Attachment_C-_A105-2017_-_Airport_Monument_Sign_ITB_JEL_edits.pdf

PDF 633 KB Posted

Attached to
Airport Monument Sign
Solicitation number
ITB-06-2026
Issued by
Rutherford County, Newport City, Tennessee

About this file

This document is an AIA Document A105-2017 Standard Short Form of Agreement Between Owner and Contractor, involving the City of Murfreesboro, Tennessee and an unnamed contractor. The project involves the installation of a new monument sign at Murfreesboro Airport, located at 1930 Memorial Blvd, Murfreesboro, TN 37129. The contract specifies a 120-calendar day completion period from the date the Contractor accepts the pre-engineered building on the project site, with the work to commence upon the Owner's issuance of a Notice to Proceed.

The contract does not specify the exact contract sum, which is to be reflected in Exhibit J (Contractor's Bid Response). The agreement includes comprehensive insurance requirements, with the Contractor required to maintain Commercial General Liability insurance with policy limits of $2,000,000 per occurrence and aggregate, Automobile Liability coverage of $1,000,000, Workers' Compensation at statutory limits, and additional Umbrella/Excess coverage of $3,000,000. The Owner will retain 5% retainage until Substantial Completion and then reduce to 2% until final payment. The contract includes provisions for payment within 30 days of the Owner receiving the Contractor's Application for Payment, with an interest rate of 3.0% per annum for late payments.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AIA

Document A105TM – 2017 Standard Short Form of Agreement Between Owner and Contractor

AIA Document A105™ – 2017. Copyright © 1993, 2007 and 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 00:10:05 ET on 12/19/2018 under Order No.9160003892 which expires on 12/18/2019, and is not for resale.

User Notes: (1714968887)

ADDITIONS AND DELETIONS:

The author of this document has added information needed for its completion.

The author may also have revised the text of the original AIA standard form.

An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.

This document has important legal consequences.

Consultation with an attorney is encouraged with respect to its completion or modification.

ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.

AGREEMENT made as of the « ___ day of « ________ » in the year « 2025 » (In words, indicate day, month and year.)

BETWEEN the Owner:

(Name, legal status, address and other information)

« City of Murfreesboro, Tennessee»,« a Tennessee municipal corporation» « 111 West Vine Street » « Murfreesboro, TN 37130» and the Contractor:

(Name, legal status, address and other information) for the following Project:

(Name, location and detailed description)

«Installation of a new monument sign Murfreesboro Airport 1930 Memorial Blvd, Murfreesboro, TN 37129»

The Architect:

(Name, legal status, address and other information)

«Johnson + Bailey Architects P.C.» «100 East Vine Street» «City Center Suite 700» «Murfreesboro, TN 37130»

The Owner and Contractor agree as follows.

TABLE OF ARTICLES

1 THE CONTRACT DOCUMENTS

2 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

3 CONTRACT SUM

4 PAYMENTS

5 INSURANCE

6 GENERAL PROVISIONS

7 OWNER

8 CONTRACTOR

9 OWNER

10 CHANGES IN THE WORK

11 TIME

12 PAYMENTS AND COMPLETION

13 PROTECTION OF PERSONS AND PROPERTY

14 CORRECTION OF WORK

15 MISCELLANEOUS PROVISIONS

16 TERMINATION OF THE CONTRACT

17 OTHER TERMS AND CONDITIONS

ARTICLE 1 THE CONTRACT DOCUMENTS

The Contractor shall complete the Work described in the Contract Documents for the Project. The Contract Documents consist of

.1 this Agreement signed by the Owner and Contractor;

.2 the drawings and specifications prepared by the Engineers, dated «as set forth below», and enumerated as follows:

Drawings:

Number Title Date Project No. 2407 New Monument Sign

Murfreesboro Airport 8/20/25

Specifications:

Section Title Pages New Monument Sign at

Murfreesboro Airport dated August 20, 2025

1-20

.3 addenda prepared by the Engineers as follows:

Number Date Pages None

.4 written orders for changes in the Work, pursuant to Article 10, issued after execution of this

Agreement; and

.5 other documents, if any, identified as follows:

« 1. Exhibit A – Supplemental Conditions

2. Exhibit B – Insurance Requirements

3. Exhibit C – Non-Collusion Affidavit

4. Exhibit D – Drug Free Workplace Affidavit

5. Exhibit E – Iran Divestment Act Affidavit

6. Exhibit F – Performance Bond

7. Exhibit G – Payment Bond

8. Exhibit H – Specifications

9. Exhibit I – Invitation to Bid

10. Exhibit J – Contractor’s Bid Response

In the event of a conflict between the terms of this Agreement and those of either Exhibit A or Exhibit B, the exhibit’s terms shall take precedence.»

ARTICLE 2 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

§ 2.1 The Contract Time is the number of calendar days available to the Contractor to substantially complete the Work.

§ 2.2 Date of Commencement:

« The date of commencement shall be the date on which the Owner issues the Notice to Proceed. »

§ 2.3 Substantial Completion:

Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion, as defined in Section 12.5, of the entire Work:

(Check the appropriate box and complete the necessary information.)

[ « X » ] Not later than «one hundred twenty» ( «120» ) calendar days from the date of Contractor accepts the pre-engineered building on the Project site..

