Attachment C_FRC East Contract Installation Requirements Updated 122023.pdf

PDF 206 KB Posted

Attached to
Immersion Tank Replacement at FRCE
Solicitation number
N68520-26-SIMACQ-JC00000-0172
Issued by

About this file

This document is an attachment to a federal contract solicitation that specifies FRC East contract installation requirements for Industrial Plant Equipment (IPE) at Fleet Readiness Center East, a U.S. Navy facility located at Marine Corps Air Station Cherry Point, North Carolina.

The requirements are organized into general installation requirements (Section 3.1) applicable to all contracts and conditional requirements (Section 3.2) applicable only when specified in the contract. General requirements include compliance with FRC East instructions covering environmental compliance, occupational safety and health, emergency response, security, parking, contractor check-in/checkout, tool control, electrical arc flash protocols, weight handling equipment, dress code, and tobacco use policies. Contractors must comply with OSHA standards, Navy safety manuals, and Army Corps of Engineers safety requirements while onsite. Specific technical requirements address tool control procedures (including mandatory check-in at the Central Tool Room), hazardous materials handling with Safety Data Sheets submission, contractor-owned crane operations (requiring Certificate of Compliance and critical lift plans submitted 15 days prior), system shutdowns (requiring 30-day advance written notice), facility design and installation standards using DoD UFC criteria and 2015 IBC, installation plan development with monthly reviews, electrical connections by licensed North Carolina electrical contractors conforming to NFPA standards, and telecommunications coordination with facility IT personnel. Conditional requirements include lead and asbestos testing by North Carolina accredited inspectors, compressed air system connections with specific filtration and dryness standards, existing equipment removal procedures with proper lockout/tagout protocols, machine foundation work with Ground Penetrating Radar scans, and comprehensive environmental controls for work within Operable Unit 1 (OU-1), including geotechnical boring approvals, soil testing and disposal procedures, vapor intrusion mitigation, off-site soil authorization, and contaminated groundwater management requiring treatment to 70 parts per trillion PFAS/PFOA levels before discharge.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment C 20 December 2023

FRC EAST CONTRACT INSTALLATION REQUIREMENTS

1. SCOPE. This document specifies FRC East requirements for contract installations of

Industrial Plant Equipment (IPE). Inspection for conformity is required for acceptance.

2. REFERENCES. The documents listed in this section are cited in section 3. While every effort has been made to ensure the completeness of this list, document users are cautioned that they must meet all specified requirements of documents cited in sections 3, whether or not they are listed here. All documents below shall be the current revision unless otherwise listed.

2.1. FLEET READINESS CENTER EAST INSTRUCTION (FRCEASTINST)

FRCEASTINST 5090.1 – Environmental Compliance Manual

FRCEASTINST 5100.2 – Occupational Safety and Health Manual

FRCEASTINST 5102.2 – Unified Emergency Response Plan

FRCEASTINST 5500.1 – Security Manual

FRCEASTINST 5560.1 – Parking Policy

FRCEASTINST 7561.1 – Contractor Check-In and Checkout Process

FRCEASTINST 10290.1 – Tool Control Program

FRCEASTINST 10380.1 – Electrical Arc Flash Program

FRCEASTINST 11450.1 – Weight Handling Equipment Management Program.

FRCEASTINST 12000.5 – Proper Wearing Apparel for Persons Entering Fleet Readiness Center East

FRCEASTINST 12600.1 – Policy Concerning Breaks and Tobacco Use

2.2. AMERICAN CONCRETE INSTITUTE (ACI)

ACI 301: Specifications for Structural Concrete

ACI 304R: Guide for Measuring, Mixing, Transporting, and Placing Concrete

ACI 305R: Guide to Hot Weather Concreting

ACI 306R: Guide to Cold Weather Concreting

2.3. UNIFIED FACILITIES CRITERIA (UFC)

UFC 1-200-01: Design: General Building Requirements

2.4. TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)

TIA-232-F: Interface between Data Terminal Equipment and Data Circuit-Terminating Equipment Employing Serial Binary Data Interchange

