- Solicitation number
- DCAM-26-CS-IFB-0004
- Issued by
- District of Columbia
About this file
This is a Bid Form submitted in response to an Invitation for Bids issued by the District of Columbia Department of General Services for construction services to develop a compartmented access area for the Metropolitan Police Department at the Marion S. Barry, Jr. Building located at 441 4th Street NW, Washington, DC 20001. The project encompasses approximately 422 square feet of construction work on the sixth floor, including selective demolition, interior partitioning, flooring installation, ceiling systems, wall finishes, door and hardware installation with security access controls, mechanical systems (HVAC), complete electrical systems with lighting and power distribution, telecommunications cabling with Category 6A copper cabling, fire alarm systems, and radiofrequency and electromagnetic shielding. The mandatory pre-bid conference and site visit was scheduled for March 2, 2026, at 10:00 AM, with written questions due by March 4, 2026, at 4:00 PM. Bids were due by March 16, 2026, at 12:00 PM, with opening at 3:30 PM the same day. The contract term extends from Notice to Proceed through a Substantial Completion Date of June 1, 2026, and Final Completion Date of June 30, 2026, with liquidated damages of $500 per day assessed for failure to meet the Substantial Completion Date.
Bidders must submit a lump sum price for CLIN 001 (all labor, materials, and equipment) plus a DGS Controlled Allowance of $20,000.00, with detailed price breakdowns organized by MasterFormat construction divisions. The estimated project budget is approximately $287,500. A 35 percent minimum allocation of contract work to Small Business Enterprises (SBEs) or Certified Business Enterprises (CBEs) is required, with enhanced credit multipliers of 1.10x for resident-owned businesses and 1.25x for disadvantaged businesses. Bidders must comply with prevailing wage requirements under Davis-Bacon, the Living Wage Act minimum of $17.50 per hour (increasing to $17.95 per hour July 1, 2025), and First Source Employment Agreement requirements mandating 51 percent District resident hiring. Submission requirements include a 5 percent bid bond or cashier's check guarantee, evidence of ability to furnish Performance and Payment Bonds equal to 100 percent of the contract amount, an SBE Subcontracting Plan, a First Source Employment Agreement with a Revised Employment Plan, a Bidder/Offeror's Certification Form, a Tax Affidavit, an Equal Employment Opportunity Statement, a Campaign Finance Reform Contractor Self-Certification Form, and a Bid Guaranty Certification. Comprehensive insurance requirements include Commercial General Liability of $1,000,000 per occurrence, Automobile Liability of $1,000,000, and Workers' Compensation insurance. The contract is subject to the Buy American Act requiring domestic construction materials except where specifically waived.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
[Contractor’s Letterhead] [Insert Date]
Ms. Kianna Shepherd Contracting Officer District of Columbia Department of General Services 3924 Minnesota Avenue NE Washington, DC 20019
Reference: Invitation for Bid DCAM-26-CS-IFB-0004 Construction Services for Metropolitan Police Department (“MPD”) Compartmented Access Area at Marion Barry Building
Dear Ms. Shepherd:
On behalf of [INSERT NAME OF BIDDER] (the “Bidder”), I am pleased to submit this bid in response to the Department of General Services’ (the “Department” or “DGS”) Invitation for Bid (the “IFB”) for the construction services for MPD Compartmented Access Area at Marion Barry Building (“MBB”) located at 441 4th Street NW, Washington, D.C 20001.
The Bidder has reviewed the IFB and the attachments thereto, any addenda thereto, and the proposed Form of Contract (collectively, the “Bid Documents” or “Contract Documents”) and has conducted such due diligence and analysis as the Bidder, in its sole judgment, has deemed necessary in order to submit its bid in response to the IFB. The Bidder’s bid and the Lump Sum Price are based on the Bid Documents as issued and assume no material alteration of the terms of the Bid Documents. (Collectively, the bid and the Lump Sum Price are referred to as the “Bidder’s Bid”.)
The Bidder’s Bid is as follows:
| CLIN |
| Description |
| Lump Sum Price |
| 001 |
| Provide all labor, materials, and equipment to build out a compartmented access area for the MPD at Marion S. Barry, Jr. Building in accordance with the Drawings (Attachment A), Specifications (Attachment B) and Scope of work, Section C of the IFB. |
ALLOWANCES
| 002 |
| DGS Controlled Allowance |
| $20,000.00 |
| Total Lump Sum Price Including Allowances (CLIN 001- CLIN 002) |
| $ |
TOTAL LUMP SUM PRICE WITH ALLOWANCE AND INCLUDING CLIN 001 TO CLIN 002 IN WORDS:
The Bidder’s Bid is based on and subject to the following conditions:
1. The Bidder agrees to hold its bid open for a period of at least one hundred twenty (120) days after the IFB closing date.
2. Assuming the Bidder is selected by the Department, the Bidder agrees to enter into a contract with the Department on the terms and conditions described in the Bid Documents within ten (10) days of the notice of the award.
3. Both the Bidder and the undersigned represent and warrant that the undersigned has the full legal authority to submit this bid form and bind the Bidder to the terms of the Bidder’s bid. The Bidder further represents and warrants that no further action or approval must be obtained by the Bidder in order to authorize the terms of the Bidder’s bid.
4. The Bidder and its principal team members hereby represent and warrant that they have not: (i) colluded with any other group or person that is submitting a bid in response to the IFB in order to fix or set prices; (ii) acted in such a manner so as to discourage any other group or person from submitting a bid in response to the IFB; or (iii) otherwise engaged in conduct that would violate applicable anti-trust law.
5. The Bidder hereby certifies that neither it nor any of its team members have entered into any agreement (written or oral) that would prohibit any contractor, subcontractor or subconsultant that is certified by the District of Columbia Office of Department of Small and Local Business Enterprises as a Local, Small, Resident Owned or Disadvantaged Business Enterprise (collectively, “LSDBE Certified Companies”) from participating in the work if another company is awarded the contract.
This Form of Offer Letter and Bid Form are being submitted on behalf of [INSERT FULL LEGAL NAME, TYPE OF ORGANIZATION, AND STATE OF FORMATION FOR THE BIDDER].
Sincerely, Company:
Name:
Title:
Date:
Signature:
Exhibit 1- Price Breakdown Form for the Lump Sum Price
Construction services for MPD Compartmented Access Area at MBB
| DIVISION NO. |
| DESCRIPTION |
| DIVISION COST |
| Div. 01 |
| General Requirements |
| Div. 02 |
| Existing Conditions (incl. abatement/demo) |
| Div. 03 |
| Concrete |
| Div. 04 |
| Masonry |
| Div. 05 |
| Metals |
| Div. 06 |
| Woods and Plastics |
| Div. 07 |
| Thermal and Moisture Protection |
| Div. 08 |
| Openings |
| Div. 09 |
| Finishes |
| Div. 10 |
| Specialties |
| Div. 11 |
| Equipment |
| Div. 12 |
| Furnishings |
| Div. 13 |
| Special Construction |
| Div. 14 |
| Conveying Systems |
| Div. 21 |
| Fire Suppressions |
| Div. 22 |
| Plumbing |
| Div. 23 |
| Heating, Ventilation and Air Conditioning |
| Div. 26 |
| Electrical |
| Div. 27 |
| Communications |
| Div. 28 |
| Electronic Safety and Security |
| Div. 31 |
| Earthwork |
| Div. 32 |
| Exterior Improvements |
| Div. 33 |
| Utilities |
Total Lump Sum Price of CLIN 001: