Attachment III SOW 637-23-103 Upgrade-Replace Fire and Storage Room Doors Bldg 47 and 62.pdf
PDF 175 KB Posted
- Attached to
- Z1DA--Fire and Storage Room Doors Federal contract opportunity
- Solicitation number
- 36C24625B0009
About this file
This Statement of Work outlines requirements for upgrading and replacing fire and storage room doors at Buildings 47 and 62 at the Asheville VA Medical Center in North Carolina. The project involves replacing 92 fire door/frame combinations, 49 smoke door/frame combinations, and 24 hazardous storage room door/frame combinations, including adjusting/replacing hinges, installing door sweeps and astragals, adjusting door closers and latches, and filling holes in doors and frames.
The construction magnitude ranges from $500,000 to $1,000,000 with a total contract period of 225 calendar days (15 days for bonds, 30 days for submittals, 180 days for construction). Key requirements include developing a Project Management Plan within 60 days of submittal NTP, maintaining a project website, providing bi-weekly progress reports, and implementing quality control measures. The contractor must coordinate with Miller-Remick, LLC as architect-engineers, comply with VA construction specifications, obtain necessary permits and licenses, and provide TB screening documentation for all workers. Normal work hours are 8:00 AM to 4:30 PM Monday-Friday, with construction access from 7:30 AM to 4:30 PM Saturday-Thursday, excluding federal holidays.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Award Notification 36C24625C0032_1.pdf | ||
| 36C24625B0009 0008.pdf | ||
| Attachment XII SOW Upgrade Replace Fire and Storage Room Doors 47 and 62 March 27 2025.pdf | ||
| Attachment VIII Abestos Report.pdf | ||
| 36C24625B0009 0007.pdf | ||
| Attachment XI Response to RFIs.pdf | ||
| Attachment X Bid Specifications March 21 2025.pdf | ||
| Attachment IX GC109.pdf | ||
| 36C24625B0009 0006.pdf | ||
| 36C24625B0009 0004.pdf | ||
| 36C24625B0009 0003.pdf | ||
| Attachment VI - Bid Cost Breakdown.xlsx | XLSX spreadsheet | |
| 2nd Site Visit Sign-In Sheet.pdf | ||
| 36C24625B0009.pdf | ||
| Map of 2nd Site Visit Location.pdf | ||
| 36C24625B0009 00002.pdf | ||
| 36C24625B0009 00001.pdf | ||
| Site Visit Sign-In Sheet.pdf | ||
| Attachment IV Wage Determination.pdf | ||
| Attachment V - Campus Map.pdf | ||
| Attachment I Drawings.pdf | ||
| Attachment VI IFB 36C24625B0009.pdf | ||
| Attachment II Bid Specifications.pdf | ||
| 36C24625B0009.docx | DOCX document |
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Project # 637-23-103
January 13, 2025
UPGRADE/REPLACE FIRE AND STORAGE ROOM DOORS BLDGS 47 AND
ASHEVILLE, NC
Place of Performance: Tasks will be performed at the
Asheville VAMC, Asheville, NC.
Magnitude of Construction range: between $500,000 to
$1,000,000.
Construction schedule: Base Bid: 15 days for bonds, 30 days for submittals and 180 days for construction. Total contract time: 225 calendar days.
1.0 Scope
Construction Services: Provide materials, labor, tools, supervision and equipment necessary to perform work as described in the construction drawings and specifications to be provided at solicitation. Work includes, but not limited to: Contractor shall completely prepare site for building operations, including demolition and removal of existing structures where necessary, and furnish labor and materials to perform the repairs, replacement and/or upgrade of 92 fire door/frame combinations, 49 smoke door/frame combination, and 24 hazardous storage room door/frame combinations. Work consists of but not limited to door and frame replacement, adjusting or replacing hinges, installing door sweeps and astragals, adjusting door closers and latches, and filling in holes in doors and frames. All work shall be performed in accordance with the attached Construction Drawings and specifications.
2.0 Basic Requirements
Overall requirements include the efficient management of the Contract, but not limited to, the submission of accurate, on time, and quality contract deliverables, as well as, timely identification and solution of impediments to successful project execution. Technical requirements include, but are not limited to, early involvement in the process to allow for the development of the most cost-effective and technically sound approach or solution. The Asheville Engineering Projects Section will rely on the contractor’s expertise in recognizing and addressing problematic issues and successful execution of this Contract. The Contractor shall perform all work in accordance with federal, state, and local codes, statutes and regulations.