TIA-568.1-E: Commercial Building Telecommunications Infrastructure Standard

TIA-569-E: Telecommunications Pathways and Spaces

2.5. AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)

ASME A13.1 - Scheme for the Identification of Piping Systems

2.6. NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70: National Electrical Code

NFPA 70E: Standard for Electrical Safety in the Workplace

2.7. US NAVY

OPNAV 5100.23G w/change 1: Navy Safety and Occupational Health Program Manual

2.8. OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA)

29 CFR 1910: General Industry, OSHA Safety and Health Standards

2.9. US ARMY CORPS OF ENGINEERS (USACE)

COE EM 385-1-1: Safety and Health Requirements Manual

3. REQUIREMENTS.

3.1. General Installation Requirements. Contractor shall be responsible for compliance with all requirements in section 3.1.

3.1.1. General.

3.1.1.1. Contractor shall be responsible for compliance with all FRC East

Instructions listed in Section 2.1 (Copies can be obtained from the Project Manager).

3.1.1.2. While onsite at FRC East, the Contractor must comply with the US Army Corps of Engineers Safety and Health Requirements Manual, EM-385-1-1.

3.1.1.3. All Government provided drawings shall not be scaled for installation purposes. In the event of omission of necessary dimensions, the Contractor shall notify the FRC East Project Manager (PM).

3.1.1.4. The Contractor shall secure and pay for all permits, fees, and licenses required for proper execution of all installation work.

3.1.1.5. The contractor shall be responsible for and be required to pay incurred expenses resulting from damages to work or materials in place on the premises, or included in the contract, during the execution of the contract.

3.1.1.6. The Contractor shall verify with the manufacturer/supplier the size, location and characteristics of all work and equipment that is to be furnished by the Government or other Contractors prior to installation work pertaining to the same has begun.

3.1.1.7. No equipment loads shall be added to a building roof without prior approval from the FRC East Facility and Plant Planning (F&PP) Division.

3.1.1.8. The Contractor shall not transport loads across any mezzanine or building roof without prior approval of a contractor supplied rigging plan by contacting the FRC East PM.

3.1.1.9. Contractors are prohibited from using Government equipment to accomplish installation work and are prohibited from operating Navy owned Category 1 and Category 2 cranes.

3.1.1.10. Installed equipment shall not inhibit the travel of any material handling bridge crane system or jib crane over the entire footprint of the crane travel.

3.1.2. Tool Control Program (TCP).

3.1.2.1. Contractors shall comply with tool control requirements per

FRCEASTINST 10290.1R.

3.1.2.2. Commercial contractors providing facilities maintenance support or touch labor on products within FRC East shall abide by all TCP policies and procedures, as well as the terms and conditions of their contract.

3.1.2.3. All other commercial contractors and/or vendors shall abide by all TCP policies and procedures. In addition, they will check in with the Central Tool Room (CTR) (Shop 32310, Building 137) upon arrival and check out with the CTR before they leave FRC East, if they bring tools with them.

3.1.2.4. The CTR will inventory the tools brought into FRC East during the check in so they can compare when the tools are being removed during check out to ensure nothing is left behind. The CTR will also provide TCP guidance before any work begins.

3.1.2.5. All contractors shall ensure constant control of their tools and materials throughout their stay at FRC East.

3.1.2.6. Upon entry and exit into a shop area, contractors will notify the affected shop supervisor.

3.1.2.7. Any tools left unattended shall be confiscated and turned into the TCP Manager and will be reported to the appropriate contracting officer, if applicable.

3.1.2.8. The FRC East Project Manager will be responsible for briefing and supplying a copy of this chapter to contractor personnel designated to work within FRC East.

3.1.2.9. Procedures for commercial contractors and vendors does not apply for FRC East detachments (New River and Beaufort). The FRC East is not responsible for providing Squadrons or contractors hazardous material, safety gear (PPE), consumable material, or expendable tooling such as drill bits and reamers. These items will not be loaned or given to anyone, other than FRC East employees, by TPAs unless otherwise instructed to do so by their immediate supervisor, branch head or division director.

