This request for proposals (RFP) solicits fixed-price construction services for HVAC and electrical repairs and replacements at two buildings of the USDA Carl Hayden Bee Research Center in Tucson, Arizona. The work includes providing all labor, materials, tools, equipment, supplies, transportation, and supervision to renovate the buildings in conformance with applicable local and state building codes. The solicitation will be posted on March 17, 2022 to SAM.gov and issued electronically only, with questions due to Theodore Blume by email. The requirement is set aside for small businesses with a size standard of $39.5 million for NAICS code 236220. The disclosed magnitude of the contract is between $500,000 and $1,000,000. A site visit date will be specified in the solicitation. The U.S. Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Pacific West Area is the contracting agency.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture
Carl Hayden Bee
Research Center
TUCSON, ARIZONA
SPECIFICATIONS
LSY No. 20037.01
Final Submission
July 13, 2021
Archi tects & Laboratory Planners
Louviere, Stratton & Yokel, LLC
8484 Georgia Avenue Suite 650
Silver Spring, Maryland 20910
T 301.588.1500
F 301.5885300 www.lsyarchitects.com
RFQ 12905B22R0007 Tucson AZ 1
United States
Department of
Agriculture
Carl Hayden Bee
Research Center
TUCSON, ARIZONA
SPECIFICATIONS
LSY No. 20037.01
July 13, 2021
Burns & McDonnell
8201 Norman Center
Drive, Suite 500
Bloomington, Minnesota
Telephone: 952-656-6003 www.burnsmcd.com
Archi tects & Laboratory Pl anners
Louviere, Stratton & Yokel, LLC
8484 Georgia Avenue Suite 650
Silver Spring, Maryland 20910
T 301.588.1500
F 301.5885300 www.lsyarchitects.com
07/12 /21
ELECTRICAL MECHANICAL
RFQ 12905B22R0007 Tucson AZ 2
USDA CHBRC, Tucson, AZ
Carl Hayden Bee Research Center Design TABLE OF CONTENTS
LSY Architects, LLC 00 01 10 - 1
DOCUMENT 00 01 10
TABLE OF CONTENTS
Section No. Title
Title Page
00 01 10 TABLE OF CONTENTS
DIVISION 01 00 00 GENERAL REQUIREMENTS
01 1000 SUMMARY
01 4000 WORK RESTRICTIONS
01 3100 PROJECT MANAGEMENT AND COORDINATION
01 3200 CONSTRUCTION PROGRESS DOCUMENTATION
01 3300 SUBMITTAL PROCEDURES
01 3550 CONSTRUCTION SECURITY REQUIREMENTS
01 4500 QUALITY REQUIREMENTS
01 4200 REFERENCES
01 4500 CONSTRUCTION QUALITY CONTROL
01 5000 TEMPORARY FACILITIES AND CONTROLS
01 5950 SAFETY AND HEALTH
01 6000 PRODUCT REQUIREMENTS
01 7000 EXECUTION REQUIREMENTS
01 7310 CUTTING AND PATCHING
01 7350 FIRE PREVENTION PRECAUTIONS FOR HOT WORK
01 7419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 7700 CLOSEOUT PROCEDURES
01 7810 PROJECT RECORD DOCUMENTS
01 7823 OPERATION AND MAINTENANCE DOCUMENTATION
01 8111 SUSTAINABLE DESIGN REQUIREMENTS
DIVISION 02 00 00 EXISTING CONDITIONS
02 4100 SEECTIVE DEMOLITION
DIVISION 05 00 00 METALS
05 5000 METAL FABRICATIONS
DIVISION 06 00 00 WOOD, PLASTICS AND COMPOSITES
06 1000 ROUGH CARPENTRY
DIVISION 09 00 00 FINISHES
09 2900 GYPSUM BOARD
09 5113 ACOUSTICAL PANEL CEILINGS
09 9123 INTERIOR PAINTING
DIVISION 22 00 00 PLUMBING
22 0523 GENERAL-DUTY VALVES FOR PLUMBING PIPING
22 0719 PLUMBING PIPING INSULATION
22 1116 DOMESTIC WATER PIPING
22 4500 EMERGENCY PLUMBING FIXTURES
DIVISION 23 00 00 MECHANICAL
23 0513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT
23 0523 GENERAL-DUTY VALVES FOR HVAC PIPING
23 0529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
23 0548 VIBATION CONTROLS FOR HVAC PIPING AND EQUIPMENT
RFQ 12905B22R0007 Tucson AZ 3
USDA CHBRC, Tucson, AZ
Carl Hayden Bee Research Center Design TABLE OF CONTENTS
LSY Architects, LLC 00 01 10 - 2
23 0553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
23 0593 TESTING, ADJUSTING, AND BALANCING
23 0713 DUCT INSULATON
23 0719 HVAC PIPING INSULATION
23 0923 DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC
23 2113 HYDRONIC PIPING
23 3113 METAL DUCTS
23 3300 AIR DUCT ACCESSORIES
23 3713 DIFFUSERS, REGISTERS, AND GRILLES
23 8219 FAN COIL UNITS
DIVISION 26 00 00 ELECTRICAL
26 0510 BASIC ELECTRICAL REQUIREMENTS
26 0519 LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
26 0526 GROUNDING
26 0529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 0533 RACEWAY, BOXES, SLEEVES, SEALS FITTINGS ELECTRICAL SYSTEMS
26 0553 ELECTRICAL IDENTIFICATION
26 2416 PANELBOARDS
26 2726 WIRING DEVICES
26 2816 CIRCUIT AND MOTOR DISCONNECT SWITCH
26 2913 ENCLOSED CONTROLLERS
26 5000 INTERIOR LIGHTING FIXTURES
-- End of TOC --
RFQ 12905B22R0007 Tucson AZ 4
USDA, CHBRC Tucson, AZ
Carl Hayden Bee Research Center Design SUMMARY
LSY Architects, LLC 011000 - 1
SECTION 011000
SUMMARY
PART 1 - GENERAL
1.1 PROJECT IDENTIFICATION
A. Project Name and Location: USDA Carl Hayden Bee Research (CHBRC)
Design; Tucson, AZ.
