Attachment J-3 Key Requirements Verification Matrix Rev B.xlsx
XLSX spreadsheet 11 KB Posted
- Attached to
- Navy Cable Ship Replacement T-ARC(X) Federal contract opportunity
- Solicitation number
- N00024-20-R-2211R1
About this file
This document contains an attachment to a Navy solicitation for proposals to replace the Navy's cable ships. The attachment provides a key requirements verification matrix listing technical and operational requirements for the new cable ships. Requirements include a minimum bollard pull of 120 metric tons, sustained speed of 15 knots, unrefueled range of 14,500 nautical miles at 15 knots, and accommodations. The matrix also outlines requirements for cable handling equipment capacity and capabilities, dynamic positioning systems, mission sonar systems, and more. Interested parties should respond to solicitation N00024-20-R-2211R1 with proposals by August 18, 2020. The solicitation is for Phase I of the Navy Cable Ship Replacement T-ARC program conducted by the Naval Sea Systems Command.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N0002420R2211 Amend 0004 091420.pdf | ||
| N00024-20-R-2211 T_ARC QA 26AUG2020.xlsx | XLSX spreadsheet | |
| N00024-20-R-2211 T-ARC(X) Amendment 0003.docx | DOCX document | |
| N00024-20-R-2211 T-ARC(X) Conformed through Amendment 0003.docx | DOCX document | |
| N00024-20-R-2211 T_ARC QA 21AUG2020.xlsx | XLSX spreadsheet | |
| T-ARC RFP Amendment 0002.pdf | ||
| N00024-20-R-2211 T_ARC QA 13AUG2020.xlsx | XLSX spreadsheet | |
| N00024-20-R-2211 T-ARC Conformed.pdf | ||
| N00024-20-R-2211 T_ARC QA 03AUG2020.xlsx | XLSX spreadsheet | |
| N00024-20-R-2211 T-ARC Amendment 0001.pdf | ||
| T-ARC(X) System Spec Appendix B Model Test Requirements.pdf | ||
| TARC RFP FINAL 17 Jul 2020.pdf | ||
| Attachment J-1 and J-2.docx | DOCX document | |
| Attachment L-2 Resume Template (T-ARC(X)).docx | DOCX document | |
| Attachment J-4 T-ARC(X) Specification Change Recommendation Form Rev A clean.docx | DOCX document | |
| Attachment L-1 Bidders Question Form.xls | XLS spreadsheet |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Attachment J-3 Key Requirements Verification Matrix | |||||
| Requirement Name | Requirement Description | Spec Section | Contractor Verification | Verification Method | Related DI |
| Bollard pull | At least 120 MT | 3.070.3 | |||
| Sustained Speed | 15 knots | 3.070.3 | |||
| Unrefueled Range | 14,500 nm at 15 knots | 3.070.3 | |||
| Accommodations | Total number of accommodations | 3.070.3 | |||
| Bubble Sweepdown | Flow streamlines requirement with respect to the MBSS-DW | 3.073.3 | |||
| Ice Class | ABS Baltic 1C | 3.070.12 | |||
| Seakeeping - Cable Ops | Cable operations through SS5 | 3.079 | |||
| Seakeeping - ROV | ROV LARS through SS5 | 3.079, 3.573.5.3 | |||
| Seakeeping - Sea Plow | Sea Plow LARS through SS5 | 3.079, 3.573.5.4 | |||
| Seakeeping - Moonpool | Moonpool UUV and Package LARS through SS3 and Package Heavy Lift through SS3 | 3.079, 3.573.5.5, 3.573.5.6 | |||
| Diesel engine emissions | Emission requirements per regulatory bodies | 3.233 | |||
| DP Capability - Environment | Position keeping and trackline through SS5 | 3.420 | |||
| DP Capability - Redundancy | ABS DPS-2 | 3.420 | |||
| Mission Sonar Systems | Mission sonar system transducer arrangements and sonar self-noise levels | 3.073.2 and 3.461 | |||
| Cable Pathways | Pathway to/from each cable tank to/from each of the three main CHE (two CDE and one LCE) | 3.595.1.1 | |||
| Cable Tank Capacity | Main cable tanks at least 3,200 m3 and 4,812 MT; Spare cable tanks at least 500 m3 and 688 MT | 3.595.2 | |||
| CDE Capability | CDE overboarding tension at least 50 MT; Hold two simultaneously up to 40 MT each | 3.595.5.1 | |||
| LCE Capability | 25,000 lb tension | 3.595.5.2 | |||
| Sea Plow Capability | 3m burial to 1,500 m depth up to 1.5 km/hr | 3.595.6 | |||
| ROV Capability | 1m burial to 3,000 m depth up to 400 m/hr | 3.595.7 | |||
| Moonpool Size | Sized to accommodate payloads | 3.595.9 |
File details come from the government source that posted it. Updated .