Questions and Responses_Feb 26 2021.pdf
PDF 77 KB Posted
- Attached to
- Peer Review Services for Performance Based Structural Design Federal contract opportunity
- Solicitation number
- 697DCK-21-R-00044
About this file
This document contains questions and responses regarding solicitation number 697DCK-21-R-00044 from the Federal Aviation Administration for peer review services for performance based structural design. The solicitation requires a Structural Peer Review Panel to verify the accuracy, completeness, and acceptability of structural submittals for the replacement of the existing Airport Traffic Control Tower and Terminal Radar Approach Control facility at Ted Stevens International Airport in Anchorage, Alaska. Offerors must be prepared to execute optional additional periods of performance if awarded and onsite structural support may be required during construction. Phase I proposals were due by March 5, 2021 and any proposal received after 5:00 PM Pacific Time on that date would be considered non-responsive.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 697DCK-21-R-00044 Amendment 0001.pdf | ||
| ATTACHMENT J-3 FINANICAL CAPABILITY Amendment 0001.pdf | ||
| 697DCK-21-R-00044 Amend 0001.pdf | ||
| ATTACHMENT J-2 INFORMATION ON OFFEROR_Amendment 0001.pdf | ||
| ATTACHMENT J-5 KEY PERSONNEL EXPERIENCE_Amendment 0001.pdf | ||
| 697DCK-21-R-00044.pdf | ||
| 697DCK-21-R-00044.pdf | ||
| 697DCK-21-R-00044.pdf | ||
| 697DCK-21-R-00044.pdf | ||
| 697DCK-21-R-00044.pdf | ||
| 697DCK-21-R-00044.pdf | ||
| ATTACHMENT J-5 KEY PERSONNEL EXPERIENCE.pdf | ||
| Attachment J-1 STATEMENT OF WORK.pdf | ||
| Attachment J-4 PAST PERFORMANCE QUESTIONNAIRE.pdf | ||
| ATTACHMENT J-3 FINANICAL CAPABILITY.pdf | ||
| ATTACHMENT J-2 INFORMATION ON OFFEROR.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
697DCK-21-R-00044 Questions & Responses
1. Question: For the stated Options 1 & 2. Does the offeror must be prepared to execute these potential options if awarded? Note: the concern is the place of performance.
Refer to question 2.
Response: Offeors must be prepared to execute Option 1 and Option 2 if the Government requires continued performance as stated in 3.2.4-34 OPTION TO EXTEND SERVICES (OCT 2019). The Government has the right to exercise Option 1 and Option 2 by unilateral modification as stated in H.1.
The total duration of contract in 3.2.4-35 OPTION TO EXTEND THE TERM OF THE CONTRACT (OCT 2019) has been corrected from 42 months to 54 months if both options are exercised.
2. Question: Also, for the described constructability reviews the proposed team/personnel (three - professional engineers) has to be onsite and/or in the vicinity of the project location?
Response: As stated in Attachment J-1 SOW the FAA may require the SPRP to provide onsite structural support during the construction phase. This is a Time and Materials contract and if travel is required during the course of the contract, travel will be negotiated between the FAA and contractor after award.