B. Project Summary Description: The purpose of this project is to design, repair, or replace HVAC and Electrical components in Building 107 and
Building 108, of the USDA Carl Hayden Bee Research Center in Tucson
Arizona, that do not conform to the current edition of applicable local and state building codes.
C. Architect: The term Architect refers to the project designer. The
Architect’s status relative to the construction will be delineated in writing by the Contracting Officer prior to the pre-construction conference. The project was designed by:
1. Louviere, Stratton & Yokel, LLC (LSY), Contact: Indicated on drawings.
D. Correspondence from the Contractor to the Architect will be through the Contracting Officer.
E. The Contracting Officer is identified on the drawings and has been assigned as the Contracting Officer for this Project to serve as the representative of the Owner and to provide assistance in administering the Contract for Construction between Government and Contractor.
1.2 WORK UNDER OTHER CONTRACTS
A. The Contractor shall cooperate with other contractors performing related work, including providing labor, materials and other costs necessary to satisfactorily coordinate the Contract work with work performed under other contracts.
B. Preceding Work: Separate contract work may be awarded by USDA for performance of certain construction operations that are expected to be substantially complete before the Work of this Contract begins.
Follow-on activities under this Contract shall be satisfactorily conducted to protect and, if indicated on the drawings, to complete the related preceding separate Contract work.
C. Concurrent Work: Separate contract work be awarded by USDA for performance of certain construction operations that will be conducted simultaneously with the work of this contract.
RFQ 12905B22R0007 Tucson AZ 5
Carl Hayden Bee Research Center Design SUMMARY
LSY Architects, LLC 011000 - 2
Interface work under this contract shall be satisfactorily conducted in compliance with the schedule requirements of the related concurrent separate contract work.
1. Unless otherwise noted on the drawings, a separate contract will be awarded for installation of telecommunication and data systems
(IT Systems).
1.3 MISCELLANEOUS PROVISIONS
A. Work in the extension of existing conditions shall correspond in all respects with the existing conditions to which it connects, or to similar existing conditions, in materials, workmanship and finish.
B. Alterations to Existing Conditions: Existing conditions shall be cut, drilled, removed, temporarily removed, or removed and replaced, as necessary for performance of work under the contract.
1. Replacements of existing conditions that are removed shall match similar existing conditions.
2. Unless otherwise indicated, existing structural members shall not be cut or altered without authorization by the Contracting
Officer.
3. Conditions remaining in place, which are damaged or defaced during the work, shall be restored to the condition existing at time of award of contract.
4. Discolored or unfinished surfaces exposed by removal of existing conditions, that are indicated to be final exposed surfaces, shall be refinished or replaced as necessary to produce uniform and harmonious contiguous surfaces.
C. Existing structures will remain in place
D. Existing utility services shall be disconnected and removed to the extent indicated.
E. Removed items indicated to remain the property of USDA or the government and shall be stored on site where directed by the
Contracting Officer.
1.4 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections using the 33-division format and CSI/CSC's "Master
Format" numbering system.
1. Section Identification: The Specifications use section numbers and titles to help cross-referencing in the Contract Documents.
Sections in the specifications are in numeric sequence; however, the sequence is incomplete. Consult the table of contents at the beginning of the specifications to determine numbers and names of sections included in the Contract Documents.
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, RFQ 12905B22R0007 Tucson AZ 6
Carl Hayden Bee Research Center Design SUMMARY
LSY Architects, LLC 011000 - 3 words, and phrases when used in particular situations. These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the
Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not applicable)
END OF SECTION 011000
RFQ 12905B22R0007 Tucson AZ 7
Carl Hayden Bee Research Center Design WORK RESTRCTIONS
LSY Architects, LLC 011400 - 1
SECTION 011400
WORK RESTRICTIONS
PART 1 - GENERAL
RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.
CONTRACTOR USE OF PREMISES
A. The Contracting Officer will conduct a pre-construction survey with the
Contractor to review and document the existing conditions surrounding the project premises prior to the beginning of any construction activity.
B. During that construction period, the Contractor shall have full use of the premises for construction operations, including full use of the site, limited only by the Government’s right to perform work or retain other contractors to perform work on portions of the project.
