This request for proposals (RFP) solicits fixed-price construction services for HVAC and electrical repairs and replacements at two buildings of the USDA Carl Hayden Bee Research Center in Tucson, Arizona. The work includes providing all labor, materials, tools, equipment, supplies, transportation, and supervision to renovate the buildings in conformance with applicable local and state building codes. The solicitation will be posted on March 17, 2022 to SAM.gov and issued electronically only, with questions due to Theodore Blume by email. The requirement is set aside for small businesses with a size standard of $39.5 million for NAICS code 236220. The disclosed magnitude of the contract is between $500,000 and $1,000,000. A site visit date will be specified in the solicitation. The U.S. Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Pacific West Area is the contracting agency.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture

Carl Hayden Bee

Research Center

TUCSON, ARIZONA

SPECIFICATIONS

LSY No. 20037.01

Final Submission

July 13, 2021

Archi tects & Laboratory Planners

Louviere, Stratton & Yokel, LLC

8484 Georgia Avenue Suite 650

Silver Spring, Maryland 20910

T 301.588.1500

F 301.5885300 www.lsyarchitects.com

RFQ 12905B22R0007 Tucson AZ 1

United States

Department of

Agriculture

Carl Hayden Bee

Research Center

TUCSON, ARIZONA

SPECIFICATIONS

LSY No. 20037.01

July 13, 2021

Burns & McDonnell

8201 Norman Center

Drive, Suite 500

Bloomington, Minnesota

Telephone: 952-656-6003 www.burnsmcd.com

Archi tects & Laboratory Pl anners

Louviere, Stratton & Yokel, LLC

8484 Georgia Avenue Suite 650

Silver Spring, Maryland 20910

T 301.588.1500

F 301.5885300 www.lsyarchitects.com

07/12 /21

ELECTRICAL MECHANICAL

RFQ 12905B22R0007 Tucson AZ 2

USDA CHBRC, Tucson, AZ

Carl Hayden Bee Research Center Design TABLE OF CONTENTS

LSY Architects, LLC 00 01 10 - 1

DOCUMENT 00 01 10

TABLE OF CONTENTS

Section No. Title

Title Page

00 01 10 TABLE OF CONTENTS

DIVISION 01 00 00 GENERAL REQUIREMENTS

01 1000 SUMMARY

01 4000 WORK RESTRICTIONS

01 3100 PROJECT MANAGEMENT AND COORDINATION

01 3200 CONSTRUCTION PROGRESS DOCUMENTATION

01 3300 SUBMITTAL PROCEDURES

01 3550 CONSTRUCTION SECURITY REQUIREMENTS

01 4500 QUALITY REQUIREMENTS

01 4200 REFERENCES

01 4500 CONSTRUCTION QUALITY CONTROL

01 5000 TEMPORARY FACILITIES AND CONTROLS

01 5950 SAFETY AND HEALTH

01 6000 PRODUCT REQUIREMENTS

01 7000 EXECUTION REQUIREMENTS

01 7310 CUTTING AND PATCHING

01 7350 FIRE PREVENTION PRECAUTIONS FOR HOT WORK

01 7419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 7700 CLOSEOUT PROCEDURES

