Attachment E _ SAMPLE Construction Agreement.pdf

PDF 479 KB Posted

Attached to
GATEWAY MONUMENT AND PARK IDENTIFICATION SIGNAGE
Solicitation number
PE-66869-NONST-2025-000000018
Issued by
Dekalb County, Georgia

About this file

This is a Sample Construction Agreement for the City of Stonecrest, Georgia, establishing the contractual framework for the Gateway Monument Sign and Park Identification Signage project. The work encompasses construction and installation of a gateway monument sign at Silver River and park identification signage at six park locations: Panola Shoals Trailhead for South River Trail, Salem Park, Browns Mill Recreation Center, Fairington Park, Everett Park, and an additional unnamed location. The contractor shall furnish all labor, materials, equipment, personnel, tools, supervision, transportation, machinery, and other incidentals necessary to complete the work. The contract commences upon execution and terminates at the close of the calendar year in which it was executed, with renewal options available at the sole discretion of the Owner, determined no less than forty-five days prior to year-end with thirty days' written notice to the contractor. The contract time for achieving substantial completion shall be measured in calendar days from receipt of the Notice to Proceed and Purchase Order, with the specific number of days to be completed in the final executed agreement.

The contract price is a lump sum amount to be completed in the final executed agreement, with progress payments made monthly at ninety percent of properly performed work, less retainage. Upon substantial completion, retainage witholding ceases once fifty percent of the contract value is reached and the Owner is satisfied with work progress. Liquidated damages of two hundred fifty dollars per day apply for unexcused delays in achieving substantial completion and final completion. The contractor must provide separate performance and payment bonds equal to the contract price, commercial general liability coverage of one million dollars per occurrence, workers' compensation insurance, professional liability insurance of one million dollars per occurrence, business automobile liability of one million dollars combined single limit, and property coverage at one hundred percent of total project cost with a maximum deductible of twenty-five thousand dollars. The contractor must also participate in the federal work authorization program throughout the contract period and provide a signed, notarized E-Verify affidavit. The governing law is the State of Georgia with venue in DeKalb County.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

THE CITY OF STONECREST, GEORGIA

CONTRACT FOR GATEWAY MONUMENT SIGN

AND

PARK IDENTIFICATION SIGNAGE

i

Table of Contents

ARTICLE I THE CONTRACT AND THE CONTRACT DOCUMENTS

1.1 The Contract

1.2 The Contract Documents

1.3 Entire Agreement

1.4 No Privity with Others

1.5 Intent and Interpretation

1.6 Ownership of Contract Documents

1.7 Hierarchy of Contract Documents

ARTICLE II THE WORK

ARTICLE III CONTRACT TIME

3.1 Contract Term

3.2 Time and Liquidated Damages

3.3 Substantial Completion

3.4 Time is of the Essence

ARTICLE IV CONTRACT PRICE

4.1 The Contract Price

ARTICLE V PAYMENT OF THE CONTRACT PRICE

5.1 Schedule of Values

5.2 Payment Procedure

5.3 Withheld Payment

5.4 Unexcused Failure to Pay

5.5 Substantial Completion

5.6 Completion and Final Payment

ARTICLE VI THE OWNER

6.1 Information, Services and Things Required from Owner

6.2 Right to Stop Work

6.3 Owner’s Right to Perform Work

ARTICLE VII THE CONTRACTOR

7.1 The Contractor

7.2 Compliance with Contract

7.3 Reasonable Care and Skill

ii

7.4 Warranty

7.5 Permits

7.6 Supervision

7.7 Schedules

7.8 Required Documents at the Site

7.9 Shop Drawings, Product Data and Samples

7.10 Cleaning the Site and the Project

7.11 Access to Work

7.12 Indemnity

7.13 Means, Methods, Techniques, Sequences, Procedures and Safety

7.14 Separate Contracts

ARTICLE VIII CONTRACT ADMINISTRATION

8.1 Engineering ..................................................................... Error! Bookmark not defined.

8.2 Engineer’s Administration

8.3 Claims by the Contractor

8.4 Extension of Contract Time for Unusually Adverse Weather Conditions not Reasonably Anticipated

ARTICLE IX SUBCONTRACTORS

9.1 Definition

9.2 Award of Subcontracts

ARTICLE X CHANGES IN THE WORK

10.1 Changes Permitted

10.2 Change Order Defined

10.3 Changes in the Contract Price

10.4 Effect of Executed Change Order

10.5 Notice to Surety; Consent

ARTICLE XI UNCOVERING AND CORRECTING WORK

11.1 Uncovering Work

11.2 Correcting Work

11.3 Owner May Accept Defective or Nonconforming Work

ARTICLE XII CONTRACT TERMINATION

12.1 Termination by the Contractor

iii

12.2 Termination by the Owner

12.3 Renewal

ARTICLE XIII OWNER’S RIGHT TO SUSPEND CONTRACTOR’S PERFORMANCE

ARTICLE XIV INSURANCE

ARTICLE XV MISCELLANEOUS

15.1 Governing Law

15.2 Successors and Assigns

15.3 Interpretation

15.4 Severability

15.5 Amendment and Waiver

15.6 Notice

15.7 Time is of the Essence

15.8 Participation in Federal Work Authorization Program

15.9 Counterparts

15.10 Captions

15.11 Surety

15.12 Interpretation

EXHIBIT A SCOPE OF WORK

EXHIBIT B COST ESTIMATE

EXHIBIT C E-VERIFY AFFIDAVIT

CONTRACT FOR GATEWAY MONUMENT AND PARK IDENTIFICATION

SIGNAGE

AND INCORPORATED GENERAL CONDITIONS

This Agreement is made by and between the CITY OF STONECREST, GEORGIA, a municipal corporation of the State of Georgia (the "Owner"), and ________________________, a corporation created and existing under the laws of the State of Georgia (the "Contractor"), under seal for the gateway monument and park identification signage within the City of Stonecrest (the "Project"). For and in consideration of the mutual promises set forth herein and other good and valuable consideration, the receipt and sufficiency of which are hereby acknowledged, the Owner and the Contractor hereby agree as follows:

ARTICLE I

THE CONTRACT AND THE CONTRACT DOCUMENTS

1.1 The Contract

1.1.1 The Contract between the Owner and the Contractor, of which this Agreement is a part, consists of the Contract Documents. It shall be effective on the date this Agreement is executed by the last party to execute it.