[ « » ] By the following date: « »

ARTICLE 3 CONTRACT SUM

§ 3.1 The Contract Sum shall include all items and services necessary for the proper execution and completion of the Work. Subject to additions and deductions in accordance with Article 10, the Contract Sum is:

______, as reflected in greater detail in Exhibit J.

§ 3.2 For purposes of payment, the Contract Sum includes the following values related to portions of the Work:

(Itemize the Contract Sum among the major portions of the Work.)

Portion of the Work Value N/A N/A

§ 3.3 The Contract Sum is based upon the following alternates, if any, which are described in the Contract Documents and hereby accepted by the Owner:

(Identify the accepted alternates. If the bidding or proposal documents permit the Owner to accept other alternates subsequent to the execution of this Agreement, attach a schedule of such other alternates showing the amount for each and the date when that amount expires.)

«N/A »

§ 3.4 Allowances, if any, included in the Contract Sum are as follows:

(Identify each allowance.)

Item Price N/A N/A

§ 3.5 Unit prices, if any, are as follows:

(Identify the item and state the unit price and quantity limitations, if any, to which the unit price will be applicable.)

Item Units and Limitations Price per Unit ($0.00)

§3.6 The Contractor shall pay all taxes, levies, duties, and assessments of any nature, that are applicable to any Work under this Contract. The Contract Sum and any agreed variations thereof shall include all taxes imposed by law. The Contractor shall make any and all payroll deductions required by law. The Contractor herein indemnifies and holds the Owner harmless from any liability on account of any and all such taxes, levies, duties, assessments, and deductions.

ARTICLE 4 PAYMENTS

§ 4.1 Based on Contractor’s Applications for Payment certified by the Owner, the Owner shall pay the Contractor, in accordance with Article 12, as follows:

(Insert below timing for payments and provisions for withholding retainage, if any.)

« any undisputed amount not later than thirty (30) days after the Owner receives the Contractor’s Application, provided, however, the Owner may withhold five percent (5%) of any undisputed amount as retainage »

§ 4.2 Payments due and unpaid under the Contract Documents shall bear interest from the date payment is due at the rate below, or in the absence thereof, at the legal rate prevailing at the place of the Project.

(Insert rate of interest agreed upon, if any.)

« 3.0 » % «per annum»

ARTICLE 5 INSURANCE

§ 5.1 The Contractor shall maintain, at its own expense, the following types and limits of insurance until the expiration of the period for correction of Work as set forth in Section 14.2, subject to the terms and conditions set forth in this Section 5.1 and Exhibit B:

§ 5.1.1 Commercial General Liability insurance for the Project, written on an occurrence form, with policy limits of not less than «Two Million Dollars » ($ «$2,000,000.00 » ) each occurrence, «Two Million Dollars » ($ «$2,000,000.00 » ) general aggregate, and «Two Million Dollars » ($ «$2,000,000.00 » ) aggregate for products-completed operations hazard.

§ 5.1.2 Automobile Liability covering vehicles owned, and non-owned vehicles used, by the Contractor, with policy limits of not less than «One Million Dollars » ($ «$1,000,000.00 » ) per accident, for bodily injury, death of any person, and property damage arising out of the ownership, maintenance, and use of those motor vehicles along with any other statutorily required automobile coverage.

§ 5.1.3 The Contractor may achieve the required limits and coverage for Commercial General Liability and Automobile Liability through a combination of primary and excess or umbrella liability insurance, provided that such primary and excess or umbrella insurance policies result in the same or greater coverage as those required under Section 5.1.1 and 5.1.2, and in no event shall any excess or umbrella liability insurance provide narrower coverage than the primary policy. The excess policy shall not require exhaustion of the underlying limits only through the actual payment by the underlying insurers.

§ 5.1.4 Workers’ Compensation at statutory limits.

§ 5.1.5 Employers’ Liability with policy limits not less than «One Million Dollars » ($ «$1,000,000.00 » ) each accident, «One Million Dollars » ($ «1,000,000 » ) each employee, and «One Million Dollars » ($ «1,000,000.00 » ) policy limit.

§ 5.1.6 The Contractor shall provide builder’s risk insurance to cover the total value of the entire Project on a replacement cost basis.

§ 5.1.7 Other Insurance Provided by the Contractor (List below any other insurance coverage to be provided by the Contractor and any applicable limits.)

Coverage Limits Umbrella/Excess Three Million Dollars ($3,000,000.00)

§ 5.2 Omitted intentionally: Section 5.2 has been removed in its entirety because the City’s insurance program will not provide property insurance coverage for this Work during construction. Upon project completion, the City’s property insurance will provide coverage for the signage, but not during construction.

§ 5.3 The Contractor shall obtain an endorsement to its Commercial General Liability insurance policy to provide coverage for the Contractor’s obligations under Section 8.12.

§ 5.4 Prior to commencement of the Work, each party shall provide certificates of insurance showing their respective coverages. All insurance required of Contractor under this Article 5 and Exhibit B shall be primary for the Work until the expiration of the period for correction of Work as set forth in Section 14.2.

