Attachment_D_Asbestos_Survey.pdf
PDF 5 MB Posted
- Attached to
- Demolition of Former Motel in Micco
- Solicitation number
- B-2-26-38
- Issued by
- Brevard County, Miramar Beach CDP, Florida
About this file
This is an Asbestos-Demolition Survey Report prepared by UES Professional Solutions LLC for Brevard County Public Works Facilities Engineering & Construction regarding the former Micco Hotel located at 8820 and 8830 Highway 1 in Micco, Brevard County, Florida. The survey was conducted on October 7, 2025, in accordance with EPA Title 40, Part 61, Subpart M (NESHAP) and Chapter 61-145 of Florida regulations to identify asbestos-containing materials (ACM) in advance of the anticipated demolition project. UES collected and analyzed 43 bulk samples from 22 homogeneous materials using Polarized Light Microscopy (PLM) at an NVLAP-accredited laboratory. The survey encompassed accessible areas of the two structures with a combined base area of 4,759 square feet and maximum height of approximately 30 feet, including the former motel and two-story duplex building.
The survey findings indicate that asbestos fibers in excess of one percent were not detected in any of the homogeneous materials sampled. The report notes that the survey was limited to readily accessible areas and did not employ extensive destructive sampling or exploratory demolition methods. UES explicitly states that inspection and sampling of suspect ACMs were limited to accessible materials at the time of inspection, and that some materials may remain hidden beneath overlying materials such as flooring or concealed walls. The report emphasizes that contractors performing demolition or renovation work should be made aware of these limitations and take appropriate precautions, with any suspected materials encountered during demolition to be analyzed for asbestos content prior to removal.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Geotechnical & Geophysical Engineering | Environmental | Occupational Health & Safety| Building Code Compliance Drilling Services | Construction Materials Testing | Threshold Inspection | Facilities Consulting
ASBESTOS – DEMOLITION - SURVEY
Conducted on:
Micco Hotel 8820 and 8830 Highway 1
Micco, Brevard County, Florida 32976
UES Project No. A25146.01691.000 UES Report No. 2158596
Survey Date: October 7, 2025 Report Date: October 17, 2025
Prepared for:
Mr. James Monarchy, Construction Coordinator Brevard County Public Works - Facilities Engineering & Construction
2725 Judge Fran Jamieson Way, Suite 201 Viera, Brevard County, Florida 32940
Prepared by:
UES Professional Solutions LLC.
820 Brevard Avenue
Rockledge, Florida 32955
(321) 638-0808
Business License No. ZA-0000017 www.Team UES.com
ATTACHMENT D - ASBESTOS SURVEY
820 Brevard Avenue | Rockledge, FL 32955 | p 321-638-0808 | f 407-638-0978 | www.TeamUES.com
October 17, 2025
Mr. James Monarchy, Construction Coordinator Brevard County Facilities Engineering & Construction 2725 Judge Fran Jamieson Way, Suite 201 Viera, Brevard County, Florida 32940
Reference: ASBESTOS-DEMOLITION SURVEY Micco Hotel 8820 and 8830 Highway 1 Micco, Brevard County, Florida 32976
UES Project No. A25146.01691.000 UES Report No. 2158596
Dear Mr. Monarchy:
On behalf of Brevard County Public Works Facilities (the “client”), UES Professional Solutions (UES) has completed a National Emissions Standard for Hazardous Air Pollutants (NESHAP) Asbestos Containing Materials Building Demolition Survey Report. This survey was conducted in accordance with Chapter 61- 145 of the Environmental Protection Agency’s (EPA) Title 40, Part 61, Subpart M of the Code of Federal Regulations (CFR) for the above-referenced property (the “subject property). UES performed this ACM survey on Tuesday, October 07, 2025, to categorize and assess readily available suspect homogeneous materials. UES collected forty-three (43) bulk samples from twenty-two (22) homogeneous materials. The bulk samples were transported to a National Voluntary Laboratory Accreditation Program (NVLAP) accredited laboratory and analyzed using Polarized Light Microscopy (PLM) for the presence of asbestos fibers.