3.1.3. Hazardous Materials.

3.1.3.1. Contractors shall comply with FRCEASTINST 5090.1 Chapter 31, before introducing or removing any hazardous materials from the FRC East.

3.1.3.2. The contractor shall submit all Safety Data Sheets (SDS) to the FRC East PM prior to bringing any hazardous materials on site at the FRC East.

3.1.3.3. All hazardous materials shall be properly stored in original manufacturer’s containers that ensure the proper control, safe transportation and storage of product contents. If the material must be transferred into a secondary container, the secondary container must be properly labeled. Label information can be requested of the Environmental Division via the Project Manager.

3.1.3.4. All containers shall be labeled with information revealing the exact contents, hazards, and manufacture name and phone number.

3.1.4. Contractor Owned Crane. Contractors requiring the use of a crane to accomplish equipment installation work shall notify the FRC East PM After Contract Award (ACA) and comply with the following:

a. The Contractor shall submit a completed Certificate of Compliance, critical lift plan, and proof of crane operator license to the FRC East Weight Handling Certifying Official or Chief Crane Engineer at least fifteen (15) days prior to scheduled lift.

b. The Contractor shall perform a Ground Penetrating Radar (GPR) scan to locate buried utilities including, but not limited to, water, storm, sewage, communication, electrical lines…etc. The area and buried utilities shall be marked to properly position the crane.

c. The FRC East will provide a lift supervisor from the Weight Handling Equipment

(WHE) group to be onsite and supervise all lifts. The crane may travel to the work site and be erected, but no lifting operations shall occur until the designated WHE group lift supervisor is onsite. The crane shall have a flag attached to the highest aspect of the boom.

3.1.5. System Shutdowns.

3.1.5.1. The contractor must request in writing 30 calendar days in advance, of the need to have the Government shutdown and/or drain existing facility systems (i.e. electrical, water, sewer, chilled water, fire suppression, etc.) associated with the equipment installation. The request shall include the duration and number of day for the system to be shut down.

3.1.5.2. The contractor shall coordinate these shutdowns with the FRC East. The

FRC East and the contractor must mutually agree upon shutdown dates, times and duration.

3.1.5.3. No government utility systems may be shut down or drained without FRC East approval/concurrence. The FRC East Project Manager will provide final approval/concurrence.

3.1.5.4. The contractor must follow the standard practice of Lockout/Tagout procedures as identified in OSHA 29 CFR 1910.147, OSHA 29 CFR 1910.332, and FRCEASTINST 10380.1.

3.1.6. Facility Design and Installation.

3.1.6.1. To install new equipment within FRC East, the contractor must use the

Department of Defense (DoD) United Facilities Criteria (UFC) system for planning, design, construction, operation and maintenance, sustainment, restoration, and modernization as prescribed by MIL-STD 3007. The MIL- STD 3007 applies to all Military Departments, Defense Agencies, and DoD field Activities. Use the 2015 International Building Code (IBC) as modified by UFC 1-200-01 for all facility connections and modifications to existing building systems. Understand how to use the “Whole Building Design Guide”, located at the public website www.wbdg.org/ffc/dod, to install new equipment or relocate existing equipment within any Department of Defense (DoD) facility.

3.1.6.2. Prior to performing any work associated with new equipment utility connections, the contractor shall lockout/tagout the utility sources in accordance with Paragraph 3.1.5.4.

3.1.6.3. Pipe Labeling. All newly installed pipe shall be labeled per ASME A13.1 guidelines. Color scheme for “Any water except for water used in fire suppression systems” is white letters on green background. Labels shall be Dura Label Premium Vinyl Tape, or equivalent, with prior approval by the FRC East Hazardous Materials Program Manager. All newly installed insulated piping systems shall be labeled “ASBESTOS FREE” with white lettering on blue field.

3.1.7. Installation Plan.

3.1.7.1. The FRC East F&PP Division and the Contractor shall review the plan on a monthly basis.

3.1.7.2. The Contractor shall notify the FRC East F&PP Division prior to making any changes to the Installation Plan.

3.1.7.3. All changes to the Installation Plan shall be approved in advance by the FRC East F&PP Division.

3.1.7.4. The contractor shall field verify all dimensions and site conditions while developing the Installation Plan.

3.1.7.5. The contractor and all personnel working under this contract shall always utilize the most recent FRC East F&PP Division approved Installation Plan for execution of installation work.