01 7810 PROJECT RECORD DOCUMENTS

01 7823 OPERATION AND MAINTENANCE DOCUMENTATION

01 8111 SUSTAINABLE DESIGN REQUIREMENTS

DIVISION 02 00 00 EXISTING CONDITIONS

02 4100 SEECTIVE DEMOLITION

DIVISION 05 00 00 METALS

05 5000 METAL FABRICATIONS

DIVISION 06 00 00 WOOD, PLASTICS AND COMPOSITES

06 1000 ROUGH CARPENTRY

DIVISION 09 00 00 FINISHES

09 2900 GYPSUM BOARD

09 5113 ACOUSTICAL PANEL CEILINGS

09 9123 INTERIOR PAINTING

DIVISION 22 00 00 PLUMBING

22 0523 GENERAL-DUTY VALVES FOR PLUMBING PIPING

22 0719 PLUMBING PIPING INSULATION

22 1116 DOMESTIC WATER PIPING

22 4500 EMERGENCY PLUMBING FIXTURES

DIVISION 23 00 00 MECHANICAL

23 0513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT

23 0523 GENERAL-DUTY VALVES FOR HVAC PIPING

23 0529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

23 0548 VIBATION CONTROLS FOR HVAC PIPING AND EQUIPMENT

RFQ 12905B22R0007 Tucson AZ 3

USDA CHBRC, Tucson, AZ

Carl Hayden Bee Research Center Design TABLE OF CONTENTS

LSY Architects, LLC 00 01 10 - 2

23 0553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

23 0593 TESTING, ADJUSTING, AND BALANCING

23 0713 DUCT INSULATON

23 0719 HVAC PIPING INSULATION

23 0923 DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC

23 2113 HYDRONIC PIPING

23 3113 METAL DUCTS

23 3300 AIR DUCT ACCESSORIES

23 3713 DIFFUSERS, REGISTERS, AND GRILLES

23 8219 FAN COIL UNITS

DIVISION 26 00 00 ELECTRICAL

26 0510 BASIC ELECTRICAL REQUIREMENTS

26 0519 LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

26 0526 GROUNDING

26 0529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

26 0533 RACEWAY, BOXES, SLEEVES, SEALS FITTINGS ELECTRICAL SYSTEMS

26 0553 ELECTRICAL IDENTIFICATION

26 2416 PANELBOARDS

26 2726 WIRING DEVICES

26 2816 CIRCUIT AND MOTOR DISCONNECT SWITCH

26 2913 ENCLOSED CONTROLLERS

26 5000 INTERIOR LIGHTING FIXTURES

-- End of TOC --

RFQ 12905B22R0007 Tucson AZ 4

USDA, CHBRC Tucson, AZ

Carl Hayden Bee Research Center Design SUMMARY

LSY Architects, LLC 011000 - 1

SECTION 011000

SUMMARY

PART 1 - GENERAL

1.1 PROJECT IDENTIFICATION

A. Project Name and Location: USDA Carl Hayden Bee Research (CHBRC)

Design; Tucson, AZ.

B. Project Summary Description: The purpose of this project is to design, repair, or replace HVAC and Electrical components in Building 107 and

Building 108, of the USDA Carl Hayden Bee Research Center in Tucson

Arizona, that do not conform to the current edition of applicable local and state building codes.

C. Architect: The term Architect refers to the project designer. The

Architect’s status relative to the construction will be delineated in writing by the Contracting Officer prior to the pre-construction conference. The project was designed by:

1. Louviere, Stratton & Yokel, LLC (LSY), Contact: Indicated on drawings.

D. Correspondence from the Contractor to the Architect will be through the Contracting Officer.

E. The Contracting Officer is identified on the drawings and has been assigned as the Contracting Officer for this Project to serve as the representative of the Owner and to provide assistance in administering the Contract for Construction between Government and Contractor.

1.2 WORK UNDER OTHER CONTRACTS

A. The Contractor shall cooperate with other contractors performing related work, including providing labor, materials and other costs necessary to satisfactorily coordinate the Contract work with work performed under other contracts.

B. Preceding Work: Separate contract work may be awarded by USDA for performance of certain construction operations that are expected to be substantially complete before the Work of this Contract begins.

Follow-on activities under this Contract shall be satisfactorily conducted to protect and, if indicated on the drawings, to complete the related preceding separate Contract work.

C. Concurrent Work: Separate contract work be awarded by USDA for performance of certain construction operations that will be conducted simultaneously with the work of this contract.

RFQ 12905B22R0007 Tucson AZ 5

Carl Hayden Bee Research Center Design SUMMARY

LSY Architects, LLC 011000 - 2

Interface work under this contract shall be satisfactorily conducted in compliance with the schedule requirements of the related concurrent separate contract work.

1. Unless otherwise noted on the drawings, a separate contract will be awarded for installation of telecommunication and data systems

(IT Systems).

1.3 MISCELLANEOUS PROVISIONS

A. Work in the extension of existing conditions shall correspond in all respects with the existing conditions to which it connects, or to similar existing conditions, in materials, workmanship and finish.

B. Alterations to Existing Conditions: Existing conditions shall be cut, drilled, removed, temporarily removed, or removed and replaced, as necessary for performance of work under the contract.

1. Replacements of existing conditions that are removed shall match similar existing conditions.

2. Unless otherwise indicated, existing structural members shall not be cut or altered without authorization by the Contracting

Officer.

3. Conditions remaining in place, which are damaged or defaced during the work, shall be restored to the condition existing at time of award of contract.

4. Discolored or unfinished surfaces exposed by removal of existing conditions, that are indicated to be final exposed surfaces, shall be refinished or replaced as necessary to produce uniform and harmonious contiguous surfaces.

C. Existing structures will remain in place

D. Existing utility services shall be disconnected and removed to the extent indicated.

E. Removed items indicated to remain the property of USDA or the government and shall be stored on site where directed by the

Contracting Officer.

1.4 SPECIFICATION FORMATS AND CONVENTIONS

A. Specification Format: The Specifications are organized into Divisions and Sections using the 33-division format and CSI/CSC's "Master

Format" numbering system.

1. Section Identification: The Specifications use section numbers and titles to help cross-referencing in the Contract Documents.

Sections in the specifications are in numeric sequence; however, the sequence is incomplete. Consult the table of contents at the beginning of the specifications to determine numbers and names of sections included in the Contract Documents.

B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, RFQ 12905B22R0007 Tucson AZ 6

Carl Hayden Bee Research Center Design SUMMARY

LSY Architects, LLC 011000 - 3 words, and phrases when used in particular situations. These conventions are as follows:

1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the

Contract Documents indicates.

2. Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.

a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION (Not applicable)

END OF SECTION 011000

RFQ 12905B22R0007 Tucson AZ 7

Carl Hayden Bee Research Center Design WORK RESTRCTIONS

LSY Architects, LLC 011400 - 1

SECTION 011400

WORK RESTRICTIONS

PART 1 - GENERAL

RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

CONTRACTOR USE OF PREMISES

A. The Contracting Officer will conduct a pre-construction survey with the

Contractor to review and document the existing conditions surrounding the project premises prior to the beginning of any construction activity.