Based on review of the Bulk Sample Analysis Report, asbestos fibers in excess of one percent was not detected in any of the homogeneous materials sampled during the course of this ACM survey. Additional details regarding the ACM Survey conducted by UES are presented in the attached report.
UES appreciates this opportunity to provide environmental services to you and we look forward to future endeavors. If you have, any comments or questions regarding the information contained within this report or if we can be of further service, please contact the undersigned.
Respectfully submitted, UES Professional Solutions LLC.
Written by, Reviewed by, Brandon M. Selph Jonathan A. Bulley Senior Project Manager Florida Licensed Asbestos Consultant EPA Accredited Asbestos Inspector Florida License No. AX133 b l JoJoJoJoJoJoJJooJooJoJoJoJoJoJoJooooJJoJJJoJoJooJoJoJJJJoJoJoJJoJoJJJooooJoooooooooooooooooooooooooooooooonananananananaaannnanannanananananannnannnnnnnananannnnannnannnnannanannananannanannnnaaanannnaanaaaaannnnaaaanaannannnaaaathan A. Bulley i
TABLE OF CONTENTS
1.0 Introduction
1.1 Limitations and Exclusions
1.2 Purpose and Scope of Work
2.0 Building Characteristics and Information
2.1 General
2.2 Available Building Information
2.3 Current Building Use
3.0 Building Inspection
3.1 Inspection Procedures
3.2 Suspected Asbestos-Containing Building Materials
4.1 Polarized Light Microscopy
4.2 Point Count Analysis
5.0 Findings
6.0 Summary of Asbestos-Containing Materials
7.0 Regulatory information
8.0 Controlling Agency
9.0 CONDITIONS AND LIMITATIONS OF THIS SURVEY
ii
LIST OF APPENDICES
APPENDIX A
Bulk Sample Location Map ............................................................................................................... A
APPENDIX B
PLM Analytical Report & Chain-of-Custody Documentation ........................................................... B
APPENDIX C
Inspector(s) Certification ................................................................................................................. C
Asbestos-Demolition Survey UES Project No. A25146.01691.000 8820 and 8830 Highway 1 UES Report No.2155865 Micco, Brevard County, Florida 32940 October 17, 2025
1.0 INTRODUCTION
UES Professional Solutions (UES) conducted a pre-demolition Asbestos-Containing Materials (ACM) Survey of the structures located at 8820 and 8830 Highway 1 in Micco, Brevard County, Florida 32940.
The purpose of this survey was to identify and sample accessible suspect ACM and provide information regarding the identity, location, and condition in anticipation of a renovation and/or demolition.
This service was conducted based on the written authorization of Brevard County Public Works Facilities, dated October 3, 2025, under Work Order #5078109. This service was conducted according to proposal 2156261v4 dated September 22, 2025. This survey was conducted in accordance with the conditions which are incorporated into the Client authorized agreement that governs this assessment.
This survey was conducted in accordance with Chapter 61-145 of the Environmental Protection Agency’s (EPA) Title 40, Part 61, Subpart M of the Code of Federal Regulations (CFR).
1.1 Limitations and Exclusions
This survey report is not intended to be used as a specification or work plan. The indicated material quantities of ACM (if documented) are estimates based on UES’ field observations on the date(s) of the inspection(s), and should be considered preliminary in nature. All parties utilizing this report for proposal, estimation or contract negotiations are required to field verify the quantities of material prior to submission of proposal. These estimates should not be used for bidding purposes without verification by the asbestos abatement contractor. The asbestos abatement contractor should ascertain for themselves, by site measurements and inspection, the exact nature and extent of the work to be done.