1.2 The Contract Documents

1.2.1 The Contract Documents consist of this Agreement, any and all Exhibits attached hereto, the Specifications, the Drawings, all Change Orders and Task Orders issued hereafter, any other amendments hereto executed by the parties hereafter, together with the following (if any):

Advertisement for Competitive Sealed Bids/Proposals; Instructions to Offerors;

Bid/Proposal Form; Bid Bond; Payment Bond; Performance Bond; Notice of Award;

Change Order; Certificate of Substantial Completion; Notice to Proceed.

Documents not enumerated in this Paragraph 1.2 or not otherwise incorporated by reference hereunder are not Contract Documents and do not form part of this Contract.

1.3 Entire Agreement

1.3.1 This Contract, together with the Contractor’s performance and payment bonds for the Project, Contract Documents, constitute the entire and exclusive agreement between the Owner and the Contractor with reference to the Project. Specifically, but without limitation, this Contract supersedes any bid documents and all prior written or oral communications, representations and negotiations, if any, between the Owner and Contractor.

1.4 No Privity with Others

1.4.1 Nothing contained in this Contract shall create or be interpreted to create privity or any other contractual agreement between the Owner and any person or entity other than the Contractor.

1.5 Intent and Interpretation

1.5.1 The intent of this Contract is to require complete, correct and timely execution of the Work.

Any Work that may be required, implied or inferred by the Contract Documents, or any one or more of them, as necessary to produce the intended result shall be provided by the Contractor for the Contract Price.

1.5.2 This Contract is intended to be an integral whole and shall be interpreted as internally consistent. What is required by any one Contract Document shall be considered as required by the Contract.

1.5.3 When a word, term or phrase is used in this Contract, it shall be interpreted or construed, first, as defined herein; second, if not defined, according to its generally accepted meaning in the construction industry; and third, if there is no generally accepted meaning in the construction industry, according to its common and customary usage.

1.5.4 The words "include", "includes", or "including", as used in this Contract, shall be deemed to be followed by the phrase, "without limitation."

1.5.5 The specification herein of any act, failure, refusal, omission, event, occurrence or condition as constituting a material breach of this Contract shall not imply that any other non-specified act, failure, refusal, omission, event, occurrence or condition shall be deemed not to constitute a material breach of this Contract.

1.5.6 Words or terms used as nouns in this Contract shall be inclusive of their singular and plural forms unless the context of their usage clearly requires a contrary meaning.

1.5.7 The Contractor shall have a continuing duty to read, carefully study and compare each of the Contract Documents, the Shop Drawings and the Product Data and shall give written notice to the Owner of any inconsistency, ambiguity, error or omission which the Contractor may discover with respect to these documents before proceeding with the affected Work. The issuance, or the express or implied approval by the Owner or the Engineer of the Contract Documents, Shop Drawings or Product Data shall not relieve the Contractor of the continuing duties imposed hereby, nor shall any such approval be evidence of the Contractor's compliance with this Contract. The Owner has requested the Engineer to only prepare documents for the Project, including the Drawings and Specifications for the Project, which are accurate, adequate, consistent, coordinated and sufficient for construction. HOWEVER, THE OWNER MAKES NO REPRESENTATION

OR WARRANTY OF ANY NATURE WHATSOEVER TO THE CONTRACTOR

CONCERNING SUCH DOCUMENTS. By the execution hereof, the Contractor acknowledges and represents that it has received, reviewed and carefully examined such documents, has found them to be complete, accurate, adequate, consistent, coordinated and sufficient for construction, and that the Contractor has not, does not, and will not rely upon any representation or warranties by the Owner concerning such documents as no such representation or warranties have been or are hereby made.

1.5.8 Neither the organization of any of the Contract Documents into divisions, sections, paragraphs, articles, (or other categories), nor the organization or arrangement of the Design, shall control the Contractor in dividing the Work or in establishing the extent or scope of the Work to be performed by Subcontractors.

1.6 Ownership of Contract Documents

1.6.1 The Contract Documents, and each of them, shall remain the property of the Owner. The Contractor shall have the right to keep one record set of the Contract Documents upon completion of the Project; provided, however, that in no event shall Contractor use, or permit to be used, any or all of such Contract Documents on other projects without the Owner's prior written authorization.

1.7 Hierarchy of Contract Documents

1.7.1 In the event of any conflict, discrepancy, or inconsistency among any of the Contract

Documents, the following hierarchy shall control: (a) as between figures given on drawings and the scaled measurements, the figures shall govern; (b) as between large scale drawings and small scale drawings, the large scale shall govern; (c) as between drawings and specifications, the requirements of the specifications shall govern; (d) as between the Contract for Construction and the specifications, the requirements of the Contract for Construction shall govern. As set forth hereinabove, any and all conflicts, discrepancies, or inconsistencies shall be immediately reported to the Engineer in writing by the Contractor.