3.0 General requirements
This section sets forth the general requirements for the Contractor. Contractor and any subcontractor shall possess applicable licensures prior to award of the Contract in order to meet the requirements to perform construction works identified in this Contract and its subsequent attachments.
The Contractor shall comply with all applicable VA Master Construction Specifications, Technical
Information Library (TIL), and all other applicable standards/regulations. In the event of conflicting criteria, the Contractor shall notify the Contracting Officer (CO) and seek guidance. The contractor shall be required to perform the requirements contained in any of the Contract attachments, drawings, specifications, exhibits and other documents. The contractor shall follow order of precedence as established in the basic contract clauses 52.215-8, Order of Precedence, and 52.236-21, Specifications and
Drawings for Construction, and its Alternate I. Contractors shall not use conflicts between guidance, interpretation of the guidance and order of precedence as a basis for a later request for equitable adjustment. Regulations and standards that may be applicable to the work in this Contract include but are not limited to federal, state, local statutes/regulations; Department of Veteran Affairs instructions, manuals, handbooks, regulations, guidance, and policy letters National Association of Corrosions
Engineers (NACE); National Fire Protection Association (NFPA); Steel Structures and Painting Counsel
(SSPC); National Electrical Code (NEC); and International Building Code (IBC), including all changes and amendments in effect on the date of issuance of this Contract.
The Contractor shall implement a full-range construction activity as specified in this Contract in accordance with all applicable compliance documents. The Contractor shall be responsible for providing all manpower, equipment, material, services, and transportation necessary to accomplish the work assigned unless otherwise specified in the Contract and its attachments. The Contractor shall perform management, planning, and performance reporting to effectively secure and monitor prime and subcontract work. At a minimum, Contractor shall provide weekly status reports to the Contracting
Officer (CO) and Contracting Officer Representative (COR).
3.1 Project Management Plan (PMP)
The Contractor shall prepare and submit for approval a Project Management Plan (PMP) for the Contract within sixty 60 Calendar Days of issuance of Submittal NTP. The PMP shall include, but is not limited to, the following; Project Phasing Plan, Project Schedule/Milestone Chart, Document Control Plan, Area
Use Plan, Contractor’s Quality Control Plan, Construction Security Plan, Testing and Commissioning
Plan, Environmental Protect Plan, Demolition Debris/Construction Waste Management Plan, and Project
Organization POC Chart. The Contractor shall develop the schedule utilizing the Critical Path Method
(CPM), plan and schedule demonstrating fulfillment of the contract requirements (Project Schedule) and shall keep the Project Schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). Conventional Critical Path Method (CPM) technique shall be utilized to satisfy both time and cost applications.
3.1.1 Project Schedule
The Contractor shall be responsible for the development, maintenance, and implementation of a detailed
Project Schedule. The Contractor Project Schedule (CPS) shall indicate detailed activities for the projected life of the project. The CPS shall consist of detailed activities and their restraining relationships.
It will also detail manpower usage throughout project. The contractor shall utilize the Critical Path
Method as detailed in the applicable specification section. The project schedule shall show all task requirements and shall follow the WBS for the Contract. The project schedule shall include all major pre-construction activities in order to receive construction Notice to Proceed (NTP) (all preconstruction deliverables), all major price/schedule drivers, such as validation of existing conditions, major material submittals and/or long lead-time items, abatement, transportation, work plans, major demolition/construction tasks, training, meetings and project close-out. The contractor shall allow time in the schedule for 10 calendar days from time of award for the pre-construction meeting to occur. In addition, the schedule shall be submitted in a Gantt chart format as a PDF file for the purpose of presentations, meetings, and discussions. The project schedule shall show deliverable milestones and critical paths for project and shall be used for tracking work progress towards achieving milestones. Updates to the project schedule shall be made, as required, throughout the project period of performance (PoP). These updates shall show actual progress relative to the approved project schedule. Schedule updates showing activity extending beyond the PoP are not an extension of the
PoP. PoP extensions will only be granted through contract modifications issued by the CO. The project schedule and subsequent progress updates shall depict projected percent complete and actual percent complete for the Contract.