Inspection and collection of bulk samples of suspect ACMs were limited to those materials readily accessible at the time of inspection. Destructive sampling techniques (such as wall and ceiling testing, and carpet cuts to expose underlying flooring) were employed in limited measures in the areas inspected and completed in a way to minimize disruption to operations and damage to building components. Extensive destructive sampling methods were not used, and exploratory demolition of walls and/or removal of fixed items were not conducted. No attempt was made by UES to observe conditions in spaces not generally accessible, including but not limited to crawlspaces, pipe chases, plenums or confined spaces. Some materials may be hidden or masked by overlying materials such as flooring, carpeting or concealed walls.
Although every effort is made to locate all suspect ACMs, it is impossible to rule out the possibility that undiscovered asbestos materials may be present. If the building is to undergo major refurbishment or demolition, it is recommended that the persons carrying out the work are made aware of this and take sufficient precautions, as may be appropriate, to ensure the health and safety of their own employees and any other parties who may be affected by the works. Any suspected building materials not addressed in this report, which are encountered during demolition or renovation should be analyzed for asbestos content prior to being damaged and/or removed.
1.2 Purpose and Scope of Work
The purpose of this study was to perform an evaluation of the above-referenced facility for the presence of ACMs, specifically those building materials which may be present or impacted during potential demolition or renovation activities. The activities and procedures used to accomplish this task were as follows:
1) A review of available building documents to identify potential locations of suspect ACMs;
2) Visual building inspection of accessible areas by a United States Environmental Protection Agency
(EPA) Asbestos Hazard Emergency Response Act (AHERA) accredited asbestos building inspector to identify suspect ACMs;
3) Once identified, homogeneous materials (materials which are uniform in color, texture, construction/application date, and general appearance) were determined;
4) Determine whether the suspect ACM is friable (a material that when dry, may be crumbled, pulverized or reduced to powder by hand pressure) or non-friable;
5) Collection of bulk samples of each homogeneous suspect ACM. Record sample information on Asbestos Bulk Sample Forms (chain-of-custody sheets), which were signed, dated, and sent with the samples to the laboratory;
6) Analysis of the collected bulk samples at a National Voluntary Laboratory Accreditation Program (NVLAP) accredited laboratory using Polarized Light Microscopy (PLM) for the presence of asbestos fibers;
7) If applicable, confirmatory analysis of bulk samples documented by PLM analysis as containing less than one percent (<1%), were further analyzed utilizing the “Quantitation using 400 Point Count Procedure” for asbestos analysis of bulk material via EPA method 600/R-93/116.
8) Approximate locations of the bulk samples were defined. Computer Assisted Drafting and Design (CADD) drawings were developed indicating sample locations. In addition, approximate quantities of identified ACM were also determined; and,
9) Prepare and submit a report.
2.0 BUILDING CHARACTERISTICS AND INFORMATION
2.1 General
A summary of the subject buildings characteristics are outlined in the table below. Information on the buildings was obtained by UES through our field inspection, review of available building documents and/or property appraiser records.
Main Building
General
Facility Type Retail Store Multiple Units
Construction Date 1954
Building Size 4,506 SF
Number of Stories 2
Structural
Foundation Slab-on-Grade
Wall Support Concrete Block
Wall Finish Stucco/ Cutt Brick
Roof Support Wood Trusses
Roof System Type Asphalt Shingle – Roll Composition
Mechanical/ Plumbing
HVAC Type Exterior Central Unit / Window Unites
Duct Type Flex
Pipe Insulation Walk in Cooler Lines
Interior
Wall Substrates Wood
Wall Finishes Smooth Drywall
Floor Substrates Concrete
Floor Finishes Ceramic Tile
Ceiling Systems Drop Down Grid System / Oppen Truss
Ceiling Finishes Ceiling Tile
Other None
Building 2 Hotel
General
Facility Type Duplex
Construction Date 1977
Building Size 1,026 SF
Number of Stories 2
Structural
Foundation Slab-on-Grade
Wall Support Concrete Block
Wall Finish Stucco / Cutt Brick
Roof Support Wood Trusses
Roof System Type Asphalt / Gravel
Mechanical/ Plumbing
HVAC Type Window Unites
Duct Type None
Pipe Insulation None
Interior
Wall Substrates Wood
Wall Finishes Smooth Drywall
Floor Substrates Concrete / Wooden
Floor Finishes Ceramic Tile
Ceiling Systems Drop Down Grid System
Ceiling Finishes Ceiling Tile
Other None
2.2 Available Building Information
A previous asbestos survey report or other relevant building construction information was not provided in reference to the structures located within the subject property.