§ 5.5 Unless specifically precluded by the Owner’s property insurance policy, the Owner and Contractor waive all rights against (1) each other and any of their subcontractors, suppliers, agents, and employees, each of the other; and

(2) the Engineer, Engineer’s consultants, and any of their agents and employees, for damages caused by fire or other causes of loss to the extent those losses are covered by property insurance or other insurance applicable to the Project, except such rights as they have to the proceeds of such insurance.

§ 5.6 Payment and Performance Bonds.

§ 5.6.1 Unless waived by the Owner in the event of a Contract Sum less than $100,000, the Contractor shall secure performance and payment bonds for 100% of the Contract Sum on a form acceptable to the Owner covering the faithful performance and completion of the Agreement and the payment of all obligations arising there under. Bonds shall be issued by a surety licensed in the State of Tennessee and satisfactory to the Owner.

§ 5.6.2 The Contractor must provide evidence of Bonds prior to the beginning of work. If the Performance and Payment Bonds are not furnished within 30 days of Notice of Award, the Contractor Bid Bond may be forfeited, and the Contract may be awarded to an alternate contractor.

§ 5.6.3 The Owner will require the Contractor to increase the Performance and Payment Bonds to accommodate Change Orders that individually or cumulatively exceed 10% of the original Contract Sum. The Contractor shall furnish to the Owner and keep in force during the term of the Contract, performance and labor and material payment bonds guaranteeing that the Contractor will perform its obligations under the Contract and will pay for all labor and materials furnished for the Work.

ARTICLE 6 GENERAL PROVISIONS

§ 6.1 The Contract The Contract represents the entire and integrated agreement between the parties and supersedes prior negotiations, representations or agreements, either written or oral. The Contract may be amended or modified only by a written modification in accordance with Article 10.

§ 6.2 The Work The term “Work” means the construction and services required by the Contract Documents, and includes all other labor, materials, equipment, and services provided, or to be provided, by the Contractor to fulfill the Contractor’s obligations.

§ 6.2.1 Specifications may describe types and quantities of materials, equipment, and other items of the Work and methods of installation that cannot be easily shown on the Drawings. It is not intended that the Specifications will mention every item of Work that can be adequately shown on the Drawings nor is it intended that the Drawings will show all items of Work adequately described or required by the Specifications, even if it is the case that such Work could have been shown thereon. The Contract Documents are complimentary, and what is required by, or reasonably inferable, by one shall be as binding as if required by all. In the event of conflicts or discrepancies among the Contract Documents, this Agreement will take precedent over the Specifications and Drawings.

§ 6.2.2 Prior to the inspections for Substantial Completion and Final Completion, as applicable, the Contractor shall clean exterior and interior surfaces exposed to view; remove temporary labels, stains, putty, soil, paint and foreign substances from all surfaces, including glass and painted surfaces; polish transparent and glossy surfaces;

clean equipment and fixtures to a sanitary condition; replace air filters in mechanical equipment; clean roofs, gutters, and downspouts; remove obstructions and flush debris from drainage systems; clean site; sweep paved areas and rake clean other surfaces; remove trash and surplus materials from the site: clean and polish all floors:

clean and polish all hardware; and repair all Work damaged during cleaning.

§ 6.3 Intent The intent of the Contract Documents is to include all items necessary for the proper execution and completion of the Work by the Contractor. The Contract Documents are complementary, and what is required by one shall be as binding as if required by all. In the event there are conflicts or discrepancies among the Contract Documents, interpretations will be based on the following priorities:

1. Amendments or Change Orders, with those of later date having precedence over those of earlier date

2. The Agreement

3. Exhibits and Addenda, with those of later date having precedence over those of earlier date.

4. Drawings and Specifications

5. In the case of any conflicts or discrepancies between Drawings and Specifications or within or among the Contract Documents and not clarified by Addendum, the better quality or greater quantity of Work shall be provided in accordance with the Owner's interpretation.

§ 6.4 Ownership and Use of Engineers’ Drawings, Specifications and Other Documents Documents prepared by the Engineers are instruments of the Engineers’ service for use solely with respect to this Project. The Engineers shall retain all common law, statutory, and other reserved rights, including the copyright. The Contractor, subcontractors, sub-subcontractors, and suppliers are authorized to use and reproduce the instruments of service solely and exclusively for execution of the Work. The instruments of service may not be used for other Projects or for additions to this Project outside the scope of the Work without the specific written consent of the Engineers.

§ 6.5 Electronic Notice Written notice under this Agreement may be given by one party to the other by email as set forth below.

(Insert requirements for delivering written notice by email such as name, title, and email address of the recipient, and whether and how the system will be required to generate a read receipt for the transmission.)

To Owner: To Contractor:

Darren W. Gore, City Manager dgore@murfreesborotn.gov with copies to:

• Chad Gehrke, Airport Director cgehrke@murfreesborotn.gov

• Scott Elliott, Manager of Project Development selliott@murfreesborotn.gov

Any notice sent via email shall be sent requesting a delivery receipt for the message. If the party sending the notice does not receive a delivery receipt within 24 hours, the party shall send notice via Certified U.S. Mail, private courier, or hand delivery to the other party.»

§ 6.5 Non-Discrimination. It is the policy of the Owner not to discriminate on the basis of age, race, sex, color, national origin, or disability in its hiring and employment practices, or in admission to, access to, or operation of its programs, services, and activities. With regard to all aspects of this Contract, the Contractor certifies and warrants it will comply with this policy.