3.1.2 Contractor Quality Control Plan
The Contractor shall be responsible for the development, maintenance and implementation of a CQC Plan to implement all requirements of the Contract. The plan shall be submitted at time of Proposal.
Construction will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. At a minimum, the plan shall contain the following, construction operations, both on-site and off-site, including work by subcontractors, consultants, architect/engineers (AE), fabricators, suppliers, and purchasing agents. The plan shall detail the contractor’s approach to ensuring that all contract deliverables conform to the requirements of the contract and its attachments.
3.1.3 Work Breakdown Structure (WBS)
The Contractor shall prepare and submit for approval a WBS. The WBS shall be used for project planning and to report the schedule status for the Contract. A narrative description of all task activities shall be included. All required tasks shall be included in the WBS per the scheduling specification.
3.1.4 Area Use Plan
The Contractor shall submit for Government, within five calendar days of the on-site Pre-Construction
Conference, an Area Use Plan designating intended use of all areas within the project boundaries. This plan shall include, but not necessarily be limited to, the following: the proposed location and dimensions of any area to be fenced and used by the Contractor; construction plant and building installations/the number of trailers and facilities to be used; avenues of ingress/egress to the fenced areas and details of the fence installation; drawings showing temporary electrical installations; temporary water and sewage disposal installations; material storage areas; hazardous storage areas. Any areas which may have to be graveled shall also be identified. The plan shall also include a narrative description of the building structural system, the site utility system; and the office or administration facilities. The Contractor shall also indicate if the use of a supplemental or other staging area is desired. The Contractor shall not begin construction of the mobilization facilities prior to approval of the Area Use Plan.
3.1.5 Environmental Protection
The Contractor shall be responsible for the development, maintenance and implementation of activities in a manner that protects existing site utilities (including underground), structures, surface features
(including roads), service operations, and the general site environment. This includes the protection of trees, shrubs, and other vegetation not in the affected zone from damage, soil compaction, and physical contact with machines and equipment. The Contractor shall repair or replace any damaged items at no additional cost. Repairs must match existing conditions. If appropriate, the Contractor shall conserve uncontaminated topsoil by removal, storage, or redistribution. All reasonable measures shall be taken to minimize and suppress fugitive emissions of dust, vapors, and other site materials during site work. All fill materials shall be non-contaminated. The Contractor shall conduct operations and activities with the intent of reducing the amount of pollution generated. Specific areas to be focused on are generation of solid waste, use of hazardous materials, use of ozone depleting substances, generation of hazardous waste, and use of energy and water. The Contractor shall plan, construct, operate, maintain, optimize, and commission systems necessary to control storm water run-on and run-off; and transport surface water drainage to a treatment plant, discharge location, or other destination. Project information pertaining to hazardous materials abatement is detailed in Spec Section 02 82 11 Traditional Asbestos Abatement. The
Contractor shall obtain all environmental permits required to successfully perform this contract.
3.1.6 Waste Management/Demolition Debris Management Plan
The Contractor shall be responsible for the development, maintenance and implementation a written demolition debris management plan. The plan shall include the requirements defined in 01 74 19 (initial and monthly deliverable).
3.2 Permits, Licensing, Certifications, Notifications & Requests.
The Contractor shall be responsible for the ensure that all trades performed under this contract possess the necessary licenses for the performance of works. The Contractor shall be responsible for submitting associated evidence, as required by this contract and/or attachments, of any and all required Permits, Licensures and Certifications. The Contractor shall also be responsible for providing timely notifications as required and submitting any and all requests within the time constraints defined by this contract and its attachments. See Section 5.0 and attached specification for additional details.
3.3 Tuberculosis Screening
Contractor shall provide written certification that all contract employees assigned to the work site have had a pre-placement tuberculosis screening within 90 days prior to assignment to the worksite and been found have negative TB screening reactions. Contractors shall be required to show documentation of negative TB screening reactions for any additional workers who are added after the 90-day requirement before they will be allowed to work on the work site.
3.4 Documentation/Daily Logs
The Contractor shall maintain daily log documenting the activity each day during construction for the
Contract. The logbook shall document people entering and leaving the construction site, discussions held, issues identified, actions needed, resolutions reached, and other pertinent information. The logbooks shall be kept on-site at all times. Copies of the logbooks shall be submitted to the Government at the conclusion of the project.