ARTICLE II

THE WORK

2.1 The Contractor shall perform all of the Work required, implied or reasonably inferable from, this Contract.

2.2 The term "Work" shall mean whatever is done by or required of the Contractor to perform and complete its duties under this Contract, including the following: construction of the whole or a designated part of the Project; furnishing of any required surety bonds and insurance; and the provision or furnishing of labor, supervision, services, materials, supplies, equipment, fixtures, appliances, facilities, tools, transportation, storage, power, permits and licenses required of the Contractor, fuel, heat, light, cooling and all other utilities as required by this Contract. The Work to be performed by the Contractor is generally described as follows: See Exhibit A, which is attached hereto and is incorporated herein by reference.

ARTICLE III

CONTRACT TIME

3.1 Contract Term

3.1.1 This Agreement shall commence on the effective date of this Agreement and shall terminate absolutely and without further obligation on the part of the Owner at the close of the calendar year in which it was executed, unless renewed pursuant to Paragraph 12.3.

3.2 Time and Liquidated Damages

3.2.1 The Contractor shall commence the Work under this Agreement on the date established by a written Notice to Proceed given by the Owner to the Contractor fixing the date on which the Contract time will commence to run. The Contractor shall achieve Substantial Completion of the Work within __________calendar days from receipt of the Notice to Proceed (NTP) and Purchase Order (PO), unless another date is provided within the written Notice to Proceed. The number of consecutive calendar days from the date on which the Work is permitted to proceed, through the date set forth for Substantial Completion, shall constitute the “Contract Time.”

3.2.2 The Contractor shall pay the Owner the sum of two hundred and fifty ($250.00) per day for each and every business day of unexcused delay in achieving Substantial Completion beyond the date set forth herein for Substantial Completion of the Work. Any sums due and payable hereunder by the Contractor shall be payable, not as a penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by the Owner, estimated at or before the time of executing this Contract. When the Owner reasonably believes that Substantial Completion will be inexcusably delayed, the Owner shall be entitled, but not required, to withhold from any amounts otherwise due the Contractor an amount then believed by the Owner to be adequate to recover liquidated damages applicable to such delays.

If and when the Contractor overcomes the delay in achieving Substantial Completion, or any part thereof, for which the Owner has withheld payment, the Owner shall promptly release to the Contractor those funds withheld, but no longer applicable, as liquidated damages.

3.3 Substantial Completion

3.3.1 “Substantial Completion” shall mean that stage in the progression of the Work when the Work is sufficiently complete in accordance with this Contract that the Owner can enjoy beneficial use and occupancy of the Work and can utilize the Work for its intended purpose.

Partial use or occupancy of the Project shall not result in the Project being deemed substantially complete, and such partial use or occupancy shall not be evidence of Substantial completion.

3.4 Time is of the Essence

3.4.1 All limitations of time set forth in the Contract Documents are of the essence of this Contract.

ARTICLE IV

CONTRACT PRICE

4.1 The Contract Price

4.1.1 The Owner shall pay, and the Contractor shall accept, as full and complete payment for the Contractor’s timely and full performance of its obligations hereunder, the total lump sum amount set forth in Paragraph 4.1.2. The lump sum amount set forth in Paragraph 4.1.2 shall not be modified except by Change Order(s) as provided in this Agreement.

4.1.2 The total lump sum amount to be paid by the Owner to the Contractor for the Contractor’s limitedly and full performance of its obligations under the Agreement shall not exceed _________________ ($_____________). See Exhibit B (Cost Estimate) attached hereto and incorporated by reference herein.

ARTICLE V

PAYMENT OF THE CONTRACT PRICE

5.1 Schedule of Values

5.1.1 For all portions of this Agreement not payable in unit values, within ten (10) calendar days of the effective date hereof, the Contractor shall submit to the Owner and to the Engineer a Schedule of Values allocating the Contract Price to the various portions of the Work. The Contractor's Schedule of Values shall be prepared in such form, with such detail, and supported by such data as the Engineer or the Owner may require to substantiate its accuracy. The Contractor shall not imbalance its Schedule of Values nor artificially inflate any element thereof. The violation of this provision by the Contractor shall constitute a material breach of this Contract.

The Schedule of Values shall be used only as a basis for the Contractor's Applications for Payment and shall only constitute such basis after it has been acknowledged in writing by the Engineer and the Owner.

5.2 Payment Procedure

5.2.1 The Owner shall pay the Contract Price to the Contractor as provided below.

5.2.2 Progress Payments -- Based upon the Contractor's Applications for Payment submitted to the Engineer and upon Certificates for Payment subsequently issued to the Owner by the Engineer, the Owner shall make progress payments to the Contractor on account of the Contract Price.

5.2.3 On or before the 1st day of each month after commencement of the Work, the Contractor shall submit an Application for Payment for the period ending the 30th day of the month to the Engineer in such form and manner, and with such supporting data and content, as the Owner or the Engineer may require. Therein, the Contractor may request payment for ninety percent (90%) of that portion of the Contract Price properly allocable to Contract requirements properly provided, labor, materials and equipment properly incorporated in the Work plus ninety percent (90%) of that portion of the Contract Price properly allocable to materials or equipment properly stored on-site (or elsewhere if approved in advance in writing by the Owner) for subsequent incorporation in the Work, less the total amount of previous payments received from the Owner. Payment for stored materials and equipment shall be conditioned upon the Contractor's proof satisfactory to the Owner, that the Owner has title to such materials and equipment and shall include proof of required insurance. Such Application for Payment shall be signed by the Contractor and shall constitute the Contractor's representation that the Work has progressed to the level for which payment is requested in accordance with Articles 4 and 5 of this Agreement, that the Work has been properly installed or performed in full accordance with this Contract, and that the Contractor knows of no reason why payment should not be made as requested. Thereafter, the Engineer will review the Application for Payment and may also review the Work at the Project site or elsewhere to determine whether the quantity and quality of the Work is as represented in the Application for Payment and is as required by this Contract. The Engineer shall determine and certify to the Owner the amount properly owing to the Contractor.