3.1.7.6. The Installation Plan shall include, but not be limited to, the following:

3.1.7.6.1. Detailed description of existing equipment disassembly and removal, existing foundation removal, and existing utilities removal as required

3.1.7.6.2. Detailed description of foundation work, including foundation drawings certified by a licensed Professional Engineer (P.E.) as required.

http://www.wbdg.org/ffc/dod

3.1.7.6.3. A detailed site layout including position and orientation of new machine with any ancillary equipment, additional equipment, and maintenance access clearances

3.1.7.6.4. General equipment specifications (i.e. size, weight, etc.)

3.1.7.6.5. Facilities preparation instructions, including detailed information concerning any equipment that applies a load to a facility structure, wall, or roof as required

3.1.7.6.6. Structural modifications or additions as required

3.1.7.6.7. Utility requirements and locations

3.1.7.6.8. Pertinent electrical details per Paragraph 3.1.8.

3.1.7.6.9. Pertinent compressed air details, as required, per Paragraph 3.2.2.

3.1.8. Work Plan. Required for any project involving geotechnical investigations (soil borings), interior concrete penetrations or foundation work. Work Plan must be reviewed and approved by MCAS Environmental Affairs Department (EAD) prior to commencing any activities. Allow a minimum of 30 days to review the work plan, respond to and incorporate comments, and review the revised Work Plan. For more details on the Work Plan, see Appendix A at end of this attachment.

3.1.9. Electrical Connection.

3.1.9.1. Electrical connections made to the facility electrical system shall be completed by a contractor holding a current electrical contractor’s license issued by the North Carolina Board of Examiners of Electrical Contractors in accordance with the provisions and requirements of Chapter 87, Article 4 of The General Statutes of North Carolina. Contractor shall provide proof of current electrical contractor’s license within 30 days ACA.

3.1.9.2. Electrical connections shall conform to NFPA 70 and be performed in accordance with NFPA 70E and UFC 1-200-01.

3.1.9.3. Electrical connections shall not inhibit the travel of any material handling bridge crane system or jib crane over the entire footprint of the crane travel.

3.1.9.4. Electrical connections shall not cause a tripping hazard or interfere with foot traffic, maintenance access, or pathways (recommend 8 feet above finished floor when possible).

3.1.9.5. The contractor shall be responsible for providing the correct size and type of power source enclosure, with the appropriate circuit breaker, for over-current protection of machine and ancillary equipment. The circuit breaker shall match kAIC rating of source.

3.1.9.6. Connection boxes, outlet boxes, junction boxes, and similar devices and fixtures exposed to the weather, condensation, or excessive dampness shall comply with NEMA ICS 6.

3.1.9.7. Enclosures, in interior locations, exposed to dripping liquids or falling objects shall meet NEMA 250 Type 2 as a minimum.

3.1.9.8. Enclosures, in interior locations, exposed to water spray, mist or splashing water shall meet NEMA 250 Type 4X as a minimum.

3.1.9.9. Watertight distribution panel cabinets shall be cast or welded construction with external mounting lugs and externally operable switches.

3.1.9.10. Any penetration into an enclosure shall not affect the degree of protection of the enclosure.

3.1.9.11. Ferrous components of equipment subject to corrosion shall be galvanized or similarly treated before painting.

3.1.9.12. Painting is an acceptable corrosion resistant treatment for switchboard panels, distribution cabinets, and similar enclosures.

3.1.9.13. The contractor shall provide a three (3) inches × five (5) inches (W × L) engraved identification placard for new power source enclosure, fusible safety disconnect switch, and motor controller with the following information:

equipment name, volt, amp, hertz, and power source feed. The placard shall be black lettering on a white background and attached to the center of the motor controller, main disconnect and all disconnect covers. The placard shall provide all power feed information if the motor controller has multiple power sources (120VAC, 208VAC, and 480VAC etc.).