3.5 Reports - Progress/Status Reporting
The Contractor shall provide bi-weekly Progress Reports for the Contract. Monthly Progress Reports shall be submitted NLT the 15th calendar day of the following month and shall contain information about contract, contract performance, schedule, and deliverables. The Progress Reports shall also describe progress of activities necessary to achieve the project objectives and shall contain a description of activities accomplished during the month, activities forecasted for the future months, and problems and issues associated with the performance of the SOR. The biweekly and monthly report shall be used to review and evaluate the overall progress of the project, along with any existing or potential problem areas. The report shall include a summary of the events that occurred during the reporting period, discussion of performance, identification of problems, proposed solutions, corrective actions taken and outstanding issues. The progress report shall depict projected percent complete and actual percent complete for the Contract.
3.6 Material and Data Submittals
The Contractor shall manage submittals for the Contract in accordance with this Statement of
Work. The number of copies specified in the Contract is for both hard copies and electronic media copies. All submittals requiring approval will be reviewed and approved by the CO within 30 calendar days of submission. Government review includes review and recommendations from the government’s representatives and/or the government’s agents/contractors. The Contractor shall send all deliverables and/or submittals, weekly status progress reports, Pre-Final and Final Inspection Requests, and
Contractor’s posted website address to the CO, Contract Specialist (CS), and Contracting Officer’s
Representative (COR). Additionally, all Contractor deliverables/submittals shall be posted on the
Contractor’s website.
3.7 Submittal Register
The Contractor shall create and maintain a submittal register for the Contract. The submittal register shall be incorporated into the Project Website.
3.8 Master Document List (MDL)
The Contractor shall create and maintain an MDL for this Contract that includes all documents, whether the documents are a deliverable or not, which are prepared during the course of the Contract. The MDL also shall contain the PMP, material and data submittal register, contract progress/status reports, and daily
QC construction log documentation. The MDL and its documents shall be maintained in libraries readily available for submittal to the government.
3.9 Request for Information (RFI)
The Contractor shall use the RFI process to ascertain the government’s intent and/or clarifications applicable to scope, drawings, specifications, and/or other contract documents. The Contractor shall identify the specific issue, applicable circumstances, proposed solutions, and a date by when a decision is requested to the COR. The COR shall provide a recommendation to the CO for approval. The Contractor will not be authorized to move forward regarding the issue(s) related to the RFI until formal direction is provided, in writing, by the CO or COR.
3.10 Project Website
The Contractor shall establish a project website with real-time worldwide access available to the government within 15 days after Notice to Proceed (NTP). The website shall include, but not be limited to, a submittal tracker/register, an RFI tracker, a Contract and Contract Modification Tracker, a photo log, the project schedule, daily logs, and project progress and status reports, and correspondence. It shall provide a means to post by the Contractor and to post by the government and its identified key personnel, to include but not limited to, the Contracting Officer, Contracting Officer Representative, Projects
Manager, Industrial Hygienist. Documents or other materials posted on the site may not be deleted without CO approval. The Contractor shall submit a complete digital archive of the site to the CO for project closeout. Hard copies (one copy of each) submitted to the Contracting Office shall be in letter size, six-section classification folders, earth red color with 2 inch capacity fasteners two hole punch at the top of the folder and tab dividers. All documents will be submitted in hard copy with appropriate numbering for easy identification. More than one submittal may be sent in one folder, however, they must contain similar submittal types each folder (i.e, material submittals in one folder, meeting minutes in one folder, requests for information in one folder). Hard copies shall be mailed on a bi-weekly basis at a minimum. The folders shall be filled to capacity. There shall be no markings or labels on the outside of the folders. An index shall be provided in each folder stating what the folder contains. The Website shall also notify via email all applicable personnel of any changes to its project content (i.e. Uploads, Submittal submission coordination status such as submitted, resubmitted, approvals, denials, deletions, etc..) for the purposes of efficient information notification and completion of action items by either party.
3.11 Meetings and Conferences
The Contractor shall attend and support meetings and teleconferences to discuss technical requirements, issues, and project progress and status as required. The Contractor shall prepare, and submit for review, presentation materials for meetings and an agenda. The Contractor shall be responsible for taking meeting minutes prepare and submit minutes for all meetings attended no later than 3 business days after the meeting has occurred. The minutes shall be sent to the Contracting Officer and COR for coordination and approval prior to distribution.
