Attachment C Plans and Drawings to S-24800-00010840~1.pdf
PDF 2 MB Posted
- Attached to
- C-24-2001 - PANG Basewide Pavement Repair
- Solicitation number
- S-24800-00010840
- Issued by
- Multnomah County, Oregon
About this file
This document contains the project plans and drawings for the Basewide Pavement Repair project (Project No. FY24C) at the Portland Air National Guard Base in Oregon. The project scope includes crack sealing, milling and overlay, pavement patching and repair, concrete work, and pavement markings. The project is divided into priority levels, with the highest priority being crack sealing, followed by milling and overlay, patch and repair, concrete work, and pavement markings. The drawings provide detailed specifications for the work, including material requirements, application methods, and quality control measures.
The related state and local contract opportunity (C-24-2001 - PANG Basewide Pavement Repair) is being issued by the state of Oregon. The contract duration and any renewal options are not specified in the provided information. Pricing terms, set-asides, incumbent contractors, funding sources, and other financial details are also not included in the documents provided.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT NAME: BASEWIDE PAVEMENT REPAIR
PROJECT NO: FY24C Date: 06/04/2024 Drawing No:
Drawing Title:
BASEWIDE PAVEMENT REPAIR
Portland Air National Guard Base, Oregon
COVER
G‐01
SHEET INDEX
G‐01 COVER
G‐02 NOTES
D‐03 DRAWINGS – CRACK SEAL
D‐04 DRAWINGS – MILL AND OVERLAY
D‐05 DRAWINGS – PATCH AND REPAIR
D‐06 DRAWINGS – CONCRETE PAD
D‐07 DRAWINGS – PAVEMENT MARKINGS
*DRAWINGS TO BE READ IN CONJUNCTION WITH SCOPE OF WORK IN THE ITB.
Drawing Title:
GENERAL SITE NOTES:
1. CONTRACTOR TO THROUGHLY DRY AND CLEAN THE CRACKS
AND ANY AREA TO BE PATCHED OR REPAIR, WITH
COMPRESSED AIR (100CFM OR GREATER) TO REMOVE
OXIDEZED PAVEMENT, LOOSE AGGREGATE AND FOREIGN
DEBRIS.
2. ALL DEBRIS TO BE DISPOSED OFF BASE. WASTE TICKETS TO
BE SUBMITTED TO PANG ENVIRONMENTAL DEPARTMENT.
3. SEALANTS TO CONFORM WITH ASTMD6690, TYPE II OR ASTM
D6690, TYPE I. PREFERRED BRAND: COLJOINT 6690 TYPE I
AND II OR APPROVED EQUAL.
4. BACKER ROD MATERIAL- WHEN REQUIRED, USE BACKER ROD
MATERIAL IN ALL CRACKS THAT OTHERWISE WOULD
REQUIRE EXCESSIVE SEALANT. PLACE THE BACKER ROD SO
THAT THE TOP OF THE BACKER ROD IS AT LEAST 3/4 INCH
BELOW THE TOP OF THE PAVEMENT. ENSURE THAT THE
BACKER ROD MATERIAL IS PLACED AT THE SPECIFIED DEPTH
AND IS NOT STRETCHED OR TWISTED DURING INSTALLATION.
5. RATE OF PROGRESS OF CRACK PREPARATION - LIMIT THE
STAGES OF CRACK PREPARATION, WHICH INCLUDE AIR
PRESSURE CLEANING AND PLACING OF THE BACKER ROD
MATERIAL, TO ONLY THAT LINEAR FOOTAGE THAT CAN BE
SEALED DURING THE SAME DAY.
6. PREPARATION OF SEALANT- DO NOT HEAT HOT-POURED
SEALANTS IN EXCESS OF THE SAFE HEATING TEMPERATURE
RECOMMENDED BY THE MANUFACTURER, AS SHOWN ON THE
SEALANT CONTAINERS. WITHDRAW AND WASTE SEALANT
THAT HAS BEEN OVERHEATED OR SUBJECTED TO
APPLICATION TEMPERATURES FOR OVER 4 HOURS OR THAT
HAS REMAINED IN THE APPLICATOR AT THE END OF THE
DAY'S OPERATION.
7. SUBMIT MANUFACTURER'S INSTRUCTIONS 3 DAYS PRIOR TO
THE USE OF THE MATERIAL ON THE PROJECT. INSTALLATION
OF THE MATERIAL WILL NOT BE ALLOWED UNTIL THE
INSTRUCTIONS ARE RECEIVED.