ARTICLE 7 OWNER

§ 7.1 Information and Services Required of the Owner § 7.1.1 If requested by the Contractor, the Owner shall furnish all necessary surveys and a legal description of the site.

§ 7.1.2 Except for permits and fees under Section 8.7.1 that are the responsibility of the Contractor, the Owner shall obtain and pay for other necessary approvals, easements, assessments, and charges. If the Contractor's bid includes fees that the Owner has paid, or is required to pay directly, or that the Owner may waive, the Contractor shall, at the Owner's option, either pay these fees as a part of their bid or deduct fees from Contract Sum as a deductive change order.

§ 7.1.3 Prior to commencement of the Work, at the written request of the Contractor, the Owner shall furnish to the Contractor reasonable evidence that the Owner has made financial arrangements to fulfill the Owner’s obligations under the Contract. The Contractor shall have no obligation to commence the Work until the Owner provides such evidence.

§ 7.2 Owner’s Right to Stop the Work If the Contractor fails to correct Work which is not in accordance with the Contract Documents or is in default of its material obligations under the Contract Documents, the Owner may direct the Contractor in writing to stop the Work until the correction is made or default is cured, for which there will be no Change Order extending the Contract Time or the Contract Sum.

§ 7.3 Owner’s Right to Carry Out the Work If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within a seven day period after receipt of written notice from the Owner to commence and continue correction of such default or neglect with diligence and promptness, the Owner may, without prejudice to other remedies, correct such deficiencies. In such case, the Owner may withhold or nullify a Certificate for Payment in whole or in part, to the extent reasonably necessary to reimburse the Owner for the cost of correction, provided the actions of the Owner and amounts charged to the Contractor were approved by the Owner. In addition, if payments then or thereafter due the Contractor are not sufficient to cover such amounts, the Contractor shall pay the difference to the Owner immediately upon the Owner's written demand.

§ 7.4 Owner’s Right to Perform Construction and to Award Separate Contracts § 7.4.1 The Owner reserves the right to perform construction or operations related to the Project with the Owner’s own forces, and to award separate contracts in connection with other portions of the Project.

§ 7.4.2 The Contractor shall coordinate and cooperate with the Owner’s own forces and separate contractors employed by the Owner.

ARTICLE 8 CONTRACTOR

§ 8.1 Review of Contract Documents and Field Conditions by Contractor § 8.1.1 Execution of the Contract by the Contractor is a representation that the Contractor has visited the site, become familiar with local conditions under which the Work is to be performed, and correlated personal observations with requirements of the Contract Documents.

§ 8.1.2 The Contractor shall carefully study and compare the Contract Documents with each other and with information furnished by the Owner. Before commencing activities, the Contractor shall (1) take field measurements and verify field conditions; (2) carefully compare this and other information known to the Contractor with the Contract Documents; and (3) promptly report errors, inconsistencies, or omissions discovered to the Owner. Reports of errors, inconsistencies, or omissions must be made in writing and copies provided directly to the Owner.

§ 8.1.3 The Contractor represents and warrants the following to the Owner (in addition to the other representations and warranties contained in the Contract Documents), as an inducement to the Owner to execute this Contract, which representations and warranties shall survive the execution and delivery of the Contract and the Final Completion of the Work:

.1 That the Contractor is financially solvent, able to pay its debts as they mature, and possessed of sufficient working capital to complete the Work and perform its obligations under the Contract Documents;

.2 That the Contractor is able to furnish the tools, materials, supplies, equipment and labor required to timely complete the Work and perform its obligations hereunder and has sufficient experience and competence to do so;

.3 That the Contractor is authorized to do business in the State where the Project is located and properly licensed by all necessary governmental authorities having jurisdiction over it, the Work, or the site of the Project; and

.4 That the execution of the Contract and its performance thereof are within the duly-authorized powers of the Contractor and the signatory on behalf of the Contractor.

§ 8.1.4 Contractor shall be responsible for ascertaining correct dimensions, and Contractor is not to ascertain dimensions simply by scaling drawings unless directed to do so by the Owner or Project Engineer. In case of any discrepancy between Drawings and Specifications, Contractor shall consult the Project Engineer promptly for an interpretation before proceeding with the Work.

§ 8.2 Contractor’s Construction Schedule The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner’s information a Contractor’s construction schedule for the Work. Contractor must maintain an updated project schedule and if milestones are negatively impacted, Contractor must, prior to submission of the next application for payment, provide Owner with a specific plan to return the project to the project schedule.

§ 8.3 Supervision and Construction Procedures § 8.3.1 The Contractor shall supervise and direct the Work using the Contractor’s best skill and attention. The Contractor shall be solely responsible for and have control over construction means, methods, techniques, sequences, and procedures, and for coordinating all portions of the Work.

§ 8.3.2 The Contractor, as soon as practicable after award of the Contract, shall furnish in writing to the Owner the names of subcontractors or suppliers for each portion of the Work. The Contractor shall not contract with any subcontractor or supplier to whom the Owner have made a timely and reasonable objection.

§ 8.3.3 Layout new construction lines and verify slab slope and conditions. If discrepancies between actual lines and elevations and those indicated on plans exist, notify Project Engineer and Owner and obtain a decision before starting work.