3.12 Progress Meetings
The Contractor shall perform Progress Meetings after contract award. These meetings will include the
COR, CO, Project Manager, CQC System Manager, Site superintendent, Quality Assurance Surveillance
Contractors, and other relevant personnel on an as needed basis. During construction, Progress Meetings shall be held bi-monthly. These meetings shall cover the progress made in the past period and shall include any pertinent issues which could affect future Contract progress/performance. The Contractor shall record and provide meeting minutes for all meetings. The following items shall be covered, at a minimum: Attendees and contact information; project percent complete (Actual and Scheduled); RFI’s and statuses; submittals and statuses; three-week look ahead; Project Schedule; safety; resolution of existing issues; New Business.
4.0 Government-Furnished Information, Equipment, and Property (GFI, GFE, AND GFP)
4.1 GFE and GFP
4.1.1 Any GFP to be provided under this contract are reflected in the attached drawings. The
Contractor shall be responsible for the acceptance of GFP. The Contractor Shall notify the COR in writing, 60 days in advance, of date on which Contractor will be prepared to receive any property and/or equipment furnished by Government. Arrangements will then be made by the Government for delivery of
GFE/GFP. The Contractor shall be responsible for creating and maintaining an itemized log of any
GFE/GFP in which the Government provides to the Contractor over the duration of this contract.
4.2 GFI
Refer to the drawings, specifications, and other pertinent documents and attachments.
The Offices of Miller-Remick, LLC. as architect-engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government. Management, planning, and reporting requirements
4.3 Construction
Upon issuance of the Construction Notice to Proceed (NTP) by the CO, the Contractor may commence on-site construction activities. The Contractor shall provide the manpower, equipment, material, services, and transportation, and other incidental related services, necessary to review, plan, develop, and implement quality control and oversight services during the construction phase of the Contract. Details regarding construction management requirements, inspection and testing, construction facilities and temporary controls, environmental protection, quality control system, construction quality control, and project closeout will be provided at the pre-construction conference. The Contractor shall perform construction, restoration, emergency response, repair, enhancement, maintenance, modernization, and demolition of facilities, utilities, real property systems, and infrastructure systems in support of construction, furniture, fixtures and equipment, and engineering requirements as specified in this
Contract. Shop drawings and other submittals that require approval shall be signed/approved by the CO prior to actual work placement of submitted elements. Construction activities shall be in conformance with local and Veteran Affairs standards and regulations. The Contractor shall coordinate, cooperate, and assist the Government in deconflicting field activities from those of other Contractors outside the main construction sites.
4.4 Activities Coordination
The Contractor shall coordinate worksite activities with applicable personnel to ensure the protection of human health and the environment; the prevention of damage to property, utilities, materials, supplies, and equipment; and the avoidance of work interruptions. The Contractor shall provide physical security to work areas with security equipment and personnel. The Contractor must comply with Occupational
Safety and Health Administration (OSHA) safety and health regulations, local national safety and health laws and regulations, local safety office requirements. The Contractor is required to provide copies of
OSHA and all other applicable safety and health reports submitted during the duration of the Contract.
4.5 Notification Requirements
The Contractor is required to notify the CO and COR of critical issues that may affect the contract performance and/or human health and the environment. The types of issues that require notification include, but are not limited to, health risks, spills, unexpected utility crossings, unusual weather conditions, unacceptable materials, changes in critical personnel, unforeseen hazardous material. On critical issues, verbal notification shall be made immediately followed by written notification as soon as practical. For critical issues pertaining to human health and the environment, the Contractor shall immediately notify the CO and stop work. Work shall only resume at the direction of the CO following resolution of the issue.
4.6 Pre-Final Inspection
The Contractor shall conduct a pre-final walk through inspection and publish the pre-final inspection findings in a pre-final inspection report in accordance with the format specified at the pre-construction conference and defined in the Contract.
4.7 Final Inspection
The Contractor shall conduct a final acceptance inspection and publish the findings in a final inspection report in accordance with the format specified at the pre-construction conference and defined in this
Contract. The inspection shall concentrate on the items identified at the pre-final inspection and recorded in the pre-final report. The final inspection report shall certify that all items of the design have been implemented and that the construction is complete. At the final inspection, the Contractor shall present a
Certificate of Occupancy or equivalent.