C. The Contractor shall limit use of the premises to the work areas indicated, to allow for Government occupancy and public use.
1. Confine operations at the site to areas indicated. Do not disturb portions of the site beyond the areas in which Work is indicated.
2. Keep driveways and entrances serving the premises clear and available at all times to the Government, Government employees and visitors. Do not use these areas for parking or storage of materials.
3. Schedule deliveries to minimize space and time requirements for storage of material and equipment on site.
4. Maintain existing building in safe and weather tight condition throughout the construction period. Repair damage caused by construction operations. Take precautions to protect the building, its occupants and the public during the construction period.
5. Keep public areas, such as hallways, stairs, lobbies and toilet rooms, free from accumulation of waste material, rubbish, construction debris and construction materials.
6. Space on the premises will be made available for the Contractor’s storage and related activities, provided that its use will not interfere with operations of the Government. Arrange and gain approval for use of this space through the Contracting Officer.
7. Existing materials and equipment that are removed as part of the construction operations, and that are not reused or designated to be salvaged as Government or other’s property, shall shall become
RFQ 12905B22R0007 Tucson AZ 8
Carl Hayden Bee Research Center Design WORK RESTRCTIONS
LSY Architects, LLC 011400 - 2 the property of the contractor and shall be removed from the site. Storage or sale of excess salvageable materials and equipment is not permitted on site.
8. Pollution producing equipment shall not be located near air intakes where airborne smoke or fumes could be drawn into the building.
9. No parking will be available on site. The Contractor and
Contractor’s employees shall make their own arrangements for vehicle parking off site.
1.1 GOVERNMENT OCCUPANCY
A. Unless otherwise indicated on the drawings, the project site is located in a fully occupied and functional building. The Government will occupy the adjoining administrative spaces during the entire period of construction. Cooperate with the Government’s representatives during construction operations to minimize conflicts and facilitate Government usage. Perform the Work in a manner that does not interfere with the government operations.
B. The Government reserves the right to occupy and to place and install equipment in completed areas of the building prior to Substantial
Completion, provided such occupancy does not interfere with completion of the Work. The Government’s installation of equipment and partial occupancy shall not constitute acceptance of the total Work.
1. Prior to partial Government occupancy, mechanical and electrical systems for the space shall be fully operational, and required inspections and tests shall be successfully completed. Upon occupancy, the Government will operate and maintain mechanical and electrical systems serving the occupied portions of the building.
2. Upon occupancy, Government will assume responsibility for maintenance and custodial service for the occupied portions of the building.
3. The warranty period for the occupied portion of the building only will commence on the date of occupancy by the Government.
1.2 WORKING HOURS
A. Government Occupied Hours: Government personnel are scheduled to occupy the building during the following hours on weekdays, Monday through
Friday, except for established Government Holidays: 9:00am to 5:00pm.
B. Contractor’s General Working Hours: The Contractor working hours shall be generally established to occur during Government Occupied Hours.
C. Work accomplished during Government Unoccupied Hours shall be performed at no additional cost to the Government. Contractor shall submit a proposed schedule and gain the Contracting Officer’s approval at least
RFQ 12905B22R0007 Tucson AZ 9
Carl Hayden Bee Research Center Design WORK RESTRCTIONS
LSY Architects, LLC 011400 - 3
48 hours before proceeding with any work during Government Unoccupied
Hours.
PART 2 – PRODUCTS (Not Applicable)
PART 3 – EXECUTION (Not Applicable)
END OF SECTION 011400
RFQ 12905B22R0007 Tucson AZ 10
Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION
LSY Architects, LLC 013100 - 1
SECTION 013100
PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS.
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes administrative provisions for managing and coordinating construction operations including, but not limited to, the following:
1. General project coordination.
2. Utility service interruptions.
3. Conservation.
4. Coordination Drawings.
5. Administrative and supervisory personnel.
6. Conferences and meetings.
7. Pre-installation Conferences.
8. Cleaning and protection.
B. Related Sections: This specification section is related to any and all specification sections with explicit or implicit reference to project management and coordination. Specific submittal requirements of these related specification sections are not included in this section. Related sections include but are not limited to the following specification sections:
1. Division 1 Section “Summary”
2. Division 1 Section “Work Restrictions”
3. Division 1 Section “Construction Progress Documentation”
4. Division 1 Section “Submittal Procedures”
5. Division 1 Section “Quality Requirements”
6. Division 1 Section “Safety and Health”
7. Division 1 Section “Closeout Procedures”
1.3 GENERAL PROJECT COORDINATION
A. Coordination of Trades: Coordinate construction operations included in the various sections of the Specifications to provide an efficient and orderly installation of each part of the Work. Coordinate construction operations included under different sections of the
Specifications that depend on each other for proper installation, connection or operation.
1. Schedule construction operations in the sequence required to obtain the best results where the installation of one part of the
RFQ 12905B22R0007 Tucson AZ 11
Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION
LSY Architects, LLC 013100 - 2
Work depends on installation of other components before or after that part.
2. Coordinate installation of different components to provide maximum accessibility for required maintenance, service, removal/installation of component parts, testing and repair.