B. During that construction period, the Contractor shall have full use of the premises for construction operations, including full use of the site, limited only by the Government’s right to perform work or retain other contractors to perform work on portions of the project.

C. The Contractor shall limit use of the premises to the work areas indicated, to allow for Government occupancy and public use.

1. Confine operations at the site to areas indicated. Do not disturb portions of the site beyond the areas in which Work is indicated.

2. Keep driveways and entrances serving the premises clear and available at all times to the Government, Government employees and visitors. Do not use these areas for parking or storage of materials.

3. Schedule deliveries to minimize space and time requirements for storage of material and equipment on site.

4. Maintain existing building in safe and weather tight condition throughout the construction period. Repair damage caused by construction operations. Take precautions to protect the building, its occupants and the public during the construction period.

5. Keep public areas, such as hallways, stairs, lobbies and toilet rooms, free from accumulation of waste material, rubbish, construction debris and construction materials.

6. Space on the premises will be made available for the Contractor’s storage and related activities, provided that its use will not interfere with operations of the Government. Arrange and gain approval for use of this space through the Contracting Officer.

7. Existing materials and equipment that are removed as part of the construction operations, and that are not reused or designated to be salvaged as Government or other’s property, shall shall become

RFQ 12905B22R0007 Tucson AZ 8

Carl Hayden Bee Research Center Design WORK RESTRCTIONS

LSY Architects, LLC 011400 - 2 the property of the contractor and shall be removed from the site. Storage or sale of excess salvageable materials and equipment is not permitted on site.

8. Pollution producing equipment shall not be located near air intakes where airborne smoke or fumes could be drawn into the building.

9. No parking will be available on site. The Contractor and

Contractor’s employees shall make their own arrangements for vehicle parking off site.

1.1 GOVERNMENT OCCUPANCY

A. Unless otherwise indicated on the drawings, the project site is located in a fully occupied and functional building. The Government will occupy the adjoining administrative spaces during the entire period of construction. Cooperate with the Government’s representatives during construction operations to minimize conflicts and facilitate Government usage. Perform the Work in a manner that does not interfere with the government operations.

B. The Government reserves the right to occupy and to place and install equipment in completed areas of the building prior to Substantial

Completion, provided such occupancy does not interfere with completion of the Work. The Government’s installation of equipment and partial occupancy shall not constitute acceptance of the total Work.

1. Prior to partial Government occupancy, mechanical and electrical systems for the space shall be fully operational, and required inspections and tests shall be successfully completed. Upon occupancy, the Government will operate and maintain mechanical and electrical systems serving the occupied portions of the building.

2. Upon occupancy, Government will assume responsibility for maintenance and custodial service for the occupied portions of the building.

3. The warranty period for the occupied portion of the building only will commence on the date of occupancy by the Government.

1.2 WORKING HOURS

A. Government Occupied Hours: Government personnel are scheduled to occupy the building during the following hours on weekdays, Monday through

Friday, except for established Government Holidays: 9:00am to 5:00pm.

B. Contractor’s General Working Hours: The Contractor working hours shall be generally established to occur during Government Occupied Hours.

C. Work accomplished during Government Unoccupied Hours shall be performed at no additional cost to the Government. Contractor shall submit a proposed schedule and gain the Contracting Officer’s approval at least

RFQ 12905B22R0007 Tucson AZ 9

Carl Hayden Bee Research Center Design WORK RESTRCTIONS

LSY Architects, LLC 011400 - 3

48 hours before proceeding with any work during Government Unoccupied

Hours.

PART 2 – PRODUCTS (Not Applicable)

PART 3 – EXECUTION (Not Applicable)

END OF SECTION 011400

RFQ 12905B22R0007 Tucson AZ 10

Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION

LSY Architects, LLC 013100 - 1

SECTION 013100

PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS.

A. Drawings and general provisions of the Contract, including General and

Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative provisions for managing and coordinating construction operations including, but not limited to, the following:

1. General project coordination.

2. Utility service interruptions.

3. Conservation.

4. Coordination Drawings.

5. Administrative and supervisory personnel.

6. Conferences and meetings.

7. Pre-installation Conferences.

8. Cleaning and protection.

B. Related Sections: This specification section is related to any and all specification sections with explicit or implicit reference to project management and coordination. Specific submittal requirements of these related specification sections are not included in this section. Related sections include but are not limited to the following specification sections:

1. Division 1 Section “Summary”

2. Division 1 Section “Work Restrictions”

3. Division 1 Section “Construction Progress Documentation”

4. Division 1 Section “Submittal Procedures”

5. Division 1 Section “Quality Requirements”

6. Division 1 Section “Safety and Health”

7. Division 1 Section “Closeout Procedures”

1.3 GENERAL PROJECT COORDINATION

A. Coordination of Trades: Coordinate construction operations included in the various sections of the Specifications to provide an efficient and orderly installation of each part of the Work. Coordinate construction operations included under different sections of the

Specifications that depend on each other for proper installation, connection or operation.