2.3 Current Building Use
At the time of UES’ evaluation, the subject buildings were vacant.
3.0 BUILDING INSPECTION
Three forms of ACMs are typically found in buildings. These materials are classified as follows:
Surfacing Material – material that is sprayed, troweled-on, or otherwise applied to interior and exterior structural and architectural surfaces. Surfacing material includes acoustical plaster on ceilings, fireproofing on structural members, textured paint and exterior stucco, and other materials applied to surfaces for acoustical, decorative, fireproofing, and other purposes.
Thermal System Insulation — material which is applied to interior and exterior mechanical components to reduce heat gain or loss. Thermal system insulation includes insulation on pipes, fittings, boilers, breeching, tanks, ducts, and other mechanical components.
Miscellaneous Materials — material, other than surfacing material and thermal system insulation, on interior and exterior structural, mechanical, electrical, or architectural components, and surfaces. Miscellaneous material includes but is not limited to ceiling tiles, gaskets, floor coverings and mastics, wallboard joint compound, roofing materials, and cementitious products.
An inspection of the subject buildings was conducted to identify these, and other materials present within the buildings which are typically suspected of containing asbestos.
3.1 Inspection Procedures
UES’ field inspection was performed October 7, 2025, by Brandon Selph, an inspector accredited according to Federal Regulation 40 CFR, Part 763 (AHERA), under the direction of an Asbestos Consultant licensed in the State of Florida. After a preliminary walk-through of the building, an inspection was conducted to evaluate the location and extent of the suspected asbestos containing building materials. Once identified, these materials were categorized into homogeneous areas containing materials of the same type, age, visual appearance, texture, composition, etc.
This type of survey is designed to be used as a basis for tendering the removal of ACMs from the subject building (s) prior to demolition or renovation. Therefore, the survey does not assess the condition of the asbestos, other than to note areas of damage or where additional asbestos debris may be expected to be present. The present condition of each ACM was evaluated by UES and classified as one of three categories: Good, Fair or Poor. The “fair” and “poor” categories correspond to the AHERA definitions of “damaged” and “significantly damaged,” respectively.
The number of bulk samples collected was based on the category of homogeneous material and the quantity of the material present, as follows:
AHERA Guidelines for Determining the Number of Samples to Collect HSA Category HSA Quantity Samples Required
Surfacing Materials <1,000 Square Feet 3
1,000 – 5,000 Square Feet 5 >5,000 Square Feet 7 or more
Thermal System Insulation No Stipulation 3+ (All repair patches must be sampled)
Miscellaneous Materials No Stipulation
Per AHERA Guidelines, these materials must be sampled “in a manner sufficient to determine whether or not they contain asbestos” typically 1 – 3 samples based upon the inspector’s judgement.
HSA: Homogeneous Sampling Area (materials which are uniform in color, texture, construction/application date, and general appearance)
UES’ inspector(s) employed wet methods as applicable during bulk sample collection to reduce the potential for fiber release. Each sample was documented by labeling the container with a unique sample number, entering the sample material on a bulk sample log or chain-of-custody form, and noting the location of each sample on a floor plan. Throughout the sampling process, care was taken to prevent cross-contamination of the collected bulk samples. Sampling equipment was cleaned following the collection of each sample.
Random, and in some cases judgmental, samples of each homogeneous area of material were then collected. The physical condition of each material was assessed. In addition, a tactile inspection of the material was performed to evaluate friability. If the material, when dry, can be crumbled, pulverized, or reduced to powder by hand pressure, it is considered friable. Samples from any homogeneous area where the inspector determine that the material was non-ACM (such as thermal insulation that obviously fibrous glass, foam glass, or rubber) were not collected. Certification for the inspector performing the building survey is presented in Appendix C.