3. Accommodate items scheduled for later installation.
4. Provide for coordinated incorporation of Contractor's accepted
Value Engineering proposals and Change Orders.
5. Locate pipes, conduits, ducts, equipment, and their related supports so that they do not interfere with the intended use of lifting devices for adjacent equipment and components.
B. Notification: Where required by this section and others, prepare and distribute memoranda to each party performing work at the project site, outlining special procedures required for coordination, including special procedures required for coordination, including required notices, reports, attendance at meetings and meeting minutes as part of the memoranda.
C. Administrative Procedures: Coordinate scheduling and timing of administrative procedures with other construction activities to avoid conflicts and promote orderly progress of the Work. Administrative procedures include but are not limited to the following:
1. Preparation of schedules.
2. Installation and removal of temporary facilities and controls.
3. Delivery and processing of submittals.
4. Progress meetings.
5. Project closeout activities.
1.4 COORDINATION DRAWINGS
A. Prepare coordination drawings when specified, where careful coordination is needed for installation of products and materials fabricated by separate entities, or where limited space availability necessitates maximum utilization of the space for efficient installation of different components.
1. Show the relationship of components shown on separate shop drawings.
2. Indicate required installation sequences.
3. Provide vertical and horizontal dimensions necessary to locate each component and avoid conflicts within the space.
4. Comply with shop drawing requirements for sheet size and submittal methods specified in Division 1 Section "Submittal
Procedures."
5. Refer to Division 2-16 technical specification sections for specific Coordination Drawing requirements.
B. Provide coordination drawings for equipment and system installations in mechanical and electrical rooms and spaces where two or more entities will provide the work and separate shop drawings are insufficient to show coordination.
1.5 CONSERVATION
RFQ 12905B22R0007 Tucson AZ 12
Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION
LSY Architects, LLC 013100 - 3
A. Consider conservation of energy, water and materials in the conduct of construction operation. Salvage materials and equipment involved in the performance of, but not incorporated into, the Work.
B. Waste Management Plan:
1. Establish and document a program to maximize recycling of waste materials. Program shall minimally include the following written information:
a. Designation of a waste management coordinator. Based on the workload required this may be a part-time function.
b. Identification of recyclable materials.
c. Identification of available local recycling firms and agencies to receive recyclable materials.
d. Establishment of quantity goals for collection of each recyclable material.
e. Designation of one or more locations on the project site for collection, sorting and temporary storage of recyclable materials.
f. Means and schedule for transporting and delivery of recyclable materials to recycling firms and agencies.
2. Contractor's waste management coordinator shall provide on-site instruction of workers in the identification, separation and handling of recyclable materials, and shall manage the process for the duration of the Contract.
a. Contractor shall lay out and define specific areas to facilitate separation of materials for recycling, and shall maintain collection bins clearly marked to avoid contamination of the recyclable materials.
b. The waste management coordinator shall report monthly, in writing, the quantity of each recyclable material collected during the previous month and cumulatively to date, compared to the quantity goal, and other points of interest. Copies of each report shall be distributed to each significant party of the project.
1.6 SUBMITTALS
A. Waste management Plan.
1. Submit a copy of the program to the USDA project manager for information within 14 calendar days after Notice to Proceed.
2. Update program and re-submit for information when conditions change.
1.7 ADMINISTRATIVE AND SUPERVISORY PERSONNEL
A. In addition to the Project Superintendent, the Contractor shall provide other administrative and supervisory personnel as required for proper performance of the work.
B. Waste Management Coordinator: Provide a waste management coordinator whose duties shall consist of developing and implementing a program for maximizing recycling of waste.
1.8 CONFERENCES AND MEETINGS
RFQ 12905B22R0007 Tucson AZ 13
Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION
LSY Architects, LLC 013100 - 4
A. Pre-construction Conference:
1. The Contractor shall attend a pre-construction conference scheduled by the Project Officer at a time and place convenient to both parties. Work shall not commence prior to the conference. Conference shall review responsibilities and personnel assignments.
2. Attendees: Participants at the conference shall be familiar with the project, shall be authorized to conclude matters relating to the Work, and at a minimum include representatives of the following parties or their designated representatives:
a. USDA Project Manager
b. Architect
c. Contractor
d. Major subcontractor
e. Major Suppliers
f. USDA Division of Safety, including representatives from the
Pest Management Section and the Occupational Safety and
Health Branch
g. Other concerned parties
3. Agenda: Subjects for discussion shall include items of significance that could affect progress, including but not limited to the following:
a. Tentative construction schedule
b. Critical work sequencing
c. Designation of responsible personnel
d. Procedures for processing field decisions and Change Orders
e. Procedures for processing Applications for Payment
f. Distribution of Contract Documents
g. Submittal of Shop Drawings, Product Data, and Samples
h. Preparation of Record Documents
i. Use of the premises
j. Parking availability
k. Office, work, and storage areas
l. Equipment deliveries and priorities
m. Safety procedures
n. First Aid
o. Security
p. Housekeeping and progress cleaning
q. Working hours
r. Permits
s. Integrated Pest Management procedures.
4. Reporting: No later than 3 calendar days after the conference, the Contractor shall distribute minutes of the conference to each party present and to other concerned parties.