1. Schedule construction operations in the sequence required to obtain the best results where the installation of one part of the

RFQ 12905B22R0007 Tucson AZ 11

Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION

LSY Architects, LLC 013100 - 2

Work depends on installation of other components before or after that part.

2. Coordinate installation of different components to provide maximum accessibility for required maintenance, service, removal/installation of component parts, testing and repair.

3. Accommodate items scheduled for later installation.

4. Provide for coordinated incorporation of Contractor's accepted

Value Engineering proposals and Change Orders.

5. Locate pipes, conduits, ducts, equipment, and their related supports so that they do not interfere with the intended use of lifting devices for adjacent equipment and components.

B. Notification: Where required by this section and others, prepare and distribute memoranda to each party performing work at the project site, outlining special procedures required for coordination, including special procedures required for coordination, including required notices, reports, attendance at meetings and meeting minutes as part of the memoranda.

C. Administrative Procedures: Coordinate scheduling and timing of administrative procedures with other construction activities to avoid conflicts and promote orderly progress of the Work. Administrative procedures include but are not limited to the following:

1. Preparation of schedules.

2. Installation and removal of temporary facilities and controls.

3. Delivery and processing of submittals.

4. Progress meetings.

5. Project closeout activities.

1.4 COORDINATION DRAWINGS

A. Prepare coordination drawings when specified, where careful coordination is needed for installation of products and materials fabricated by separate entities, or where limited space availability necessitates maximum utilization of the space for efficient installation of different components.

1. Show the relationship of components shown on separate shop drawings.

2. Indicate required installation sequences.

3. Provide vertical and horizontal dimensions necessary to locate each component and avoid conflicts within the space.

4. Comply with shop drawing requirements for sheet size and submittal methods specified in Division 1 Section "Submittal

Procedures."

5. Refer to Division 2-16 technical specification sections for specific Coordination Drawing requirements.

B. Provide coordination drawings for equipment and system installations in mechanical and electrical rooms and spaces where two or more entities will provide the work and separate shop drawings are insufficient to show coordination.

1.5 CONSERVATION

RFQ 12905B22R0007 Tucson AZ 12

Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION

LSY Architects, LLC 013100 - 3

A. Consider conservation of energy, water and materials in the conduct of construction operation. Salvage materials and equipment involved in the performance of, but not incorporated into, the Work.

B. Waste Management Plan:

1. Establish and document a program to maximize recycling of waste materials. Program shall minimally include the following written information:

a. Designation of a waste management coordinator. Based on the workload required this may be a part-time function.

b. Identification of recyclable materials.

c. Identification of available local recycling firms and agencies to receive recyclable materials.

d. Establishment of quantity goals for collection of each recyclable material.

e. Designation of one or more locations on the project site for collection, sorting and temporary storage of recyclable materials.

f. Means and schedule for transporting and delivery of recyclable materials to recycling firms and agencies.

2. Contractor's waste management coordinator shall provide on-site instruction of workers in the identification, separation and handling of recyclable materials, and shall manage the process for the duration of the Contract.

a. Contractor shall lay out and define specific areas to facilitate separation of materials for recycling, and shall maintain collection bins clearly marked to avoid contamination of the recyclable materials.

b. The waste management coordinator shall report monthly, in writing, the quantity of each recyclable material collected during the previous month and cumulatively to date, compared to the quantity goal, and other points of interest. Copies of each report shall be distributed to each significant party of the project.

1.6 SUBMITTALS

A. Waste management Plan.

1. Submit a copy of the program to the USDA project manager for information within 14 calendar days after Notice to Proceed.

2. Update program and re-submit for information when conditions change.

1.7 ADMINISTRATIVE AND SUPERVISORY PERSONNEL

A. In addition to the Project Superintendent, the Contractor shall provide other administrative and supervisory personnel as required for proper performance of the work.

B. Waste Management Coordinator: Provide a waste management coordinator whose duties shall consist of developing and implementing a program for maximizing recycling of waste.

1.8 CONFERENCES AND MEETINGS

RFQ 12905B22R0007 Tucson AZ 13

Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION

LSY Architects, LLC 013100 - 4

A. Pre-construction Conference:

1. The Contractor shall attend a pre-construction conference scheduled by the Project Officer at a time and place convenient to both parties. Work shall not commence prior to the conference. Conference shall review responsibilities and personnel assignments.

2. Attendees: Participants at the conference shall be familiar with the project, shall be authorized to conclude matters relating to the Work, and at a minimum include representatives of the following parties or their designated representatives:

a. USDA Project Manager

b. Architect

c. Contractor

d. Major subcontractor

e. Major Suppliers

f. USDA Division of Safety, including representatives from the

Pest Management Section and the Occupational Safety and

Health Branch

g. Other concerned parties

3. Agenda: Subjects for discussion shall include items of significance that could affect progress, including but not limited to the following:

a. Tentative construction schedule

b. Critical work sequencing

c. Designation of responsible personnel

d. Procedures for processing field decisions and Change Orders

e. Procedures for processing Applications for Payment

f. Distribution of Contract Documents

g. Submittal of Shop Drawings, Product Data, and Samples

h. Preparation of Record Documents

i. Use of the premises

j. Parking availability

k. Office, work, and storage areas

l. Equipment deliveries and priorities

m. Safety procedures

n. First Aid

o. Security

p. Housekeeping and progress cleaning

q. Working hours

r. Permits

s. Integrated Pest Management procedures.

