This document contains an amendment to a federal solicitation and the original solicitation. The amendment modifies the solicitation for repair and replacement of HVAC and electrical components at the USDA Carl Hayden Bee Research Center in Tucson, Arizona. The amendment adds an optional scope of work to test, adjust, and balance existing HVAC systems, and provides answers to questions from offerors. The original solicitation seeks a firm-fixed price construction contract to repair or replace HVAC and electrical components in two buildings at the research center. The work includes labor, materials, equipment, and supervision. The project aims to conform to applicable building codes. The solicitation is set aside for small businesses with a size standard of $39.5 million in average annual receipts. The estimated value is between $500,000 and $1,000,000. Questions are due by April 25, 2022 to the contracting officer. The Department of Agriculture Agricultural Research Service Pacific West Area is the issuing agency.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For the best experience, open this PDF portfolio in

Acrobat X or Adobe Reader X, or later.

Get Adobe Reader Now!

http://www.adobe.com/go/reader

RFQ 1290B22R0007 Amend 0002 HVAC/Electrical - Tucson

CONTINUATION OF SF1442

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

Repair/Replace HVAC

Carl Hayden Bee Research Center

Tucson AZ 85719

B.1 PRICE SCHEDULE

(a) Offers will be considered for award on the following Price

Schedule, but no offer will be considered for award on only a part of the Price Schedule.

(b) Offers are subject to the terms and conditions of this solicitation.

(c) Definitions:

a. CLIN – (Contract Line-Item Number)

PRICE SCHEDULE

CLIN Supplies or Service Quantity and Unit of Issue

Unit Price Amount

0001 Repair or replace HVAC and Electrical components in Buildings 107 and 108 of the USDA Carl Hayden Bee Research Center in Tucson Arizona in accordance with the attachments contained within this RFP and incorporated into the final contract.

For the lump sum of $

OY 0002 Perform Section 23 05 93 1.2.B Bid Option No 01 of Attachment II Final Specs- HVAC-Elect Bldg 107

For the lump sum $

TOTAL FOR PRICE SCHEDULE: $

B.2 PERIOD OF PERFORMANCE

200 calendar days after the notice to proceed.

B.3 ADDITIONAL INFORMATION

RFQ 1290B22R0007 Amend 0002 HVAC/Electrical - Tucson

Proposal MUST be received no later than 1:00pm PDT, on 25 April 2022.

Proposal must comply with all RFP instructions and emailed to: Theodore.Blume@usda.gov.

PROPOSAL MUST BE ANNOTATED AS SUCH AND REFERENCED THE SOLICITATION

NUMBER.

End of Section B mailto:Theodore.Blume@usda.gov

CONTINUATION OF SF1442

B.1 PRICE SCHEDULE

SECTION C – DESCRIPTION/SPECIFICATIONS

1.02 PRINCIPAL COMPONENTS OF WORK

See attached specifications table of contents.

1.04 DESCRIPTION OF WORK

1.05 REFERENCES & STANDARDS

1.08 PERMITS

1.14 QUALITY CONTROL

1.15 PROTECTION OF WORK AND PROPERTY/SAFETY REQUIREMENTS

1.16 TEMPORARY FACILITIES:

1.17 SITE CLEANUP

1.18 FINAL INSPECTION

1.1

1.19 WARRANTY

1.19.1 Submit data concerning the standard one-year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.

1.19.2 Extended Equipment/Product Warranties: Obtain and furnish, to the location personnel, all written warranties for equipment/products that have extended warranties (warranty periods exceeding the standard one-year warranty) furnished under the co...

1.20 ACCEPTANCE

1.1.1 Submission Requirements and Evaluation Minimum Requirements

12905B22R0007 Replace/Repair HVAC/Electrical

AMENDMENT #2

USDA Carl Hayden Bee Research Center, Tucson, AZ Questions/Answers

1. With the building being occupied during construction, is the contractor required to provide temporary heating/cooling during outages/demolition?

A. Refer to “02 41 19 Selective Demolition” section 3.2 for additional requirements regarding utility interruptions.

2. States “Install new smoke duct detector into existing supply air duct. Integrate into existing local FACP.” Please confirm this is part of the scope?

A. Yes, that is within the scope of work on this project.

3. It would appear the specification is calling for a 3rd party Testing Agency. Please clarify if a 3rd party agency is required? Is the testing limited to new installation or for the entire building?