5.2.4 The Owner shall make partial payments on account of the Contract Price to the Contractor within thirty (30) days following the Engineer's receipt of each Application for Payment. The amount of each partial payment shall be the amount certified for payment by the Engineer less such amounts, if any, otherwise owing by the Contractor to the Owner or which the Owner shall have the right to withhold as authorized by this Contract. The Engineer's certification of the Contractor's Application for Payment shall not preclude the Owner from the exercise of any of its rights as set forth in Paragraph 5.3 hereinbelow. PROVIDED, HOWEVER, that when fifty (50) percent of the contract value, including change orders and other additions to the contract value, provided for by the Contract Documents is due, and the manner of completion of the contract Work and its progress are reasonably satisfactory to the Owner, the Owner shall withhold no more retainage. At the discretion of the Owner, and with the approval of the Contractor, the retainage of any subcontractor may be released separately as the subcontractor completes its work. If, however, after discontinuing the retention, the Owner determines that the Work is unsatisfactory or has fallen behind schedule, retention may be resumed at the previous level. If retention is resumed by the Owner, the Contractor and subcontractors shall be entitled to resume withholding retainage accordingly. The rights of the Owner set forth herein to retainage are in addition to all of the other rights and remedies of the Owner set forth in this Agreement.

5.2.5 The Contractor warrants that title to all Work covered by an Application for Payment will pass to the Owner no later than the time of payment. The Contractor further warrants that upon submittal of an Application for Payment, all Work for which payments have been received from the Owner shall be free and clear of liens, claims, security interest or other encumbrances in favor of the Contractor or any other person or entity whatsoever.

5.2.6 The Contractor shall promptly pay each Subcontractor out of the amount paid to the Contractor on account of such Subcontractor’s Work, the amount to which such Subcontractor is entitled. In the event the Owner becomes informed that the Contractor has not paid a Subcontractor as herein provided, the Owner shall have the right, but not the duty, to issue future checks in payment to the Contractor of amounts otherwise due hereunder naming the Contractor and such Subcontractor as joint payees. Such joint check procedure, if employed by the Owner, shall create no rights in favor of any person or entity beyond the right of the named payees to payment of the check and shall not be deemed commit the Owner to repeat the procedure in the future.

5.2.7 No progress payment, nor any use or occupancy of the Project by the Owner, shall be interpreted to constitute an acceptance of any Work not in strict accordance with this Contract.

5.3 Withheld Payment

5.3.1 To the extent permitted by Georgia law, the Owner may decline to make payment, may withhold funds, and, if necessary, may demand the return of some or all of the amounts previously paid to the Contractor, to protect the Owner from loss because of:

(a) defective Work not remedied by the Contractor nor, in the opinion of the Owner, likely to be remedied by the Contractor;

(b) claims of third parties against the Owner or the Owner’s property;

(c) failure by the Contractor to pay Subcontractors or others in a prompt and proper fashion;

(d) evidence that the balance of the Work cannot be completed in accordance with the Contract for the unpaid balance of the Contract Price;

(e) evidence that the Work will not be completed in the time required for substantial or final completion;

(f) persistent failure to carry out the Work in accordance with the Contract;

(g) damage to the Owner or third party to whom the Owner is, or may be, liable.

In the event that the Owner makes written demand upon the Contractor for amounts previously paid by the Owner as contemplated in this Subparagraph 5.3.1, the Contractor shall promptly comply with such demand.

5.4 Unexcused Failure to Pay

5.4.1 If within forty-five (45) days after the date established herein for payment to the contractor by the Owner, the Owner, without cause or basis hereunder, fails to pay the Contractor any amount then due and payable to the Contractor, then the Contractor may, after seven (7) additional days’ written notice to the Owner and Engineer, and without prejudice to any other available rights or remedies it may have, stop the Work until payment of those amounts due from the Owner has been received. Any payment not made within forty-five

(45) days after the date due shall bear interest at the rate of three percent (3%) per annum.

5.5 Substantial Completion

5.5.1 When the Contractor believes that the Work is substantially complete, the Contractor shall submit to the Engineer and Owner notice that it believes the project has been completed.

The Engineer shall then cause the project to be inspected and provide the Contractor with either (1) a list of items to be completed or corrected by the Contractor, or (2) a Certificate of Substantial Completion. When the Engineer on the basis of an inspection determines that the Work is in fact substantially complete, it will prepare a Certificate of Substantial Completion which shall establish the date of Substantial Completion, shall state the responsibilities of the Owner and the Contractor for Project security, maintenance, heat, utilities, damage to the Work, and insurance, and shall fix the time within which the Contractor shall complete the items listed therein. The Certificate of Substantial Completion shall be submitted to the Contractor for its written acceptance of the responsibilities assigned to it in such certificate.

Upon Substantial Completion of the Work, and execution by both the Owner and Contractor of the Certificate of Substantial Completion, the Owner shall pay the Contractor an amount sufficient to increase total payment to the Contractor to one hundred percent (100%) of the Contract Price less two hundred percent (200%) of the reasonable cost as determined by the Owner for completing all incomplete Work, correcting and bringing into conformance all defective and nonconforming Work, and handling all unsettled claims.