4. Reporting: No later than 3 calendar days after the conference, the Contractor shall distribute minutes of the conference to each party present and to other concerned parties.

5. This meeting may satisfy the requirement for a Pre-construction

Safety Meeting in Division 1 Section “Safety and Health.”

B. Pre-installation Conferences: The Contractor shall conduct a pre-installation conference at the Project Site before each construction activity that requires coordination with other construction. Pre-installation conferences may be combined with Preparatory Phase meetings described in Division 1 Section “Construction Quality

Control.”

1. Attendees: In addition to the Contractor's representative, the installer and representatives of manufacturers and fabricators

RFQ 12905B22R0007 Tucson AZ 14

Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION

LSY Architects, LLC 013100 - 5 involved in or affected by the installation, and its coordination or integration with other materials and installations that have preceded or will follow, shall attend. Prior to conferences, advise the USDA Project Manager of scheduled conference dates.

2. Agenda: Review the progress of other construction activities and preparations for the particular activity under consideration at each pre-installation conference, including requirements for the following.

a. Contract Documents

b. Options

c. Related Change Orders, including accepted Value Engineering proposals

d. Purchases

e. Deliveries

f. Submittals

g. Review of mockups

h. Possible conflicts

i. Compatibility problems

j. Time schedules

k. Manufacturer’s recommendations

l. Warranty requirements

m. Compatibility of materials

n. Acceptability of substrates

o. Quality requirements

p. Temporary facilities and controls

q. Space and access limitations

r. Governing regulations

s. Safety

t. Testing and inspection requirements

u. Required performance results

v. Protection

3. Reporting: Record significant discussions and agreements and disagreements of each conference. No later than 3 calendar days after each conference, the Contractor shall distribute minutes of the conference to each party present and to other concerned parties.

4. Do not proceed with the installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to the performance of the work, and reconvene the conference at the earliest feasible date.

C. Progress Meetings: The USDA Project Manager shall conduct weekly progress meetings at the Project Site. Dates of meetings shall be coordinated with preparation of the payment request.

1. Attendees: In addition to the Contractor, each subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work. The USDA Project Manager shall include the project designer in these meetings as required.

2. Agenda: Review and correct or approve minutes of the previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project.

RFQ 12905B22R0007 Tucson AZ 15

Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION

LSY Architects, LLC 013100 - 6

3. Contractor's Construction Schedule: Review progress since the last meeting. Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine the required contractor response to construction behind schedule; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

a. At each progress meeting, the Contractor will provide a list of construction activities completed in the previous seven calendar days, activities in progress with percent completed, activities scheduled to start in the next 14 calendar days, and activities to start in the next thirty calendar days as derived from the accepted project schedule.

4. Review the present and future needs of each entity present, including but not limited to the following:

a. Interface requirements

b. Time

c. Sequence of operations

d. Status of submittals

e. Deliveries

f. Off-Site fabrication

g. Access

h. Site Utilization

i. Temporary facilities and controls

j. Hours of work

k. Hazards and risks

l. Proposed or scheduled utility service interruptions

m. Housekeeping and progress cleaning

n. Quality and work standards

o. Deficiencies

p. Change Orders

q. Documentation of information for payment requests

r. Updating of Record Documents

5. The Contractor shall present Record Drawings at progress meetings for review by USDA, if so requested.

6. The Progress meeting may be in conjunction with the Quality

Control (QC) Meeting required per Division 1 Section

“Construction Quality Control.”

D. Coordination Meetings: Conduct biweekly project coordination meetings as required, to verify detailed coordination procedures for the upcoming construction operations in order to avoid potential problems and misunderstandings.

1. Attendees: In addition to the Contractor, each subcontractor, supplier or other entity involved in coordination or planning construction activities shall be represented. Participants shall be authorized to conclude matters relating to the work.

2. Agenda: Review the plans and requirements of each entity present, including but not limited to the subjects listed for

Progress Meetings.

3. Reporting: No later than 3 calendar days after each meeting, the

Contractor shall distribute minutes of the meeting to each party present and to other concerned parties who should have been

RFQ 12905B22R0007 Tucson AZ 16

Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION

LSY Architects, LLC 013100 - 7 present. Include a brief summary, in narrative form, of progress since the previous meeting and report.

PART 2 - PRODUCTS (Not applicable)

PART 3 - EXECUTION

3.1 GENERAL COORDINATION PROVISIONS

A. Inspection of Conditions: Prior to installations, require the installer of each major component to inspect both the substrate and conditions under which work is to be performed.

1. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.

B. Construction in Progress: Keep construction in progress, adjoining materials in place, and adjoining materials clean during handling and installation. Apply protective coverings where required for protection from damage or deterioration.

C. Completed Construction: Clean completed construction, and provide maintenance, as frequently as necessary to prevent damage or soiling or other deterioration through the remainder of the construction period. Adjust and lubricate operable components as necessary to assure operability without damage.