§ 8.3.4 The Contractor shall establish and maintain reference points required for the work. Contractor shall lay out on the rough floor the exact locations of partitions, openings, etc. as a guide to all trades. Contractor shall verify elevations, lines, levels, and dimensions indicated on the drawings before commencing work.

§ 8.3.5 The Contractor shall be responsible to the Owner for the acts and omissions of all his employees and all Subcontractors, their agents and employees, and all other persons performing any of the Work under a contract with the Contractor.

§ 8.4 Labor and Materials § 8.4.1 Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for labor, materials, equipment, tools, utilities, transportation, and other facilities and services necessary for proper execution and completion of the Work.

§ 8.4.2 The Contractor shall enforce strict discipline and good order among the Contractor’s employees and other persons carrying out the Contract Work. The Contractor shall not permit employment of unfit persons or persons not skilled in tasks assigned to them.

§ 8.4.3 Contractor agrees to keep the Project free and clear from all mechanic's liens, materialmen liens, and other liens. The Contractor shall discharge any such lien immediately but in no event more than 30 days after filing of such a lien. In the event such lien is not released or discharged within such 30 days period, the Owner shall have the right to pay all sums necessary to discharge such liens and the Owner shall have the right to deduct such amounts from any amounts due hereunder or demand immediate payment from the Contractor. In the event of any such deduction, the Contract Sum due under the Contract Documents automatically shall be reduced by the amount of such payment without the need for any Change Order. In no instance shall this provision affect any limitation or restriction imposed by law or regulation on the placement or enforcement of liens.

§ 8.4.4 Substitutions:

.1 Where materials, equipment, apparatus, or other products are specified by manufacturer, brand name, type or catalog number, such designation shall establish standards of quality and style desired. Any reasonable request for substitution will be considered, if in the opinion of the Owner such materials are equal to the material specified and entirely satisfactory for use in the project. The Owner shall be the sole judge of acceptability of substitution.

. 2 By making requests for substitutions, the Contractor:

A. Represents that it has personally investigated the proposed substitute product and determined that it is equal or superior in all respects to that specified;

B. Represents that it will provide the same warranty for the substitution as it would for the product specified;

C. Certifies that the cost data presented is complete and includes all related costs for the substituted product and for Work that must be changed as a result of the substitution, and waives all claims for additional costs related to the substitution that subsequently become apparent; and D. Shall coordinate the installation of the accepted substitute, making such changes as may be required for the Work to be complete in all respects. .

.3 When a material, equipment or system is specified by the name of one or more manufacturers, such material, equipment, or system shall form the basis of the Contract. If the Contractor desires to make a substitution, Contractor shall comply with Specification Sections 01 25 13 and 00 43 25.

.4 The Owner shall be entitled to reimbursement from the Contractor for amounts the Owner pays to an engineer or consultant for reviewing the Contractor proposed substitutions and making agreed-upon changes in the Drawings and Specifications resulting from such substitutions.

§ 8.4.5 The use of undocumented workers is not permitted.

§ 8.4.6 The Contractor shall have the Subcontractor who installs them, correct defects in bases, surfaces, or substrates on which finishing materials are to be applied, construction is to be added, or equipment is to be mounted.

§ 8.4.7 The Contractor shall disclose the existence and extent of any financial interest, whether direct or indirect, he has in subcontractors or material suppliers which he may propose for this project.

§ 8.5 Warranty § 8.5.1 The Contractor warrants to the Owner that: (1) materials and equipment furnished under the Contract will be new and of good quality unless otherwise required or permitted by the Contract Documents; (2) the Work will be free from defects not inherent in the quality required or permitted; and (3) the Work will conform to the requirements of the contract documents. The warranty provided in this Section shall be in addition to and not in limitation of any other warranty, including, manufacturer or supplier warranties, or remedy required by law or by the Contract Documents, and notwithstanding anything to the contrary contained in the Contract Documents. This warranty commences upon Final Completion. The Contractor shall promptly repair and replace, at the Contractor’s sole cost and expense, any materials, equipment, or Work covered by and violating the warranty. All warranty work shall be coordinated with the Owner in order to limit the disruption of operation and completed Project. All such warranty work shall be completed in compliance with the terms and conditions of the Contract Documents.

§ 8.5.2 Work not conforming to these requirements, including substitutions not properly approved and authorized, may be considered defective. The Contractor’s warranty excludes remedy for damage or defect caused by abuse of Owner or Owner’s invitees, modifications not executed by the Contractor, improper or insufficient maintenance, improper operation, or normal wear and tear and normal usage. If required by the Owner, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment.

§ 8.5.3 Any material or equipment warranties required by the Contract Documents shall be issued in the name of the Owner, or shall be transferrable to the Owner, and shall commence in accordance with Section 12.5.

§ 8.6 Taxes The Contractor shall pay sales, consumer, use, and similar taxes that are legally required when the Contract is executed.

§ 8.7 Permits, Fees and Notices § 8.7.1 The Contractor shall obtain and pay for the building permit and other permits and governmental fees, licenses, and inspections necessary for proper execution and completion of the Work.

