This document is a GSA notification letter dated 02/28/2024 detailing the presence of asbestos-containing materials (ACM) and presumed asbestos-containing materials (PACM) in the John Weld Peck Building (OH0189CN). The comprehensive table lists 13 different types of asbestos materials located throughout the building, including fittings on fiberglass lines (21,200 units), floor tiles and mastic (634,350 sq ft), duct insulation (19,000 sq ft), and tank insulation in the sub-basement mechanical room (800 sq ft).
The letter emphasizes GSA's commitment to safety and regulatory compliance, stating that all relevant OSHA and EPA regulations will be strictly followed during any maintenance or construction activities involving ACM or PACM. GSA will notify tenant agencies prior to disturbing these materials and will only use licensed and certified asbestos removal contractors. Tenant agencies are required to notify GSA Property Management before conducting any construction work, and asbestos inspection reports are available for review. For additional information, contractors can contact GSA Property Management at 513/246-4472.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
02/28/2024
Dear Tenant Agency Representative:
Pursuant to the Code of Federal Regulations all building owners are required to provide notification of the presence, location, and quantity of asbestos containing materials (ACM) and presumed asbestos containing materials (PACM) in their facilities. This notification is provided as a safeguard, to ensure tenant agencies occupying the facility are aware of this information.
Asbestos containing material is present in the John Weld Peck Building (OH0189CN) in the following forms, locations, and quantities:
Type Location Quantity
Fittings on Fiberglass Line Throughout Building 21200 ea Tank Insulation Sub-Basement Mechanical Room 800 sf Duct Insulation Throughout 19000 sf Elevator Door Insulation Throughout 1300 sf Mastic on AHU Supply Duct Throughout Building Supply Duct 13600 sf Caulk (Painted Grey) Sub-Basement Mechanical Room 10 lf Electrical Conduit Putty 3rd Floor West Hall Telephone Closet 100 sf Interior Window Glazing Throughout Building Undefined1 Mastic on Car Shell Freight Elevator Car Shell 500 sf Insulation on Converter Tank Penthouse 500 sf Floor Tile and Mastic Throughout Building 634350 sf Ceiling Tile 1st & 3rd Floor 5400 sf Gold HVAC Sealant 7th Floor Hallway Undefined2
Mastic Associated with 12”x12” White Floor Tile with Tan Specks
2nd, 7th, and 9th Floor Undefined2
Mirror Mastic Throughout Undefined2
Fire Doors Throughout Undefined2
Should GSA construction or maintenance activities in areas accessible to tenants or the public disturb or necessitate removal of ACM or PACM, we will notify you prior to the start of any such work. All relevant OSHA and EPA regulations governing ACM and PACM maintenance, removal, and disposal are strictly adhered to, and only licensed and certified asbestos removal contractors are employed for this work.
Notification of the presence, location, and quantity of ACM and PACM in the facility must be provided to all contractors performing work in the facility. Tenant agencies performing construction in their space must notify GSA Property Management prior to the start of any work, so information is shared accordingly.
Please be assured the condition of all ACM and PACM within the facility is monitored. To ensure transparency, asbestos inspection reports for this facility are available for your review. If you have any questions, please contact our Property Management staff at 513/246-4472.