D. Limiting Exposures: Supervise construction operations to prevent exposure of any part of construction, completed or in progress, to harmful, dangerous, damaging or otherwise deleterious conditions during the construction period. Such conditions include but are not limited to the following:

1. Excessive static or dynamic loading.

2. Excessive internal or external pressures.

3. Excessively high or low temperatures.

4. Thermal shock.

5. Excessively high or low humidity.

6. Pollution and air contamination.

7. Water or ice.

8. Chemicals and solvents.

9. Light

10. Radiation

11. Puncture

12. Abrasion

13. Heavy Traffic

14. Soiling, staining, and corrosion

15. Bacteria

16. Rodent and insect infestation

17. Combustion

18. Electrical Current

19. High-speed operation

20. Improper lubrication

21. Unusual wear or other misuse

22. Contact between incompatible materials

23. Destructive testing

RFQ 12905B22R0007 Tucson AZ 17

Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION

LSY Architects, LLC 013100 - 8

24. Misalignment

25. Excessive weathering

26. Unprotected storage

27. Improper shipping or handling

28. Theft or vandalism

END OF SECTION 013100

RFQ 12905B22R0007 Tucson AZ 18

Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION

LSY Architects, LLC 013200 - 1

SECTION 013200

CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and

Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes certain schedules and reports required for documenting the progress of construction during the performance of the work, including the following:

1. Preliminary Construction Schedule

2. Contractor's Construction Schedule

3. Material and Equipment Delivery Schedule

4. Submittal Schedule

5. Contractor's Production Report

6. Material Location Reports

7. Field Condition reports

8. Special reports

B. Related Sections: This specification section is related to any and all specification sections with explicit or implicit reference to construction progress documentation. Specific submittal requirements of these related specification sections are not included in this section. Related sections include but are not limited to the following specification sections:

1. Division 1 Section "Summary"

2. Division 1 Section "Work Restrictions"

3. Division 1 Section "Submittal Procedures"

4. Division 1 Section "Quality Requirements"

5. Division 1 Section "References"

6. Division 1 Section "Construction Quality Control"

7. Division 1 Section "Temporary Facilities and Controls"

8. Division 1 Section "Safety and Health"

9. Division 1 Section "Execution Requirements"

10. Division 1 Section "Cutting and Patching"

11. Division 1 Section "Closeout Procedures"

12. Division 1 Section "Project Record Documents"

13. Division 1 Section "Operation and Maintenance Documentation"

14. Division 2 Section "Selective Demolition"

RFQ 12905B22R0007 Tucson AZ 19

Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION

LSY Architects, LLC 013200 - 2

1.3 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor activity is an activity that must be completed before a given activity can be started.

B. CPM: Critical Path Method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

C. Critical Path: The longest continuous chain of activities through the network schedule that establishes the minimum overall Project duration and contains no float.

D. Event: The starting or ending point of an activity.

E. Float: The measure of leeway in starting and completing an activity.

1. Float time is not for the exclusive use or benefit of either the

USDA or the Contractor.

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the following activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

F. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

G. Milestone: A key or critical point in time for reference or measurement.

H. Network Diagram: A graphic diagram of a network schedule, showing activities and activity relationships.

1.4 SUBMITTALS

A. Submittal Schedule: Prepare and submit a complete schedule of submittals within 10 calendar days after receipt of Notice to Proceed.

B. Field Condition Reports: When the need to take corrective action requires a departure from the Contract Documents, prepare a detailed report describing the problem and recommended changes and submit a copy to the USDA.

RFQ 12905B22R0007 Tucson AZ 20

Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION

LSY Architects, LLC 013200 - 3

PART 2 - PRODUCTS

2.1 MATERIAL AND EQUIPMENT DELIVERY SCHEDULE.

A. Submit for Contractor Officer approval a schedule showing procurement plans for materials, plant, and equipment. Submit in the format and content as directed by the Contractor Officer and include as a minimum the following information:

1. Description

2. Date of purchase order

3. Promised shipping date

4. Name of manufacturer or supplier

5. Date delivery is expected

6. Date the material or equipment is required according to the current construction schedule

B. Update the equipment delivery schedule at monthly intervals indicating material deliveries and purchases. Reflect any changes occurring since the last update. Submit copies of the purchase orders and confirmation of the delivery dates as directed.

1. Revisions to the approved schedule which will change completion dates require USDA approval.

2.2 PRELIMINARY CONSTRUCTION SCHEDULE:

A. Prepare and submit for Contracting Officer approval a preliminary time scaled arrow diagram for the project comprised of an outline of activities for the first thirty calendar days of construction. Include each significant construction activity. Coordinate each activity in the network with other activities. Schedule each activity in proper sequence and show the critical path graphically. Include the following minimum information for each activity:

1. Beginning event number

2. Description

3. Duration estimate

4. Scheduled start or days after commencement of the contract

5. Scheduled finish date or days after commencement of the contract.

B. Provide a separate fragnet for each Definable Feature of Work included in the Draft Contractor QC Plan required by Division 1 Section

"Construction Quality Control."

C. Schedule shall be time scaled in not more than weekly increments with dates of the first day of each week (Sunday) indicated.