§ 8.7.2 The Contractor shall comply with and give notices required by agencies having jurisdiction over the Work. If the Contractor performs Work knowing it to be contrary to applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities, the Contractor shall assume full responsibility for such Work and shall bear the attributable costs. The Contractor shall promptly notify the Owner in writing of any known inconsistencies in the Contract Documents with such governmental laws, rules, and regulations.

§ 8.8 Submittals The Contractor shall promptly review, approve in writing, and submit to the Owner shop drawings, product data, samples, and similar submittals required by the Contract Documents. Shop drawings, product data, samples, and similar submittals are not Contract Documents.

§ 8.9 Use of Site The Contractor shall confine operations at the site to areas permitted by law, ordinances, permits, the Contract Documents, and the Owner.

§ 8.10 Cutting and Patching The Contractor shall be responsible for cutting, fitting, or patching required to complete the Work or to make its parts fit together properly.

§ 8.11 Cleaning Up The Contractor shall keep the premises and surrounding area free from accumulation of debris and trash related to the Work. At the completion of the Work, the Contractor shall remove its tools, construction equipment, machinery, and surplus material; and shall properly dispose of waste materials. If the Contractor fails to clean-up as provided in the Contract Documents, the Owner may do so and the cost thereof shall be charged to the Contractor and deducted from the remaining. No on-site burning of trash is allowed.

§ 8.12 Indemnification To the fullest extent permitted by law, the Contractor shall indemnify and hold harmless the Owner, Engineers, Engineers’ consultants, and agents and employees of any of them, from and against claims, damages, losses and expenses, including but not limited to attorneys’ fees, arising out of or resulting from performance of the Work, provided that such claim, damage, loss, or expense is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself), but only to the extent caused by the negligent acts or omissions of the Contractor, a subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, regardless of whether or not such claim, damage, loss or expense is caused in part by a party indemnified hereunder. The provisions of this Section 8.12 shall survive the completion of the Work or termination of the Agreement.

ARTICLE 9 PROJECT MANAGEMENT

§ 9.1 The Owner will provide administration of the Contract as described in the Contract Documents. The Owner will have authority to act on behalf of the Owner only to the extent provided in the Contract Documents.

§ 9.2 The Owner will visit the site at intervals appropriate to the stage of construction to become generally familiar with the progress and quality of the Work. Representatives of the Owner and Contractor shall meet periodically at mutually agreed-upon intervals for the purposes of establishing procedures to facilitate cooperation, communication, and timely responses among the participants. By participation in this arrangement, the parties do not intend to create additional contractual obligations or modify the legal relationship which may otherwise exist.

§ 9.3 The Owner will not have control over or charge of, and will not be responsible for, construction means, methods, techniques, sequences, or procedures, or for safety precautions and programs in connection with the Work, since these are solely the Contractor’s responsibility. The Owner will not be responsible for the Contractor’s failure to carry out the Work in accordance with the Contract Documents.

§ 9.4 Based on the Owner’s observations and evaluations of the Contractor’s Applications for Payment, the Owner will review and certify the amounts due the Contractor.

§ 9.5 The Owner has authority to reject Work that does not conform to the Contract Documents.

§ 9.6 The Owner will promptly review and approve or take appropriate action upon Contractor’s submittals, but only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.

§ 9.7 On written request from either the Owner or Contractor, the Owner will promptly interpret and decide matters concerning performance under, and requirements of, the Contract Documents.

§ 9.8 Interpretations and decisions of the Owner will be consistent with the intent of, and reasonably inferable from the Contract Documents.

ARTICLE 10 CHANGES IN THE WORK

§ 10.1 The Owner, without invalidating the Contract, may order changes in the Work within the general scope of the Contract, consisting of additions, deletions or other revisions, and the Contract Sum and Contract Time shall be adjusted accordingly, in writing.

§ 10.1.1 Changes in the Work may be accomplished by Change Order, Change Directive, or Field Order, all of which the Contractor shall diligently effectuate and carry out.

.1 A Change Order is a written instrument prepared by the Owner and signed by the Owner and the Contractor, stating their agreement upon all of the following: (i) the change of the Work: (ii) the amount of the adjustment, if any, in the Contract Sum; and (iii) the extent of the adjustment, if any, in the Contract Time. No change to the Contract Sum or Contract Time is effective without a written, signed Change Order. The Contractor’s sole remedy for any changes is to secure a Change Order.

.2 A Change Directive is a change required by the Owner that does not affect the Contract Time or Contract Sum and will be issued by the Owner in writing to the Contractor.

.3 A Field Order is a minor change or deviation in the Specifications or Drawings and not inconsistent with the Contract that do not affect the Contract Time or Contract Sum and can be made verbally by the Owner and summarized within seven days in writing provided to the Contractor. The Contractor may request that the Owner convert a Field Order to a Change Directive.

§ 10.1.2 Should the Contractor believe a Change Directive requires a Change Order, the Contractor must make a Claim in accordance with the Agreement within 15 days of the Change Directive being issued.

§ 10.1.3 The Owner's representative shall have authority to authorize contract modifications less than $10,000.00.

Contract modifications of $10,000.00 or greater require approval by Murfreesboro City Council.

§ 10.2 The Owner may authorize or order minor changes in the Work that are consistent with the intent of the Contract Documents and do not involve an adjustment in the Contract Sum or an extension of the Contract Time.

