Attachment C - Past Performance Questionnaire.docx

DOCX document 35 KB Posted

Attached to
Intelligence Analysts Support Services Federal contract opportunity
Solicitation number
15F06725R0000245
Issued by
Department of Justice Federal Bureau of Investigation Redstone Arsenal Field Office

About this file

The document is a Past Performance Questionnaire used by the Federal Bureau of Investigation (FBI) to collect performance evaluation information from previous contractors. The form provides a comprehensive assessment framework for rating a contractor's performance across five key areas: Program Management, Technical Performance, Timeliness of Performance, Quality/Customer Satisfaction, and Cost Control. Each area can be rated on a scale from Exceptional (E) to Unsatisfactory (U), with specific evaluation criteria provided for each rating category.

The questionnaire is part of a larger solicitation (Solicitation Number: 15F06725R0000245) for Intelligence Analysts Support Services, which seeks to award a single firm-fixed price contract for intelligence analyst services. The contract has a 12-month base period with four option years and a potential 6-month extension. The procurement is classified under NAICS code 541611 for Administrative Management and General Management Consulting Services, with a size standard of $24,500,000. The FBI Procurement Section is conducting the solicitation in accordance with FAR part 15, with vendors required to submit proposals that clearly demonstrate their capabilities for providing intelligence analyst support services.

View the file

Other files for this federal contract opportunity

Other files attached to Intelligence Analysts Support Services, newest first.
File Type Posted
P00001_Attachment D -Pricing Template.xlsx XLSX spreadsheet
P00003_SF30_RFP15F06725R0000245_Amendment 03.pdf PDF
P00003_Intel Analysts 15F06725R0000245 - Instructions to Offerors.pdf PDF
RFP15F06725R0000245 P00002.pdf PDF
Updated_Attachment F - Resume Template.docx DOCX document
Attachment J - WD 2015-4603 V2.pdf PDF
Attachment K - SF30_RFP15F06725R0000245_Amendment P00001.pdf PDF
Updated_Attachment C - Past Performance Questionnaire.docx DOCX document
Updated_Intel Analysts 15F06725R0000245 - Instructions to Offerors.pdf PDF
Copy of Attachment I - Questions and Answers_Government Response.pdf PDF
Updated_Attachment D -Pricing Template.xlsx XLSX spreadsheet
Updated_Attachment A - Statement of Work_Intelligence Analyst Support.pdf PDF
Updated - 5.14.2025 Intel Analysts 15F06725R0000245 - Instructions to Offerors.pdf PDF
Attachment A - Statement of Work_Intelligence Analyst Support.pdf PDF
Attachment H - Acquisition Risk Questions and KMPL.docx DOCX document
Attachment F - Resume Template.docx DOCX document
Intel Analysts 15F06725R0000245 - Instructions to Offerors.pdf PDF
Attachment D -Pricing Template.xlsx XLSX spreadsheet
Attachment G - SF1449_RFP15F06725R0000245.pdf PDF
Attachment E - Solicitation - Quoter Question and Answer.xlsx XLSX spreadsheet
Attachment B - Past Performance Information Sheet.docx DOCX document
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Past Performance Questionnaire Background This questionnaire will be used to provide information to support the Federal Bureau of Investigation (FBI) Procurement Team.

Message to the Assessor Your feedback is requested by the FBI to assist with establishing the performance history for the Contractor identified below. To expedite receipt of the requested information, the FBI requests that you e-mail the completed questionnaire(s) as a PDF to: swalker4@fbi.gov and mjfinamore@fbi.gov. Your support and participation in this matter is essential and greatly appreciated!

Instructions for Offeror and Assessor

· Sections I and II to be completed by the Quoter and provided to the Assessor (the Government / Commercial personnel that had experience with the Quoter on a previous relevant contract/project). The Assessor shall in turn, verify Sections I and II, complete the questionnaire, and submit to the Contracting Officer and Contract Specialist at the emails listed above.

· If any information in Section II is incorrect, please annotate and provide the correct information accordingly.

· Sections III through VI to be completed in their entirety by the assessor.

I. Customer Identification Customer or Agency Name

Customer or Agency Description

Geographic Description of Services Under This Contract (i.e., single location, multiple locations, CONUS (in U.S.), or OCONUS (Outside U.S.)

II. Current or Historical Contract Identification Contractor Name/Address

Contract Number:

Email:

Contract Type:

Initial Period of Performance:

Current/Final Period of Performance:

Initial Contract Value (base only):

Current/final Contract Value (base and exercised options only):

Reason if Initial Contract Value and Current/final Contract Value above are different.

Brief description of services provided

Contractor Role (Prime or Subcontractor)

ASSESSOR

The information submitted by the company above is: CORRECT ☐ OR INCORRECT ☐

III. Assessor Information Assessor Name

Title

Phone Number/Email Address

Role (examples: PM/PCO/ACO/Contract Specialist/COR/Quality Assurance Specialist, etc.)

Assessor’s number of years working on contract

IV. Assessment Definitions The following definitions should be used in your assessment of the Contractor performance.

RATING
RATING DEFINITION
EXCEPTIONAL (E)
Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
VERY GOOD (VG)
Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
SATISFACTORY (S)
Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
MARGINAL (M)
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being evaluated reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.
UNSATISFACTORY (U)
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
NOT APPLICABLE (N)
No information or did not apply to your contract. Unable to provide assessment.

V. Performance Evaluation

Program Management
E
VG
S
M
U
N

OVERALL PROGRAM MANAGEMENT

(Example: Was the Contractor effective in integrating and coordinating all activities required to execute the contract? Did the Contractor appropriately assign responsibilities to its workforce?)

MANAGEMENT RESPONSIVENESS

(Example: Did Contractor management provide timely, complete, and quality problem identification? Did Contractor management provide effective business relations?)

MANAGEMENT OF PERSONNEL

(Example: Did the Contractor show an ability to select, retain, support, and replace personnel with the experience and expertise necessary to accomplish the Government’s requirement within schedule and budget?)

Technical Performance
E
VG
S
M
U
N

QUALITY OF TECHNICAL APPROACH

(Example: Were the provided services comprehensive, complete, and feasible? Did the provided services meet requirements and accommodate changing requirements?)

UNDERSTANDING OF REQUIREMENTS

(Example: Did the Contractor show an understanding of the scope of the requirements and an appreciation of the complexity of the requirements? If applicable, did the Contractor effectively identify flaws, inconsistencies, and other inaccuracies in technical direction?)

Timeliness of Performance
E
VG
S
M
U
N

TIMELINESS OF PERFORMANCE

(Example: Was the Contractor successful in planning and proposing realistic schedules, monitoring performance, completing work on time, and implementing corrections / changes in a timely manner?)

Quality / Customer Satisfaction
E
VG
S
M
U
N

QUALITY OF PERFORMANCE / CUSTOMER SATISFACTION

BUSINESS BEHAVIOR

(Example: Was the Contractor reasonable and cooperative at the corporate and program levels in response to changes in technical direction?)

COMMUNICATION

(Example: Did the Contractor work and communicate well with Contracting Officer, Contracting Officer’s Representative, other contractors, subcontractors, and Government staff?)

Cost Control
E
VG
S
M
U
N

COST CONTROL

(Example: Was the Contractor successful in planning and proposing realistic costs, monitoring performance, operating at or below budget, and implementing corrections / changes in a cost - effective manner?)

Overall Rating
E
VG
S
M
U
N

Overall rating of Contractor’s Performance on contract being assessed.

VI. General Comments

Assessor’s Signature Date