D. Completion of the work shall be in advance of the date for completion of the contract.

E. Provide a skeleton diagram for the work beyond the preliminary time scaled arrow diagram.

F. Tabulation of Submittals: With the submission of the Preliminary

Construction Schedule, include a tabulation by date of submittals

RFQ 12905B22R0007 Tucson AZ 21

Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION

LSY Architects, LLC 013200 - 4 required during the first forty-five calendar days of construction, or show the submittals on the arrow diagram. Include those submittals required to maintain orderly progress of the work and those required early because of long lead-time for maintenance or fabrication.

1. Submittal review timelines shall be as specified in Division 1

Section "Submittal Procedures." No additional time shall be allowed the contractor for failure to allow the specified time in the submittal schedule for review, approval, and follow on contractor tasks such as delivery and installation.

G. Cash Requirements Prediction: With the submission of the Preliminary

Construction Schedule, include a preliminary monthly cash requirement prediction based on the scheduled progress of the activities.

H. Distribution: Submit 3 copies of the preliminary construction schedule to the Contracting Officer.

I. Within 7 calendar days after receipt of the preliminary construction schedule, the Contracting Officer will meet with the Contractor for a joint review, correction and adjustment of the preliminary schedule.

J. Within 3 calendar days after the joint review, the Contractor shall revise the preliminary construction schedule in accordance with agreements at the joint review, and submit 3 copies of the revised

Preliminary Construction Schedule to the Contracting Officer. The resubmission will be reviewed by the Contracting Officer and, if found to be adequate, one approved copy will be returned to the Contractor as the basis for the Contractor's construction schedule.

K. Review comments made by USDA on the Preliminary Construction Schedule shall not relieve the Contractor from compliance with the requirements of the Contract Documents. The Contractor remains responsible for scheduling, sequencing and prosecuting the work to comply with the requirements of the Contract documents. USDA acceptance extends only to the activities of the contractor's schedule that USDA has been assigned responsibility for and agrees it is responsible. USDA will also review for contract-imposed schedule constraints and conformance, and cost loading of the CPM activities. Comments offered on other parts of the schedule which the Contractor is assigned responsibility are offered as a courtesy and are not conditions of USDA acceptance;

but are for the general conformance with established industry schedule concepts.

2.3 CONTRACTOR'S CONSTRUCTION SCHEDULE

A. Prepare and periodically update a comprehensive, fully developed, construction schedule.

1. Depending on the size and complexity of the project, prepare a

CPM-program based type or a time scaled, bar chart type schedule.

The type of schedule required for the project is indicated on the drawings.

RFQ 12905B22R0007 Tucson AZ 22

Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION

LSY Architects, LLC 013200 - 5

2.4 TIME SCALED, BAR CHART TYPE CONTRACTOR’S CONSTRUCTION SCHEDULE

A. Basis for developing the Contractor's Construction Schedule shall be the approved Preliminary Construction Schedule including updates and feedback received since the start of construction. Requirements for the Contractor's Construction Schedule are in addition to those of the

Preliminary Construction Schedule as appropriate.

B. Prepare a time scaled, bar chart type construction schedule meeting all of the requirements stipulated for the Preliminary Schedule and expanded to include the entire construction duration. Include each significant construction activity. Provide a separate fragnet for each Definable Feature of Work included in the Draft Contractor QC

Plan required by Division 1 Section "Construction Quality Control."

Coordinate each activity in the network with other activities.

Schedule each activity in proper sequence. Include the following minimum data for each activity:

1. Beginning event number.

2. Description.

3. Scheduled start date.

4. Scheduled finish date.

5. Actual start date, when applicable.

6. Actual finish date, when applicable.

7. Percent complete.

2.5 CPM-PROGRAM BASED TYPE CONTRACTOR’S CONSTRUCTION SCHEDULE

A. Basis for developing the Contractor's Construction Schedule shall be the approved Preliminary Construction Schedule including updates and feedback received since the start of construction. All requirements for the Contractor's Construction Schedule are in addition to those of the Preliminary Construction Schedule as appropriate.

B. Include each significant construction activity. Provide a separate fragnet for each Definable Feature of Work included in the Draft

Contractor QC Plan required by Division 1 Section "Construction

Quality Control." Coordinate each activity in the network with other activities. Schedule each activity in proper sequence. Show critical path graphically. Include the following minimum data for each activity:

1. Beginning event number.

2. Description.

3. Duration estimate.

4. Cost estimate.

5. Scheduled start date.

6. Scheduled finish date.

7. Actual start date, when applicable.

8. Actual finish date, when applicable.

9. Percent complete.

C. Schedule shall be produced by a computer program that has been developed specifically to manage construction schedules and capable of accepting revised completion dates as modified by approved time

RFQ 12905B22R0007 Tucson AZ 23

Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION

LSY Architects, LLC 013200 - 6 adjustments and re-computation of all tabulation dates and float accordingly. Computer program shall be capable of displaying the schedule in a variety of graphical formats including Gannt Charts and

Pert Charts.

D. Cost Correlation: Provide a cost correlation line at the head of the schedule to indicate planned and actual cost. As work progresses, show dollar volume of work performed as of the dates used for applications for payment. The total of all activity costs shall equal the contract price.

