Attachment J-3 - Deliverables Price Schedule 10-5-26 (4 Pages).docx
DOCX document 24 KB Posted
- Attached to
- Creative Exhibit Design Services
- Solicitation number
- 030ADV27R0010
- Issued by
-
Library of Congress
About this file
This is a Deliverables Price Schedule for the Library of Congress Creative Exhibit Design Services solicitation (030ADV27R0010). The offeror must provide firm fixed pricing for each deliverable across ten distinct phases spanning from December 2026 through July 2028. The contract requires comprehensive museum exhibit design services for the Comics changing exhibition in the Library's SW Gallery (approximately 3,700 SF), including one rotational package and promotional graphics.
The deliverables are structured across ten phases with specific due dates: Initial Project Set-up and Planning (12/18/26) including kickoff meeting documentation, design schedules, and roles/responsibilities matrices; Concept Design (02/26/27) with three design concepts and preliminary cost estimates; Schematic Design (04/30/27) including 3D/2D layouts and lighting/AV systems packages; Design Development (06/30/27) with 50% and 100% design packages; Final Design (08/31/27) with 95% and 100% final design packages; Rotation Requirements (06/01/28) for case layouts and object identification; Final Digital Artwork and Production Ready Art (04/15/28); Construction Administration/Fabrication (04/30/28) including shop drawing and sample reviews; Construction Administration/Installation (05/31/28) with punch list documentation; and Closeout (07/31/28). All pricing must be submitted for each deliverable, with the exception of those marked as Not Separately Priced (NSP), or the proposal will be rejected.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation 030ADV27R0010.pdf | ||
| Attachment J-2 - Past Performance Questionnaire 10-5-2026 (2 Pages).docx | DOCX document | |
| Attachment J-1 AOC Design Standards 2-26-2018 (160 Pages).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment J-3 – 030ADV27R0010 – Deliverables Price Schedule 10-5-26 (4 Pages)
Offeror shall provide a firm fixed price for each deliverable in the below price schedule. Proposals that do not provide prices for each deliverable (excluding the deliverable marked as Not Separately Priced (NSP) will not be accepted.
| Paragraph Reference |
| Description of Event/ Deliverable |
| Due Date |
| Price |
C.3.2.1 Initial Project Set-up and Planning (START) Phase:
· Agenda and Meeting Notes from Kick-off Meeting
· Initial and revised (post Kick-off Meeting discussion) detailed design schedule
· Roles/Responsibilities Matrix
· Exhibit Design Requirement List
· Pre-Design Field Report
· Project Management Deliverables (throughout project) to include
· Regular progress meetings and/or calls with meeting notes submitted no later than 48 hours after the meeting/call
· Weekly maintained and distributed design schedule, including all phases, from start to completion, highlighting any critical deadlines and/or edits to the schedule since previous submission
· Review of Library-furnished content assets (object information and images) to confirm accuracy and useability in design purposes; the Contractor shall alert the Library COR, in writing, of any issues/concerns that may impact the content or design integrity, schedule, costs, or maintenance of the exhibit No later than 12/18/26
C.3.2.2. Concept Design (CD) Phase:
· CD Phase Schedule
· CD Phase Milestone Presentation Package of (3) concepts (presentation and digital submission)
· CD Phase Initial Cost Estimate (for each concept)
· CD Phase Brochure and Poster Design Package
No later than 02/26/27
C.3.2.3. Schematic Design (SD) Phase:
· SD Phase Schedule
· SD Phase Milestone Presentation Package including 3D, 2D, and case layouts)
· SD Phase Lighting Package
· SD Phase AV Systems Package
· SD Phase Prototype Report
· SD Phase Preliminary Cost Estimate
No later than 04/30/27
C.3.2.4 Design Development (DD) Phase:
· 50% DD design package (presentation and digital submission)
· DD exhibit assessment report
· 100% DD design package (presentation and digital submission)
· DD exhibit lighting package, aligned with DD design and within established project budget and schedule parameters as needed
· DD AV systems design package, aligned with DD design and within established project budget and schedule parameters as needed
· DD media package (presentation and digital submission) as needed
No later than 06/30/27
C.3.2.5 Final Design (FD) Phase:
· 95% FD design package (presentation and digital submission)
· 100%-Final FD design package (presentation and digital submission)
· FD exhibit lighting package, aligned with FD design and within established project budget and schedule parameters
· FD AV systems design package, aligned with FD design and within established project budget and schedule parameters
· FD prototype report
· FD exhibit assessment report (digital submission)
· FD cost estimate (digital submission)
· FD schedule (digital submission)
No later than 08/31/27
C.3.2.6 Rotation Requirements:
· revised detailed case/object layouts, with object images clearly identified with object numbers and layout dimensions
· frame, mat, mount, and cradles schedules, which includes all suggested dimensions and materials
· final designs for any new case furniture and interior case graphics, as needed
· FDA graphic files for any necessary text alterations, new labels, and any related graphics associated with each rotation
· indications for how the layout changed from the previous rotation No later than 06/01/28
C.3.2.7 Final Digital Artwork (FDA) and Production Ready Art (PRA) Phase:
· Initial FDA package (digital submission)
· Final FDA package (including packaged files ready for graphic production output) (digital submission)
· FDA Tracking Log that verifies completion of all FDA in accordance with FD Package and graphic schedule (quantities, numbering, sizing, production method, and inclusion of approved Library content)
No later than 04/15/28
C.3.2.8 Construction Administration/Fabrication (CA/FAB) Phase:
· Written responses to CA/FAB RFI entries
· Review and written responses to all CA/FAB shop drawing reviews, noting approval, approved as noted, or not approved/resubmit for Library concurrence
· Review and written responses to all CA/FAB samples (materials and finishes), noting approval, approved as noted, or not approved/resubmit for Library concurrence
· Review and written feedback on Fabricator-supplied schedule for fabrication and installation, noting issues-concerns related to overall completion
· Review and written feedback on Fabricator-proposed substitutions with recommendation on approval/rejection and supporting reasons
· Review and written feedback on Fabricator-proposed Change Orders (cost and/or no cost) with recommendation on approval/rejection and supporting reasons No later than 04/30/28
C.3.2.9 Construction Administration/Installation (CA/INSTALL) Phase:
· Written responses to CA/INSTALL RFI entries
· Draft punch list of final installation
· Final punch list of final installation
· Documented resolution of punch list
· Checklist confirming delivery of all contractual requirements per this contract (including date submitted and written proof of receipt/approval acceptance by the Library) No later than 05/31/28
| C.3.2.10 Closeout (CLOSE) Phase |
| · Final design closeout package |
| No later than 07/31/28 |