5.6 Completion and Final Payment

5.6.1 When all of the Work is finally complete, and the Contractor is ready for a final inspection, it shall notify the Owner and the Engineer thereof in writing. Thereupon, the Engineer will make final inspection of the Work and, if the Work is complete in full accordance with this Contract and all Contract Documents, and this Contract has been fully performed, the Engineer will promptly issue a final Certificate for Payment certifying to the Owner that the Project is complete and the Contractor is entitled to the remainder of the unpaid Contract Price, less any amount withheld pursuant to this Contract. Guarantees required by the Contract shall commence on the date of Final Completion of the Work. If the Engineer is unable to issue its final Certificate for Payment and is required to repeat its final inspection of the Work, the Contractor shall bear the cost of such repeat final inspection(s) which cost may be deducted by the Owner from the Contractor’s final payment.

5.6.1.1 If the Contractor fails to achieve final completion within the time fixed therefore by the Engineer in its Certificate of Substantial Completion, the Contractor shall pay the Owner the sum of Two Hundred and Fifty Dollars ($250.00) per day for each and every calendar day of unexcused delay in achieving final completion beyond the date set forth herein for final completion of the Work. Any sums due and payable hereunder by the Contractor shall be payable, not as penalty, but as liquidated damages representing an estimate of delay damages likely to be sustained by the Owner, estimated at or before the time of executing this Contract.

When the Owner reasonably believes that final completion will be inexcusably delayed, the Owner shall be entitled, but not required, to withhold from any amounts otherwise due the Contractor an amount then believed by the Owner to be adequate to recover liquidated damages applicable to such delays. If and when the Contractor overcomes the delay in achieving final completion, or any part thereof, for which the Owner has withheld payment, the Owner shall promptly release to the Contractor those funds withheld, but no longer applicable, as liquidated damages.

5.6.2 The Contractor shall not be entitled to final payment unless and until it submits to the Engineer and Owner all documents required by the Contract, including, but not limited to, its affidavit that all payrolls, invoices for materials and equipment, and other liabilities connected with the Work for which the Owner, or the Owner’s property might be responsible, have been fully paid or otherwise satisfied; releases and waivers of lien from all Subcontractors of the Contractor and of any and all other parties required by the Engineer or the Owner; consent of Surety, if any, to final payment. If any third party fails or refuses to provide a release of claim or waiver of lien as required by the Owner, the Contractor shall furnish a bond satisfactory to the Owner to discharge any such lien or indemnify the Owner from liability.

5.6.3 The Owner shall make final payment of all sums due the Contractor within thirty (30) days of the Engineer’s execution of a final Certificate for Payment.

5.6.4 Acceptance of final payment shall constitute a waiver of all claims against the Owner by the Contractor except for those claims previously made in writing against the Owner by the Contractor, pending at the time of final payment, and identified in writing by the Contractor as unsettled at the time of its request for final payment.

5.6.5 The Owner and Contractor expressly agree that the terms of payment, payment periods, and rates of interest herein shall control to the exclusion of any provisions set forth in the Georgia Prompt Pay Act, O.C.G.A. Section 13-11-1 et al., and the provisions of said Act are herein waived.

ARTICLE VI

THE OWNER

6.1 Information, Services and Things Required from Owner

6.1.1 If the Contractor requests in writing, the Owner shall furnish to the Contractor, prior to the execution of this Contract, any and all written and tangible material in its possession concerning conditions below ground at the site of the Project. Such written and tangible material is furnished to the Contractor only in order to make complete disclosure of such material and for no other purpose. By furnishing such material, the Owner does not represent, warrant, or guarantee its accuracy either in whole, in part, implicitly or explicitly, or at all, and shall have no liability, therefore. The Owner shall also furnish surveys, legal limitations and utility locations (if known), and a legal description of the Project site.

6.1.2 Excluding permits and fees normally the responsibility of the Contractor, the Owner shall obtain all approvals, easements, and the like required for construction and shall pay for necessary assessments and charges required for construction, use or occupancy of permanent structures or for permanent changes in existing facilities.

6.1.3 The Owner shall furnish the Contractor, free of charge, three (3) copies of the Contract Documents for execution of the Work (if applicable). The Contractor will be charged, and shall pay the Owner, Fifty Dollars ($50.00) per additional set of Contract Documents which it may require.

6.2 Right to Stop Work

6.2.1 If the Contractor persistently fails or refuses to perform the Work in accordance with this Contract, the Owner may order the Contractor to stop the Work, or any described portion thereof, until the cause for stoppage has been corrected, no longer exists, or the Owner orders that Work be resumed. In such event, the Contractor shall immediately obey such order.

6.3 Owner’s Right to Perform Work

6.3.1 If the Contractor’s Work is stopped by the Owner under Paragraph 6.2, and the Contractor fails within seven (7) days of such stoppage to provide adequate assurance to the Owner that the cause of such stoppage will be eliminated or corrected, then the Owner may, without prejudice to any other rights or remedies the Owner may have against the Contractor, proceed to carry out the subject Work. In such a situation, an appropriate Change Order shall be issued deducting from the Contract Price the cost of correcting of the subject deficiencies, plus compensation for the Engineer’s additional services and expenses necessitated thereby, if any. If the unpaid portion of the Contract Price is insufficient to cover the amount due to the Owner, the Contractor shall pay the difference to the Owner.