Such authorization or order shall be in writing and shall be binding on the Owner and Contractor. The Contractor shall proceed with such minor changes promptly.

§ 10.3 If concealed or unknown physical conditions are encountered at the site that differ materially from those indicated in the Contract Documents or from those conditions ordinarily found to exist, the Contract Sum and Contract Time shall be subject to equitable adjustment.

§ 10.4 The combined overhead and profit included in the total cost to the Owner of a change in the Work shall be based upon the following schedule:

.1 For the Contractor, for Work performed by the Contractor's own forces at the fee negotiated with the owner of the cost.

.2 For the Contractor, for Work performed by the Contractor's Subcontractor, five percent (5%) of the amount due the Subcontractor.

.3 For each Subcontractor or Sub-Subcontractor involved, for Work performed by that Subcontractor's or Sub-Subcontractor's own forces, ten percent ( 10%) of the cost.

.4 For each Subcontractor, for Work performed by the Subcontractor's Sub- Subcontractors, five percent (5%) of the amount due the Sub-Subcontractor.

.5 Cost to which overhead and profit is to be applied shall be determined in accordance with Section 10.1.1.

.6 In order to facilitate checking of quotations for extras or credits, all proposals, except those so minor that their propriety can be seen by inspection, shall be accompanied by a complete itemization of costs including labor, materials and Subcontracts. Labor and materials shall be itemized in the manner prescribed above. Where major cost items are Subcontracts, they shall be itemized also. In no case will a change involving over $500.00 be approved without such itemization.

ARTICLE 11 TIME

§ 11.1 Time limits stated in the Contract Documents are of the essence of the Contract. Extensions of time will not be granted for delays caused by inadequate construction force, the failure of the Contractor to place orders for equipment or materials sufficiently in advance to ensure delivery when needed, or the failure of Contractor to protect properly the site from inclement weather.

§ 11.2 If the Contractor is delayed at any time in progress of the Work by changes ordered in the Work, or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties, or other causes beyond the Contractor’s control, the Contract Time shall be subject to equitable adjustment. If the Contractor is delayed at any time in progress of the work by an act or neglect of the Owner or its employee(s), or of a separate Contractor employed by the Owner, or by changes ordered in the work that affect the "critical path" of the work, or by labor disputes, fire, unavoidable casualties, or other causes beyond the Contractor's control, except as defined in Articles 3 and 15, or by other causes which the Owner determines may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as Owner may determine. Extended overhead, profit, and other indirect costs related to the extension of the contract time will not be allowed.

§ 11.3 Costs caused by delays or by improperly timed activities or defective construction shall be borne by the responsible party.

ARTICLE 12 PAYMENTS AND COMPLETION

§ 12.1 Contract Sum The Contract Sum stated in this Agreement, including authorized adjustments, is the total amount payable by the Owner to the Contractor for performance of the Work under the Contract Documents.

§ 12.2 Applications for Payment § 12.2.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Owner an itemized Application for Payment for Work completed in accordance with the values stated in this Agreement. The Application shall be supported by data substantiating the Contractor’s right to payment as the Owner may reasonably require, such as evidence of payments made to, and waivers of liens from, subcontractors and suppliers. Payments shall be made on account of materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work. If approved in advance by the Owner, payment may similarly be made for materials and equipment stored, and protected from damage, off the site at a location agreed upon in writing. The form of Application for Payment duly notarized shall be a current authorized edition of AlA Document G702-1992 Application and Certificate for Payment, supported by a current authorized edition of AlA Document G703-1992, Continuation Sheet.

§ 12.2.2 The Contractor warrants that title to all Work covered by an Application for Payment will pass to the Owner no later than the time of payment. The Contractor further warrants that upon submittal of an Application for Payment, all Work for which Certificates for Payment have been previously issued and payments received from the Owner shall, to the best of the Contractor’s knowledge, information, and belief, be free and clear of liens, claims, security interests, or other encumbrances adverse to the Owner’s interests.

§ 12.2.3 In Applications for Payment, the amount represented as total completed and stored to date shall reflect the portion of the Contract Sum properly allocable to labor, materials, and equipment incorporated in the Work, and materials and equipment suitably stored in accordance with Subparagraph 4.2 and not exceed the Contract Sum less the value of incomplete work and corrections required. This total completed and stored to date shall not be construed to define completion as determined for Substantial Completion or final completion of the Work according to 12.5 or 12.6.

§ 12.2.4 Applications for Payment shall indicate retainage withheld from the total completed and stored to date as follows: Five percent (5%) until acceptance of a Certificate of Substantial Completion, and thereafter two percent (2%) until final payment. The resulting amount shall be indicated as the total earned less retainage. Applications that reduce retainage shall be accompanied by Consent of Surety.

§ 12.2.5 Applications for Payment shall indicate the total earned less retainage, and the aggregate of previous payments made subtracted therefrom, and an amount requested.