5. This meeting may satisfy the requirement for a Pre-construction
Safety Meeting in Division 1 Section “Safety and Health.”
B. Pre-installation Conferences: The Contractor shall conduct a pre-installation conference at the Project Site before each construction activity that requires coordination with other construction. Pre-installation conferences may be combined with Preparatory Phase meetings described in Division 1 Section “Construction Quality
Control.”
1. Attendees: In addition to the Contractor's representative, the installer and representatives of manufacturers and fabricators
RFQ 12905B22R0007 Tucson AZ 14
Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION
LSY Architects, LLC 013100 - 5 involved in or affected by the installation, and its coordination or integration with other materials and installations that have preceded or will follow, shall attend. Prior to conferences, advise the USDA Project Manager of scheduled conference dates.
2. Agenda: Review the progress of other construction activities and preparations for the particular activity under consideration at each pre-installation conference, including requirements for the following.
a. Contract Documents
b. Options
c. Related Change Orders, including accepted Value Engineering proposals
d. Purchases
e. Deliveries
f. Submittals
g. Review of mockups
h. Possible conflicts
i. Compatibility problems
j. Time schedules
k. Manufacturer’s recommendations
l. Warranty requirements
m. Compatibility of materials
n. Acceptability of substrates
o. Quality requirements
p. Temporary facilities and controls
q. Space and access limitations
r. Governing regulations
s. Safety
t. Testing and inspection requirements
u. Required performance results
v. Protection
3. Reporting: Record significant discussions and agreements and disagreements of each conference. No later than 3 calendar days after each conference, the Contractor shall distribute minutes of the conference to each party present and to other concerned parties.
4. Do not proceed with the installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to the performance of the work, and reconvene the conference at the earliest feasible date.
C. Progress Meetings: The USDA Project Manager shall conduct weekly progress meetings at the Project Site. Dates of meetings shall be coordinated with preparation of the payment request.
1. Attendees: In addition to the Contractor, each subcontractor, supplier, or other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at the conference shall be familiar with the Project and authorized to conclude matters relating to the Work. The USDA Project Manager shall include the project designer in these meetings as required.
2. Agenda: Review and correct or approve minutes of the previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to the status of the Project.
RFQ 12905B22R0007 Tucson AZ 15
Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION
LSY Architects, LLC 013100 - 6
3. Contractor's Construction Schedule: Review progress since the last meeting. Determine where each activity is in relation to the Contractor's Construction Schedule, whether on time or ahead or behind schedule. Determine the required contractor response to construction behind schedule; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
a. At each progress meeting, the Contractor will provide a list of construction activities completed in the previous seven calendar days, activities in progress with percent completed, activities scheduled to start in the next 14 calendar days, and activities to start in the next thirty calendar days as derived from the accepted project schedule.
4. Review the present and future needs of each entity present, including but not limited to the following:
a. Interface requirements
b. Time
c. Sequence of operations
d. Status of submittals
e. Deliveries
f. Off-Site fabrication
g. Access
h. Site Utilization
i. Temporary facilities and controls
j. Hours of work
k. Hazards and risks
l. Proposed or scheduled utility service interruptions
m. Housekeeping and progress cleaning
n. Quality and work standards
o. Deficiencies
p. Change Orders
q. Documentation of information for payment requests
r. Updating of Record Documents
5. The Contractor shall present Record Drawings at progress meetings for review by USDA, if so requested.
6. The Progress meeting may be in conjunction with the Quality
Control (QC) Meeting required per Division 1 Section
“Construction Quality Control.”
D. Coordination Meetings: Conduct biweekly project coordination meetings as required, to verify detailed coordination procedures for the upcoming construction operations in order to avoid potential problems and misunderstandings.
1. Attendees: In addition to the Contractor, each subcontractor, supplier or other entity involved in coordination or planning construction activities shall be represented. Participants shall be authorized to conclude matters relating to the work.
2. Agenda: Review the plans and requirements of each entity present, including but not limited to the subjects listed for
Progress Meetings.
3. Reporting: No later than 3 calendar days after each meeting, the
Contractor shall distribute minutes of the meeting to each party present and to other concerned parties who should have been
RFQ 12905B22R0007 Tucson AZ 16
Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION
LSY Architects, LLC 013100 - 7 present. Include a brief summary, in narrative form, of progress since the previous meeting and report.
PART 2 - PRODUCTS (Not applicable)
PART 3 - EXECUTION
3.1 GENERAL COORDINATION PROVISIONS
A. Inspection of Conditions: Prior to installations, require the installer of each major component to inspect both the substrate and conditions under which work is to be performed.
1. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.
B. Construction in Progress: Keep construction in progress, adjoining materials in place, and adjoining materials clean during handling and installation. Apply protective coverings where required for protection from damage or deterioration.
C. Completed Construction: Clean completed construction, and provide maintenance, as frequently as necessary to prevent damage or soiling or other deterioration through the remainder of the construction period. Adjust and lubricate operable components as necessary to assure operability without damage.