ARTICLE VII

THE CONTRACTOR

7.1 The Contractor

7.1.1 The Contractor is again reminded of its continuing duty set forth in Subparagraph

1.5.7. The Contractor shall perform no part of the Work at any time without adequate Contract Documents or, as appropriate, approved shop Drawings, Product Data or Samples for such portion of the Work. If the Contractor performs any of the Work knowing it involves a recognized error, inconsistency, or omission in the Contract Documents without such notice to the Engineer, the Contractor shall bear responsibility for such performance and shall bear the cost of correction.

7.2 Compliance with Contract

7.2.1 The Contractor shall perform the work strictly in accordance with this Contract.

7.3 Reasonable Care and Skill

7.3.1 The Contractor shall supervise and direct the Work and warrants that it will perform all services or Work using reasonable care and skill and in workmanlike manner consistent with industry standards. The Contractor shall be responsible to the Owner for any and all acts or omissions of the Contractor, its employees and others engaged in the Work on behalf of the Contractor.

7.4 Warranty

7.4.1 The Contractor warrants to the Owner that all labor furnished to progress the Work under this Contract will be competent to perform the tasks undertaken, that the product of such labor will yield only first-class results, that materials and equipment furnished will be of good quality and new unless otherwise permitted by this Contract, and that the Work will be of good quality free from faults and defects and in strict conformance with this Contract. All Work not conforming to these requirements may be considered defective.

7.4.2 The standard of care applicable to the Contractor’s services shall be the standard of skill and diligence normally employed by businesses performing the same or similar services at the time the Contractor’s services are performed. For a twelve (12) month period commencing with the completion of the Work, the Contractor shall re-perform, solely at its own cost and without additional compensation due from the Owner, any services not meeting this standard. The Contractor further warrants that any service it undertakes in the performance of the Work will be adequate and sufficient to accomplish the purposes for which they are performed, and no review or approval thereof by the City shall be deemed to diminish this warranty in any way.

7.5 Permits

7.5.1 The Contractor shall obtain and pay for all permits, inspections, fees and licenses necessary and ordinary for the Work. The Contractor shall comply with all lawful requirements applicable to the Work and shall give and maintain any and all notices required by applicable law, ordinance, or regulation pertaining to the Work.

7.6 Supervision

7.6.1 The Contractor shall employ and maintain at the Project site only competent supervisory personnel. Absent written instruction from the Contractor to the contrary, the superintendent shall be deemed the Contractor’s authorized representative at the site and shall be authorized to receive and accept any and all communications from the Owner or the Engineer.

7.6.2 Key supervisory personnel assigned by the Contractor to this Project are as follows:

Name Function

So long as the individuals named above remain actively employed or retained by the Contractor, they shall perform the functions indicated next to their names unless the Owner agrees to the contrary in writing. In the event one or more individuals not listed above subsequently assumes one or more of those functions listed above, the Contractor shall be bound by the provisions of this Subparagraph 7.6.2 as though such individuals had been listed above.

7.7 Schedules

7.7.1 The Contractor, within fifteen (15) days of commencing the Work, shall submit to the Owner for their information the Contractor’s schedule for completing the Work. Additionally, within fifteen (15) days of commencing the Work, the Contractor shall submit to the Owner and the Engineer a separate shop drawing and submittal schedule detailing the schedule for the submission to the Engineer of all shop drawings (if applicable) submittals, product data and other similar documents. Each of the schedules required herein shall be revised no less frequently than monthly (unless the parties otherwise agree in writing) and shall be revised to reflect conditions encountered from time-to time and shall be related to the entire Project.

Each such revision shall be furnished to the Owner and the Engineer. The schedules, and all revisions, shall be in such form, and shall contain such detail, as the Owner or the Engineer may require. THE PARTIES SPECIFICALLY AGREE THAT ANY FLOAT CONTAINED

IN THE SCHEDULES SHALL BELONG TO THE PROJECT AND IN NO EVENT SHALL

THE CONTRACTOR MAKE CLAIM FOR ANY ALLEGED DELAY, ACCELERATION,

OR EARLY COMPLETION SO LONG AS THE PROJECT IS COMPLETED WITHIN

THE CONTRACT TIME. Strict compliance with the requirements of this Paragraph is condition precedent for payment to the Contractor, and failure by the Contractor to strictly comply with said requirements shall constitute a material breach of this Contract.

7.8 Required Documents at the Site

7.8.1 The Contractor shall continuously maintain at the site, for the benefit of the Owner and the Engineer, one record copy of this Contract marked to record on a current basis changes, selections and modifications made during construction. Additionally, the Contractor shall maintain at the site for the Owner and the Engineer the approved Shop Drawings (if applicable), Product Data, Samples, and other similar required submittals. Upon final completion of the Work, all of these record documents shall be delivered to the Owner.

7.9 Shop Drawings, Product Data and Samples

7.9.1 Shop Drawings (if applicable), Product Data, Samples and other submittals from the Contractor do not constitute Contract Documents. Their purpose is merely to demonstrate the manner in which the Contractor intends to implement the Work in conformance with information received from the Contract Documents.

7.9.2 The Contractor shall not perform any portion of the Work requiring submittal and review of Shop Drawings (if applicable), Product Data or Samples unless and until such submittal shall have been approved by the Engineer. Approval by the Engineer, however, shall not be evidence that Work installed pursuant thereto conforms with the requirements of this Contract.

7.10 Cleaning the Site and the Project

7.10.1 The Contractor shall keep the site reasonably clean during performance of the Work.

Upon final completion of the Work, the Contractor shall clean the site and the Project and remove all waste, together with all of the Contractor’s property therefrom.

7.11 Access to Work

7.11.1 The Owner and the Engineer shall have access to the Work at all times from commencement of the Work through final completion. The Contractor shall take whatever steps necessary to provide access when requested.