3.2 Suspected Asbestos-Containing Building Materials
Based on UES’ review of the available building system information and thorough visual survey of the subject buildings twenty-two (22) homogeneous materials were identified at the subject buildings commonly suspected of containing asbestos. Refer to Table 1 in section 5.0 Findings for a list of the homogeneous materials. A map illustrating the sample locations is included as Appendix A of this report.
4.0 LABORATORY ANALYSIS
4.1 Polarized Light Microscopy
The samples of the suspected ACMs collected during the field inspection were transported with chain-of-custody documentation to EMSL Analytical, Inc. located in Orlando, Florida. EMSL Analytical is an accredited laboratory for bulk sample analysis according to the National Voluntary Laboratory Accreditation Program (NVLAP) (Accreditation No. NVLAP 101151-0).
Bulk samples were analyzed for the presence of asbestos fibers using Polarized Light Microscopy (PLM).
The analyses were performed according to EPA Method 600/R-93/116 July 1993 “Method for the Determination of Asbestos in Bulk Building Materials.” This analytical method can be used for qualitative identification of six morphologically different types of asbestos fibers: chrysotile, amosite, crocidolite, tremolite, actinolite and anthophylite. PLM analysis requires the microscopist to take a portion of the sample and treat it with an oil of specific refractive index. The prepared slide is then subjected to a variety of tests while being viewed under varying polarizations of light. Each type of asbestos displays unique characteristics when subjected to these tests.
The method specifies that the asbestos content in a bulk sample shall be estimated and reported as a finite percentage within the range of 0 to 100. Minute quantities of asbestos in bulk samples may be reported as “trace” or less than one percent (<1%). The analytical method determines the asbestos percentage by means of visual estimation technique. If analysis of the sample of a suspect ACM reveals a negative result, UES considers the material to be non-asbestos-containing. If at any time during the analytical process a sample tests positive, that material must be treated as asbestos-containing.
4.2 Point Count Analysis
None of the samples of suspect ACMs collected during the field inspection were point counted as part of this survey.
5.0 FINDINGS
Twenty-two (22) suspect homogeneous materials were identified at the subject building. Following AHERA guidelines, the appropriate number of bulk samples were collected from the identified homogeneous material and submitted for laboratory analysis. The laboratory analyses indicated that asbestos fibers were not detected in excess of one percent in any of the homogeneous materials analyzed from the buildings. Table 1 presents the analytical results of the suspect asbestos containing materials (ACMs) and general information regarding the suspect ACMs.
TABLE 1
Sample Number HSA Material Material Location Condition
Asbestos Analytical
Results
NESHAPS
Category
Estimated Quantity
A-1, 2 A Stucco Brick Building 1, 1st Floor Exterior Walls Good None Detected N/A N/A
A-3, 4 B Stucco Yellow Building1, Exterior Walls Good None Detected N/A N/A
A-5, 6 C Concrete Slab Building 1, Slab Good None Detected N/A N/A
A-7, 8 D Drywall, Joint Compound, Tape
Building 1, Interior 1st Floor
Significantly Damaged None Detected N/A N/A
A-9, 10 E Linoleum Tile Building 1, Interior 1st Floor
Significantly Damaged None Detected N/A N/A
A-11, 12 F 12”x12” Tan Vinyl Floor Tile, Mastic Interior, 1st Floor Significantly
Damaged None Detected N/A N/A
A-13, 14 G Popcorn Ceiling Interior, 2nd Floor Ceiling
Significantly Damaged None Detected N/A N/A
A-16 H 12” x 12” Vinyl Floor Tile, Mastic Interior, Kitchen Damaged None Detected N/A N/A
A-17, 18 I Grey Rolled Roof, Black Mastic
Exterior Flatt Roof, Hotel Building
Significantly Damaged None Detected N/A N/A
A-19, 20 J Stucco Exterior, Hotel Building