3.1.9.14. The contractor shall provide an ampere-rating label for new busway plug-in unit. The ampere-rating label shall be 7/8-inch × two and one quarter (2-1/4) inches (W × H) size, black letter with yellow background color, vinyl film or similar material type as other existing enclosure labels.

3.2. As Required by Contract. Compliance with requirements in section 3.2 shall only be required when specified in the contract.

3.2.1. Lead and Asbestos Testing. The FRC East has a known presence of Asbestos- Containing Materials (ACM) and Lead-Based Paints (LBP).

3.2.1.1. Contractor shall ensure an onsite survey for Lead and Asbestos is performed by a North Carolina Accredited Asbestos Inspector to identify any suspected material that appears to be involved in the project.

3.2.1.2. Assume the presence of asbestos and lead paint is a possibility and be prepared to do some sampling and analysis.

3.2.1.3. Provide a North Carolina Accredited Asbestos Inspector signed report certifying the inspection. The report should:

3.2.1.3.1. State the findings of the inspection;

3.2.1.3.2. State if the area appears to be asbestos free;

3.2.1.3.3. Present the results of the sampling and analysis;

3.2.1.3.4. Must be certified by the Asbestos Inspector and include the Inspector's certification number; and

3.2.1.3.5. Show locations of any samples taken, as well as on the Installation Plan.

3.2.1.4. If either of these two substances are found in areas that will be disturbed by the installation, and will pose a health and safety threat, the contractor must notify the contracting officer for direction to either abate those areas or to avoid the areas. The contractor will not be required, in this contract, to abate the areas.

3.2.2. Compressed Air Connection. SCFM is CFM at standard conditions. The standard conditions of air are defined as 60 degrees Fahrenheit, 14.7 PSIA and relative humidity of zero. The piping installation shall meet or exceed the current Department of Defense construction criteria as defined in UFC 1-200-01.

3.2.2.1. Contractor shall provide color code marking of piping/tubing conforming to ASME A13.1. Contractor shall provide pipe flow markings, warning and identification tape, and metal tags as required.

3.2.2.2. All new piping:

3.2.2.2.1. Shall be installed parallel and perpendicular to the building structure;

3.2.2.2.2. New piping installation shall not block or restrict any existing or new equipment operation or maintenance access;

3.2.2.2.3. Shall not inhibit the travel of any material handling bridge crane system or jib crane over the entire footprint of the crane travel; and

3.2.2.2.4. Shall not cause a tripping hazard or interfere with foot traffic, maintenance access, or pathways (recommend 8 feet above finished floor when possible).

3.2.2.3. Contractor shall:

3.2.2.3.1. Provide all compressed air requirements, materials, equipment, engineering details, calculations, and drawings with the Installation Plan submittal;

3.2.2.3.2. Provide all details to install the compressed air piping, which shall include pipe size, piping material, weights, dimensions, calculations, etc.;

3.2.2.3.3. Provide detailed information as to the offered equipment’s required compressed air SCFM (Volumetric Flow Rate at standard conditions), pressure (psi), cleanliness (i.e. state in writing the required filtration level) and dryness (i.e. state in writing the required dew point in degrees Fahrenheit);

3.2.2.3.4. Design the proper stages in filtration to minimize pressure drop across all filters. All filtration used shall be monitored by a differential pressure gauge with color indicators;

3.2.2.3.5. Provide a single point connection to the new equipment with a lockable shutoff valve;

3.2.2.3.6. Install adequate course and fine filtration for particle removal;

3.2.2.3.7. Install adequate filters and separators to remove oil vapor and fine aerosols, as required;

3.2.2.3.8. Install an air dryer if the existing compressed air is not dry enough

(i.e. if the dew point of the compressed air needs to be lowered);

3.2.2.3.9. Install adequate filters, separators to remove moisture, water particulates, water, and water vapor, as required; and.

3.2.2.3.10. Design and protect the new equipment from any wet saturated compressed air conditions due to an occasional catastrophic compressed air dryer failure in the currently supplied compressed air.