D. Limiting Exposures: Supervise construction operations to prevent exposure of any part of construction, completed or in progress, to harmful, dangerous, damaging or otherwise deleterious conditions during the construction period. Such conditions include but are not limited to the following:
1. Excessive static or dynamic loading.
2. Excessive internal or external pressures.
3. Excessively high or low temperatures.
4. Thermal shock.
5. Excessively high or low humidity.
6. Pollution and air contamination.
7. Water or ice.
8. Chemicals and solvents.
9. Light
10. Radiation
11. Puncture
12. Abrasion
13. Heavy Traffic
14. Soiling, staining, and corrosion
15. Bacteria
16. Rodent and insect infestation
17. Combustion
18. Electrical Current
19. High-speed operation
20. Improper lubrication
21. Unusual wear or other misuse
22. Contact between incompatible materials
23. Destructive testing
RFQ 12905B22R0007 Tucson AZ 17
Carl Hayden Bee Research Center Design PROJECT MANAGEMENT AND COORDINATION
LSY Architects, LLC 013100 - 8
24. Misalignment
25. Excessive weathering
26. Unprotected storage
27. Improper shipping or handling
28. Theft or vandalism
END OF SECTION 013100
RFQ 12905B22R0007 Tucson AZ 18
Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION
LSY Architects, LLC 013200 - 1
SECTION 013200
CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes certain schedules and reports required for documenting the progress of construction during the performance of the work, including the following:
1. Preliminary Construction Schedule
2. Contractor's Construction Schedule
3. Material and Equipment Delivery Schedule
4. Submittal Schedule
5. Contractor's Production Report
6. Material Location Reports
7. Field Condition reports
8. Special reports
B. Related Sections: This specification section is related to any and all specification sections with explicit or implicit reference to construction progress documentation. Specific submittal requirements of these related specification sections are not included in this section. Related sections include but are not limited to the following specification sections:
1. Division 1 Section "Summary"
2. Division 1 Section "Work Restrictions"
3. Division 1 Section "Submittal Procedures"
4. Division 1 Section "Quality Requirements"
5. Division 1 Section "References"
6. Division 1 Section "Construction Quality Control"
7. Division 1 Section "Temporary Facilities and Controls"
8. Division 1 Section "Safety and Health"
9. Division 1 Section "Execution Requirements"
10. Division 1 Section "Cutting and Patching"
11. Division 1 Section "Closeout Procedures"
12. Division 1 Section "Project Record Documents"
13. Division 1 Section "Operation and Maintenance Documentation"
14. Division 2 Section "Selective Demolition"
RFQ 12905B22R0007 Tucson AZ 19
Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION
LSY Architects, LLC 013200 - 2
1.3 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor activity is an activity that must be completed before a given activity can be started.
B. CPM: Critical Path Method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
C. Critical Path: The longest continuous chain of activities through the network schedule that establishes the minimum overall Project duration and contains no float.
D. Event: The starting or ending point of an activity.
E. Float: The measure of leeway in starting and completing an activity.
1. Float time is not for the exclusive use or benefit of either the
USDA or the Contractor.
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the following activity.
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
F. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
G. Milestone: A key or critical point in time for reference or measurement.
H. Network Diagram: A graphic diagram of a network schedule, showing activities and activity relationships.
1.4 SUBMITTALS
A. Submittal Schedule: Prepare and submit a complete schedule of submittals within 10 calendar days after receipt of Notice to Proceed.
B. Field Condition Reports: When the need to take corrective action requires a departure from the Contract Documents, prepare a detailed report describing the problem and recommended changes and submit a copy to the USDA.
RFQ 12905B22R0007 Tucson AZ 20
Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION
LSY Architects, LLC 013200 - 3
PART 2 - PRODUCTS
2.1 MATERIAL AND EQUIPMENT DELIVERY SCHEDULE.
A. Submit for Contractor Officer approval a schedule showing procurement plans for materials, plant, and equipment. Submit in the format and content as directed by the Contractor Officer and include as a minimum the following information:
1. Description
2. Date of purchase order
3. Promised shipping date
4. Name of manufacturer or supplier
5. Date delivery is expected
6. Date the material or equipment is required according to the current construction schedule
B. Update the equipment delivery schedule at monthly intervals indicating material deliveries and purchases. Reflect any changes occurring since the last update. Submit copies of the purchase orders and confirmation of the delivery dates as directed.
1. Revisions to the approved schedule which will change completion dates require USDA approval.
2.2 PRELIMINARY CONSTRUCTION SCHEDULE:
A. Prepare and submit for Contracting Officer approval a preliminary time scaled arrow diagram for the project comprised of an outline of activities for the first thirty calendar days of construction. Include each significant construction activity. Coordinate each activity in the network with other activities. Schedule each activity in proper sequence and show the critical path graphically. Include the following minimum information for each activity:
1. Beginning event number
2. Description
3. Duration estimate
4. Scheduled start or days after commencement of the contract
5. Scheduled finish date or days after commencement of the contract.
B. Provide a separate fragnet for each Definable Feature of Work included in the Draft Contractor QC Plan required by Division 1 Section
"Construction Quality Control."
C. Schedule shall be time scaled in not more than weekly increments with dates of the first day of each week (Sunday) indicated.