Significantly Damaged None Detected N/A N/A
A-21, 22 K 1’ x 1’ White Ceiling Tile
Interior, Hotel Building North Unit
Damaged None Detected N/A N/A
A-23, 24 L 2’ x 4’ White Ceiling Tile
Interior, Hotel Building Hotel
Building North Unit
Significantly Damaged None Detected N/A N/A
A-25, 26 M Drywall, Joint Compound, Tape
Interior Walls, Hotel Building North Unit
Damaged None Detected N/A N/A
A-27, 28 N Drywall
Interior Cut Walls Above Ceiling, Hotel Building North Unit
Damaged None Detected N/A N/A
A-29, 30 O Drywall Texture Interior, Hotel
Building North Unit
Damaged None Detected N/A N/A
A-31, 32 P Stucco Brick Interior Hotel Building, Unit 102 Good None Detected N/A N/A
A-33, 34 Q Concrete Block Exterior Hotel Good None Detected N/A N/A
Sample Number HSA Material Material Location Condition
Asbestos Analytical
Results
NESHAPS
Category
Estimated Quantity
Morter Building Walls
A-35, 36 R Concrete Cut Brick Stucco
Hotel Building, 2nd Floor Exterior Walls Damaged None Detected N/A N/A
A-37, 38 S Multiple Layers of Shingles
Hotel Building, Roofing Damaged None Detected N/A N/A
A-39, 40 T Concrete Hotel Slab Good None Detected N/A N/A
A-41, 42 U Gray Mastic Exterior HVAC Hotel Building Ductwork Damaged None Detected N/A N/A
A-43, 44 V Black Pipe Insulation West Exterior Hotel
Building Cooler Lines
Significantly Damaged None Detected N/A N/A
Table Notes and Definitions:
HSA: Homogeneous Sampling Area (materials which are uniform in color, texture, construction/application date, and general appearance) NESHAPS = National Emission Standards for Hazardous Air Pollutants N/A = Not Applicable SF = Square Feet LF = Linear Feet EA = Each TBD = To Be Determined *Note* - The indicated material quantities are estimates based on UES’ field observations and should be considered preliminary in nature.
These estimates should not be used for bidding purposes without verification by the asbestos abatement contractor.
6.0 SUMMARY OF ASBESTOS-CONTAINING MATERIALS
Inspection of the subject buildings, located at 8820 and 8830 Highway 1 in Micco, Brevard County, Florida 32940, identified twenty-two (22) materials suspected of containing asbestos fibers. Bulk samples of each material were collected and submitted to an NVLAP accredited laboratory for analysis.
The results indicated that none of the suspect materials contained asbestos fibers in excess of one percent. The bulk sample laboratory report and associated chain-of-custody documentation are presented in Appendix C.
7.0 REGULATORY INFORMATION
There are federal and state statutes and regulations which govern the abatement and disposal of ACMs.
The renovation or demolition of buildings and roofs containing ACMs is regulated under the NESHAP statute. The NESHAP regulations require notification to the controlling agency and removal of all regulated asbestos containing materials (RACM) prior to renovation or demolition. RACM is defined as
(1) friable asbestos material, (2) Category I non-friable asbestos containing material that has become friable, (3) Category I non-friable asbestos containing material that will be or has been subjected to sanding, grinding, cutting or abrading, or (4) Category II non-friable asbestos containing material that has a high probability of becoming or has become crumbled, pulverized, or reduced to powder by the forces expected to act on the material in the course of demolition or renovation operations regulated by NESHAP. We strongly recommend that you contact the Controlling Agency prior to renovation or demolition regarding the proper disposition of the ACMs. It is important to note that even though an activity may be exempt from the EPA NESHAP regulations; such exemption does not extend to Occupational Safety and Health Administration (OSHA) standards or other state and federal statutes.
Renovation or demolition of this structure should be conducted in strict compliance with the aforementioned federal statutes and other applicable regulations, and good health and safety practices.