4.8 Delivery and Warranty
The Contractor shall complete all inspection and commissioning requirements prior to final inspection.
The warranty shall be issued in accordance with FAR 52.246-21, Warranty of Construction. Extended warranties offered by the Contractor and its subcontractors or suppliers may be accepted at the government’s discretion. The Contractor shall provide system Operations and Maintenance (O&M) manuals, parts list, and spare parts to the government and train maintenance personnel in system operations prior to delivery to the government. O&M manuals shall be part of an O&M plan developed by the Contractor for the O&M of all systems and facilities.
4.9 As-Built Documentation
The Contractor shall maintain, prepare, and deliver to the Government and its AE Partner final record of redlined drawings showing As-Built & approved/required deviations for the drawings supplied by this contract. Delivery of As-Built documentation is required at Final Acceptance Inspection and shall occur prior to final payment.
5.0 Hours of Work
The normal hours of work on installations are from 8:00 a.m. to 4:30 p.m., Monday through Friday, excluding holidays. Construction hours of work and access to work sites are from 7:30 a.m. to 4:30 p.m., Saturday through Thursday, excluding holidays. For work during other than these hours of work, the
Contractor shall submit, in writing, for the Contracting Officer's approval, a notice of any period of scheduled work other than the normal hours of work specified above. This notice shall be submitted not less than two weeks prior to each period of work scheduled at times other than normal hours of work including holidays.
US Government holidays. When any of the US Government Holidays fall on a non-work day, the holiday will be observed on either the preceding or succeeding workday. The choice of any such preceding or succeeding workday shall be coordinated with the COR and the CO.
Federal Holidays: The following Federal Legal Holidays are observed by Asheville VA Medical Center:
• New Year’s Day – 1 January
• Martin Luther King’s Birthday – Third Monday in January
• Presidents Day – Third Monday in February
• Memorial Day – Last Monday in May
• Juneteenth/Freedom Day – 19 June
• Independence Day – 4 July
• Labor Day – First Monday in September
• Columbus Day – Second Monday in October
• Veterans Day – 11 November
• Thanksgiving Day – Fourth Thursday in November
• Christmas Day – 25 December
• Any other Federal Holiday granted by the President of the United States
5.1 Compliance with Emergency Management directives
Contractors shall comply with all safety directives and emergency management instructions as directed by the local VA Medical Center site specific policies & procedures, Local Construction Handbook, and any subsequent updates to the handbook directed by policy or law. These directives are to ensure preparedness and safety of all personnel doing business on the VA Medical Center property. Notifications of
“Exercise” and Real-World events are typically made via a Public Address/Giant Voice Systems. The contractor shall responsible for the participation of their on-site employees and reasonably respond to these announcements in the safest means practicable.
All employees of the contract are required to participate in mandatory required facility exercises to meet facility accreditation and compliance. The timeframe for these exercises are typically short. Examples include, but not limited, Active Shooter/Active Threat, Tornado, Bomb Threat and Fire Drills. The contractor/subcontractor employees shall be required to respond to any VA Medical Center Drill as if it were a real-world emergency/threat.
All employees of the contractor/subcontractor shall participate in preparations for all VAMC Safety or
Emergency Management as directed. All hazards, events, and disasters including inclement weather, earthquakes, mandatory evacuations and also includes site safety and preparations for visits by high profile VIP’s.
5.2 Severe Weather
During Forecasted Severe Weather Events, Contractors will be expected to take all precautions necessary, and are required to secure or remove any loose items that may become projectiles, especially any material or equipment stored on elevated levels. Contractors will be required to perform the following when requested by the VA (as needed according to the type of severe weather event) -
• A survey of your areas to determine the potential exposure to high winds and flooding. Identify areas in need of protection, material removal, etc.
• Examine structures or materials covered with tarps to ensure they will remain standing in a storm. The wind can fill a tarp and cause it to pull down materials or structures.
• Examine any materials stored in your laydown area and secure as needed. The Laydown area onsite may be prone to flooding, recommend anything of value to be removed.
• Dumpster removal.
• Porta-John removal.
• Scaffolding removal.
• Removal of any ladders, trailers, temporary structures, or other items that could become a projectile.
• Removal of any materials, supplies, or tools that are stored on rooftops.
• Removal of any materials identified by the VA that could become a hazard during severe