ATTACHMENT D-Fillable-MATRIX OF CMR SERVICES-UPDATE101326.pdf

PDF 203 KB Posted

Attached to
002-FY27 - CMAR - ALTAVISTA COMBINED SCHOOL RFP
Solicitation number
CMR-128999
Issued by
Caroline County, Virginia

About this file

This file is a fillable matrix form titled "Matrix of CMR Services" for the Altavista Combined Schools Renovation Project, a Construction Manager At-Risk (CMAR) engagement with Campbell County Public Schools in Virginia. The matrix is designed for proposing construction management firms to identify key personnel responsible for delivering pre-construction and construction phase services. Pre-construction services include design review, schedule monitoring, cost estimating, value engineering, guaranteed maximum price (GMP) preparation, and design/constructability reviews. Construction phase services encompass CPM scheduling, trade contract award and management, progress and owner meetings, requests for information (RFI), substitution requests, change order management, project safety, quality assurance/inspections, monthly reporting, shop drawing and submittal review, site documentation, project closeout, and claims avoidance and resolution. The matrix requires proposers to designate individual team members across multiple disciplines—including Project Executive, Senior Project Manager, Project Manager, Field Superintendent, Chief Estimator, and BIM Manager—with primary, secondary, or participatory responsibility levels for each service, with only one person permitted to serve as primary for each service area.

The form establishes role-specific responsibilities across all project phases, with particular emphasis on BIM coordination capabilities, as the construction manager must include personnel capable of accessing and reviewing BIM models from the architect/engineer to coordinate work with subcontractors. This matrix serves as a key staffing and organizational proposal component that allows Campbell County Public Schools to evaluate how each shortlisted firm plans to structure its team and allocate expertise across the full scope of CMAR delivery services. No pricing, contract term, or other commercial terms are specified within this attachment, as it functions solely as a personnel assignment and capability documentation tool for the procurement process.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 - 2 - P -

Service Project

Executive Sr. Project Manager

Project Manager

Field Supt Chief

Estimator BIM Manager*

Project/Design Review

Design Schedule Monitor

Cost Model/Estimates

Value Engineering

GMP Preparation

Design/Constructability Reviews

Overall CMAR Team Mgmt

Service Project

Executive Sr. Project Manager

Project Manager

Field Supt Chief

Estimator BIM Manager*

CPM Schedule

Trade Contract Award

Trade Contract Mgmt

Conduct Progress Mtgs.

Conduct Owner’s Mtgs.

RFI’s

Substitution Requests

Change Orders

Project Safety

QA/Inspections

Monthly Report

Shop Drwg/Submmittals

Project Site Documents

Project Close Out

Claims Avoid/Resolve

Overall CMAR Team Mgmt

* CM must include someone who can access BIM models from the A/E to review and coordinate work with CM's subcontractors

ATTACHMENT D

MATRIX OF CMR SERVICES

PROPOSER’S NAME:

Complete the matrix by indicating the Key Person responsible for the following CMAR services as follows:

Construction Phase:

Primary Responsibility Secondary Responsible Party Participates in the service - not in a Primary or Seconday capacity

Note: Only one person can be designated as primary (“1”) for each service.

Pre-Construction Phase:

Proposer's Name:
PE-DESIGN REVIEW:
PE-MONITOR:
PE-COST ESTIMATES:
PE-VE:
PE-GMP PREP:
PE-REVIEWS:
PE-TEAM MGMT:
SR:
PM-DESIGNREVIEW:
PM-MONITOR:
PM-COST ESTIMATES:
PM-VE:
PM-GMR PREP:
PM-REVIEWS:
PM-TEAM MGMT:
PM-DESIGN REVIEW:
PM-MONITOR:
PM-COST ESTIMATES:
PM-VE:
PM-GMR PREP:
PM-REVIEWS:
PM-TEAM MGMT:
PE-CPM SCHED:
PE-AWARD:
PE-MGMT:
PM-PROGRESS MTG:
FIELD SUPER-DESIGN REVIEW:
FIELD SUPER--MONITOR:
FIELD SUPER--ESTIMATES:
FIELD SUPER-VE:
FIELD SUPER-GMP PREP:
FIELD SUPER-REVIEWS:
FIELD SUPER--MGMT:
ESTIMATOR-REVIEW:
ESTIMATOR-MONITOR:
ESTIMATOR-ESTIMATES:
ESTIMATOR-VE:
ESTIMATOR-GMP PREP:
ESTIMATOR-CONS REVIEWS:
ESTIMATOR-CMAR MGMT:
BIM-REVIEW:
BIM-MONITOR:
BIM-ESTIMATES:
BIM-VE:
BIM-GMP PREP:
BIM-CONS REVIEWS:
BIM-CMAR MGMT:
PE-CO:
PE-SAFETY:
PE-QA:
PE-MONTHLY REPORT:
PE-SHOP DWGS:
PE-SITE DOCS:
PE-CLOSE OUT:
PE-CLAIMS:
PE-OVERALL MGMT:
PM-CPM SCHED:
PM-AWARD:
PM-CONTR MGMT:
PM-PROGRESS MTGS:
PM-OWNER MTGS:
PM-RFI:
PM-SUBS REQ:
PE-RFI:
PE-SUB REQ:
PE-OWNER MTG:
PM-CO:
PM-SAFETY:
PM-QA:
PM-MONTHLY REPORTS:
PM-SHOP DWGS:
PM-SITE DOCS:
PM-CLOSE OUT:
PM-CLAIMS:
PM-OVERALL MGMT:
M-CPM SCHED:
M-AWARD:
M-MGMT:
M-PROGRESS MTGS:
M-OWNER MTGS:
M-RFI:
M-SUB REQ:
M-CO:
M-SAFETY:
M-QA:
M-MONTHLY REPORT:
M-SHOP DWGS:
M-SITE DOCS:
M-CLOSE OUT:
M-CLAIMS:
M-OVERALL MGMT:
SUPER-CMPSCHED:
SUPER-AWARD:
SUPER-CONTRACT MGMT:
SUPER-PROGRESS MTG:
SUPER-OWNER MTG:
SUPER-RFI:
SUPER-SUBS REQ:
SUPER-CO:
SUPER-SAFETY:
SUPER-QA:
SUPER-MONTHLY REPORT:
SUPER-SHOP DWG:
SUPER-SITE DOCS:
SUPER-CLOSE OUT:
SUPER-CLAIMS:
SUPER-OVERALL MGMT:
EST-CPM:
EST-AWARD:
EST-CONTRACT:
EST-PROGRESS MTG:
EST-OWNER MTGS:
EST-RFI:
EST-SUBS REQ:
EST-CO:
EST-SAFETY:
EST-QA:
EST-MONTHY REPORT:
EST-SHOP DWG:
EST-SITE DOCS:
EST-CLOSE OUT:
EST-CLAIMS:
EST-OVERALL MGMT:
BIM-CPM:
BIM-AWARD:
BIM-MGMT:
BIM-PROGRESS MTG:
BIM-OWNER MTGS:
BIM-RFI:
BIM-SUBS REQ:
BIM-CO:
BIM-SAFETY:
BIM-QA:
BIM-MONTHY REPORT:
BIM-SHOP DWG:
BIM-SITE DOCS:
BIM-CLOSE OUT:
BIM-CLAIMS:
BIM-OVERALL MGMT:

File details come from the government source that posted it. Updated .