All procedures, methods and documentation should be accomplished by and be the responsibility of appropriately licensed professionals (asbestos consultants and contractors). Any material identified as non-friable ACM must be treated as friable ACM when the material is about to become friable as a result of activities performed within the building.
There are federal and state statutes and regulations which govern the abatement and disposal of ACMs.
The renovation or demolition of buildings and roofs containing ACMs is regulated under the NESHAP statute. The NESHAP regulations require notification to the controlling agency and removal of all regulated asbestos containing materials (RACM) prior to renovation or demolition. RACM is defined as (1) friable asbestos material, (2) Category I non-friable asbestos containing material that has become friable, (3) Category I on-friable asbestos containing material that will be or has been subjected to sanding, grinding, cutting or abrading, or (4) Category II non-friable asbestos containing material that has a high probability of becoming or has become crumbled, pulverized, or reduced to powder by the forces expected to act on the material in the course of demolition or renovation operations regulated by NESHAP. We strongly recommend that you contact the Controlling Agency prior to renovation or demolition regarding the proper disposition of the ACMs. It is important to note that even though an activity may be exempt from the EPA NESHAP regulations, such exemption does not extend to Occupational Safety and Health Administration (OSHA) standards or other state and federal statutes.
Renovation or demolition activities in buildings and on roofs that contain ACM or presumed asbestos containing material (PACM) are regulated under the OSHA Asbestos Construction Standard (29 CFR 1926.1101). The OSHA standard requires the building owner to inform their employees who will work in or adjacent to areas containing ACM or PACM, perspective employers applying or bidding for work whose employees reasonably can be expected to work in or adjacent to areas containing ACM or PACM, all employers of employees on multi-employer work sites who will be performing work with or adjacent to areas containing asbestos and tenants who will occupy areas containing ACM or PACM, of the presence, location, and quantity of ACM or PACM at the work sites in their building and facilities. Further, the OSHA standard (29 CFR 1926.1101) requires employers who discover ACM or PACM to convey information concerning the presence, location and quantity of such newly discovered ACM or PACM to others employers of employees working at the work site within 24 hours of discovery. While OSHA says the notification can be written or personal communication, there are many advantages to written communication.
The OSHA construction standard (29 CFR 1926.1101) also contains specific training, work practices, procedures, engineering controls, notifications, permissible exposure limits, personal protection, record keeping and a multitude of other requirements for the demolition, renovation, construction, alterations, repair, maintenance of structures, substrates or portions thereof that contain asbestos. It should be noted that recent court rulings have exempted roofing cement from the OSHA Construction Industry Asbestos Standard.
Renovation or demolition of the structures and roofs that could potentially disturbed the ACM located within the subject property should be conducted in strict compliance with the aforementioned federal statutes and other applicable regulations, and good health and safety practices. All procedures, methods and documentation should be accomplished by and be the responsibility of appropriately licensed professionals (asbestos consultants and contractors). Any material identified as non-friable ACM must be treated as friable ACM when the material is about to become friable as a result of activities performed within the building.
The U.S. Environmental Protection Agency (EPA) defines asbestos containing material (ACM) as any material which contains greater than one percent asbestos. When samples analyzed by Polarized Light Microscopy contain asbestos in amounts less than ten percent (< 10%), a more exact method of analysis called point counting may be performed at the client’s request. The EPA point count method allows a sample in which asbestos was visually detected, but which is visually estimated to have 10% or less asbestos, to be quantified using a point count procedure. If not point counted, a sample in which asbestos was visually detected and estimated (including trace to ≤1%) must be assumed to be greater than 1% and treated as an ACM. Per EPA’s regulations, materials which have been point-counted and, therefore, quantitatively determined to have less than or equal to one percent (≤1%) asbestos, can be treated as non-ACM.
8.0 CONTROLLING AGENCY
The Controlling Agency for the coordination of projects involving asbestos removal or demolition for Brevard County is the Florida Department of Environmental Protection (FDEP) Orange County Environmental Protection Division. The District Air Compliance Contact for asbestos is Mr. John Parker, who can be reached by phone at (407) 836-1400 or by email at John.Parker@ocfl.net.