A. It is allowable for contractor to perform cable insulation resistance and infrared testing. All test results are to be signed, dated and submitted for COR review per of Specification 26 05 19 Part 1.5 and Part 3.5.C and 3.5.D. Testing is only required for newly installed conductors and terminations.

4. It would appear the specification is calling for a 3rd party Testing Agency. Q: Please clarify if a 3rd party agency is required? Is the testing limited to new installation or for the entire building?

A. It is allowable for contractor to perform grounding resistance tests and termination torque verification of all lugs/terminations. All test results are to be signed, dated and submitted for COR review per of Specification 26 05 26 Part 1.5.b.3. Testing is only required for newly installed grounding conductors and terminations.

5. Will the contractor be allowed to use the lift outside basement to remove demo’d materials?

A. Yes, the contractor will be allowed to utilize the lift.

6. Is the Contractor responsible for draining systems prior to work? Or will that be done by the owner?

A. The Contractor shall be responsible for draining and refilling the system.

7. States "1. Use rigid steel... in mechanical equipment rooms, electrical equipment rooms...

below 18'...etc. Currently there is a mix of EMT conduit and GRC conduit." Please clarify if EMT is acceptable in mechanical and electrical rooms and under 18'?

A. Rigid Steel Conduit is required below 18 feet in all mechanical and electrical rooms per Specification 26 05 33 Part 3.2.B.1.

8. On many of the Mechanical Drawings there appears a keynote for “Bid Option 1” involving performing a TAB service for the VAVs on the first floor (in addition to new work). The instructions for this option seem excessively vague and the complete as-built mechanical drawings with the required balancing values was not provided. Additionally, the SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS for this RFP denotes one Lump Sum Price Line for the entire project. Will the USDA provide a detailed statement of work and adequate backup drawings to estimate the cost for Bid Option 1, as well as a REVISED Section B Price Schedule, or will the USDA delete the requirement for Bid Option 1 for this project?

A. Original MEP drawings, dated 1965, are available from USDA and include original design airflows. TAB scope of work would involve capturing existing conditions and equipment performance for VAV AHU system serving Non-Lab areas of building (exterior offices and corridors), comparing it to the original drawings, and making adjustments as required to balance the system and identify areas of deficiency. The square footage to bid the office TAB efforts can be accomplished utilizing a VAV AHU system.

Option CLIN 0002 has been added to Section B of the CLIN Schedule for Bid Option 1.

9. Provision Clauses, Section 1.08, page 6. Are there any city, county or state permits required at this facility?

A. No permits are required.

10. Attachment III, Final Drawings, A100, General Demolition Notes, D - Are we required to provide temporary HVAC to the areas that are being disturbed?

A. Yes, contractor is responsible for temporary utilities during construction, depending on the season and temperatures. This is a requirement indicated in the specifications.

11. Attachment III, Final Drawings, A100, Demo RCP, Key Notes, 01, Room 015 storage basement lid, is there going to be any ceiling at all re-installed after the grid ceiling is demoed in this room?

A. There is no new ceiling in Storage Rm 015. That room will house HVAC equipment and needs to be open to deck.

12. Attachment III, Final Drawings, A100, General Demolition Notes, I - Is all construction debris being put in USDA provided dumpsters? Also see Attachment III, Final Drawings, M- 100, General Notes, Item 15, that HVAC debris is to be removed from the property and disposed of per federal and local laws?

A. The contractor shall be responsible to supply dumpsters for all construction debris. Also, the contractor shall be responsible for all debris removal in accordance with applicable federal and/or local laws.

13. Attachment III, Final Drawings, ED-602 Keynote #1, Please restate differently. Is disconnected equipment to remain functional during change out?

A. As stated in Keyed Note 1 disconnect equipment to be removed all other equipment on circuit to remain operational. See new Panel M schedule on E-603 for re-circuiting of equipment being replaced. Coordinate with work shown on ED 101 and E-102. Keyed Note 1 on ED 101 states to remove existing FCU wiring back to source and existing conduit can be reused as appropriate.

Keyed Note 2 on E-102 stated to provide new conduit and wiring from source panel to motor (existing conduit may be reused as appropriate).

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

INSTRUCTIONS (Back Page):

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date).

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data).

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:

(2) Accounting classification Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification).

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i) Total contract price increased by $

(ii) Total contract price decreased by $

(iii) Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(g)

(h)

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

(i) A reference to the letter determination; and

(ii) A statement of the net amount determined to be due in settlement of the contract.