E. Within each construction activity's time fragnet, indicate estimated completion percentages in not more than 5 percent increments and, as work progresses, place marks to indicate actual completion percentages.

F. Within 10 calendar days after receipt of the preliminary construction schedule, the Contracting Officer will meet with the Contractor for a joint review, correction and adjustment of the preliminary schedule.

G. Within 5 calendar days after the joint review, the Contractor shall revise the preliminary construction schedule in accordance with agreements at the joint review, and submit 1 copy of the revised

Preliminary Construction Schedule to the Contracting Officer. The resubmission will be reviewed by the Contracting Officer and, if found to be adequate, one approved copy will be returned to the Contractor as the basis for the Contractor's construction.

H. Review comments made by USDA on the Preliminary Construction Schedule shall not relieve the Contractor from compliance with the requirements of the Contract Documents. The Contractor remains responsible for scheduling, sequencing and prosecuting the work to comply with the requirements of the Contract documents. USDA acceptance extends only to the activities of the contractor's schedule that USDA has been assigned responsibility for and agrees it is responsible. USDA will also review for contract-imposed schedule constraints and conformance, and cost loading of the CPM activities. Comments offered on other parts of the schedule which the Contractor is assigned responsibility are offered as a courtesy and are not conditions of USDA acceptance;

but are for the general conformance with established industry schedule concepts.

I. Each activity will be assigned a Schedule Activity Number.

J. Activity Duration: Define activities so no activity is longer than thirty calendar days, unless specifically allowed by Contracting

Officer.

K. Procurement Activities: Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 days, as separate activities in the schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.

RFQ 12905B22R0007 Tucson AZ 24

Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION

LSY Architects, LLC 013200 - 7

L. Submittal Review Time: Include review and resubmittal times indicated in Division 1 Section "Submittal Procedures" in the schedule.

Coordinate submittal review times in the Contractor's Construction

Schedule with the Submittals Schedule.

M. Startup and Testing Time: Include not less than twenty-one calendar days for startup and testing.

N. Include a separate activity for each contract if work is under more than one contract.

O. Include a separate activity for each portion of the work performed by

USDA or other USDA contractors that directly impacts the work of this contract.

P. Include a separate activity for each product. Include any delivery dates indicated in Division 1, Section "Summary." Delivery dates indicated stipulate the latest possible delivery date.

Q. Work Restrictions: Show the effect of the following items on the schedule:

1. Coordination with existing construction.

2. Limitations of continued occupancies.

3. Uninterruptible services.

4. Partial occupancy before Substantial Completion.

5. Use of premises restrictions.

6. Provisions for future construction.

7. Seasonal variations.

8. Environmental control.

R. Work Stages: Indicate important stages of construction for each major portion of the work, including, but not limited to, the following:

1. Subcontract awards.

2. Submittals.

3. Purchases.

4. Mockups.

5. Fabrication.

6. Sample testing.

7. Deliveries.

8. Installation.

9. Tests and inspections.

10. Adjusting.

11. Curing.

12. Startup and placement into final use and operation.

13. Commissioning

S. Area Separations: Identify each major area of construction for each major portion of the work. Indicate where each construction activity within a major area must be sequenced or integrated with other construction activities to provide for the following:

1. Completion of mechanical installation.

2. Completion of electrical installation.

3. Substantial Completion.

RFQ 12905B22R0007 Tucson AZ 25

Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION

LSY Architects, LLC 013200 - 8

4. Commissioning

T. Other Constraints: None.

U. Milestones: Include milestones indicated in the Contract Documents in the schedule including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Acceptance.

V. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall project schedule.

W. Updating: Provide an updated schedule in conjunction with project meeting requirements specified in Division 1 Section "Project

Management and Coordination." In addition, should actual timelines for events or activities suggest a significant change in the planned progress of the work, the contractor shall submit for Contracting

Officer approval a revised schedule with justification for the change.

Highlight or otherwise emphasize revisions for ease of identification.

1. Show construction schedule baseline of initially approved construction schedule on each updated schedule.

X. Reports: As a minimum, be prepared to furnish the following computer produced reports from sorts of the basic activity data. Actual reports required and report frequency will be determined by the

Contracting Officer.

1. Activity sort by the preceding event number from lowest to highest and then in the order of the following event number.

2. Activity sort by amount of total float, then in order of preceding event number.

3. Activity sort in order of latest allowable start dates, then in order of preceding event numbers.

4. Activity sort in order of latest allowable finish dates, then in order of preceding event numbers.

5. Activity sort by trade code, early start date and total float.

6. Contractor's monthly payment request sorted by responsibility.

Y. Float is not for the exclusive use or benefit of either USDA or the

Contractor, but must be used in the best interest of completing the project on time. Extensions of time for performance required under the Contract Clauses entitled "Changes", "Differing Site Conditions", or other applicable clauses, will be granted only to the extent that the equitable time adjustment for the activity or activities affected exceeds the total float along the activities involved.

Z. Distribution: Print and distribute copies of the initial Contractor's

Construction Schedule, and each updated or revised schedule, to the

Contracting Officer, as…