7.12 Indemnity

7.12.1 To the fullest extent permitted by law, the Contractor shall indemnify and hold harmless the Owner, its officials, officers, employees, agents and representatives from and against liability, claims, damages, losses and expenses, including attorneys’ fees, arising out of or resulting from performance of the Work, provided that such liability, claims, damage, loss or expense is attributable to injury, bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself) including loss of use resulting therefrom, but only to the extent caused in whole or in part by negligent or willful acts or omissions of the Contractor, a Subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, regardless of whether or not such liability, claim, damage, loss or expense is caused in part by a party indemnified hereunder.

7.12.2 For any claim against any person or entity indemnified under this Paragraph 7.12 by an employee of the Contractor, a Subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, the indemnification obligation under this Paragraph 7.12 shall not be limited by a limitation on amount or type of damages, compensation or benefits payable by or for the Contractor or a Subcontractor under workers’ compensation acts, disability benefits acts or other employee benefits acts.

7.13 Means, Methods, Techniques, Sequences, Procedures and Safety

7.13.1 The Contractor is fully responsible for, and shall have control over, all construction means, methods, techniques, sequences, procedures and safety, and shall coordinate all portions of the work required by the Contract Documents. Nothing contained herein, however, shall in any manner whatsoever relieve, release or discharge the Engineer from any of its duties, responsibilities, obligations, or liabilities as set forth in its contract with the Owner, or as provided by law.

7.14 Separate Contracts

7.14.1 The Owner reserves the right to perform work on the premises with its own forces or by the use of other Contractors. In such event, the Contractor shall fully cooperate with the Owner and such other Contractors and shall coordinate, schedule and manage its work so as not to hinder, delay or otherwise interfere with the separate work of the Owner or other Contractors.

ARTICLE VIII

CONTRACT ADMINISTRATION

8.1 Engineer’s Administration

8.2.1 The Engineer, unless otherwise directed by the Owner in writing, will perform those duties and discharge those responsibilities allocated to the Engineer as set forth in this Contract. The Engineer shall be the Owner's representative from the effective date of this Contract until final payment has been made. The Engineer shall be authorized to act on behalf of the Owner only to the extent provided in this Contract.

8.2.2 The Owner and the Contractor shall communicate with each other in the first instance through the Engineer.

8.2.3 The Engineer shall be the initial interpreter of the requirements of the drawings and specifications and the judge of the performance thereunder by the Contractor. The Engineer shall render written or graphic interpretations necessary for the proper execution or progress of the Work with reasonable promptness on request of the Contractor.

8.2.4 The Engineer will review the Contractor's Applications for Payment and will certify to the Owner for payment to the Contractor, those amounts then due the Contractor as provided in this Contract.

8.2.5 The Engineer shall have authority to reject Work which is defective or does not conform to the requirements of this Contract. If the Engineer deems it necessary or advisable, the Engineer shall have authority to require additional inspection or testing of the Work for compliance with Contract requirements.

8.2.6 The Engineer will review and approve, or take other appropriate action as necessary, concerning the Contractor's submittals including Shop Drawings, Product Data and Samples. Such review, approval or other action shall be for the sole purpose of determining conformance with the design concept and information given through the Contract Documents.

8.2.7 The Engineer will prepare Change Orders and may authorize minor changes in the Work by Field Order as provided elsewhere herein.

8.2.8 The Engineer shall, upon written request from the Contractor, conduct inspections to determine the date of Substantial Completion and the date of Final Completion, will receive and forward to the Owner for the Owner's review and records, written warranties and related documents required by this Contract and will issue a final Certificate for Payment upon compliance with the requirements of this Contract.

8.2.9 The Engineer's decisions in matters relating to aesthetic effect shall be final if consistent with the intent of this Contract.

8.2.10 THE DUTIES, OBLIGATIONS AND RESPONSIBILITIES OF THE CONTRACTOR

UNDER THIS AGREEMENT SHALL IN NO MANNER WHATSOEVER BE CHANGED,

ALTERED, DISCHARGED, RELEASED, OR SATISFIED BY ANY DUTY, OBLIGATION

OR RESPONSIBILITY OF THE ENGINEER. THE CONTRACTOR IS NOT A THIRD-PARTY

BENEFICIARY OF ANY AGREEMENT BY AND BETWEEN THE OWNER AND THE

ENGINEER. IT IS EXPRESSLY ACKNOWLEDGED AND AGREED THAT THE DUTIES

OF THE CONTRACTOR TO THE OWNER ARE INDEPENDENT OF, AND ARE NOT

DIMINISHED BY, ANY DUTIES OF THE ENGINEER TO THE OWNER.

8.3 Claims by the Contractor

8.3.1 All Contractor claims shall be initiated by written notice and claim to the Owner and Engineer. Such written notice and claim must be furnished within seven (7) days after occurrence of the event, or the first appearance of the condition, giving rise to the claim.

8.3.2 Pending final resolution of any claim of the Contractor, the Contractor shall diligently proceed with performance of this Contract and the Owner shall continue to make payments to the Contractor in accordance with this Contract. The resolution of any claim under this Paragraph 8.3 shall be reflected by a Change Order executed by the Owner, the Engineer, and the Contractor.