3.2.3. Existing Equipment and Utilities Removal.

3.2.3.1. The Contractor shall notify the FRC East Project Manager at least 10 business days prior to removing any equipment. No equipment should be removed from service or the site until approval received from FRC East Project Manager.

3.2.3.2. Prior to removal of any equipment, the contractor shall lockout/tagout all energy sources in accordance with OSHA 29 CFR 1910.147 and FRCEASTINST 10380.1. The FRC East may choose to dual lockout/tagout the equipment.

3.2.3.3. The Contractor shall be responsible for disposal of all removed materials in accordance with all local, state and federal laws and regulations.

3.2.3.3.1. Any metals intended for recycling, including pipe, conduit, electrical wiring and/or ductwork, shall be routed to the FRC East Recycle Center, Building 4785, via the FRC East Project Manager.

3.2.3.3.2. The Contractor shall provide waste collection containers (i.e.

hoppers, drums, roll-off container, etc.) for the accumulation of all debris generated as a result of the project. All debris/waste shall be removed each day prior to concluding work or at an agreed upon interval, especially for larger containers (such as a roll-off).

3.2.3.4. All equipment removed from FRC East buildings for transport shall be double wrapped in a minimum of 4mil thick industrial grade plastic. The industrial grade plastic shall be properly secured to the machine to prevent loosening or falling off during transport. Any gaps in the industrial grade plastic shall be eliminated to prevent potential FOD on the roadways. If FOD is deposited on the roadway, all work shall cease and the FOD shall be cleaned up and contained before any work continues.

3.2.3.5. All equipment having the requirement for decontamination prior to disposition (identified during pre-planning meeting, or sooner) must be coordinated in advance (48-72 hours minimum) between the Contractor, via the FRC East PM, and FRC East Environmental Operations Branch. The equipment shall be delivered to Shelter 4466 (Decontamination Berm) at the pre-approved time/date. The equipment shall not be left unattended outside of Shelter 4466. At the completion of the decontamination process, FRC East Environmental will coordinate pickup by the Contractor via the FRC East PM.

3.2.4. Machine Foundation.

3.2.4.1. The Contractor shall perform a Ground Penetrating Radar (GPR) scan of the existing foundation to locate any buried utilities prior to development of the Installation Plan, Section 3.1.7.

3.2.4.1.1. The results of the GPR scan shall be provided to the FRC East

3.2.4.1.2. When GPR scan reveals a previously unknown condition, the Contractor shall provide a proposal to the Government for review.

3.2.4.2. The Contractor shall perform all demolition, excavation, removal and disposal of demolished and excavated material and foundation fill, as required.

See Appendix A (at the end of this attachment) for more details on Requirements for working within Operable Unit 1 (OU-1).

3.2.4.3. To comply with EM 385-1-1, section 06.N.01, wet cutting and HEPA vacuums shall be the engineering controls used to control silica dust generation. Any slurry generated as a result of wet cutting shall not be disposed via any FRC East drainage system (sanitary, industrial waste, or storm sewer).

3.2.4.4. All concrete used shall conform to the American Concrete Institute guidelines ACI 301, ACI 304R, ACI 305R, and ACI 306R.

3.2.5. Telecommunications Connection. The Contractor shall be responsible for assisting the FRCE IT group with the final connection and completion of active communication signals of equipment along with any required stand-alone computers to the Government facility Distributed Numerical Control (DNC) system. All Cat 6 cable connections and Four (4) active RJ45 ports will be provided and installed by FRCE IT technicians.

Appendix A - Requirements for Working within Operable Unit 1 (OU-1)

1. Background. Due to historical contamination, Marine Corps Air Station Cherry Point

(MCAS CP) is registered on the National Priorities List (NPL) which is the Environmental Protection Agency (EPA) official register of facilities that are subject to federal regulatory cleanup standards. MCAS CP has an officially signed Record of Decision (ROD) detailing remediation strategies at sites referred to as Operable Units (OUs) that include Land Use Controls (LUCs) for each site. FRC East is within Operable Unit 1 (OU-1) where a significant portion of the industrial buildings are subject to LUC’s. In addition to LUCs for vapor intrusion and groundwater impacts, excavation of soil and geotechnical soil boring have specific requirements for management, handling and disposal. The following sections will break down the requirements for each and must be followed as they apply to the project. Applicability of each requirement should be determined at the earliest stage of the project between the Contractor and FRC East

a. LUCs for OU-1 include:

i. Prohibition of all uses of groundwater and construction activities with the potential to result in worker exposure to groundwater from the surficial aquifer within the LUC boundaries unless written approval is obtained from US EPA and North Carolina Department of Environmental Quality