(2)

(3)

(4)

(5)

(6)

STANDARD FORM 30 (REV. 11/2016) BACK

(1) Accounting classification Net increase $

1.2

C:\PERFORM\FORMS\S30.FRP

Forms Management

C:PERFORMFORMSS30.FRP

Acrobat PDFWriter 2.01 for Windows

D:19971010095222

D:19990614133004

C:PERFORMFORMSS30.FRP

Standard Form 30 - Amendment of Solicitation/Modification of Contract

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER

3. EFFECTIVE DATE

4. REQUISITION/PURCHASE REQUISITION NUMBER

5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6)

CODE

STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.

is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY

CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code)

(X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

INSTRUCTIONS (Back Page):

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date).

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data). When appropriate, indicate the impact of themodification on each affected accounting classification by inserting one of the following entries:

(2)

Accounting classification

Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification).

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

Indicate the impact of the modification on the overall total contract price by inserting one ofthe following entries:

(i) Total contract price increased by $

(ii) Total contract price decreased by $

(iii) Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(g)

(h)

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

(i) A reference to the letter determination; and

(ii) A statement of the net amount determinedto be due in settlement of the contract.

(2)

(3)

(4)

(5)

(6)

STANDARD FORM 30 (REV. 11/2016) BACK

(1)

Accounting classification

Net increase $

9A. AMENDMENT OF SOLICITATION NUMBER: 0002

9A. AMENDMENT OF SOLICITATION NUMBER: 12905B22R0007

7. CODE: 12905B

12. ACCOUNTING AND APPROPRIATION DATA (If required):

13A. THIS CHANGE ORDER IS ISSUED PURSUANT TO. Specify authority. THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.:

13C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

13D. OTHER. Specify type of modification and authority.:

15A. NAME AND TITLE OF SIGNER. Type or print.:

16A. NAME AND TITLE OF CONTRACTING OFFICER. Type or print.: Michael Hassett/Contracting Officer

14. DESCRIPTION OF AMENDMENT OR MODIFICATION (Organized by UCF section headings, including solicitation or contract subject matter where feasible.): RFP 12905B22R0007 - HVAC/Electrical Upgrade for USDA-ARS at Tucson, AZ.

The purpose of this amendment is to: 1) Add new Section B which adds Option CLIN 0002 Option to test, adjust, and balance existing HVAC systems not affected by the normal scope of work of this project (Section 23 05 93 of Attachment II); and 2) To give answers to questions offers had; see the following pages for details. The due date for this RFP remains unchanged.

FACILITY CODE:

6. ISSUED BY: USDA ARS PWA AAO ACQ/PER PROP

800 BUCHANAN STREET

ALBANY CA 94710

Theodore.Blume@usda.gov

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code):

7. ADMINISTERED BY (If other than Item 6):

1. CONTRACT ID CODE:

4. REQUISITION/PURCHASE REQUISITION NUMBER: 1053794

10A. MODIFICATION OF CONTRACT/ORDER NUMBER:

5. PROJECT NUMBER. If applicable.: LSY 20037.01

PAGE:

PAGES:

3. EFFECTIVE DATE. Enter 2 digit month, 2 digit day and 4 digit year.: 2022-04-20

9B. DATED. SEE ITEM 11. Enter 2 digit month, 2 digit day and 4 digit year.: 2022-03-25

10B. DATED. SEE ITEM 13. Enter 2 digit month, 2 digit day and 4 digit year.:

9A. AMENDMENT OF SOLICITATION NUMBER: 1

10A. MODIFICATION OF CONTRACT/ORDER NUMBER: 0

11. The above numbered solicitation is amended as set forth in Item 14. : 1

13A. THIS CHANGE ORDER IS ISSUED PURSUANT TO. Specify authority. THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.: 0

13B. THE ABOVE NUMBERED CONTRACT OR ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES. Such as changes in paying office, appropriation date, etc. SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103b.: 0

13C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF: 0

13D. OTHER Specify type of modification and authority.: 0

13E. IMPORTANT: Contractor is not required to sign this document and return copies to the issuing office.: 0

13E. IMPORTANT: Contractor is required to sign this document and return copies to the issuing office.: 0

11. The hour and date specified for receipt of Offers is extended : 0

11. The hour and date specified for receipt of Offers is not extended : 1

15B. CONTRACTOR OR OFFEROR. Signature of person authorized to sign. Digital Signature.:

16C. DATE SIGNED. Enter 2 digit month, 2 digit day and 4 digit year.:

number of copies: 1.00000000 number of copies:

Enter the total (in dollars) the contract price increased. :