§ 12.3 Certificates for Payment § 12.3.1 The Owner will, within seven days after receipt of the Contractor’s Application for Payment, either (1) issue to the Owner a Certificate for Payment in the full amount of the Application for Payment, with a copy to the Contractor; (2) issue to the Owner a Certificate for Payment for such amount as the Owner determines is properly due, and notify the Contractor and Owner in writing of the Owner’s reasons for withholding certification in part; or

(3) withhold certification of the entire Application for Payment, and notify the Contractor of the Owner’s reason for withholding certification in whole. If certification or notification is not made within such seven-day period, the

Contractor may, upon seven additional days’ written notice to the Owner, stop the Work until payment of the amount owing has been received. The Contract Time and the Contract Sum shall be equitably adjusted due to the delay.

§ 12.3.2 The Owner may withhold a Certificate for Payment in whole or in part, to the extent reasonably necessary to protect the Owner. If the Owner is unable to certify payment in the amount of the Application, the Owner will notify the Contractor. If the Contractor and the Owner cannot agree on a revised amount, the Owner will promptly issue a Certificate for Payment for the amount for which the Owner is able to make such representations. The Owner may also withhold a Certificate for Payment or, because of subsequently discovered evidence, may nullify the whole or a part of a Certificate for Payment previously issued, to such extent as may be necessary in the Owner’s opinion to protect the Owner from loss for which the Contractor is responsible, including loss resulting from acts and omissions, because of, but not limited to:

.1 defective Work not remedied;

.2 third party claims filed or reasonable evidence indicating probable filing of such claims unless security acceptable to the Owner is provided by the Contractor;

.3 failure of the Contractor to make payments properly to Subcontractors or for labor, materials or equipment;

.4 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum;

.5 damage to the Owner or a separate contractor;

.6 reasonable evidence that the Work will not be completed within the Contract Time, and that the unpaid balance would not be adequate to cover actual or liquidated damages for the anticipated delay;

.7 persistent failure to carry out the Work in accordance with the Contract Documents or unsatisfactory execution of the Work;

.8 failure of the Contractor to comply with applicable Codes, Laws, or Regulations;

.9 failure to update as-built drawings or provide construction photographs with the Application for Payment as required by the Contract Documents. (If these documents/items are not provided for actual work performed for a period of work covered by an Application for Payment and cannot be accurately provided due to passage of time, the Owner may deduct a reasonable amount from the Agreement sum to reflect work not performed that cannot be recovered due to progress of work.)

.10 failure to update the CPM schedule concurrent with the request for payment; or

.11 Any other reasonable basis to withhold certification.

§ 12.3.4 When the above reasons for withholding certification are removed, certification will be made for amounts previously withheld. The Owner shall have no liability whatsoever for interest or other charges resulting from withholding of payment for any reason stated in this Article.

§ 12.3.5 If any claim or lien is made or filed with or against the Owner, the Project or the Premises by any person claiming that the Contractor or any Subcontractor or other person under it has failed to make payment for any labor, services, materials, equipment, taxes or other items or obligations furnished or incurred for or in connection with the Work, or if at any time there shall be evidence of such nonpayment or of any claim or lien for which, if established, the Owner might become liable and which is chargeable to the Contractor, or if the Contractor or any Subcontractor or other person under it causes damage to the Work or to any other work on the Project, or if the Contractor fails to perform or is otherwise in default under any of the terms or provisions of the Contract Documents, the Owner shall withhold certification, and the Owner shall have the right to retain from any payment then due or thereafter to become due an amount which the Owner shall deem sufficient to:

.1 satisfy, discharge and/or defend against any such claim or lien or any action which may be brought or judgement which may be recovered thereon, .2 make good any such nonpayment, damage, failure or default, and

.3 compensate the Owner for and indemnify it against any and all losses, liability, damages, costs and expenses, including reasonable attorneys’ fees and disbursements, which may be sustained or incurred by the Owner in connection therewith. The Owner shall have the right to apply and charge against the Contractor so much of the amount retained as may be required for the foregoing purposes. If such amount is insufficient therefore, the Contractor shall be liable for the difference and pay the same to the Owner.

§ 12.4 Progress Payments § 12.4.1 After the Owner has issued a Certificate for Payment, the Owner shall make payment in the manner provided in the Contract Documents.

§ 12.4.2 The Contractor shall promptly pay each subcontractor and supplier, upon receipt of payment from the Owner, an amount determined in accordance with the terms of the applicable subcontracts and purchase orders.

§ 12.4.3 The Owner shall have responsibility for payments to a subcontractor or supplier.

§ 12.4.4 A Certificate for Payment, a progress payment, or partial or entire use or occupancy of the Project by the Owner shall not constitute acceptance of Work not in accordance with the requirements of the Contract Documents.

§ 12.4.5 The Owner may, at its sole option, issue joint checks to the Contractor and to any Subcontractor or material or equipment suppliers to whom the Contractor failed to make payment for Work properly performed or material or equipment suitably delivered. If the Owner makes payments by joint check, the Owner shall reflect such payment on the next Certificate for Payment.

§ 12.5 Substantial Completion § 12.5.1 Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficient complete in accordance with the Contract Documents so the Owner can occupy or utilize the Work for its intended use and when all required occupancy permits have been issued such as, but not limited to, Local Building Occupancy Permits, and copies of same have been delivered to the Owner. In order to occupy or utilize the Work for its intended use, Owner must have received complete Project Data, Operating and Maintenance Data, orientation and training, as may be required by the specifications.