(NC DEQ);

ii. Prohibition of all intrusive activities below the water table unless prior written approval obtained from US EPA and NC DEQ;

iii. Evaluation of the potential for vapor intrusion impacts from new building construction, major physical modifications or changes in occupancy/use of existing structures prior to their implementation; and,

iv. Maintaining the integrity of any existing or future monitoring or remediation system at the site.

2. Geotechnical Borings. Depending on the depth of the boring, many borings may extend deep into the shallow aquifer (i.e. Surficial) allowing contaminants to vertically migrate into the aquifer. In many cases, a boring can penetrate an aquifer ‘confining unit’ (or dense clay layer) that separates two hydraulically distinct aquifers thereby enabling contaminated groundwater from one aquifer to migrate into another deeper aquifer and cross-contaminate underlying aquifers.

a. The Project Manager shall notify EAD early into the project of the requirement to install geotechnical borings.

b. The Contractor shall obtain the services of a Geotechnical contractor, who will then provide a work plan to EAD, via the Project Manager, detailing how the borings are to be installed and sealed.

c. The work plan shall include a figure showing the location of each borings, the boring nomenclature, depth & diameter of each boring, how each boring is to be installed and sealed, and how drill cuttings and water are to be managed in accordance with “Environmental Guidance – Geotechnical Soil Boring Activities dtd April 2022”.

i. For more detailed information about requirements of the Work Plan, boring installation, sealing, acceptable grouts, and management of both drill cuttings and groundwater, the Contractor shall request a copy of the MCAS Cherry Point guidance document via the Project Manager.

d. The work plan will be must be reviewed and approved prior to commencing drilling activities.

e. The regulatory approval process can be time consuming (60-90 days) and EAD must obtain written approval from NC DEQ and EPA before geotechnical soil boring activities can be conducted within a LUC boundary.

3. Soil Handing

a. Stockpiling

i. Any excavated soil shall be stockpiled on plastic, bermed, and covered in accordance with NC DEQ Ground water Guidelines and Resource Conservation and Recovery Act (RCRA), or placed in a plastic lined roll-off container and covered with plastic.

ii. All excavated soil may be re-utilized as backfill at the same location from which it was removed unless petroleum contamination is discovered. If any soil encountered during excavation exhibits an abnormal/unnatural color, chemical/petroleum odor, or is saturated with a chemical/petroleum, the Contractor shall immediately stop work in that area and notify the

b. Analytical Testing

i. Contactor shall provide supporting laboratory analysis and waste profile to the EAD, through the Project Manager, for review.

ii. One composite sample shall be taken and analyzed for each 200 cubic yards of the stockpile, per NC DEQ Guidelines.

iii. Contractor shall identify and use a certified laboratory to perform the specified soil analyses.

1. First 4 analyses (1-4) – Must be certified by the State of North Carolina, for all 4 of these analyses

2. Last analysis (5) – Must select a DoD Environmental Laboratory Accreditation Program (ELAP) accredited laboratory certified for the method/matrix/analyte

iv. The stockpile sample(s) shall be analyzed for the following:

1. Std Method 5030 sample prep with Modified 8015 (CA GC-FID

Method) -Gasoline Range Organics;

2. Std Method 5030 and 3550 sample prep with Modified 8015 - Diesel Range Organics;

3. EPA Method 9071 - Oil & Grease, with silica gel wash; and

4. Full TCLP; and

5. Draft Method 1633 Analysis of Per- and Polyfluoroalkyl

Substances (PFAS) in Aqueous, Solid, Biosolids, and Tissue Samples by LC-MS/MS

v. Contractor shall consult with the selected laboratory about the specific sample handling procedures required by the analytical methods. Sample containers, volumes, procedures, and preservation vary among methods and should be identified early to understand requirements and need.

vi. Sampling shall be conducted by qualified personnel following proper chain-of-custody protocol.

c. Disposal

i. Any excess soil that cannot be re-utilized as backfill at the same location from which it was removed shall be disposed at a Subtitle D landfill (e.g.