8.3.3 Claims for Concealed and Unknown Conditions -- Should concealed and unknown conditions encountered in the performance of the Work (a) below the surface of the ground or (b) in an existing structure be at variance with the conditions indicated by this Contract, or should unknown conditions of an unusual nature differing materially from those ordinarily encountered in the area and generally recognized as inherent in Work of the character provided for in this Contract, be encountered, the Contract Price shall be equitably adjusted by Change Order upon the written notice and claim by either party made within seven (7) days after the first observance of the condition. As a condition precedent to the Owner having any liability to the Contractor for concealed or unknown conditions, the Contractor must give the Owner and the Engineer written notice of, and an opportunity to observe, the condition prior to disturbing it. The failure by the Contractor to make the written notice and claim as provided in this Subparagraph shall constitute a waiver by the Contractor of any claim arising out of or relating to such concealed or unknown condition.

8.3.4 Claims for Additional Costs -- If the Contractor wishes to make a claim for an increase in the Contract Price, as a condition precedent to any liability of the Owner therefore, the Contractor shall give the Engineer written notice of such claim within seven (7) days after the occurrence of the event, or the first appearance of the condition, giving rise to such claim.

Such notice shall be given by the Contractor before proceeding to execute any additional or changed Work. The failure by the Contractor to give such notice and to give such notice prior to executing the Work shall constitute a waiver of any claim for additional compensation.

8.3.4.1 In connection with any claim by the Contractor against the Owner for completion in excess of the Contract Price, any liability of the Owner shall be strictly limited to direct costs incurred by the Contractor and shall in no event include indirect costs or consequential damages of the Contractor. The Owner shall not be liable to the Contractor for claims of third parties, including Subcontractors, unless and until liability of the Contractor has been established therefore in a court of competent jurisdiction.

8.3.5 Claims for Additional Time -- If the Contractor is delayed in progressing any task which at the time of the delay is then critical or which during the delay becomes critical, as the sole result of any act or neglect to act by the Owner or someone acting in the Owner’s behalf, or by Changes Ordered in the Work, unusual delay in transportation, unusually adverse weather conditions not reasonably anticipatable, fire or any causes beyond the Contractor’s control, then the date for achieving Substantial completion of the Work shall be extended upon the written notice and claim of the Contractor to the Owner and the Engineer, for such reasonable time as the Engineer may determine. Any notice and claim for an extension of time by the Contractor shall be made not more than seven (7) days after the occurrence of the event or the first appearance of the condition giving rise to the claim and shall set forth in detail the Contractor’s basis for requiring additional time in which to complete the Project. In the event the delay to the Contractor is continuing, only one notice and claim for additional time shall be necessary. If the Contractor fails to make such claim as required in this Subparagraph, any claim for an extension of time shall be waived.

8.4 Extension of Contract Time for Unusually Adverse Weather Conditions not

Reasonably Anticipated

8.4.1 Pursuant to the provisions of subparagraph 8.3.5 of this Contract, the contract time may be extended upon written notice and claim of the Contractor to the Owner and the Engineer as set forth in such subparagraph and as further set forth herein. It is, however, expressly agreed that the time for completion as stated in the Contract Documents includes due allowance for calendar days on which work cannot be performed out-of-doors.

8.4.2 In addition to the notice requirements set forth in the aforesaid subparagraph 8.3.5, the Contractor agrees that it shall provide written notice to the Owner and the Engineer on the day of any adverse weather not anticipated and for which a request for a time extension has been, or will be, made. Said notice shall state with particularity a description of the adverse weather as well as a description of the nature and extent of any delay caused by such weather. Receipt of this notice by the Owner and the Engineer is a condition precedent to the submission of any claim for an extension of time as provided by subparagraph 8.3.5. Furthermore, as required by subparagraph 8.3.5, the Contractor shall submit a written claim for extension of time within seven (7) days after the occurrence of the adverse weather and such claim shall be supported by such documentation including, but not limited to, official weather reports, as the Owner or the Engineer may be required. To the extent that any of the terms and conditions set forth in this paragraph are in conflict with any of the terms and conditions of subparagraph 8.3.5 as identified herein, the terms and conditions of this paragraph shall govern and control.

ARTICLE IX

SUBCONTRACTORS

9.1 Definition

9.1.1 A Subcontractor is an entity, which has a direct contract with the Contractor to perform a portion of the Work.

9.2 Award of Subcontracts

9.2.1 Upon execution of the Contract, the Contractor shall furnish the Owner, in writing, the names of persons or entities proposed by the Contractor to act as a Subcontractor on the Project. The Owner shall promptly reply to the Contractor, in writing, stating any objections the Owner may have to such proposed Subcontractor. The Contractor shall not enter into a Subcontract with a proposed Subcontractor with reference to whom the Owner has made timely objection. The Contractor shall not be required to Subcontract with any party to whom the Contractor has objection.

9.2.2 All Subcontracts shall afford the Contractor rights against the Subcontractor which correspond to those rights afforded to the Owner against the Contractor herein, including those rights afforded to the Owner by Subparagraph 12.2.1 below.

ARTICLE X

CHANGES IN THE WORK

10.1 Changes Permitted

10.1.1 Changes in the Work within the general scope of this Contract, consisting of additions, deletions, revisions, or any combination thereof, may be ordered without invalidating this Contract, by Change Order or by Task/Field Order.

10.1.2 Changes in the Work shall be performed under applicable provisions of this Contract and the Contractor shall proceed promptly with such changes.

10.2 Change Order Defined

10.2.1 Change Order shall mean a written order to the Contractor executed by the Owner and Engineer, issued after execution of this Contract, authorizing, and directing a change in the Work or an adjustment in the Contract Price or the Contract Time, or any combination thereof.

The Contract Price and the Contract Time may be changed only by Change Order.

10.3 Changes in the Contract Price

10.3.1 Any change in the Contract Price resulting from a Change Order shall be determined as…