; etc.): ____________________________
Final Contract Cost: $______________________________
Original Contract Cost: $____________________________
Reason(s) for change in cost: _________________________
Percentage of Project Design Performed by A/E: ___________
Original Completion Date: ___________________________________________
Actual Date of Completion: ___________________________________________________
Reason(s) for time extension: __________________________________________________
Key Team Members critical to project success and is proposed for this FAA Project (if applicable):
4. List a minimum of one (1), but no more than three (3) projects of any type designed by the Structural Engineer of Record in locations with similar site and environmental conditions in the last 7 years from date of this solicitation. Projects similar in size and scope to this FAA’s project preferred, including office facilities.
Names and references must be current and verifiable. (Copy for additional sheets)
Project Name/Location: _____________________________________________
POC Name and Telephone Number: _______________________________
Description of Work Performed: ___________________________
Project Delivery (Design-Build; Design-Bid-Build; etc.): ____________________________
Final Contract Cost: $______________________________
Original Contract Cost: $____________________________
Reason(s) for change in cost: _________________________
Percentage of Project Design Performed by A/E: ___________
Original Scheduled Completion Date: ___________________________________________
Actual Date of Completion: ___________________________________________________
Reason(s) for time extension: __________________________________________________
Key Team Members critical to project success and is proposed for this FAA Project (if applicable):
Name/Title: ___________________________________________
5. List a minimum of one (1), but no more than three Projects as the Electrical Engineer of Record, designed in the United States, in the last 7 years from date of this solicitation.
Names and references must be current and verifiable. (Copy for additional sheets)
Project Name/Location: _____________________________________________
POC Name and Telephone Number: _______________________________
Description of Work Performed: ___________________________
Project Delivery (Design-Build; Design-Bid-Build; etc.): ____________________________
Final Contract Cost: $______________________________
Original Contract Cost: $____________________________
Reason(s) for change in cost: _________________________
Percentage of Project Design Performed by A/E: ___________
Original Completion Date: ___________________________________________
Actual Date of Completion: ___________________________________________________
Reason(s) for time extension: __________________________________________________
Key Team Members critical to project success and is proposed for this FAA Project (if applicable):