The owner or operator shall provide the above-referenced department with a ten-day notice of the asbestos removal project or demolition by timely submittal of a completed "Notification of Asbestos Removal Project" form, as promulgated under Florida Administrative Code. The notification can be submitted on Florida’s Department of Environmental Protection’s Business Portal, located online at https://www.fldepportal.com/DepPortal/go/home.
9.0 CONDITIONS AND LIMITATIONS OF THIS SURVEY
A representative of UES obtained samples of building materials which were observed during an inspection of the building at the subject site that are typically suspected of containing asbestos as a constituent. The bulk samples were submitted to an NVLAP approved laboratory for analysis using EPA approved methods for industry-accepted standards. No other warranty is expressed or implied.
In general, non-destructive inspection and sampling procedures were incorporated which allowed assessment of reasonably accessible building materials. This survey did not include a significantly destructive search behind walls or below existing floors. Some materials may be hidden or masked by overlying materials such as flooring, carpeting or concealed walls. While a reasonable effort was made by UES to collect and analyze samples of suspect materials, some may remain unobserved by the inspector.
Any suspected building materials not addressed in this report, which are encountered during demolition or renovation should be analyzed for asbestos content prior to being damaged and/or removed. The building’s equipment fixtures or stored materials were not inspected or sampled as part of this evaluation.
Analysis of resinously bound materials by EPA Method 600/R-93/116 July 1993, may yield false-negative results because of method limitations in separating closely bound fibers and in detecting fibers of small length and diameter. Should you desire, other analytical methods including Transmission Electron Microscopy can be used to further evaluate these types of materials.
This survey report is not intended to be used as an asbestos abatement specification or work plan. The indicated material quantities of ACM (if documented) are estimates based on UES’ field observations on the date(s) of the inspection and should be considered preliminary in nature. All parties utilizing this report for proposal, estimation or contract negotiations are required to field verify the quantities of material prior to submission of proposal. These estimates should not be used for bidding purposes without verification by the asbestos abatement contractor. The asbestos abatement contractor should ascertain for themselves, by site measurements and inspection, the exact nature and extent of the work to be done.
APPENDIX A
ASBESTOS DEMOLITION SURVEY
8820 AAND 8830 HIGHWAY 1
MICCO, BREVARD COUNTY, FLORIDA 2158596
BMS 10/17/2025 BMS 10/17/2025
Not To Scale A25146.001691.000 1
DRAWN BY DATE CHECKED BY DATE
SCALE PROJECT NO. REPORT NO. FIGURE NO.
SAMPLE LOCATION PLAN
SOURCE: Brevard County Property Appraiser
WWW
ASBESTOS DEMOLITION SURVEY
8820 AAND 8830 HIGHWAY 1
MICCO, BREVARD COUNTY, FLORIDA 2158596
BMS 10/17/2025 BMS 10/17/2025
Not To Scale A25146.001691.000 1
DRAWN BY DATE CHECKED BY DATE
SCALE PROJECT NO. REPORT NO. FIGURE NO.
APPENDIX
OrderID: 342521211
APPENDIX
Rcertifies
Brandon Selph 820 Brevard Ave, Rockledge, Fl, 32907
Having passed a 25-question exam with a score of 70% or higher has successfully met training requirements for
Asbestos Refresher: Inspector Online FDBPR Asbestos Licensing Unit: Provider #0000995; Course #FL49-0006389 (½ Day; 3.40 Contact Hours)
Conducted
6/23/2025
Certificate #: 0091 - 004-41176 Exam Date: 6/23/2025 EPA accreditation expires: 6/23/2026 Principal Instructor: Brian Duchene, PE, LAC CEUs: 0.4 FBPR LAC: #0000995; Course ## 0006389 FBPE CEHs: #0004021; Course #0009083/Educational Institutions: 4 CEHs
File details come from the government source that posted it. Updated .