D. Completion of the work shall be in advance of the date for completion of the contract.
E. Provide a skeleton diagram for the work beyond the preliminary time scaled arrow diagram.
F. Tabulation of Submittals: With the submission of the Preliminary
Construction Schedule, include a tabulation by date of submittals
RFQ 12905B22R0007 Tucson AZ 21
Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION
LSY Architects, LLC 013200 - 4 required during the first forty-five calendar days of construction, or show the submittals on the arrow diagram. Include those submittals required to maintain orderly progress of the work and those required early because of long lead-time for maintenance or fabrication.
1. Submittal review timelines shall be as specified in Division 1
Section "Submittal Procedures." No additional time shall be allowed the contractor for failure to allow the specified time in the submittal schedule for review, approval, and follow on contractor tasks such as delivery and installation.
G. Cash Requirements Prediction: With the submission of the Preliminary
Construction Schedule, include a preliminary monthly cash requirement prediction based on the scheduled progress of the activities.
H. Distribution: Submit 3 copies of the preliminary construction schedule to the Contracting Officer.
I. Within 7 calendar days after receipt of the preliminary construction schedule, the Contracting Officer will meet with the Contractor for a joint review, correction and adjustment of the preliminary schedule.
J. Within 3 calendar days after the joint review, the Contractor shall revise the preliminary construction schedule in accordance with agreements at the joint review, and submit 3 copies of the revised
Preliminary Construction Schedule to the Contracting Officer. The resubmission will be reviewed by the Contracting Officer and, if found to be adequate, one approved copy will be returned to the Contractor as the basis for the Contractor's construction schedule.
K. Review comments made by USDA on the Preliminary Construction Schedule shall not relieve the Contractor from compliance with the requirements of the Contract Documents. The Contractor remains responsible for scheduling, sequencing and prosecuting the work to comply with the requirements of the Contract documents. USDA acceptance extends only to the activities of the contractor's schedule that USDA has been assigned responsibility for and agrees it is responsible. USDA will also review for contract-imposed schedule constraints and conformance, and cost loading of the CPM activities. Comments offered on other parts of the schedule which the Contractor is assigned responsibility are offered as a courtesy and are not conditions of USDA acceptance;
but are for the general conformance with established industry schedule concepts.
2.3 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Prepare and periodically update a comprehensive, fully developed, construction schedule.
1. Depending on the size and complexity of the project, prepare a
CPM-program based type or a time scaled, bar chart type schedule.
The type of schedule required for the project is indicated on the drawings.
RFQ 12905B22R0007 Tucson AZ 22
Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION
LSY Architects, LLC 013200 - 5
2.4 TIME SCALED, BAR CHART TYPE CONTRACTOR’S CONSTRUCTION SCHEDULE
A. Basis for developing the Contractor's Construction Schedule shall be the approved Preliminary Construction Schedule including updates and feedback received since the start of construction. Requirements for the Contractor's Construction Schedule are in addition to those of the
Preliminary Construction Schedule as appropriate.
B. Prepare a time scaled, bar chart type construction schedule meeting all of the requirements stipulated for the Preliminary Schedule and expanded to include the entire construction duration. Include each significant construction activity. Provide a separate fragnet for each Definable Feature of Work included in the Draft Contractor QC
Plan required by Division 1 Section "Construction Quality Control."
Coordinate each activity in the network with other activities.
Schedule each activity in proper sequence. Include the following minimum data for each activity:
1. Beginning event number.
2. Description.
3. Scheduled start date.
4. Scheduled finish date.
5. Actual start date, when applicable.
6. Actual finish date, when applicable.
7. Percent complete.
2.5 CPM-PROGRAM BASED TYPE CONTRACTOR’S CONSTRUCTION SCHEDULE
A. Basis for developing the Contractor's Construction Schedule shall be the approved Preliminary Construction Schedule including updates and feedback received since the start of construction. All requirements for the Contractor's Construction Schedule are in addition to those of the Preliminary Construction Schedule as appropriate.
B. Include each significant construction activity. Provide a separate fragnet for each Definable Feature of Work included in the Draft
Contractor QC Plan required by Division 1 Section "Construction
Quality Control." Coordinate each activity in the network with other activities. Schedule each activity in proper sequence. Show critical path graphically. Include the following minimum data for each activity:
1. Beginning event number.
2. Description.
3. Duration estimate.
4. Cost estimate.
5. Scheduled start date.
6. Scheduled finish date.
7. Actual start date, when applicable.
8. Actual finish date, when applicable.
9. Percent complete.
C. Schedule shall be produced by a computer program that has been developed specifically to manage construction schedules and capable of accepting revised completion dates as modified by approved time
RFQ 12905B22R0007 Tucson AZ 23
Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION
LSY Architects, LLC 013200 - 6 adjustments and re-computation of all tabulation dates and float accordingly. Computer program shall be capable of displaying the schedule in a variety of graphical formats including Gannt Charts and
Pert Charts.
D. Cost Correlation: Provide a cost correlation line at the head of the schedule to indicate planned and actual cost. As work progresses, show dollar volume of work performed as of the dates used for applications for payment. The total of all activity costs shall equal the contract price.
E. Within each construction activity's time fragnet, indicate estimated completion percentages in not more than 5 percent increments and, as work progresses, place marks to indicate actual completion percentages.