Tuscarora), as a minimum, with the understanding that the analytical testing results shall determine the final disposal facility.

ii. The Contractor shall complete the manifest/bill of lading. Documentation should include the amount of soil (weight) being removed and supporting laboratory results for review.

iii. The EAD shall be responsible for review and signature on the waste manifests/bill of lading for the soil disposal prior to any soil leaving

MCAS CP.

iv. All moving, storing, testing, and berm costs associated with the excavated soil shall be the responsibility of the Contractor. All soil shall be stockpiled until used as backfill or final disposal.

4. Vapor Intrusion. Vapor intrusion must be considered in the early project planning. Any penetration to the foundation creates potential for subsurface vapors to enter into a work space and must therefore be evaluated prior to any work.

a. Vapor intrusion monitoring/evaluation may require the Contractor conduct actions to protect their own workers from potential exposures to vapors (or contaminated groundwater).

i. If this requirement is identified, the Contractor must develop a Health and Safety Plan (HASP) which details how the workers will be protected during the time the subsurface soil is exposed.

ii. The HASP is provided to EAD via the Project Manager for documentation; however, is not required to be approved prior to work.

b. There are 2 methods of disturbance – Open cutting for a new foundation, isolation pad, etc. and/or small penetrations into subsurface. Requirements for each type:

i. Foundation - As a minimum, the contractor shall use a vapor barrier below the new foundation that meets ASTM E1745 CLASS A polyethylene sheeting, minimum 15 mil thicknesses or ASTM E1993/E1993M bituminous membrane or other equivalent material with a maximum permanence rating of 0.01 perms per ASTM E96/E96M. The vapor barrier shall be resistant to chlorinated solvents.

ii. Penetration through the concrete into the subsurface (i.e. bore holes, drill holes or other small openings) - Requires appropriate sealing to ensure no cavities or voids remain which would allow potential subsurface vapors to enter into indoor work spaces. These openings should be sealed appropriately. Appropriate sealing guidance can be found in the Soil Boring Guidance document.

5. Requirements for Off-Site Soil (RFOSS). No soils shall be furnished or transported onto MCAS CP, or outlying fields, when such act would violate the Comprehensive Environmental Response Compensation and Liability Act (CERCLA) or the General Statutes of North Carolina.

a. The Contractor shall provide documentation certifying that all soil furnished under the contract contains no petroleum, hazardous or toxic materials as stated in DoD Instruction 4715.6, which implements 10 U.S.C. 2692. This documentation shall include the Soil Authorization Form (SAF) showing the volume of soil needed, analytical test data to support the environmental condition of the soil, and a copy of the State-issued “mining permit” for the borrow pit source. The MCAS CP EAD will review these documents before off site soil is considered approved for use.

b. For specific details on how to meet the RFOSS, contractor shall contact the Project Manager to receive guidance from the FRC East Environmental.

6. Requirements for Contaminated Groundwater. This project is located in a known contaminated groundwater area.

a. If dewatering is required during excavation, the groundwater shall not be discharged to the ground surface or storm sewer. The Contracting Officer shall coordinate with the Environmental Affairs Department (EAD).

b. This project is located in an area with known cVOC and/or PFAS contamination.

If dewatering is required during excavation, the groundwater shall not be allowed to discharge to the ground surface or storm sewer. The contractor shall provide a granular activated carbon/ion exchange groundwater treatment system capable of removing PFAS/PFOA to less than or equal to 70 parts per trillion (ppt). No groundwater discharge resulting from dewatering activities will be allowed without analysis proving treatment limits are met. The contractor must provide adequate holding tank volume until all groundwater is accepted by EAD for discharge. No groundwater discharge will be allowed without approval of the Contracting Officer and EAD.