8. TIME OF APPLICATION - SEAL CRACKS IMMEDIATELY
FOLLOWING FINAL CLEANING AND DRYING OF THE CRACK
WALLS AND FOLLOWING THE PLACEMENT OF THE BACKER
ROD MATERIAL (WHEN REQUIRED). PLACE SEALANT ONLY
WHEN CRACKS ARE DRY. RECLEAN CRACKS THAT CANNOT BE
SEALED UNDER THE CONDITIONS SPECIFIED, OR WHEN RAIN
INTERRUPTS SEALING OPERATIONS, AND ALLOW TO DRY OR
DRY BY MECHANICAL MEANS PRIOR TO INSTALLING THE
SEALANT
9. SEALING THE CRACK - IMMEDIATELY PRECEDING, BUT NOT
MORE THAN 50 FEET AHEAD OF THE CRACK SEALING
OPERATIONS, PERFORM A FINAL CLEANING AND DRYING WITH
COMPRESSED AIR. CRACKS SHOULD BE FILLED NO HIGHER
THAN 1/8 INCH ABOVE THE PAVEMENT. REMOVE EXCESS OR
SPILLED SEALANT FROM THE PAVEMENT BY APPROVED
METHODS AND DISCARD IT. INSTALL THE SEALANT IN A
MANNER WHICH PREVENTS THE FORMATION OF VOIDS AND
ENTRAPPED AIR. SEVERAL PASSES WITH THE APPLICATOR
WAND MAY BE NECESSARY TO OBTAIN THE SPECIFIED
SEALANT DEPTH FROM THE PAVEMENT SURFACE. DO NOT
USE GRAVITY METHODS OR POURING POTS TO INSTALL THE
SEALANT MATERIAL. DO NOT PERMIT TRAFFIC OVER NEWLY
SEALED PAVEMENT UNTIL THE SEALANT HAS CURED. CHECK
CRACKS FREQUENTLY TO ENSURE THAT THE NEWLY
INSTALLED SEALANT IS CURED TO A TACK-FREE CONDITION
WITHIN 3 HOURS.
10. CRACK SEALANT INSTALLATION - TEST SECTION PRIOR TO THE
CLEANING AND SEALING OF THE CRACKS FOR THE ENTIRE
PROJECT, CONSTRUCT A TEST SECTION AT LEAST 200 FEET
LONG USING THE SPECIFIED MATERIALS AND APPROVED
EQUIPMENT TO DEMONSTRATE THE PROPOSED SEALING OF
ALL CRACKS OF THE PROJECT. FOLLOWING THE COMPLETION
OF THE TEST SECTION AND BEFORE ANY OTHER CRACK IS
SEALED, INSPECT THE TEST SECTION TO DETERMINE THAT
THE MATERIALS AND INSTALLATION MEET THE
REQUIREMENTS SPECIFIED. IF MATERIALS OR INSTALLATION
DO NOT MEET REQUIREMENTS, REMOVE THE MATERIALS AND
RE-CLEAN AND RESEAL THE CRACKS AT NO COST TO THE
GOVERNMENT.
11. CLEANUP - DAILY, REMOVE UNUSED MATERIALS FROM THE
SITE AND LEAVE THE PAVEMENT IN A CLEAN CONDITION.
GENERAL PROJECT NOTES:
1. CONTRACTOR SHALL VERIFY EXISTING CONDITIONS AND
ADJUST WORK PLAN ACCORDINGLY, PRIOR TO
BEGINNING CONSTRUCTION.
2. WORK TO BE COMPLETED IN RESTRICTED AREA.
GOVERNEMTN ESCORT REQUIRED FOR THE DURATION
OF THE PROJECT.
3. PROJECT SCHEDULE (DAYS AND TIMES) MUST BE
APPROVED 72 HOURS PRIOR TO START OF WORK, TO
SCHEDULE GOVERNMENT ESCORT.
4. THE CONTRACTOR SHALL BE RESPONSIBLE FOR
COORDINATING WITH 142 SFS/RESOURCE PROTECTION
OFFICE FOR ACCESS TO PANG BASE (SEE ITB/CONTRACT
FOR DETAILS).
5. FOD TRAINING IS REQUIRED FOR ALL CONTRACTORS
WORKING PAST THE FLIGHTLINE. PANG WILL PROVIDE
FOD TRAINING.
6. CONTRACTOR TO PROVIDE SANITARY STATION.
7. CONTRACTOR TO PROVIDE WATER FOR PROJECT. NO
TRUCK OR EQUIPMENT WASHING IS APPROVED ON
BASE.
REFERENCES:
1. FFA ADVISORY CIRCLE DATED 10/10/2014 AC
NO:150/5380-6C
2. ASTMD6690
3. UFC 3-250-01
G‐02
Notes
Drawing Title:
SCOPE OVERVIEW
D‐03
Highest Priority
CRACK SEAL
PRIORITY LEVEL
Middle Priority
Lowest Priority
Airfield
Drawing Title:
SCOPE OVERVIEW
D‐04
Highest Priority
Middle Priority
MILL AND OVERLAY
PRIORITY LEVEL
Drawing Title:
SCOPE OVERVIEW
D‐05
Highest Priority
PATCH AND REPAIR
PRIORITY LEVEL
Middle Priority
Drawing Title:
SCOPE OVERVIEW
D‐06
Highest Priority
CONCRETE
PRIORITY LEVEL
Middle Priority
Drawing Title:
SCOPE OVERVIEW
D‐07
Highest Priority
PAVEMENT MARKINGS
PRIORITY LEVEL
Airfield NOTES:
1. Two boxes, for aircraft to park require markings. Markings will be determined on site.
2. Any existing pavement markings, that are disturbed by this project, shall be repaired under this scope.
File details come from the government source that posted it. Updated .