F. Within 10 calendar days after receipt of the preliminary construction schedule, the Contracting Officer will meet with the Contractor for a joint review, correction and adjustment of the preliminary schedule.
G. Within 5 calendar days after the joint review, the Contractor shall revise the preliminary construction schedule in accordance with agreements at the joint review, and submit 1 copy of the revised
Preliminary Construction Schedule to the Contracting Officer. The resubmission will be reviewed by the Contracting Officer and, if found to be adequate, one approved copy will be returned to the Contractor as the basis for the Contractor's construction.
H. Review comments made by USDA on the Preliminary Construction Schedule shall not relieve the Contractor from compliance with the requirements of the Contract Documents. The Contractor remains responsible for scheduling, sequencing and prosecuting the work to comply with the requirements of the Contract documents. USDA acceptance extends only to the activities of the contractor's schedule that USDA has been assigned responsibility for and agrees it is responsible. USDA will also review for contract-imposed schedule constraints and conformance, and cost loading of the CPM activities. Comments offered on other parts of the schedule which the Contractor is assigned responsibility are offered as a courtesy and are not conditions of USDA acceptance;
but are for the general conformance with established industry schedule concepts.
I. Each activity will be assigned a Schedule Activity Number.
J. Activity Duration: Define activities so no activity is longer than thirty calendar days, unless specifically allowed by Contracting
Officer.
K. Procurement Activities: Include procurement process activities for long lead items and major items, requiring a cycle of more than 60 days, as separate activities in the schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.
RFQ 12905B22R0007 Tucson AZ 24
Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION
LSY Architects, LLC 013200 - 7
L. Submittal Review Time: Include review and resubmittal times indicated in Division 1 Section "Submittal Procedures" in the schedule.
Coordinate submittal review times in the Contractor's Construction
Schedule with the Submittals Schedule.
M. Startup and Testing Time: Include not less than twenty-one calendar days for startup and testing.
N. Include a separate activity for each contract if work is under more than one contract.
O. Include a separate activity for each portion of the work performed by
USDA or other USDA contractors that directly impacts the work of this contract.
P. Include a separate activity for each product. Include any delivery dates indicated in Division 1, Section "Summary." Delivery dates indicated stipulate the latest possible delivery date.
Q. Work Restrictions: Show the effect of the following items on the schedule:
1. Coordination with existing construction.
2. Limitations of continued occupancies.
3. Uninterruptible services.
4. Partial occupancy before Substantial Completion.
5. Use of premises restrictions.
6. Provisions for future construction.
7. Seasonal variations.
8. Environmental control.
R. Work Stages: Indicate important stages of construction for each major portion of the work, including, but not limited to, the following:
1. Subcontract awards.
2. Submittals.
3. Purchases.
4. Mockups.
5. Fabrication.
6. Sample testing.
7. Deliveries.
8. Installation.
9. Tests and inspections.
10. Adjusting.
11. Curing.
12. Startup and placement into final use and operation.
13. Commissioning
S. Area Separations: Identify each major area of construction for each major portion of the work. Indicate where each construction activity within a major area must be sequenced or integrated with other construction activities to provide for the following:
1. Completion of mechanical installation.
2. Completion of electrical installation.
3. Substantial Completion.
RFQ 12905B22R0007 Tucson AZ 25
Carl Hayden Bee Research Center Design CONSTRUCTION PROGRESS DOCUMENTATION
LSY Architects, LLC 013200 - 8
4. Commissioning
T. Other Constraints: None.
U. Milestones: Include milestones indicated in the Contract Documents in the schedule including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Acceptance.
V. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall project schedule.
W. Updating: Provide an updated schedule in conjunction with project meeting requirements specified in Division 1 Section "Project
Management and Coordination." In addition, should actual timelines for events or activities suggest a significant change in the planned progress of the work, the contractor shall submit for Contracting
Officer approval a revised schedule with justification for the change.
Highlight or otherwise emphasize revisions for ease of identification.
1. Show construction schedule baseline of initially approved construction schedule on each updated schedule.
X. Reports: As a minimum, be prepared to furnish the following computer produced reports from sorts of the basic activity data. Actual reports required and report frequency will be determined by the
Contracting Officer.
1. Activity sort by the preceding event number from lowest to highest and then in the order of the following event number.
2. Activity sort by amount of total float, then in order of preceding event number.
3. Activity sort in order of latest allowable start dates, then in order of preceding event numbers.
4. Activity sort in order of latest allowable finish dates, then in order of preceding event numbers.
5. Activity sort by trade code, early start date and total float.
6. Contractor's monthly payment request sorted by responsibility.
Y. Float is not for the exclusive use or benefit of either USDA or the
Contractor, but must be used in the best interest of completing the project on time. Extensions of time for performance required under the Contract Clauses entitled "Changes", "Differing Site Conditions", or other applicable clauses, will be granted only to the extent that the equitable time adjustment for the activity or activities affected exceeds the total float along the activities involved.
Z. Distribution: Print and distribute copies of the initial Contractor's
Construction Schedule, and each updated or revised schedule, to the
Contracting Officer, as…